You are on page 1of 77

POWER

TRANSFORMERS

Eng. Ashraf Zaki


Eng. Hossam Samir Testing & Acceptance Conditions
Power Transformers

Power Transformers
TESTING & ACCEPTANCE CONDITIONS

INDEX
Part (1) ……… Reference International Standards

Part (2) ……… Reference Database Documents

Part (3) ……… General Test Requirements

Part (4) ……… List of Tests applied

Part (5) ……… Detailed (Routine / Sample) Test procedure (FAT)

Part (6) ……… Reference Test Reports

Part (7) ……… Informative Documents

Page 1
Power Transformers

Part (1)
Reference International Standards

Page 2
Power Transformers

 IEC 60076-1
(Power transformers –General)
 IEC 60076-2
(Power transformers –Temperature Rise)
 IEC 60076-3
(Power transformers –Insulation levels & Dielectric Test)
 IEC 60076-5
(Ability to withstand short circuit)
 IEC 60076-10
(Determination of Sound Levels)

Page 3
Power Transformers

Part (2)
Reference Database Documents
This Document is to be read in conjunction with the following Database
Documents:

(Tap Changers – Part(1) – On load Tap Changers – Testing and Acceptance Conditions)

Page 4
Power Transformers

Part (3)
General requirements for routine, type and special tests
(Preparatory Check List)

Page 5
Power Transformers

1- Tests shall be made at any ambient temperature between 10 °C and 40 °C


and with cooling water (if required) at any temperature not exceeding 25 °C.

2- Tests shall be made at the manufacturer's works, unless otherwise agreed


between the manufacturer and the purchaser.

3- All external components and fittings that are likely to affect the performance
of the transformer during the test shall be in place.

4- Tapped windings shall be connected on their principal tapping, unless the


relevant test clause requires otherwise or unless the manufacturer and the
purchaser agree otherwise.

5- The test basis for all characteristics other than insulation is the rated
condition, unless the test clause states otherwise.

6- All measuring systems used for the tests shall have certified traceable
accuracy and be subjected to periodic calibration, according to the rules of
4.11 of ISO 9001.

7- Where it is required that test results are to be corrected to a reference


temperature, this shall be:

For oil-immersed transformers: 75 °C;


For dry-type transformers: according to the general requirements for
tests in IEC 60726.

Page 6
Power Transformers

Part (4)
List of All Tests that may be applied

Page 7
Power Transformers

• Routine Tests
1- Measurement of winding resistance.
2- Measurement of voltage ratio and check of phase displacement.
3- Measurement of short-circuit impedance and load loss.
4- Measurement of no-load loss and current.
5- Dielectric routine tests (IEC 60076-3) which includes:
a) Switching Impulse Test.
(Not Applicable for Um≤72.5kV)
b) Lightning Impulse Test.
(Originally a Type Test, in some cases it’s considered a Routine Test)
c) Separate Source AC withstand voltage test.
d) Short duration induced AC withstand voltage test
e) Long duration induced AC withstand voltage test
(Not Applicable for Um≤72.5kV)
6- Functional Checks on Marshalling & Remote control Panel.
7- Operation Tests on On-Load Tap Changer.
(Found under Tap changer test report)

• Type Tests
1- Temperature-rise test (IEC 60076-2).
2- Dielectric type tests (IEC 60076-3).

• Special Tests
1- Dielectric special tests (IEC 60076-3).
2- Determination of capacitances windings-to-earth, and between windings.
3- Determination of transient voltage transfer characteristics.
4- Measurement of zero-sequence impedance(s) on three-phase
transformers (10.7).
5- Short-circuit withstand test (IEC 60076-5).
6- Determination of sound levels (IEC 60551).
7- Measurement of the harmonics of the no-load current (10.6).
8- Measurement of the power taken by the fan and oil pump motors.
9- Measurement of insulation resistance to earth of the windings, and/or
measurement of dissipation factor (tan d) of the insulation system
capacitances. (These are reference values for comparison with later
measurement in the field. No limitations for the values are given here.)

