You are on page 1of 16

Lesson 16 – Aggregate Planning

The Production Plan


The aggregate plan shows the overall production by families of product.
The aggregate plan can not be used for production because it
. . . .

is at the group level rather than the individual product level.


-

Once the aggregate accepted, it is broken down into more details to give
Master Schedule (MS)
-
That is, the aggregate plan must be broken down into specific product
requirements.
. . . .

- .

Based on the specific products, then calculating detail of manpower,


material and inventory requirements.

The MS‘disaggregate’ the aggregate plan and specifies number of


individual products to be made in, typically, each week.
MS gives a detailed timetable of planned output for each product and
-

is the first time due-dates are associated with individual products.


- -

Disaggregation

The MS is constrained by the aggregate plan.

That is, the overall production in the MS must equal the production
specified in the aggregate plan.

There may be some differences to allow for short-term variations,


incorrect forecasts, capacity constraints, etc., but should be small.

Copyright – Harland E. Hodges, Ph.D 16-1


Lesson 16 – Aggregate Planning

Master Schedule (MS)


The overall objective of the MS is to devise a detailed timetable for
individual products, which allows the aggregate plan to be achieved as
efficient as possible.

The MS is a presentation of

 the demand, including the forecast and the backlog (customer orders
received),
 the MPS - master production schedule (the supply plan),
 the projected on-hand (POH) inventory, and
 the available-to-promise (ATP) quantity.

The MS shows quantity and period of specific products. It usually


-
covers 6 to 12 weeks.

The MS then is used as the basis for short term planning.

Relationship of Master Scheduling to other Manufacturing


Planning Control (MPC) activities

The master schedule (MS) is Creates demand Creates demand


Is the “key” in
developing the
a key link in the manufacturing requirements requirements master
schedule
planning and control chain.

The MS interfaces with


marketing, distribution
planning, production planning,
and capacity planning.

The MS drives the material


requirements planning (MRP)
system.

Master scheduling calculates Is the “key”


link
the quantity required to meet Calculates net
requirements
demand requirements from all
sources Input-Output Control &
Operation Scheduling

Copyright – Harland E. Hodges, Ph.D 16-2


Lesson 16 – Aggregate Planning

Master Production Schedule (MPS)

Master schedule states quantity and delivery time of specific


products. -

It says we need 100 push lawnmowers in January.


But it does not say how we get it - from production, or
from inventory.

The master production schedule (MPS) is the primary output of


the MS process. It is the “plan” for providing the supply to meet
the demand.

MPS: Quantity and period of planned production.

MPS determines
the Promised Inventory, and
the Production Requirements available to promise
inventory for each period.
5

What is the MPS?


• The MPS translates the Sales & Operations Plan
(SOP) into a plan for producing specific products in
the future.
• The MPS is the translation of the SOP into
producible products that make up the output.

At the operational level . .


• The MPS is developed to generate a sustainable
Materials Requirement Planning (MRP) system
and to provide the information for coordination
with sales.
• The MPS is a statement of planned future output.

Copyright – Harland E. Hodges, Ph.D 16-3


Lesson 16 – Aggregate Planning

As a statement of output, the MPS


• forms the basic communication between the
market and manufacturing.
• is stated in product specification terms (part
numbers) for which there are Bill of Materials
(BOM).

MPS can be stated in terms of


• End-item product designations
• Options or modules from which a variety of end
products could be assembled.
• Numbers of units of an “average” final product

Master Schedule : Inputs


• Inputs to the master schedule include
– The production plan
– The forecast
– Orders from customers
– Additional independent demand
– Inventory levels
– Capacity constraints
• As the forecasts are not totally accurate, MPS gives the first opportunity
to compare actual customer orders with forecast demand.
• Shortages should be usually avoided, so the demand is a set at the
maximum{Forecast , Actual Customer Orders}
• Demand can be met from stock, so current stock levels and production
capacities are compared, and a master production schedule designed to
make up any difference.
• MPS must keep within constraints (set by aggregate plan, the
available capacities, etc.).

Copyright – Harland E. Hodges, Ph.D 16-4


Lesson 16 – Aggregate Planning

Master Schedule : Outputs


• Outputs from the master schedule include
– The Projected Inventory
– The MPS
– The Available To Promise (ATP) (uncommitted inventory)

NOTE: As orders are received, they “consume” available


production and inventory
– Any part not consumed is available-to-promise
(ATP)

• In principle, designing a master schedule is like designing an


aggregate plan.
• It is matter of balancing supply and demand.

MPS : Available-to-Promise
Available-to-Promise is

– the uncommitted portion of a company’s inventory and


planned production, maintained in the master schedule to
support customer order promising.

– The ATP quantity is the uncommitted inventory balance in


the first period and is normally calculated for each period in
which an MPS receipt is scheduled.

– The ATP calculation assumes that the entire ATP will be sold/
consumed before the next scheduled receipt. When calculating
ATP, consider all orders until the next scheduled receipt.

10

Copyright – Harland E. Hodges, Ph.D 16-5


Lesson 16 – Aggregate Planning

Master Scheduling Process


Inputs Outputs

Projected
Beginning Inventory
Inventory
Master
Master
Forecast Production
scheduling
Schedule
Customer 3 inputs and 3 outputs
Orders Available To
Promise
(uncommitted
inventory)

The key idea is: we have a forecast, but it turns into an actual order when we
receive a customer order.

MPS starts with a preliminary calculation of projected inventory.

This reveals “when the production is needed” to get additional inventory.

