LOGISTICS PANEL ASSESSMENT b. Unilever RFM Ice Cream Inc.

– Selecta Ice cream


sachet
OVERVIEW c. Lamoiyan – personal & household care products
1. Production Planning (Hapee, Dazz sachet)
- Orders d. Derm Pharma – personal care (Gluta White & Firm,
- Production Schedule Derm A, Derm Plus)
- Job Order e. Pet One Inc – dog food (SM Bonus dog food)
- Machine Schedule f. Invivo NSA Phils – chicken feeds (Warhawk)
g. Refinette Cosmetic Industry – cosmetic products
2. Raw Material Planning (Myra E)
- Computation h. ACS Manufacturing Corp – household (Pride
- Purchasing Detergent)
i. IMSPI – powdered drinks (Coffee Joe)
3. Report Making j. INAVET Nutrition Technologies Inc – animal
- Waste Monitoring supplements (Swine Lean Pak, Sow Performance Pak)
- Speed
- Machine Efficiency PRODUCTION SCHEDULE
- Machine Utilization 1. Preparation and Computation of Production Schedule
- Receive order and 3 months’ projection from sister
4. Costing companies
- Alternative raw materials - For sister companies such as Rebisco, First Baker
Corporation, Best Baker Food Inc, Multirich Food Corporation,
CONVERTING Suncrest Foods Inc, and SPI Corporation computation of
quantity to be produced are as follows
PRODUCTION PLANNING 4 weeks’ order + 2 weeks’ advance production
1. Receive Order from Client - For JBC and Pinnacle, computation of quantity to produced
2. Production Schedule is based on order only
3. Job Order – based on approved Prod Sched - For external clients, Production Schedule is based on order
4. Distribute Job Order only
- Ink Matching, Printing, Lamination, Slitting - Get Daily Finished Goods Stock Position from Warehouse as
- Warehouse of 6am, 27th day of the month
- QC - Get Daily Stocks In Process Monitoring from Converting as
of, 27th day of the month
RECEIVE ORDER FROM CLIENT - Secure Printing Balance as of 6am, 27th day of the month
1. INTERNAL CLIENTS from Production Planner
 Sister companies – monthly order - Get Delivery Balance from Sales Coordinator as of 6am, 27th
Orders and 3 months’ projection thru fax / email day of the month
 JBC and Pinnacle – Purchase Order ang gamit - Compute final quantity to be produced
- Submit PS to Senior Analyst & Asst. Logistics Head for
Internal Clients checking and/or revisions
a. Rebisco – biscuits - Submit PS to Logistics Head for approval
b. Suncrest Foods, Inc. – snack and cake products
(doowee, chocotops, Mrs. Goodman, funky) JOB ORDER (Existing)
c. JBC Foods Corp – nuts and seed snacks (happy, 1. Get Prod Sched from Prod planner
dingdong. Dragonseed) 2. Check material specs from Updated Product Information
d. Multirich Food Corp – cream paste and wafer Sheet
products (krimstix) 3. If existing product, mark exact repeat if without change,
e. SPI – candies and REPEAT WITH CHANGE if there are changes made.
f. SFI Multimix – dairy products (creamline)
Note: If REPEAT WITH CHANGE get Product Change Notice to
2. EXTERNAL CLIENTS serve as a basis of changes and indicate changes on JO
- receive Purchase Order from BDO of Sales Department
- PO must be approved by Managing Director 4. Input total qty to produce based on CVT Prod Sched (kg)
- no particular time for order

