Professional Documents
Culture Documents
7. SUMMARY OF TENDER 64
8. APPENDICES
INTRODUCTION OF TENDER
FOR
INTRODUCTION OF TENDER
FILE NO 05/2019
Email kpcwee@gmail.com
Page | 1
INTRODUCTION OF TENDER
06. Project Team & Experience All tenderers are to provide a list of the proposed project
team, names, responsibility and similar project completed over the last 02 (two) years
including Client names and contact detail for review and reference checking.
Email lucas@boxdesignstudio.com.my
Page | 2
BOH PLANTATION SDN BHD
INSTRUCTION TO TENDERERS
FOR
INSTRUCTION TO TENDERERS
1. Tenders will be received for the CONSTRUCTION OF BOH TEA BOUTIQUE HOTEL AT BOH
SUNGAI PALAS TEA CENTRE, JALAN GUNUNG BRINCHANG, BRINCHANG, CAMERON
HIGHLANDS, PAHANG. Subject to the following condition:
a) Tenders will be considered for acceptance only on the Tender Form provided
which must be submitted under seal cover bearing no identity of the sender
b) Tender document shall only be issues to the tenderer upon the payment in cash
of :
Page | 3
INSTRUCTION TO TENDERERS
c) A contractor may not submit more than one tender in respect of this contract.
d) Mutilated or defaced tender forms may be rejected. Tenderer must ensure that his
tender submission including all accompanying document are firmly and
functionally intact in preferably, one piece. The employer does not hold itself
responsible for loss or misplacement or loose document.
e) The work or service, for which this tender will be received, shall be carried out in
accordance with drawing Nos. as specified together with the Agreement &
Condition of Building Contract and Specification attached thereto and such
detailed drawings and instruction as may be necessary during the Performance of
this work or service.
f) Tenderer shall state in his tender ONE SUM for thorough completion of work as
shown and described in the drawings and specification, inclusive of all
contingencies and liabilities to which he is or may become liable under the said
Drawings, Agreement & Condition of Building Contract and Specification.
- On no account is the tenderer for works allowed to insert any items or
condition of his own. The ONE SUM above should account for all terms and
condition as laid down in the drawings, Agreement & Conditions of Building
Contract and Specifications. Any clarification must be stipulated in a
covering letter and not at the back of the Tender Form or elsewhere.
- The contractor whose tender is accepted shall when required enter into a
formal contract with the Employer for the due execution of the works.
- Tender will remain open for acceptance for a period of 90 days from the day
the tender close
2. The employer does not bind itself to accept the lowest or any tender.
3. Tenderers will not be reimbursed for any expenses incurred in the preparation and
submission of the tender documents.
02/05/2019 WEE PL
DATE OWNER
Page | 4
BOH PLANTATION SDN BHD
FORM OF TENDER
FOR
FORM OF TENDER
1. These instructions to tenderers in so far as they may affect the execution of the Contract
shall be deemed to form part of the condition of the contract.
2. Each tender and all accompanying document and letter must be submitted in a sealed
cover bearing no indication of the identity of the sender. The cover shall be endorsed.
CONSTRUCTION OF BOH TEA BOUTIQUE HOTEL AT BOH SUNGAI PALAS TEA CENTRE, JALAN
GUNUNG BRINCHANG, BRINCHANG, CAMERON HIGHLANDS, PAHANG.
THE MANAGER,
PROPERTY DEPARTMENT,
Also in the tender submission, proposed Master work program shall be submitted for
evaluation by the Architect.
3. The Employer will not defray expenses incurred in tendering and will not be bound to
accept the lowest or any tender. No reason will be assigned for the rejection of any tender.
4. Tender document shall only be issued to the tenderer upon the payment of:
a. Non-refundable Tender Fee of RM100.00, in cash upon collection of tender
document & drawing.
Page | 5
FORM OF TENDER
b. Refundable tender deposit in the form of cheque made payable to BOX DESIGN
STUDIO SDN BHD for RM 3000.00. Tender deposit for unsuccessful tender shall be
refunded and tender deposit for successful tenderer will be retained for lithography
documentation charges.
5. Tender must be made out on the Form of Tender included in the Tender Documents.
Mutilated or defaced tender form may be rejected. Tenderer must ensure that his tender
submission includes all accompanying documents are firmly attached. The employer is
not responsible for any losses or misplacement of loose documents.
6. Tenderer shall visit the site ad shall make, or cause to be made on their behalf, local
enquires concerning the availability and cost of any plant required, storage,
accommodation, labor, temporary supplies of power, water supply and access, nature
of adjacent property, nature of site, subsoil site levels, working space, etc. and obtain for
themselves on their own responsibilities all other information which may be necessary for
making a tender and entering into contract and must examine the Contract Document
ion order to ascertain the matters as to which they will be deemed to have satisfied
themselves and the risks and obligation which they are to undertake.
7. The Tenderer shall note that the Condition of Contract and the Specification are to be
strictly enforced and that no extra charges or claims in respect of extra work will be
allowed unless such extra work is clearly outside the spirit ad meaning of the scope of the
Contract and is ordered in writing and claimed for the prescribed manner and at the
prescribed time.
8. The Tenderer shall note that the prices and rates inserted in the Summary of Prices and
Schedule of Rates are to be fully inclusive of the work described under the several items
including all costs and expenses that may be required in and for the construction of the
works described, whether specifically mentioned or not, together with all general risks,
liabilities and obligation set forth or implied in the document on which the Tender is based.
9. The Tenderer (whether or not he submit a tender) shall treat the detail of the document
as private and confidential.
Page | 6
FORM OF TENDER
10. If the tender is accepted, the Tenderer shall provide a Performance Bond amounting to
5% of the Contract Sum in form of cash or banker‟s guarantee from bank established in
Malaysia for the due performance of the Contract under the term of a Bond. The Bond
shall be deposited with the Employed prior to the commencement of work. As stipulated in
Clause 37.3 (PAM Contract 2006). The Performance Bond shall remain valid until three
(3) Months after the Completion Date. Where the Works would not be completed the
Completion Date, the Contractor shall before the expiry of the Performance Bond, extend
the duration of the Performance Bond to expire three (3) Months after the projected
Practical Completion of the Works.
11. If the Contractor fails to provide or maintain the validity of the Performance Bond in
accordance with the clause 37.3 (PAM Contract 2006), then without prejudice to any
other right and remedies which the Employer may possess, the Employer shall be entitled
to withhold or deduct an amount equal to the performance Bond from any payment
due or to become due to the Contractor as stipulated in Clause 37.4 (PAM Contract
2006)
12. The accepted approved Tenderer (if any) shall be notified of such acceptance by letter
before the expiry of the validity period. The said Tenderer shall within seven (7)days from
posting, or deliver if by hand, of notification of acceptance, deposit the Performance
Bond and Insurance Policies for Contractor –All- Risk and Workmen „s Compensation with
the Employer and shall produce fir inspections receipts of premiums paid for the
insurances. All insurances shall be deposited with Esther EHP Bhd.
13. As stipulated in Clause 33.1 (PAM Contract 2006). All fossils, antiquities and other object
of interest or value which may be found on the site or in excavating the same during the
progress of the works shall become the property of the Employer.
14. The tender of any Tenderer who had not complied with the foregoing instruction may be
rejected.