Page 8
Power Transformers

Part (5)
Detailed Routine Test Procedure

Page 9
Power Transformers

MEASUREMENT OF WINDING RESISTANCE

Test Purpose:

In this test, the resistance of each transformer winding is measured using DC


current at a recorded ambient temp.

Test Precautions:

For the Dry Type- Power Transformers, the transformer shall be at rest in a
constant ambient temperature for at least 3h.

Winding resistance and winding temperature shall be measured at the same


time. The winding temperature shall be measured by sensors placed at
representative positions, preferably inside the set of windings, for example, in a
duct between the high-voltage and low voltage windings

For the Oil immersed- Power Transformers, after the transformer has been
under oil without excitation for at least 3h, the average oil temperature shall be
determined and the temperature of the winding shall be considered the same as
the average oil temperature. The average oil temperature is taken as the mean of
the top and bottom oil temperatures.

Test Description & Procedure:

1- Resistance to be measured between each main terminal pair (i.e. A-B , A-C &
C-B) in case of Delta connected windings, and between each terminal to
neutral (i.e. a-n , b-n, …etc,) in case of wye connected windings.
2- In case of tapped windings, above readings are recorded at each tap.
3- Average oil temperature is to be recorded.
4- Measured values are to be corrected to required temperatures as mentioned
under Part (2) (Preparatory Check List).

Acceptance Criteria:

Supplier’s guaranteed values of winding resistance to be taken as a reference. Any


variation to this value is to be within accepted tolerance.

Page 10
Power Transformers

MEASUREMENT OF VOLTAGE RATIO AND CHECK OF PHASE DISPLACEMENT

Test Purpose:

The voltage ratio shall be measured on each tapping in the no-load condition. The
polarity of single-phase transformers and the connection symbol of three-phase
transformers shall be checked.

Test Description & Procedure:

Part (1) Voltage Ratio

1- Turns Ratio measuring instrument is to be connected to each pair of coupled


windings (i.e. A-B & a-n)
2- Values are recorded at each tap in case of tapped windings and then
compared to calculated ratio at the same tap.

Part (2) Phase Displacement

1- 3phase voltage source with known value is applied and other generated
voltages are measured.
2- By performing some arithmetic analysis on the transformers vector group,
the phase displacement can be verified.
(For details, Refer to Part (5) “Reference Test Reports”)

Acceptance Criteria:

*Range of measured ratio shall be equal to the calculated ratio ±0.5%.

*Phase displacement is identical to approved arrangement and transformer’s


nameplate.

Page 11
Power Transformers

MEASUREMENT OF SHORT-CIRCUIT IMPEDANCE AND LOAD LOSS

Test Purpose:

In this test, the value of the short circuit impedance Z% and the load (copper)
losses (I2R) are obtained.

Test Precautions:

1- Test is performed at rated frequency.


2- Supplied current should be equal to the relevant rated current but shall not
be less than 50% of the same.
3- When measuring the short circuit impedance for a transformer having a
tapped winding, it will be as following:
a) If tapping range is less than ±5%, measurements will be carried out @
principal tape only.
b) If tapping range is Greater than ±5%, measurements will be carried out
@ principal tape as well as the two extreme tappings.
4- When measuring the load loss for a transformer having a tapped
winding, it will be as following:
a) If tapping range within±5% and rated power less than 2500kAV, load loss
guarantee refer to the principal tap only.
b) If tapping range exceeds±5% or rated power above 2500kAV, it shall be
stated for which tapping beside the principal tap the load losses will be
guaranteed by the manufacturer.

Test Description & Procedure:

1- Voltage will be applied to the terminals of one winding (usually the H.V.)
with the other winding short circuited (usually the L.V.)
2- Voltage to be increased gradually till the current in the energized winding
reaches the required value (50% to 100% rated current).
3- If transformer is equipped with a tap changer, above tapping regulations are
applied.
4- Readings to be taken as quickly as possible as the windings warm up and
the winding resistance increases. Hence, the losses value will increase
accordingly.
5- Using appropriate instruments (conventional three wattmeter method or
digital wattmeter with ammeters & voltmeters) measurements of voltage,
currents and power can be recorded.