External Clients
a. Cosmetique Asia – cosmetic products (Silka Papaya,
soap and lotion sachets)
FORMULAS:
Total gsm = (printing substrate x density) + ink gsm + adh gsm - If exact repeat, no need to check all JO details
+ (laminant film x density) - Verify product name and quantity based on
production schedule
Weight per roll = (total gsm/1000) x (roll width/1000) x length - Indicate delivery date based on required delivery
per roll dates on PO
- Check qty of films to be used based on WHS Raw
Number of rolls = total qty to produce / weight per roll Material Stock Position and Slow Non Moving
Report. If no available film, recommend alternative
Meters to produce = Number of rolls x (length per film to be used.
roll/number of outs across) / waste allowance - Return to Jr. Analyst if there are revisions, if no
revision forward to Log Head for approval
Note: Waste Allowance 6. Distribute 8 copies (QA, Production, IMT, PRT, LAM, 2 SLT,
500kg – 1000kg = 15% (for double process in Lamination only) WHS)
Below 2000kg = 10%
2000kg and above order = 7% JOB ORDER (NEW PRODUCT)
1. Receive copy of Technical Specifications from R&D
Ink gsm 2. Receive cylinder requisition slip and New Product Notice
- Based on previous JO or on updated 3 months’ from Technical Sales Engineer
documentation of Daily Ink Dry Weight Monitoring from QC 3. Send winding direction from customer to determine their
required delivery figure and indicate it in JO
Ink Requirement computation per color 4. Get Production Schedule from Production Planner
- Get Ink and Solvent Consumption Report of Ink Matching to 5. Indicate the JO number and coordinate with Ink Matching
determine the previous meters produced and ink consumed Supervisor for the color guide number
of each product 6. Include the name of the product and the customer’s name.
For Outside Job, PO# is included
Ink Requirement = (Previous Ink Consumption / Previous 7. Since it is a new product, MARK NEW JOB
meters produced) x qty to produce in meters 8. Compute and include the following
- Input total quantity to produce based on CVT Production
Slitting guide to guide = repeat across x number of outs + Schedule.
2mm - Get cylinder size, repeat around, across and number of outs
across from cylinder RS
Constants - Input the following based on Tech Specs: Printing substrate
Printing substrate: (printing substrate thickness/1000) x (thickness & width), sealant, ink gsm, adhesive gsm and
density x (film width/1000) length per roll

Laminant film: (laminant film thickness/1000) x density x (film 9. Specify the type of Printing, reverse or surface, type of ink
width/1000) 10. Adhesive
11.Color sequence, solvent ratio
PRINT: ((printing substrate thickness x density x print
gsm)/1000) x (film width/1000) JOB ORDER (REPLACEMENT RUN)
1. Receive replacement memo from converting
LAM: ((printing substrate thickness x density + print gsm + 2. Make a new copy from previous JO that needs to be
adh gsm + laminant film thickness x density)/1000) x replaced
(((printing substrate film width + laminant film 3. Type the word replaced under JO #
width)/2)/1000)

SLIT: ((printing substrate thickness x density + print gsm + adh


gsm + laminant film thickness x density)/1000) x (repeat
across/1000)

TRIM: (((printing substrate film width + laminant film


width)/2) – (repeat across x number of outs across)) /
(printing film width + laminant film width)/2 x 100

