Professional Documents
Culture Documents
Learning objectives
MAIN
SOURCE:
Manufacturing
Planning
and
Control
Systems
for
Supply
Chain
Management (5th Edition,
2005),
by
Thomas
Vollmann,
William
Berry,
Clay
Whybark,
and
Robert
Jacobs
1
23/09/19
Definition
The
MPS is
a
statement
of
what,
how
much,
and
when end
items
are
planned
to
be
produced
over
planning
periods.
2
23/09/19
3
23/09/19
1. Production
Plan
MPS
must
be
reconciled
with
Production
Plan
2. Demand
data
• Sales
forecast
• Customer
orders
• Safety
stocks
• Field
warehouse
requirements
3. Inventory
status
4. Ordering
policy
4
23/09/19
End items
MPS/FAS
Builds Finished MPS Builds
Items to Forecast Components &
Subassemblies
MTS MTO
ATO
Raw Materials
FAS Configured
Final End Items
Lead-time
Assembly of
Exact Configuration for Delivery
OP T I ONS
MPS
Builds
Components
&
Subassemblies
Lead-time for
Manufacturing
Raw Materials/
Components
5
23/09/19
Planning Horizon
Terminologies:
• Planning
horizon
à the
length
of
future
periods
included
in
the
MPS
(e.g.,
12
weeks)
• Planning
period
(or
time
bucket)
à the
time
unit of
one
period
(could
be
week,
day,
etc.)
• Normally
the
planning
horizon
should
be
longer
than
the
lead
time
(from
the
receipt
of
the
order
to
the
delivery
of
the
items)
Period 0 1 2 3 4 5 6 7 8 9 10 11 12
MPS
Planning Horizon
Planning Horizon
6
23/09/19
• It
is
an
engineering
document
that
specifies
the
ingredients
(or
subordinate
components)
required
physically
to
make
each
part
number
or
assembly.
Single-‐level
BOM
• Comprises
only
those
subordinate
components
that
are
immediately
required
(not
the
components
of
the
components).
Indented
BOM
• Is
a
list
of
components,
from
the
end
item,
down
to
the
raw
materials
(it
does
show
components
of
the
components).
7
23/09/19
Bill-‐of-‐Material
Product
Structure
Tree
Bicycle(1)
P/N 1000
1 2 3 4 5 6 7 8
8
23/09/19
1 2 3 4 5 6 7 8 9
Forecast 5 5 5 5 5 5 15 15 15
Available 25 30 35 40 45 50 45 40 35
MPS 10 10 10 10 10 10 10 10 10
On-hand 20
1 2 3 4 5 6 7 8 9
Forecast 5 5 5 5 5 5 15 15 15
Available 20 20 20 20 20 20 20 20 20
MPS 5 5 5 5 5 5 15 15 15
On-hand 20
9
23/09/19
1 2 3 4 5 6 7 8 9
Forecast 5 5 5 5 5 5 15 15 15
Available 15 10 5 30 25 20 5 20 5
MPS 30 30
On-hand 20
The lot size is to cover demand for a certain future periods.
The
MPS
applies
a
fixed
lot
size
(batch)
of
30,
which
is
scheduled
when
available/projected
available
balance
would
fall
below
5
units
10
23/09/19
2 3 4 5 6 7 8 9
Forecast 10 10 10 10 10 15 15 15
Available
MPS
On-hand 10
The top MPS doesn’t look OK. Make a revision to make it OK in a lower table.
1 2 3 4 5 6 7 8 9
Forecast 5 5 5 5 5 5 15 15 15
Orders 5 3 2
Available 15 10 5 30 25 20 5 20 5
ATP 10 30 30
MPS 30 30
On hand 20
11
23/09/19
1 2 3 4 5 6 7 8 9
Forecast 5 5 5 5 5 5 15 15 15
Orders 5 3 2
Available 15 10 5 30 25 20 5 20 5
ATP 10 30 30
MPS 30 30
On hand 20
Forecast 10 10 10 10 10 15 15 15
5 5 2 New
order
(week
2
-‐ 4)
Orders
Available 10
ATP
MPS
On hand 10
Calculate ATP in week 2
Create a feasible MPS with lot size of 30
ATP = MPS + On hand - (Orders)
12
23/09/19
MPS Stability
• A
stable
MPS
translates
into
stable
component
schedules,
which
means
improved
performance
in
plant
operations.
• Too
many
changes
– lower
productivity
• Too
few
changes
– lower
customer
service
levels.
Frozen Schedule
• This
means
that
for
the
more
recent
time
buckets
it
will
be
very
difficult
(but
still
negotiable)
to
change
the
sequence
in
which
the
orders
will
be
processed.
Time Fencing
13