Page 12
Power Transformers

6- If the measured current deviates from the rated, Power & Voltage measured
will be corrected using the following relations:

Where, (r) refers to rated values & (m) refers to measured values.

7- All recorded data are taken at ambient Temp. (Ta) which need to be
corrected at the required standard Temp (75C for Oil immersed Transformers).

Circuit Diagram for the Short Circuit impedance & Load Losses Test
Acceptance Criteria:

*Measured impedance to be within guaranteed value and nameplate value.

*Load losses to be within guaranteed values.

Page 13
Power Transformers

MEASUREMENT OF NO LOAD LOSS & NO LOAD CURRENT

Test Purpose:

In this test, the value of No-Load power (Po) & the No-Load current (Io) are
measured at rated voltage & frequency.

Test Precautions:

1- Test is performed at rated frequency.


2- Two voltmeters are connected to the energized winding, one is measuring
the voltage mean value and the other is for the R.M.S value. Test results are
considered satisfactory if the readings of the two are equal within 3%. if it’s
more than 3%, the validity of the test is subjected to agreement.
3- This test should be performed before the impulse test-if the later will be
performed as a routine test- in order to avoid readings errors

Test Description & Procedure:

1- Voltage applied (usually to H.V. windings) will be in a range starting from


90% of winding rated voltage up to 110% of the same in steps, each of 5%
(i.e. for a 33/11kV transformer, applied voltage values will be 29.7kV, 31.35kV,…..,
36.3kV)
2- Readings of watt meters, Voltmeters & Ammeters are recorded to obtain the
values of Vr.m.s, Vmean, Po and Io at each voltage step.
3- Measured value of power loss is corrected according to the following
formula:

Pc=Pm (1+d)
D= (Vmean-Vr.m.s) / Vmean

Acceptance Criteria:

*No Load losses to be within guaranteed values.

Page 14
Power Transformers

Circuit Diagram for the No-Load Losses Test

Page 15
Power Transformers

DIELECTRIC ROUTINE TESTS / GENERAL REQUIREMENTS

All Dielectric Routine tests requirements are summarized in the following Table
(IEC 60076-3):

Page 16
Power Transformers

Voltage levels required for all dielectric tests for transformers having windings with
highest voltage (Um) of not more than 170kV are summarized in the following
table:

Page 17
Power Transformers

Dielectric Tests on Transformers with Tapped windings


When applying any of the dielectric routine tests to a transformer equipped with a
tap changer (Tapped windings) the following guide lines will apply:

1- If the tapping range equals or less than ±5%, tests will be applied to
principal tap only.
2- If the tapping range is larger than ±5%, normally the tests will be
performed with the two extreme taps in addition to the principal tap.

Repetition of Dielectric Tests


Repeating a Dielectric test on any transformer will be in two cases:

1- If the transformer has been in service and was serviced or refurbished, tests
will be carried out with 80% of the original test levels.
2- If the transformer is new and, then all tests will be repeated with 100% of
the original test levels.

Page 18
Power Transformers

LIGHTNING IMPULSE TEST (LI)

Test Purpose:

The purpose of the impulse voltage test is to secure that the transformer
insulation withstand the lightning overvoltage which may occur in service.

Test Precautions:

1- For Oil immersed transformers, test voltage should be of negative


polarity.
2- Bushing spark gaps shall be removed or gap may be increased to prevent
possible flashovers during test.
3- The test impulse wave shall be a standard full impulse wave
(1.2µs ±30% / 50µs ± 20%) where 1.2 is the Front time (T1) and 50 is
the Tail time (T2).
4- The Peak Value of the voltage applied during test is obtained from Table
(2) for the value of the highest voltage (Um) for the winding under test.
5- In case of flash over on spark gaps or test circuit during the test, this trial
will be disregarded and repeated.

Test Procedure & Description:

1- Test is normally performed on both windings of the transformer.