15. Tenders shall remain valid for 90 days from being closing date for the submission of
tender and no Tenderers may withdraw his tender within this period.
Page | 7
FORM OF TENDER
16. Under and subject to the Condition of tendering annexed hereto, the undersigned does
hereby tender and offer to execute, complete and maintain the works and supply all labor
and materials and everything named, shown, described and alluded to in, or to be inferred
from, the PAM FORM OF CONTRACT AGREEMENT (without quantities) Conditions of
contract or, for the works as above described, in conformity with the said Specification
and Drawing and under subject to the said Condition of Contract for the lump sum named
herein below.
17. The undersigned agrees to be bound by and submit to the said Condition of the
Contract and Specification and agrees that the priced Rates in Summary of Prices set
down therein by the undersigned have been scrutinized and agreed to by the Architect
as being reasonable, as by the Conditions of Contract provided, shall form a basis for the
valuation of interim certificates and any deduction variation or extra work which may
from time to time ordered by the architect.
18. And further, the undersigned agreed to complete the works within a period of 8 months
(Period to be proposed by tenderer) weeks from the Date of Possession of site or within
such extended time as by the Condition of Contract provided.
19. The total amount offered in this tender is the lump sum of Malaysian Ringgit:
Nine hundred and Seventy Four Thousand Nine Hundred Seventy Seven and Thirty Cents
Only (RM 974,977.30).
20. Whereas it is understood that you reserve to yourself the right to accept or to refuse the
tender, whether it is lower or higher than any other tender, or of the same amount, the
undersigned agrees that this tender shall remain valid and shall not be withdrawn within
ninety (90) days from the final date for submission of tenders.
21. And further, the undersigned agrees, in the event of your acceptance of this tender, to
execute the formal Contract Agreement and to furnish the Performance Bond, the
Workmen‟s Compensation and SOCSO Code No, Contractor All Risk Insurance Policies
and Produce the receipts for premium paid, for inspection within fourteen (14) days from
notification of acceptance.
Page | 8
FORM OF TENDER
22. The undersigned confirms, after personal scrutiny, that the document and drawings used
by the undersigned in compiling this tender are true copies of the document and drawing
included in the Tender Table Documents.
23. We understand that you are not obliged to accept the lowest or any tender received.
24. Unless and until a formal agreement is prepared and executed, this tender together with
the “Letter of Acceptance” of tender thereof, shall constitute a binding contract
between us (Employs and main contracts).
Page | 9
BOH PLANTATION SDN BHD
CONDITIONS TO TENDERING
FOR
CONDITIONS TO TENDERING
1. SCOPE OF WORK
The works to be constructed, completed and maintained under this Contract consists
of construction of proposed building as shown and detailed on drawings and
specification herein & any other works incidental to and necessary for the satisfactory
completion of the intended works.
3. LOCATION OF SITE
The site of the work is located on Boh Sungai Palas Tea Centre, Jalan Gunung
Brinchang, Brinchang, Cameron Highlands, Pahang.
4. NATURE OF CONTRACT
This contract is a firm lump sum contract. Fluctuation in the price of material, fuel,
wages, plants, labor, government duties, etc. in connection with this contract will not
be entertained.
Page | 10
CONDITIONS TO TENDERING
5. TENDERING PARTICULARS
(a) The rates set down by the tenderer, shall be held to include for providing and
delivering all materials, unloading, cutting and waste on materials, storage,
packing carriage and cartage, hoisting, all labor setting, fitting in position, use of
plant, scaffolding, trestles, supervision, establishment charges, profit and all other
labor and everything else necessary for the due and proper completion of each
item.
(b) No alteration shall be made by the tenderer to the clauses or items in the tender
document. The printed text will be rigidly adhered to and items or clauses must
be priced as described.
(c) Where the contractor leaves any item blank or inserts only a dash against any
items in the tender document the value thereof shall be deemed to be included in
the prices or rates of other items therein.
(d) The contractor is particularly requested to check all dimension shown or figured
on the drawing and obtained his own information on all matter s which may in any
way affect his tender as no claim for extras for any alleged ignorance in respect
thereof shall be entertained.
(e) The contractor shall be hold to have understood fully all matters concerning the
work to be carried out under this contract. Any queries must be settled with the
architect prior to the submission of the tender. No consideration shall be given to
any query raised by the contractor indication lack of comprehension of the work
to be done or material to be supplied after the acceptance of the successful
tender.
Page | 11
CONDITIONS TO TENDERING
8. DRAWINGS
The list of contract drawing is as shown in the list of drawing.
9. TEMPORARY ACCESS
The contractor shall provide and maintain the necessary temporary roads, sleeper
tracks, ramps, temporary cross over and bridges if necessary to and within the site etc.
and temporary site drainage as required during the execution of the work, and clear
away same at completion, and reinstate and make good any works disturbed all to
the satisfaction of the Architect. The contractor shall pay all charges and fees in
connection therewith.
Page | 12
CONDITIONS TO TENDERING
Page | 13
CONDITIONS TO TENDERING
(b) Allow for erecting and maintain all necessary scaffolding, staging, shoring and
strutting that may be required and remove at completion and make good all works
disturbed after removal.
(c) Allow for cost of mobilization and demobilization of all labor and machinery, plant
and equipment etc.
Allow for the provision, erection, maintain and removal of all necessary
latrines for the use of site staff and labor employed upon the works and at
places approved by Architect. The latrines are to be constructed to comply
with requirement of the local health authority.
Allow for moving any or all of the above as required by the progress of the
works and for re-erecting and maintaining same as described above
throughout the contract period.
Page | 14
CONDITIONS TO TENDERING
II. The site office will be use jointly by consultants / contractor/ sub- contractor/
client. The tenderer will provide their own office furniture. The installation of
temporary electricity and water supply for the site office will be provided by
the tenderer. The charges for the monthly electricity and water consumed will
be paid solely by the tenderer.
The contractor shall be fully responsible for the correct and accurate setting out of all
elevation, position, dimensions, alignments, profiles etc. of all parts of the works based
on the information supplied by the Architect. The setting must be carried out by a
competent licensed surveyor. If during the construction or maintain of the works, any
error is discovered in the positions, levels, dimensions, alignments profiles etc. in any
part of the works due to Contractor‟s error, the Contractor shall at his own cost,
rectify such error to the satisfaction of the architect. Construction shall not commence
until the setting out has been checked and approved by architect onsite.
Page | 15
CONDITIONS TO TENDERING
The contractor shall uphold, protect, and maintain or divert all existing drain, sewers,
water mains, electric and telephone cables and other property of a like nature and
make good or pay for making good damage thereto and any consequential
damage or loss arising out of such damage.
16. FOREMEN
The contractor shall provide full and adequate site management and supervision
during the progress of the works, shall keep one or more competent authorized site
agents or general foremen, approval by architect, on the site. Such agents or
general foremen shall give his whole time to the supervision and management of the
works, and must be able to receive and act on behalf of the contractor, all
instruction, direction or orders issued by the architecture or his representatives.
Page | 16
CONDITIONS TO TENDERING
(a) Physical damage to contractor works, plant and equipment and material
onsite. The contractor shall insure against all risks of loss or damage by fire and
/or accidental external means including Act of God, all works and building
constructed or in the course of construction in pursuance of or for the
purposes of this contract and all materials and other things delivered on to the
site and approved by architect and ready for incorporation in such works and
buildings and shall keep the same insured until such work, buildings and other
things respectively are handed over to the Employer and shall continue to
insure until the satisfactory performance of the contract on expiry of the
stipulated defect liability period.
