Professional Documents
Culture Documents
Once the aggregate accepted, it is broken down into more details to give
Master Schedule (MS)
-
That is, the aggregate plan must be broken down into specific product
requirements.
. . . .
- .
Disaggregation
That is, the overall production in the MS must equal the production
specified in the aggregate plan.
The MS is a presentation of
the demand, including the forecast and the backlog (customer orders
received),
the MPS - master production schedule (the supply plan),
the projected on-hand (POH) inventory, and
the available-to-promise (ATP) quantity.
MPS determines
the Promised Inventory, and
the Production Requirements available to promise
inventory for each period.
5
MPS : Available-to-Promise
Available-to-Promise is
– The ATP calculation assumes that the entire ATP will be sold/
consumed before the next scheduled receipt. When calculating
ATP, consider all orders until the next scheduled receipt.
10
Projected
Beginning Inventory
Inventory
Master
Master
Forecast Production
scheduling
Schedule
Customer 3 inputs and 3 outputs
Orders Available To
Promise
(uncommitted
inventory)
The key idea is: we have a forecast, but it turns into an actual order when we
receive a customer order.
11
12
13
14
15
16
17
We add our next lot in week/day 9 because this is the next negative
inventory position. We then update our Projected Inventory Position,
and have completed the second output of the master scheduling
process, the Master Production Schedule.
18
19
20
can e
0000
21
22
23
24
Updating MPS
Changing to a master production schedule can be disruptive.
Particularly changes in the immediate periods of the schedule
25
26
27
⑭Mr Orodiroecei28
29
30
31
N
we
and