5. Submit JO to Senior Analyst & Asst. Log Head for checking


- If repeat with change, check JO details pertaining to
changes made. Verify details based on the attached MATERIAL PLANNING
documents (RS, Product w/ change notice, QC
Memo, and other documents) Raw Material Computation
1. Get quantity to produce from Production Schedule 14. Ask accounting clerk to sign on the yellow copy as a proof
2. Get Daily Raw Material Stock Position from Warehouse as of acceptance
of 6am, 27th day of the month 15. File the yellow copy for traceability purposes
3. Get Raw Material Daily Running Balance and Printed Stocks 16. Confirm delivery from supplier two days before expected
(for sealant films only) from production as of 6am, 27th day of date of arrival at Omni
the month Note: Lead time on raw materials deliveries is 1 week before
4. Secure Printing Balance from Production Planner as of production run
6am, 27th day of the month (for sealant films only)
5. Secure PO Balance from Raw Material Coordinator as of MACHINE SCHEDULING
6am, 27th day of the month 1. Use the following reports as basis for machine scheduling
6. Compute for the final quantity to be ordered - Production Schedule
- Imported & Local Raw Materials: 1-week buffer - Orders
7. Schedule expected date of departure from supplier - Raw Material Inventory
considering the following 2. Receive Raw Material Stocks Inventory from WHS to
- Lead time determine if there is enough quantity of raw materials for
- Sailing every JO. If there are shortages, check with client the
- Releasing duration of their stocks (finished goods and raw materials). If
- Arrival at Omni must be 1 week before production possible to extend delivery schedule, ask for adjustment,
8. Prepare the following reports otherwise below are possible options:
- Film price update (OPP, HSOPP, Matte OPP, Coex OPP, - Look for the possible size to be used preferably with
VMCPP, Plain CPP, Nylon, CorPET, ChemPET & VMPET) the least trimmings next to the original size
- Raw Material Requirements (for PE films for tolling) - If 1st step still not applicable delete number of out/s
- Raw Material Computation for adhesive across depending on available film with no or least
9. Submit to Asst. Logistics Head & Logistics Head for checking trimmings
and/or revision - Get the approval of Managing Director for material
10. Submit Raw Material Computation to Managing Director loan to other converters
for approval (for imported raw materials only) 3. Consider the quantity of the products to be produce in
choosing machine
RAW MATERIAL ORDERING - Medium run use IKD and Daejin
Objective: To provide proper direction in purchasing raw - Long run use Long New Machines
materials having the right specifications and enough quantity 4. If possible, schedule the same sizes to minimize set up time
for guaranteed and continuous production due to IRR change
5. Number of hours in printing
1. Receive approved RS from Jr. Analyst Formula:
2. Check RS if with complete details ((Quantity to produce in meters) / (Actual Speed of Printing
- Name of item Machine x 60 minutes)) / 24 hours
- Quantity - Actual Average speed in DJ and IKD = 150 mpm
- Application - Actual Average speed in LN = 170mpm
3. Ask for duration of stocks and target delivery date from Jr. 6. Start-up time
Analyst Formula for start up time with change IRR on set up
4. Make a call to existing suppliers (minimum of 3 suppliers) = Ending time of last job + (60 minutes set up time/24 hours)
or raw material to ask for the latest price. Formula for start up time without change IRR on set up
5. Choose among the suppliers while considering the = Ending time of last job + (35 minutes set up time / 24 hours)
following: 7. Determine the ending time of JO in Printing
- Lowest price Formula: Start up time + number of hours to be consumed in
- Terms of payment printing
- Availability of stocks 8. Indicate delivery date
- Allocation 9. Submit machine schedule to Logistics Head for approval
6. Prepare PO 10. Distribute the approved machine schedule to printing, Ink
7. Submit to Logistics Head for checking and to Managing Matching, QA, Ink Making and Manufacturing Head
Director for approval with the following attachments: Note:
- Previous PO (if with price changes, prepare half Sensitive products, krimstix – bawal sa bostik, morfree ang
sheet with recommendation) gamit
8. If disapproved, revise PO
9. If approved, send PO to supplier thru fax or email REPORT MAKING
10. Call the supplier and confirm receipt of PO Waste Report – profit loss
11. Inform supplier on target delivery date Printing Waste 3%
12. Log PO details on PO Monitoring Sheet
13. Forward original and pink copies of PO to accounting clerk Production / Splicing 1.8
Ink 0.3 7. Submit Production Schedule of Ink Making to Senior
Film 0.15 Analyst and Asst. Logistics Head for checking
Cylinder 0.2 8. Submit Production Schedule of Ink Making to Logistics
Machine Trouble 0.2 Head for approval
Utilities Trouble 0.10
Slitting 0.25 B. Preparation of Job Order
1. Prepare JO based on approved PSIM
Lamination Waste 1.2% single process, 2.5% double process 2. Submit JO to Senior Analyst and Asst. Logistics Head for
Slitting Waste 0.03% checking
3. Submit JO to Logistics Head for approval
Overall
Short Run 15% (less than or equal to 60000) C. Distribution of Job Order
Medium Run 10% (60001 – 190000) - Give copy of Job Order to Ink Making Department
Long Run 7% (190001 and above)
PRODUCTION SCHEDULE
Pag less than 1% pwede na iclose ung job, isama na sa Objective: To provide proper directions in generating
consolidated waste report accurate production schedule for Ink Making and to meet the
required quantity of inks to produce
Machine Efficiency
Standard Efficiency printing m/c 80% 1. Receive Production Schedule
Lamination 2. Receive the following:
SF 50%, Ext 80%, SB 75%, PP 90% a. Client’s Order – from outside clients only
(Rotopack, Keiser, Primeflex, JAC, Markenburg, etc.
Speed = total output / production time b. Ink Making Stock Inventory – from IMK
Printing: DJ 150, LN 170 Department as of 6am, 27th of the month
Lamination: c. Daily Pure Ink Monitoring – from Ink Matching
VMCPP 240, CPP 300 (SF) section as of 6am, 27th of the month