The contractor shall insure:
01. The contract works for an amount not less than the contract sum
02. Removal of debris at 10% of contract sum.
(b) Liability for injury and property damage to third party (ies)
The contractor shall effect insurance to indemnify the employee in respect of
any liability, loss, claim or proceeding whatsoever whether arising at common
law or by statue in respect of personal injuries to or death of nay person
whomsoever, losses and / or damages to his properties arising out of or in the
course of or caused by the execution of the works due to any act or neglect
of the contractor, the employer and the architect, their servants or
representatives.
Page | 17
CONDITIONS TO TENDERING
(d) Any excess or deductible under the policy (ies) shall be for the sole account of
the contractor. The employer and the contractor shall not be called upon to
contribute to such policy excess or deductible.
(e) The policy (ies) shall be taken out in the joint names of the Employer, the
contractor, all consultants and all nominated sub- contractors.
Page | 18
CONDITIONS TO TENDERING
(d) In case of failure by the contractor to effect or renew such insurance the
architect may himself effect or renew such insurance and pay the premium in
respect thereof and deduct the amount so expended from any monies due
or to become due to the contractor.
(e) Nothing in this clause shall be construed to take away or to waive or in any
manner to modify the right of the employer to be indemnified by the
contractor in respect of all compensation, costs and other expenses
whatsoever which by reason of the contractor‟s default or otherwise become
payable by the employer under the said registration or other law.
(f) For the purpose of the contract, the contractor shall effect all the above
insurance to coincide with the contract period including defects liability period.
At the request of the architect, the contractor shall extend the insurance for
further period in compliance with contract condition.
(g) All insurance policies shall be effected with a company approved by the
employer.
Page | 19
CONDITIONS TO TENDERING
21. WATCHING
Allowing for keeping efficient watchmen on the works day and night and for providing
all necessary lighting, guard, barrier and all other safeguards for the prevention of fire,
accidents, theft and losses.
23. PROTECTION
Allow for the protection of all works from inclement weather and any other
circumstances which could cause damage.
Allow for the protection of all finished works from damage from any cause whatsoever
and accept responsibility for any damage caused and make good at his own
expense.
25. VARIATION
No variation or extras shall be held valid unless authorized in writing by the architect.
This clause shall be strictly enforced and it shall be the responsibility of the contractor
to inform the architect in writing of any variations or extras not so recorded. Allow for
all costs involved in the preparation of variation orders. Should the architect instruct
to omit any item or section of the works in whole or in part, the contractor shall not
payment of fees and charges.
Page | 20
CONDITIONS TO TENDERING
Page | 21
CONDITIONS TO TENDERING
The ownership and copy write of all photographs and negatives shall be vested with
the employer and are not to be used without their permission.
31. SAFETY
The contractor shall be responsible for carrying out the whole of the works, provisions
and requirements of the contract or seeing to that they are carried out by all
concerned, in a thoroughly safe ad satisfactory manner, and in particular shall:
(a) Strictly conform to the requirement of any bye-laws, regulations, order ad advices
relating to the safety of persons on or about the site, made by any public authority
and government having jurisdiction in the matter.
(b) Ensure that all tackle, gear, staging, scaffoldings, ladders, machines, winding,
arrangement‟s and other equipment used in connection with the works shall
conform to the requirements of any Government regulation in relation thereto
and in any case be adequately strong and safe to use. Immediately
discontinue any practice or remove any equipment which becomes or is likely to
become dangerous or unsafe.
(c) Provide safety helmet and harness for use by consultants and workers.
(d) Remove promptly from the works any employee or representative who by his
conduct could create any dangerous or nuisance to himself or others.
(e) A complete first aid kit shall be kept and the site.
Page | 22
CONDITIONS TO TENDERING
The contractor shall be responsible for restricting his workmen only of the site of the
new works, and shall prevent trespass into adjoining property ad existing building ion
which work is not in progress and he shall undertake properly substantially and
effectively to reinstate and make goof all damages and shall indemnify the employer
against all claim for damages as no responsibility or liability whatsoever shall be
undertaken by the employer in respect of any if the foregoing.
Page | 23
CONDITIONS TO TENDERING
38. CO-ORDINATION
The contractor is responsible for the proper co-ordination, direction and supervision
for all the works of the contract. For this purpose he shall provide all necessary to
ensure close detailed and competent supervision of all part of the works.
41. DIMENSIONS
Written dimensions are to be preferred in every case to scaled dimensions. All scaled
dimensions may only be used after confirmation by the architect.
Page | 24
CONDITIONS TO TENDERING
Page | 25
CONDITIONS TO TENDERING
The contractor is to note that during the period of maintenance the Employer can
occupy the filled/ excavated land and carry out construction works with any type of
equipment.
49. EXPLOSIVES
In the event of explosives being used under any part of this contract, the contractor
shall obtain himself with the necessary permit or license from the appropriate
authority and shall abide by all Government regulation instruction relating to the
transport, handling, transport and use of explosives.
Page | 26
CONDITIONS TO TENDERING
The contract shall be liable for any accident, damage or injury to any person or
property resulting from the use of explosives. When necessary the Contractor shall
display warming sign and flags and shall in all cases a warning to be sounded prior to
firing. The contractor should determine, during tendering whether any explosive or
pneumatic tools are required for the successful carrying out of the work. If through his
investigation and found that the above procedures are necessary, he must allow
extra expenses in the tender.
Page | 27
CONDITIONS TO TENDERING
In the event that the Architect approval is obtained for works forming part of the
permanent works outside normal working hour, and requiring supervision by the
Architect/ Engineer, the Contractor will be required to reimburse the reimburse the
Employer for the overtime expenses incurred for such supervision. The days of receipt of
overtime expenses billed by the Employer. Falling to do so, the employer may deduct
from money due or to become due to the Contractor under this Contract.
Page | 28
CONDITIONS TO TENDERING
TABLE OF SAMPLE
APPENDIX CLAUSE
III. ) 21 To be advised
Ascertained Damages )
desires to tender
Certificates ) Monthly
Page | 29
CONDITIONS TO TENDERING
Valuation
Commencement, from )
S. O. Order to
Commence
will be issued
Page | 30
CONDITIONS TO TENDERING
Note:
a) All information regarding the site have been provided in good faith and the contactor is
to refer to the site plan in relation to the actual site for the exact location, dimensions,
areas of site and any other information relevant to his tender.
b) Every effort has been made to ensure the reliability of the information shown on drawing
but the contractor shall be deemed to have considered this information critically during
the preparation of his tender and has carried out such further investigation and test on
site as he considers necessary.
c) The group levels shown on the drawings are based on recent ground survey. The
contractor shall be deemed to have checked the accuracy of the levels shown on the
drawings and to have made allowance in his tender for the effect („other than upon
quantities measured in accordance with the contract) or discrepancies between the
various drawings and of variations which may have taken place or may take place after
those levels were determined. The contractor shall be entitled to additional rates of
payment on ground of inaccuracy of the ground or other levels shown on the drawings.
d) The contractor shall apprise himself of all difficulties of working due to the nature of the
site. He shall appraise himself of the type of material to be excavated, obstruction to be
demolished and anything else likely to affect the cost and shall include in his tender sum.
e) The contractor shall be deemed to be taken all possible weather condition into account
when preparing his tender and shall not be entitled to extra payments by reason of the
occurrence or effect of excessive rainfall, tidal water, high winds or any other
meteorological phenomena.
f) The contractor shall be deemed to have fully acquainted himself with the requirements
of the Local Authorities which may in any way hinder his work.
g) The contractor shall be absolutely and solely responsible for the method employed in
carrying out the works and for the safety and security of all temporary works and
constructional plant not withstanding any examination by the Architect/ Engineer or their
representatives.