2- When testing one of the windings, the tested line terminal is connected to
the impulse generator and the remaining line terminals of the same
winding are earthed directly or through low impedance.
(See Connection Fig. below)
3- The line terminals of the other winding are together earthed directly or
through low impedance. (See Connection Fig. below)
4- The Neutral point, as well as the transformer tank will be earthed.
5- If the winding under test is tapped (Normally the H.V.) with a range
larger than ±5%, tapping is changed when testing each line terminal.
6- Impulse waveform is applied in the following sequence
a) One reduced full wave (50% ˜ 75%) of the rated test voltage peak
value is applied.
b) Three (3) successive full waveforms are then applied.

Page 19
Power Transformers

7- If the Neutral Terminal of the transformer has a rated insulation level, it


can be verified by applying a full wave impulse related to this insulation
level to the neutral terminal with all other line terminals earthed.

Connection Diagram for the Lightning Impulse (LI) Test

Acceptance Criteria:

* Test is considered successful if the transformer withstood the test and if there’s
no significant difference between both current and voltage transients recorded by
the OCR’s or the digital recorders during the reduced or the full impulse wave
application.

Page 20
Power Transformers

SEPARATE SOURCE VOLTAGE

Test Purpose:

The object of the test is to make sure that the insulation between the windings
and the insulation between windings and the earthed parts withstand temporary
overvoltages and switching overvoltages which may occur in service.

Test Precautions:

1- The R.M.S value of the voltage applied during test is obtained from Table
(2) for the value of the highest voltage (Um) for the winding under test.
2- Voltage supplied during the test shall be of a frequency not less than 80%
of the transformer rated frequency.

Test Procedure & Description:

1- Single phase voltage is applied to all line terminals of the winding under test
(line terminals are shorted together and connected to source.
2- The line terminals of the other winding are all earthed with the neutral
terminal and the tank body.
3- Test voltage is applied for 60sec.

Acceptance Criteria:

* Test is considered successful if the transformer withstood the test and no


collapse of the test voltage occurs.

Page 21
Power Transformers

SHORT DURATION INDUCED AC VOLTAGE TEST (ACSD)

Test Purpose:

The object of the test is to secure that the insulation terminals between the phase
windings, turns, tapping leads and terminals, withstand the temporary overvoltage
and switching overvoltage to which the transformer may be subjected during its
lifetime.

Test Precautions:

1- The R.M.S value of the voltage applied during test is obtained from Table (2)
for the value of the highest voltage (Um) for the winding under test. If the
winding under test is untapped, the voltage shall be as close as possible to
twice the rated voltage.
2- Test is carried out with a frequency higher than the rated frequency to
minimize magnetizing currents.
3- Test duration is obtained as following
a) If the test frequency is up to and including twice the rated
frequency, the test duration will be 60sec.
b) If the frequency is higher than twice the rated value, test duration
can be calculated according to the formula

Test Procedure & Description:

1- 3phase AC supply with high frequency is applied to the line terminals of one
winding with the line terminals of the other winding open circuited.
2- If the transformer has a neutral, it should be earthed during the test.

Acceptance Criteria:

* Test is considered satisfactory if the transformer withstood the test and no


collapse of the test voltage occurs.

Page 22
Power Transformers

FUNCTIONAL CHECKS ON MARSHALLING & REMOTE CONTRL PANEL

Following, the list of functional checks that may be performed to Marshalling


panel, as well as the remote tap changer control panel (RTCC):

1- Operation of cooling control circuit from marshalling box.


2- Operation of WTI / OTI.
3- Interconnection between the RTCC & the OLTC box mounted on transformer.
4- Indication circuits of RTCC.
5- Electrical operation of OLTC.
6- 2kV Megger test on all Control panel’s wiring.

Page 23
Power Transformers

OPERATION TESTS ON ON-LOAD TAP CHANGER

For details about operation tests performed on tap changer mounted on


transformer, refer to:

“Tap Changers – Testing and acceptance condition Report / Part 1 /

On load Tap Changers”

Page 24
Power Transformers

Part (6)
Reference Test Reports
 Crompton Greaves, 33/11kV 20/26MVA ONAN/ONAF Power Transformer.

Page 25
Power Transformers

Part (7)
Informative Documents

Page 26

You might also like