VMCPP 150, CPP 120 (SB) d. Ink Daily Stock Position – from WHS as of 6am,
Ext 110 27th of the month
e. Printing Balance – from Production Planner as of
Utilization 80% 6am, 27th of the month
- Output f. Stock Summary – from Jr. Analyst of Converting
- Efficiency and speed 3. Compute Omni Stocks
Formula: Omni Inventory = IMK stocks + IMT stocks + WHS
Orders mataas, taas utilization stocks
Eff and speed mababa, taas utilization 4. Compute Production Balance (as of 6am, 27th of the month)
Standard Utilization Formula:
Actual Utilization Production Balance = Last month’s JO + Last last month’s
Production Balance – (Last last month’s output from 27 th day
to last month’s output until 26th day)
INK MAKING Example:
November Prod’n Bal = Nov JO + Oct Prod’n Bal – (Oct output
PRODUCTION PLANNING from 27th to Nov output until 26th day)
5. Get delivery balance from Sales Coordinator (as of 6am,
A. Preparation and Computation of Production Schedule 27th of the month)
1. Receive Production Schedule of Converting and Printing 6. Compute Present Month’s Ink Requirement
Balance as of 6am, 27th day of the month a. Input printing balance
2. Receive orders from outside clients (Rotopack, Keiser, b. Input quantity to be produced (based on Converting
Primeflex, JAC, Markenburg, etc.) Production Schedule)
3. Get the following as of 6am, 27th of the month c. Converting Requirement in kilograms = Printing
- Ink Inventory from Ink Making Department balance + Quantity to be produced
- Daily Ink Stock Position from Warehouse Number of slit rolls = Converting requirement in kilos /
Department Weight per slit roll
- Daily Pure Ink Monitoring from Ink Matching Section d. Converting Requirement in meters
4. Compute for Production Balance (as of 6am, 27 th of the Requirement (in m) = (Computed no of slit rolls x length per
month) roll) / (No of outs across x (100% - Waste Allowance))
5. Compute for final quantity to produce Note: Waste allowance (for Converting) are as follows
6. Prepare separate Production Schedule of Ink Making for 500 kg – 1000 kg = 15% (for double process in Lamination
Reverse and Surface Ink only)
Below 2000 kg = 10% 1. Get the quantity to be produced and production balance
2000 kg and above = 7% from Production Schedule of Ink Making
e. Basic Color previous ink consumption (per product per 2. Get the following as of 6am, 27th day of the month
meter) = (Ink formulation x Ink Consumption) / Quantity run - Ink Making Raw Material Inventory from Ink Making
in meters Department
Note: Data is based from Ink and Solvent Consumption from - Daily Stock Position of Raw Material of Ink from
Ink Matching Section Warehouse Department
f. Required Quantity of Basic Color in kilograms = Basic color - Daily Pure Ink Monitoring from Ink Matching Section
previous ink consumption per meter x Converting (for PE bags inventory)
requirement in meters - PO balances from Raw Material Coordinator
g. Apply to all basic colors 3. Compute final quantity to be requested
h. Sum all the values per color to get the requirement for the 4. Schedule ETA of raw materials at Omni
month - Imported & Local Raw Materials w/ 1 week buffer
7. Compute Mid Next Month’s Requirement 5. Submit Raw Material Computation to Sr. Analyst & Asst.
Formula: Logistics Head for checking
Mid Next Month’s Req’t = Projection (based on Stock 6. Submit RMC to Logistics Head for approval
Summary) / 2 7. Prepare Requisition Slip
8. Compute 1 week buffer 8. Submit Requisition Slip to Sr. Analyst & Asst. Logistics Head
One week buffer = Mid Next Month’s Requirement / 2 for checking
9. Compute Quantity to produce of ink per color 9. Submit RS to Logistics Head for approval
a. Reverse inks 10. Give copy of RS & schedule of ETA at Omni of RM to RM
Quantity to produce = Omni Inventory + Production Balance – Coordinator for PO making
Delivery Balance (outside client) – Present Month’s Ink
requirement (Converting Reverse Products) – 2 weeks REPORT MAKING
advance req’t – 1 week buffer 1. Daily Production Summary Report
b. Surface inks quantity to produce is as per requirement only - machine, product name, material description, total
(outside clients) since no Surface Products already. input, total output, solvent loss, % waste
10. Submit to Sr. Analyst & Asst. Logistics Head for checking
and to Logistics Head for approval 2. Machine Efficiency
= (man hours – downtime) / manhour
JOB ORDER (INK MAKING)
Objective: To provide proper directions in making monthly Mixer = 80%
job order for Ink Making Department to be able to give the Grinder = 85%
right type of raw material, formulation, type of ink and Machine trouble = 5% max per month (report to Sir Alex)
quantity of ink to be produced.
3. Stock Summary (Report to Sir Alex)
1. Input the following Stock (End October) + Produced (Start – End November WHS,
- Job Order Making IMK) + Reprocessed (Start – End Nov) – Delivery (Start – End
- Date of Job Order Nov) = Available (end Nov)
- Product Name
- Input quantity to produce per color 4. Waste Monitoring (Report to Sir Alex)
2.Arrange and input raw materials according to types (resins, Input = Output + Waste
additives, pigments, solvent) OPP Lam Inks – for outside (benta)
3. Compute the quantity of raw materials to be used per color Omni ginagamit na ink
Formula: Quantity per color x Raw Material Formulation Flexilam Inks
Note: Update formulation based on latest approved OPP Lam Ink
formulation provided by Ink Making Department Roto CP
4. Show the total quantity required of raw materials per CDI Lamiall
product - 1 month projection
5. Print and sign JO - Local
6. Submit JO to Senior Analyst and Asst. Logistics Head for - 1 month requirement
checking
7. Submit JO to Logistics Head for approval Expected Ink Requirement
8. Once approved JO, give 2 copies to Ink Making Production - Based 3 previous job (average)
Head
Ink Requirement = Average previous job (3job/run) x quantity
MATERIAL PLANNING (INK MAKING) present order
A. Raw Material Computation
Actual = last run x present order
- PE Bags
Machine Utilization -
Standard vs projection 10% Formula:
Standard vs actual 5% Total Requirement per month = (Quantity to produce in pcs x
Standard weight per pc x Mixing Ratio) + 1% allowance