Page | 31
CONDITIONS TO TENDERING
Note:
The contractor‟s particular attention is drawn to the fact that this tender is a lump sum fixed
price tender and his tender sum is to allow for all condition affecting the cost of the works. All
tenderers are required to fill in the rates as indicated in this schedule. The rates inserted here
in will be used for ascertaining the prices of variation under this contract. Tenderers who do not
fill in the schedule of rates will not be considered for this tender and their tender submission
will be rejected.
In pricing of execution for trenches, the contractor is to allow for the additional depth and
width in trench excavation, including subsequent backfilling as specified, that he considers
necessary for joining work, or for the installation of valves, etc. all trenches are to be kept free
from water at all times.
Where the terms “as described” or “as specified” occur, they shall mean as described or
specified in these specification. The contractor‟s attention is drawn to the requirements to
setting out of pipe lines including the provision of pegs, sight rails, bonding rods, etc and
facilities for checking by the architect.
The contractor is to note that fitting for all types of pipes are not measured separately. The
rates to be inserted by the contractor for pipes are to include for all fitting, bends, elbows,
tees, junctions, sockets, collars, connectors, brackets. Straps, flanged ends, nuts, drops,
offsets, reducers. Inspection eye pipe pieces (disc seal inspection pipe), short lengths, back
nuts, plugs or stopper and the like. Rates for pipe are also to include cost of preparation of
ends of pipes before jointing, cost of inspection and testing pipes and as well as cost of
jointing materials, equipment, labor.
Page | 32
BOH PLANTATION SDN BHD
SPECIFICATIONS (PREAMBLES)
FOR
SPECIFICATION (PREAMBLES)
1. GENERAL
1.1 The quantity of work to be executed under this Contract shall, for the purpose of Tendering,
be deemed to be that stated in the Bills of Quantities and shall be the basis of the Contract
Sum.
1.2 Each item shall have a separate rate or price and extension set against it. Items against
which no price is entered shall be considered as covered by other prices and rates in the Bills
of Quantities.
1.3 The Bills of Quantities shall be read in conjunction with the Conditions of Contract, the
Specification, the Drawings and such other relevant documents forming part of the
Contract. The rates and prices entered in the Bills of Quantities shall provide for compliance
with all the provisions of the said Conditions.
1.4 Pricing
1.4.1 The rates inserted in the Bills of Quantities shall be firm and not subject to fluctuation or any
other factor throughout the entire tenure of the contract.
Unless otherwise specifically stated in the Bills of Quantities, rates shall include everything
necessary to complete the work as described and in accordance with the Contract
Documents including:
a) labour and supervision, including all on-costs such as but not restricted to:
Page | 33
SPECIFICATIONS
b) materials and all costs in connection therewith, including but not restricted to:
i. manufacture expenditure
ii. customs and Excise duty
iii. packaging
iv. loading and unloading
v. handling
vi. transport and cartage
vii. insurances, including breakages and damage whilst in transit
c) cost of mechanical and non-mechanical plant, equipment and tools including operator,
fuel, oil, maintenance and all other costs in connection therewith
a) all temporary work as necessary and its subsequent removal including scaffolding,
staging, supports, protective screens, other protection measures and the like
b) all permanent work as necessary in supports, fixings and the like, whether shown on
drawings, specified or otherwise required to properly complete the work
Page | 34
SPECIFICATIONS
d) setting out
f) giving all necessary notices to, and taking all other necessary action in respect of,
government departments, local authorities, utility companies and other bodies having
jurisdiction over the Works
g) obtaining all necessary licenses and paying all necessary fees and charges
h) testing as specified or required including the supply of additional materials and samples
for testing
i) samples, mock ups, prototypes, quality benchmarks and other benchmarks as specified
or required
j) shop drawings and other drawings, calculations, literature and documents as specified
or required
k) providing warranties, guarantees and the like as required by the Contract Documents
m) additional fire and smoke stopping measures as set out in the Specification and as
required by local authorities, Bomba and other bodies having jurisdiction over the Works
Page | 35
SPECIFICATIONS
q) carrying out work in accordance with the requirements of the Specification including,
inter alia, all fixings, all ancillary materials, goods and accessories and all additional
labours and other work.
1.4.3 Where work is wholly or partly Contractor design the rates shall include:
a) the production of all necessary design information to the approval of the Superintending
Officer including design drawings, working drawings, structural calculations and all other
information necessary to evaluate the Contractor‟s design
1.4.4 Where work is specified by, or referred to, a manufacturer or proprietary product the rates
shall include for carrying out the work in accordance with the manufacturer‟s
recommendations, including all accessories, unless described otherwise
The rates shall be inclusive of all ancillary work and expenditure whether separately or
specifically mentioned or described in the Contract Documents or not, which are either
indispensably necessary to carry out and bring to completion the Works, or which may
contingently become necessary to overcome difficulties before completion.
Items shall be realistically priced. The Contractor shall substantiate any rates required by the
S.O., prior to the signing of the Contract. Failing which, he will be considered not to have
submitted a bona-fide tender.
All like items shall be priced at the same rate. In valuing variations the lowest rate for any
individual item will be applied if unit rates vary from Bill to Bill or Section to Section.
The value of any item unpriced (or with a dash against it) shall be deemed to be included in
the prices or rates of other items in the Bills of Quantities. Each item shall be priced
individually; lump sums or percentage additions will not be accepted.
Page | 36
SPECIFICATIONS
2. METHOD OF MEASUREMENT
2.1 Unless otherwise stated in this Preamble, the Bills of Quantities, the Conditions of Contract, or
Specification, the methods of payment and measurement shall be generally in accordance
with the Standard Method of Measurement of Building Works for use in (Malaysia) 1st Edition
(Metric) March 1976 and shall be nett as they are finished and fixed in the Works.
Deviations from the Standard Method of Measurement are not specifically stated or
itemized and the Contractor in pricing the bills is deemed to have full knowledge of the
deviations and accepted the method of measurement as contained in the Bills of
Quantities. Should any item be unclear, the Contractor shall seek clarification during tender
stage. No claim whatsoever will be subsequently entertained in this Documents, the
Employer Representative‟s decision shall be final and binding on the Contractor and the
Contractor shall not be entitled to any cost or time claim whatsoever.
Where room/location references are stated in certain items in the Bills of Quantities, they are
annotation for the Consultant Quantity Surveyor reference only.
Where work is wholly or partly Contractor‟s design the quantities shall be based on the
drawings produced by the Employer‟s designers showing the design intent. Quantities will
only be adjusted if the result of an instruction from the Superintending Officer. Quantities will
not be adjusted if the actual quantities vary due to modifications necessary to complete the
design, nor will additional items be measured if found to be necessary to complete the
design. Approval of any Contractor‟s design which requires additional items or higher
quantities in order to meet the original design intent does not constitute a variation.