11

Inputs To Master Scheduling

Projected demand is calculated based on the customer orders


and forecast.
Projected Demand = max (forecast, orders)

12

Copyright – Harland E. Hodges, Ph.D 16-6


Lesson 16 – Aggregate Planning

Outputs of Master Scheduling


Therefore, the Projected Inventory Position (previous inventory position - projected
demand) without any production can be calculated and is shown below:

Customer orders are larger Forecast is larger than


than forecast in week 1 Customer orders in week 2

Forecast is larger than


Customer orders in week 3

13

Master Production Scheduling Process

Negative projected on-hand inventory is the signal for


production.

Policy/Strategy: Suppose the economic production lot size


for this product is 70 units. Then, whenever production is
called, 70 units are produced.

The negative projected inventory of -29 in period 3 calls for


production, 70 units are produced, the projected inventory
becomes 41.

The same calculation continues across the whole planning


horizon.

14

Copyright – Harland E. Hodges, Ph.D 16-7


Lesson 16 – Aggregate Planning

Outputs Of Master Scheduling


If the lot size for this item is 70 units, we can now build the Master Production
Schedule. We add our first lot in week/day 3 because this is the first negative
inventory position. We then update our Projected Inventory Position.

15

Outputs Of Master Scheduling


We add our next lot in week/day 5 because this is the next negative inventory position.
We then update our Projected Inventory Position.

16

Copyright – Harland E. Hodges, Ph.D 16-8


Lesson 16 – Aggregate Planning

Outputs Of Master Scheduling


We add our next lot in week/day 7 because this is the next negative inventory position.
We then update our Projected Inventory Position.

17

Outputs of Master Scheduling

We add our next lot in week/day 9 because this is the next negative
inventory position. We then update our Projected Inventory Position,
and have completed the second output of the master scheduling
process, the Master Production Schedule.

18

Copyright – Harland E. Hodges, Ph.D 16-9


Lesson 16 – Aggregate Planning

Outputs of Master Scheduling


We are now ready to compute our final output of the master scheduling
process, the Available to Promise (ATP) or uncommitted inventory. This is
inventory which is available to sell and is extremely important to customer
service. The ATP is calculated for week/day 1, 3, 6, 7 and 8.

19

Outputs Of Master Scheduling


The ATP is calculated for week/day 1 by the following:
Week 1 ATP = Beginning inventory - sum of committed
inventory (customer orders) until the first master
scheduled lot
= 64 - (33 + 20) = 11

20

Copyright – Harland E. Hodges,↑ Ph.D 16-10


Lesson 16 – Aggregate Planning

can e

Acne Outputs Of Master Scheduling


The ATP is calculated for week/day 3 by the following:
Week 3 ATP = MPS for week/day 3 (that is 70 units) - sum of
committed inventory (customer
-
orders)until the next
master scheduled lot = 70 - (10 + 4) = 56
up to
2
- in God we have to
sum of
order
Cryto

0000

21

Outputs Of Master Scheduling


The ATP is calculated for week/day 5 by the following:
Week 5 ATP = MPS for week/day 5 - sum of committed
inventory (customer orders)until the next master
scheduled lot
= 70 - 2 = 68

22

Copyright – Harland E. Hodges, Ph.D 16-11


Lesson 16 – Aggregate Planning

Outputs Of Master Scheduling


The ATP is calculated for week/day 7 by the following:
Week 7 ATP = MPS for week/day 7 - sum of committed
inventory (customer orders)until the next master
scheduled lot
= 70 - 0 = 70

23

Outputs Of Master Scheduling


The ATP is calculated for week/day 8 by the following:
Week 8 ATP = MPS for week/day 8 - sum of committed
inventory (customer orders)until the next master
scheduled lot
= 70 - 0 = 70

24

Copyright – Harland E. Hodges, Ph.D 16-12


Lesson 16 – Aggregate Planning

Updating MPS
Changing to a master production schedule can be disruptive.
Particularly changes in the immediate periods of the schedule

Aggregate Plan is developed for say 1 year


Master Production Schedule is developed for a period of say
12 weeks.

MPS is updated say every 2 weeks, it is on a rolling basis.

25

26

Copyright – Harland E. Hodges, Ph.D 16-13


Lesson 16 – Aggregate Planning

Master Production Schedule

27

Master Production Schedule

⑭Mr Orodiroecei28

Copyright – Harland E. Hodges, Ph.D 16-14


Lesson 16 – Aggregate Planning

Stabilizing The Master Schedule


You can see by these calculations that changes to a Master Schedule
can be disruptive, particularly those in the first few weeks/days of a
schedule.
It is difficult to rearrange schedules, materials plans, and labor plans on
a short notice.
For these reasons, many schedules have varying degrees of changes
that are allowed. Time fences are created to indicate the level of
-
change if any that will be considered .

Frozen Firm Full Open

29

Master Production Schedule


 Specifies what is to be made and when

 Must be in accordance with the aggregate production plan

 Inputs from financial plans, customer demand, engineering,


supplier performance

 As the process moves from planning to execution, each step must


be tested for feasibility

 The MPS is the result of the production planning process


 MPS is established in terms of specific products
 Schedule must be followed for a reasonable length of time
 The MPS is quite often fixed or frozen in the near term part of the
plan
 The MPS is a rolling schedule
 The MPS is a statement of what is to be produced, not a forecast
of demand

30

Copyright – Harland E. Hodges, Ph.D 16-15


Lesson 16 – Aggregate Planning

Hierarchical Planning Process


Items Production Planning Capacity Planning Resource level
Product lines Aggregate Resource
or families Production Plan Requirements Plan Plants

Individual Master Production Rough-Cut Critical work


products Schedule Capacity Plan centers

Material Capacity All work


Components Requirements Plan Requirements Plan centers

Manufacturing Shop Floor Input/Output Individual


operations Schedule Control machines

31

N
we
and

Copyright – Harland E. Hodges, Ph.D 16-16

You might also like