MOLDING Final quantity to be requested = Total requirement for


present month + Total requirement for next month – WHS
PRODUCTION SCHEDULE stock – Production stock – PO balance

JOB ORDER (MOLDING) Note: Refer to Molding Product Information dated December
1. Input the following 19, 2013 for specification, mixing ratio and packing
- JO Number
- Date of Job Order 6. Duration
- Product Name (Arrange items per product’s part) For excess:
- Quantity to produce in pcs (from Production Number of days = (Excess / Next month’s projected
Schedule) requirement) x 30 days
- Standard weight per piece in grams
- Type of raw materials to be used per product (PVC, For additional:
PET, PP resin, masterbatch) Number of days = (Additional / Next month’s projected
- Mixing ratio of raw materials (virgin resin, recycled requirement) x 30 days
resin, masterbatch)
2. Compute the required quantity of raw materials to be used Duration date = Number of days + Cut off
Formula:
3. Sign the printed JO Expected Target Arrival (Omni Plant) = Duration date – 7 days
4. Submit Asst. Logistics Head and Logistics Head for approval
5. Give a copy to Molding Department Production Head 7. Submit RMC to Senior Analyst and Asst. Logistics Head for
checking and to Logistics Head for approval
RAW MATERIAL COMPUTATION (MOLDING) 8. Submit RS to Senior Analyst & Asst. Logistics Head for
Objective: To provide proper directions in computation of approval
Moulding raw material and to ensure enough stocks raw
materials to be used in production

1. Input quantity to produce


- Quantity to produce in Manila (Based on Production
Schedule of Manila)
- Quantity to produce in Bukidnon (Based on Prod
Sched of Bukidnon)
- Production Balance of Bukidnon and Manila
2. Receive the following
a. Plastic Moulding Daily Stock Position of Raw Materials
- From WHS as of 6am, 27th day of the month
b. Daily Raw Material Status
- From Molding as of 6am, 27th of the month
c. PO Balance (Incoming Shipment)
- From Raw Material Coordinator as of 6am, 27th
d. Section Head Daily Report (for Bukidnon only)
- From Molding, 6am, 27th
e. Delivery / Stock Summary
- From Jr. production Analyst (Molding)
3. Input received data
4. Computation must be good for 2 months
a. Present month – based on Production schedule
b. Next month – based on Projection (from Delivery /
Stock Summary)
5. Compute final quantity to be requested (additional / excess
) for the following raw materials:
- Resin
- Masterbatch