Page | 37
SPECIFICATIONS
3.1 Certain items in the Bills of Quantities represent composite works of uniform type of
construction. The tenderers shall themselves ascertain the quantities of the component works
involved in the items and price them accordingly.
4. ABBREVIATION
4.1 The following abbreviations have been used in the Bills of Quantities:
M3 Cubic Metre
M2 Square Metre
M Linear Metre
MM Millimetre
Tonne Metric Ton
KG Kilogramme
CF Cubic Foot
SF Square Foot
LF Linear Foot
NO Number
PRS Pairs
DOZ Dozens
TON Imperial Ton
CWT Hundred Weights
LBS Pounds Avoirdupois
OZ Ounce Avoirdupois
SQRS Squares - 100 feet super
SWG Imperial Standard Wire Gauge
BG Birmingham Gauge
BS The latest Standard for a particular building material or component issued by
British Standards Institution, 2, Park Street, London WI
CP British Code of Practice - Current Edition
MS Sirim Standard
AS Australian Standard
Page | 38
SPECIFICATIONS
5. DEFINITION
5.1 Wherever the term “allow for” is used in any items in the Bills of Quantities it shall mean that
the sum entered by the Contractor shall include all costs, charges and profits in respect of
the works or obligations referred to and shall be at the Contractor‟s sole risk. Payment for
such item shall be made at such times and in such installments as the S.O. may deem fit and
proper, taking into account the extent to which the works have been completed or
obligations met by the Contractor.
5.2 Wherever the term “provide a sum for” or „Provisional Sum‟ is used in any item in the Bills of
Quantities and a sum is inserted by the S.O. to cover the cost of any particular item of work,
the sum inserted shall be dealt with in accordance with Clause 30 of the Conditions of
Contract unless otherwise directed.
5.3 Wherever the word “supply” is used in any item in the Bills of Quantities it shall mean that the
article, material, plant or equipment etc., which are supplied under such item shall become
the property of the Employer.
5.4 Wherever the word “provide” or “provision of” or “providing” is used in any item in the Bills of
Quantities in the context of providing some article, material, plant or equipment (as distinct
from “provide a sum for” or „Provisional Sum‟ as described in para 5.2 above) it shall be
taken to mean that the Contractor shall make necessary arrangements to make available
for the use of the Employer or the S.O. such article, material, plant or equipment and the
sum entered by the Contractor shall include all costs, charges and profit in respect thereof.
At the end of the Contract Period or such other times as defined in the Bills of Quantities
ownership of such article, material, plant or equipment shall revert to the Contractor unless
otherwise stated. The Contractor‟s rates and prices shall include for removal, dismantling
and reinstatement of site where necessary.
5.5 The expression “Extra over” used in any item in the Bills of Quantities shall mean that
payment calculated at the rate inserted against that item is additional payment over and
above the particular item for which it is stated to be “extra over”.
5.6 Wherever the word „S.O.‟ appear or used in any part of tender document, it shall mean the
Architect.
Page | 39
SPECIFICATIONS
6. TEMPORARY WORKS
6.1 Unless specially provided for in separate items in the Bills of Quantities the cost of all
temporary works shall be deemed to be covered by the rates entered in the Bills of
Quantities and shall include the following:
a) Temporary works for the service of the works as a whole e.g., gantries, temporary
works, structures for concrete mixing plant, block yard equipment, work yard sites.
b) Temporary works to form and construct permanent works described under particular
items in the Bills of Quantities, e.g., timbering for trenches, temporary sheet piling for
drainage, forming of bunds and pumping to keep works free of water.
c) Temporary works which are required for establishing and maintaining an access to
the Site and works areas to facilitate transport of the Contractor‟s labour, materials
and plant.
d) Removal of all temporary works and disposal of rubbish and reinstatement of site.
7. MOBILISATION
7.1 The item for Mobilisation in the Bills of Quantities shall be full payment for mobilising and
bringing to site all labour, plant and equipment and incidentals necessary to perform the
Contract works and for the removal of same on completion of work and shall include:
a) Transport and assembly of all items of constructional plant and equipment or such
other plant as may be required for the performance of the works.
b) Dismantling at the work site and removal of all constructional plant and equipment
so that the Site is left in a neat and tidy condition to the satisfaction of the S.O.
7.2 The sum entered by the Contractor against the items for “Mobilisation” in the Bills of
Quantities shall be paid in installments in proportion to the progress of the works.
Page | 40
SPECIFICATIONS
8. CONCRETE WORK
Concrete work shall include for hoisting, pumping, pouring, packing, rodding and vibrating
concrete around reinforcement, completely filling the formwork to the shape required,
protecting, patching, curing and forming all necessary construction joints, cutting rebates,
grooves, chases, mortices, holes and any other sundry items of a like nature and building in
all wire ties, bolts, lugs nailing blocks, anchors and the like.
The rates for concrete shall also be deemed to include for providing trial mixes, tests on
materials and finished product, including non-destructive tests on and off-site.
Concrete beds and slabs shall include for laying on any type of sub-base, laying to falls or
cambers and preparing and leaving surfaces to receive screeds or pavings including laying
in bays and all necessary formwork to joints between bays.
The rates for concrete work are deemed to include for the following worked finishes types
specified within these contract documents:-
a) Tamped Finish : Tamp surface of poured concrete with edge of a board or beam to
give an even texture of parallel ribs
b) Trowelled Finish (Hand) : Float concrete to an even surface with no ridges or steps,
then immediately commence curing as specified in the Structural engineer‟s
specification. When the concrete is suitably stiff, hand trowel to give a uniform
smooth but not polished surface, free from trowel marks and other blemishes and
suitable to receive floor finishes by others
Surface water channels, concrete curbs and the like shall include for all angles, intersections
ends, outlets and any other sundry items of a like nature.
Precast concrete units shall include for all necessary reinforcement, moulds, holes rebates,
notching, sinkings, mortices and the like and for hoisting, bedding, jointing and pointing in
cement mortar (1:3).
Page | 41
SPECIFICATIONS
Small concrete components may have been assumed to be cast in situ or precast units. The
Contractor is to note that he may adopt either method of construction but work shall be
paid in accordance with the description in the Bills of Quantities.
Waterproofing membranes are measured nett area in contact with the surface.
1. laps and joints, turnups at angles, including bonding adhesives, bituminous sealant at
ends and interface connections with other waterproofing systems reinforcing mats
2. skirtings, upturns and upstands, angle fillets, collars around fittings etc.
3. narrow widths
5. fitting and sealing around inlets, outlets including all pipe connections, projections
7. test on joints
Page | 42
SPECIFICATIONS
9. FORMWORK
The cost for formwork shall include for all raking and circular cutting, small quantities, narrow
widths, treating surfaces in contact with concrete with mould oil or other approved
preparation as specified, all supports, staging, erecting, easing, striking and removal.
Rates for formwork shall include erection, raking and circular cutting, splayed edges,
notching, allowance for overlap and waste, passing at angles, battens and filleting to form
chamfered edges, strutting and in the case of formwork to vertical surfaces like walls,
columns and the like strutting over 12'0" high, nailing, bolting, wedging, easing, striking and
removal and oiling or lime-washing surfaces in contact with concrete before concreting.
“Sawn Formwork” shall mean formwork to produce concrete surfaces suitable for plastering
or tiling.
“Wrot Formwork” shall mean formwork to produce fair face concrete surfaces suitable for
direct application of decorations.
In case of wrot formwork, the rates shall also include for lining the formwork with suitable
material as directed by the S.O. and for cleaning fins remaining on the surfaces of the
concrete after removal of the formwork including rubbing down with carborandum stone,
making good any honey-combing or irregularities and for leaving the concrete with a true
and even surface.
Page | 43
SPECIFICATIONS
10. REINFORCEMENT
Mild steel or high tensile steel rod reinforcement shall include for cutting to lengths, waste,
hooked ends, cranks and bending as required and for securing with and including No. 16
gauge annealed iron tying wires at all intersections, distance blocks and spacer bars
including chairs, for brushing and cleaning all rods free of rust, dust, mill scale, dirt, oil and
any other deleterious matters, fixing in position and supporting whilst concreting.
Steel fabric reinforcement shall include for all preparatory work for mild steel rod as
described above and shall also include for laps, all bending, cutting, notching around
obstruction, waste, securing with and including No. 16 gauge annealed iron tying wires and
for brushing and cleaning.
The weight of steel reinforcement excludes both the weight of tying wire and any allowance
for rolling margin, spacers, chairs, weight of weld and the Contractor is to include for these
items.
b) providing, assembling, handling and moving tensioning plant, equipment and tools
together with standby units and spares; and subsequent removal from site
Page | 44
SPECIFICATIONS
g) allowance for strands projecting beyond anchorages and jacking equipment, and
initial slips
i) providing special temporary support and working platforms for tensioning and
grouting
Each item of brickwork and facings shall include for all rough and fair cuttings, over sailing
and receding courses, rough relieving and discharging arches, wedging and pinning, raking
out joints for and pointing flashings, bedding plates, bedding and pointing wood frames,
parging and coring flues, labour eaves filling, plumbing, angles, forming square and rebated
reveals, cut squints or birds-mouths, notches, forming, leaving or cutting chases, holes and
mortices, cutting and pinning and making good and other sundry items of a like nature.
Each item of blockwork shall include for all special made blocks, all rough and fair cuttings,
over sailing and receding courses, free ends, plumbing, angles, forming square and rebated
reveals, notches, cutting and pinning at top, cutting at ends and around openings, cutting
and bonding to intersections, angles and irregular angles, raking out joints for and pointing
flashings, bedding and pointing wood frames, labour eaves filling, forming notches, forming
leaving or cutting chases, holes and mortices, cutting and pinning and making good and
any other sundry items of a like nature.
Brick reinforcement shall include for all laps, cutting and waste.
Damp proof course shall include for all laps, angles, cutting, labour and materials required in
laying and pointing exposed edges.
Page | 45
SPECIFICATIONS
Each item of masonry work shall include for all rough and fair cuttings, wedging and pinning,
forming grooves or raking out for and pointing flashings, bedding plates, bedding and
pointing frames, paging and coring flues, labour eaves filling, salient angles, squints, quoins,
birdsmouths, splays, rounded angles, forming reveals, forming, leaving or cutting chases,
holes and mortices, cutting and pinning and making good and any other sundry items of a
like nature.
All necessary templates shall be included for circular work and battering work.
Rates shall be inclusive for finishing fair face on all exposed faces.
Roof covering shall include for all laps and for all straight, skew and circular cutting at eaves,
verges top edges, abutments, valleys, hips, intersections etc. and for all holes for pipes and
the like and for subsequent deep, making good. Ridges shall include for stopped and fair
ends. Hip capping shall include for cut intersections of ridges and hips and the like.
Bituminous felt, membranes and the like, roof covering shall also include narrow widths, small
quantities, temporary rules, covering up, protecting after laying and cleaning off on
completion, all labour to form channels, gutters, arrises, fair edges, etc., all cuttings and
working around pipes and the like, cement and sand fillets, expansion joints. Skirting etc. shall
include for short lengths, angles, ends, forming chases in structure.
Flashing shall be held to include for forming grooves in structure and pointing or sealing in.
Page | 46
SPECIFICATIONS
Carpentry work shall include for cutting, notching, boring, sinking, pelleting, fitting, trimming,
mitring, halving, morticing, tenoning, dovetailing, scarfing and wedging and for all ends,
splayed edges, short lengths and temporary supports and any other sundry items of a like
nature.
Carpentry work shall also include nails, screws and where plugged, including drilling all holes
for plugging in walls etc. irrespective of the materials encountered.
Joinery work shall include for wrot surfaces, all cuttings, notching, holes, housing ends,
mitring, ends and shaped ends, angles, junctions, heading joints, short lengths, tongued
joints, splay or rounded edges, chamfers, rebates, grooves, punching nail heads in exposed
timber and filling in with matching putty, screwing and pelleting and any sundry items for the
proper carrying out of the work, including all necessary nails, screws, plugs and the like.
Ironmongery shall include for samples, fitting, cutting, sinking, boring, morticing and for the
supply of screws to match, oiling, easing and adjusting all moving parts, taking off before
painting and refixing and leaving in perfect working order.
Ceiling and wall linings shall include for narrow widths, small quantities, working in panels,
planting on with panel pins, brads or nails, cuttings and wastes, cutting holes and forming
openings including extra framings, etc. for exhaust fans, light fittings, air-condition air-grilles,
access panels, pipes etc. and all other sundry items of a like nature.
No allowance has been made in the weight of steel for rolling margin and steelwork is to
include for this item.
Metalwork shall include for preparing and priming the metalwork with one coat of red oxide
zinc phosphate primer before delivery, except where otherwise described, and all necessary
hoisting to the required levels.
Page | 47
SPECIFICATIONS
Steelwork shall include for preparing and applying the specified post fabrication and post
erection treatment and painting.
Welded work on site or in shop shall include for all labour, materials and appliances.
All items shall include or setting in position, building in, tightening nuts and fixing as
described.
All items where applicable shall include for cutting to length and shapes required, mitring,
scribing, welding, grinding and polishing of weld.
Rates for aluminium works shall include everything necessary whether described herein or
otherwise for the complete installation of each unit in accordance with the Specifications,
Drawings and approved Shop Drawings. The rates shall also include the cost of design, all
testings required, samples, weatherseal and hardware, bolting lug/anchors etc. for fixing to
surrounding structures, all necessary metal framing and subframe members and supports
fixed to structure, steel support and fixing accessories, integral opening lights and windows,
associated insulation and vapour barriers, distance pieces, flashings, fire and smoke stop,
reveals, set backs, projections, edge trimming, protection etc, façade lightning protection
system, structural silicone sealant, cement filleting around frames and sealant pointing at all
exterior joints including all painting works. The rates shall also include for edges, gaskets and
end caps, cleats, brackets, channels and additional materials required for bending to profile
and shape.
Page | 48
SPECIFICATIONS
In-situ and tile pavings are to include, as applicable, for cleaning, hacking or slurrying of sub-
base to form key, wetting surfaces or soaking tiles before application, for narrow widths and
small quantities and temporary rules, for all raking and circular cutting, working or fitting up
to and around pipes, gratings, sanitary and other fittings and any other sundry items of a like
nature and for making good to this and other trades.
In-situ work is to include for all rounded edges, arrises, narrow widths, small quantities,
temporary rules and making good and other sundry items of a like nature.
Each item of skirtings, risers, moulded or rounded edges, channels and the like shall include
for short lengths, formed, cut and purpose-made angles, junctions, ends and for making
good up to and around pipes, fittings and the like and any other sundry items of a like
nature.
In-situ and tile finishes shall include for all polishing as described.
Plastering shall include for additional raking out joints of brickwork or hacking concrete
surfaces, as applicable to form key, wetting surfaces before application, providing
„Expamet‟ to timber or metal surfaces and joints between brickwork and concrete, for
narrow widths and small quantities, temporary rules, joints between different types of
plastering, internal angles, arrises, quirks, throats, groin points and other intersection of
curved surfaces, rounded coves and external angles not exceeding 25mm radius and
mitres, stops, etc., on cornices, mouldings, enrichments, coves, skirtings, gutters and strings,
all making good and any other sundry items of a like nature. Rates for plastering shall also
include for shadow gap plaster stop bead. This shall also apply to other similar works such as
Shanghai plaster, washed aggregate, granolithic paving, etc.
Lineal items of plastering such as skirtings, risers, channels and the like shall include for all
short lengths, stops, angles, ends, junctions, arrises, throating, fair edges and any other
sundry items of a like nature.
Page | 49
SPECIFICATIONS
In-situ terrazzo work shall include for additional raking out joints of brickwork or hacking
concrete surfaces, as applicable, to form key, wetting surfaces before application, for
narrow widths and small quantities, temporary rules, internal angles, mitre angles, arrises,
joints between various types of terrazzo, quirks, throats and any other sundry items of a like
nature, fitting around pipes and for all making good to this and other trades.
Wall and floor tilling shall include soaking tiles in water before laying, for rounded edges,
internal and external angles, arrises, narrow widths and small quantities, cutting and fitting
up to or around frames, grilles, air bricks, sanitary and other fittings, pipes, brackets and any
other sundry items of a like nature. This shall similarly apply to the laying of marble and
granite.
Lineal items of tile skirtings, angles, capping, mouldings and the like are to include for short
lengths, cut and factory-made angle, junctions, ends and making good and for any other
sundry items of a like nature.
Metal lathing shall include for laps, all cutting, holes, notching and any other sundry item of a
like nature and for pointing all cut edges and damaged staples etc. after erection, with a
protective coat of approved bituminous paint.
17. PLUMBING
All types of pipes are to include for all necessary short lengths cutting and waste and fixing
to tiled of plastered surfaces including making good.
Fittings to all types of pipes are to include for all necessary extra joints, cutting and waste.
Rates for all pipes are to include for fixing with approved clips, brackets or holderbats as
required.
Galvanised steel or wrought iron pipe shall include for all short lengths, sockets, connectors,
elbows, bends, fire bends, tees, diminishing pieces, plugs, crosses, lapped ends, splay cut
ends and the like and for fixing to tiled or plastered surfaces including making good.
Copper pipes shall include for all short lengths, made bends and running joints.
Page | 50
SPECIFICATIONS
Rates shall also include for jointing between diferent types of pipe, and jointing of pipes to all
types of fittings.
Rates for sanitary fittings shall include for all accessories and fixing to tiled or plastered
surfaces or unplastered blockwall including all necessary items for connecting and jointing
to services.
18. GLAZING
Glazing shall include for all gaskets and/or glazing felt, setting blocks, weatherseal,
waterproofing, raking and circular cuttings, waste, risks of breakage, cleaning all glass inside
and out, replacing all cracked, scratched or broken panes and leaving in good condition
on completion.
Painting shall include for all necessary preparation for surfaces, as specified, stopping and
additional scaffolding required, all extra labour involved in external work and all cutting into
line.
Painting shall include for the use of multi-colours to walls, doors, frames and the like.
Painting of pipes and gutters shall include for painting on all tacks, wall hooks, holderbats,
brackets, ears and the like.
Painting of vertical surfaces and soffits shall include for painting two finishing coats to all
electrical wiring and battens, roses, conduits, switches, junction boxes, blocks and the like, in
contact with the surface to match the colour of the surface to which they are fixed.
Page | 51
SPECIFICATIONS
20. STONEWORKS
Generally
The preambles for item (19) – Floor, Wall and Ceiling Finishes shall equally apply herein.
a) moisture testing to ensure that base screed to receive flooring is dry enough to
receive them
d) cutting, drilling and fitting as required for permanent penetrations through stone
caulking etc.
j) cleaning and the removal of all dirt, mortar or plaster dropping and making good
necessary water and oxalic acid and polishing to a smooth and even finish
m) protection from damage or staining with plastic sheet, plywood or other necessary
means
Page | 52
SPECIFICATIONS
a) moisture testing to ensure that base screed to receive cladding is dry enough to receive
them
d) cutting, drilling and fitting as required for permanent penetrations through stone
e) providing movement, expansion and construction joints including Latham strip, caulking
etc.
j) cleaning and the removal of all dirt, mortar or plaster dropping and making good
l) protection from damage or staining with plastic sheet, plywood or other necessary
means
bracket, anchors, dowels, fixings, anchors, fasteners and miscellaneous metal supports
and closures as required, of concealed type and all ancillary works as specified for a
Page | 53
BOH PLANTATION SDN BHD
BILL OF QUANTITES
FOR
Proposed Interior Design for Boh Tea Boutique Hotel at Boh Sungai Palas Tea Centre, Jalan Gunung Brinchang,
Brinchang, Cameron Highlands, Pahang.
1.0 PRELIMINARIES
1.5 General up keep site and clearing debris upon completion work
1.12 Provide temporary hoardings and site access period of fit out
work
Page | 54
BILL OF QUANTITIES
Proposed Interior Design for Boh Tea Boutique Hotel at Boh Sungai Palas Tea Centre, Jalan Gunung Brinchang,
Brinchang, Cameron Highlands, Pahang.
2.2 All toilet sanitary ware, wardrobe, kitchen cabinet and door. LS 4,200.00
2.4 Skirting
Page | 55
BILL OF QUANTITIES
Proposed Interior Design for Boh Tea Boutique Hotel at Boh Sungai Palas Tea Centre, Jalan Gunung Brinchang,
Brinchang, Cameron Highlands, Pahang.
Page | 56
BILL OF QUANTITIES
Proposed Interior Design for Boh Tea Boutique Hotel at Boh Sungai Palas Tea Centre, Jalan Gunung Brinchang,
Brinchang, Cameron Highlands, Pahang.
4.1 Screed
50mm cement and sand (1:3) screed to receive floor finishes m² 987 49.00 48,363.00
at corridor, living area, and hotel room.
4.3.2 600mm x 600mm Hampton Neve Polished Marble tiles at m² 388 98.00 38,024.00
corridor and living area
4.3.3 150mm x 600mm Birch Forest Gray Wood Plank Porcelain Tile m² 409 23.00 9,407.00
at all hotel room
Page | 57
BILL OF QUANTITIES
Proposed Interior Design for Boh Tea Boutique Hotel at Boh Sungai Palas Tea Centre, Jalan Gunung Brinchang,
Brinchang, Cameron Highlands, Pahang.
5.1.2 900mm (W) x 2400mm (H) x 50mm walnut veneered solid nos 11 920.00 10,120.00
wood fire resistant doors with frames and fittings at hotel room
5.1.3 900mm (W) x 2400mm (H) x 50mm laminated waterproof PVC nos 11 300.00 3,300.00
door panel at hotel washroom
6.1 Drystop fibrous plaster glass ceiling 9mm thick c/w 12mm x m² 987 39.20 38,690.00
25mm galvanized channel system, including one coat of skim
coat, edge trimming and fixing accessories.
- hotel room, corridor and living area
ITEM (5) DOOR & WINDOW + ITEM (6) CEILING WORKS CARRIED TO SUMMARY 86,410.40
Page | 58
BILL OF QUANTITIES
Proposed Interior Design for Boh Tea Boutique Hotel at Boh Sungai Palas Tea Centre, Jalan Gunung Brinchang,
Brinchang, Cameron Highlands, Pahang.
7.1.1 13 amp power point in PVC conduit at hotel room, living area Nos 56 100.00 5,600.00
and hotel washroom
7.1.2 Floor mounted power point at living area and corridor Nos 12 135.00 1,620.00
7.1.3 Automated roller blind point at living area and hotel room Nos 9 180.00 1,620.00
7.1.5 Air condition point at living area and hotel room Nos 17 235.00 3,995.00
- Down lighting point at hotel room, corridor, living area and Nos 96 73.00 7,008.00
hotel washroom
- Eyeball spot lighting point at living area and hotel room Nos 28 73.00 2,044.00
- Bedside table lighting point at lobby reception, main Nos 26 73.00 1,898.00
exhibition hall and audio-visual room
Page | 59
BILL OF QUANTITIES
Proposed Interior Design for Boh Tea Boutique Hotel at Boh Sungai Palas Tea Centre, Jalan Gunung Brinchang,
Brinchang, Cameron Highlands, Pahang.
8.1 Copper inlet pipe for cool water c/w hacking, coring work and
necessary fitting as following:-
- WC inlet pipe Nos 13 470.00 6,110.00
- WC hand bidet Nos 13 470.00 6,110.00
- Basin inlet pipe Nos 15 470.00 7,050.00
8.2 Outlet PVC pipe c/w hacking, coring work and necessary
fitting as following:-
- WC outlet Nos 13 450.00 5,850.00
- Floor trap outlet Nos 24 320.00 7,680.00
- Basin outlet Nos 15 300.00 4,500.00
Page | 60
BILL OF QUANTITIES
Proposed Interior Design for Boh Tea Boutique Hotel at Boh Sungai Palas Tea Centre, Jalan Gunung Brinchang,
Brinchang, Cameron Highlands, Pahang.
9.1 Bed
9.1.1 1935mm (L) x 2032mm (W) Beauty Platinum Spring Grove
Nos 4 10,204.00 40,816.00
13-inch Extra Firm King-size Innerspring Mattress Set at hotel
room Type A
9.2.2 500mm (L) x 500mm (W) x 600mm (H) Belham Living Carter
Nos 4 750.00 3,000.00
Mid Century Modern Veneer Side Table at hotel room Type A
Page | 61
BILL OF QUANTITIES
Proposed Interior Design for Boh Tea Boutique Hotel at Boh Sungai Palas Tea Centre, Jalan Gunung Brinchang,
Brinchang, Cameron Highlands, Pahang.
9.4 Chair
9.4.1 650mm(L) x 550mm(D) x 790mm(H) Oliver Upholstered Nos 12 680.00 8,160.00
Wingback Swivel Armchair at living area
9.4.2 470mm(L) x 460mm(D) x 550mm(H) Scoop low back chair with Nos 22 225.00 4,950.00
steel legs at hotel room
9.5 Sofa
9.5.1 Granada 3-1-1 set polyester fabric sofa with colonial blue at Nos 2 6,400.00 12,800.00
hotel room Type A
- 3 seater : [823mm (W) x 2164mm (L) x 876mm (H)]
- 1 seater : [823mm (W) x 942mm (L) x 876mm (H)]
9.5.2 823mm (W) x 1557mm (L) x 876mm (H) Granada 2 seater Nos 9 2,150.00 19,350.00
polyester fabric sofa with dark gray at living area
9.5.3 889mm (W) x 2692mm (L) x 850mm (H) Trevor 4 seater sofa Nos 3 11,211.00 33,633.00
with gibson fabric at living area
Page | 62
BILL OF QUANTITIES
Proposed Interior Design for Boh Tea Boutique Hotel at Boh Sungai Palas Tea Centre, Jalan Gunung Brinchang,
Brinchang, Cameron Highlands, Pahang.
10.1 Headboard
10.1.1 1980mm (L) x 75mm (W) x 2020mm (H) custom made solid Nos 4 4,200.00 8,400.00
walnut finished king size headboard with black metal frame
at hotel room Type A
10.1.2 1600mm(L) x 75mm(W) x 1800mm (H) custom made solid Nos 9 4,000.00 36,000.00
walnut finished queen size headboard with black metal
frame at hotel room Type B and C
Page | 63
BOH PLANTATION SDN BHD
SUMMARY OF TENDER
FOR
SUMMARY OF TENDER
LUCAS WEE PL
FONG
Signature of Tender Signature of Witness
Page | 64
BOH PLANTATION SDN BHD
APPENDICES
FOR
A Concrete
Concrete 1200 x 600 x C1 SUZUKA SHOWROOM Living Area, Natural grey
4mm Lot 6492, Jalan Haji Hotel Room color with
Concrete Abdul Manan, off Jalan And Corridor stain finishes
coating Meru, 41050, Klang,
Selangor, Malaysia.
03-32910722
B Stone
Porcelain 600 x 600 x S1 Guocera Sdn. Bhd. Hotel -
8mm 15A Jalan 51A/219, 46100 Washroom
Nashville Petaling Jaya, Selangor
Porcelain D.E. Malaysia.
floor tiles 03-7959 8147
Page | 65
APPENDICES
E Ceiling
Plaster Drystop CP1 Kayfern White Plaster Living Area, Including one
Fibrous Ceiling Sdn Bhd Hotel Room coat of skim
Plaster Glass 38M, Jln. KIP 2, KIP Ind And Corridor coat, edge
Ceiling Park,55200 Kuala Lumpur, trimming and
Malaysia. fixing
03-6272 0078 accessories
F Paint
Loxen P1 Nippon Paint (M) Sdn Bhd Corridor Seals and
Concrete & Lot I, 17, Jalan SU 4, Taman And Hotel adhere to
Mansory Perindustrian Subang Room concrete and
Primer Utama, 40300 Shah Alam, bricks
Selangor.
1-800-88-2663
G Glazing/
Glass Aluminum G1 Reliance Home Sdn. Bhd. Hotel Room Profile Finished
Tempered Clerestory No. 62 Ground Floor, And Living with Power
Glass Window with Taman Connaught, Area Coating and
6mm Tempered Jalan Cerdas, Cheras, Anodized
Glass 56000 Taman
Connaught, Federal
Territory of Kuala Lumpur.
012-219 8455
H Carpentry
Headboard Custom Made CA1 Woodpecker Carpentry Hotel Room Profile Finished
Solid Walnut (M) Sdn Bhd with Black
Finished 16, Jalan mewah 3/4, Metal Frame
Pandan Mewah, Hata
Study Desk Custom Made CA2 Industrial Centre, 68000 Hotel Room -
Natural Oak Ampang Jaya, Selangor
Mounted Desk 012-201 0583
Page | 66
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT