Professional Documents
Culture Documents
Martin
1 Section 3.0-Page 6 of 7 Hydrotest is 302035 Noted. a. Incorporated as is Closed Ng.L.Thanh
Thierry
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Ref#erence should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-MPQA-FOR-000004_Rev00 Dated 09/06/2018
1 of 23 Page 1 of 7
Block 5 - AL SHAHEEN FIELD Development
Document Title:
Inspection & Test Plan for Piping Fabrication & Erection
(Topsides & Bridges)
Document Number: WHP01-PMC1-ASYYY-23-182002-0001 Date: 24-Sep-2019 Rev.: 02
REVISION HISTORY
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Ref#erence should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-MPQA-FOR-000004_Rev00 Dated 09/06/2018
2 of 23 Page 2 of 7
Block 5 - AL SHAHEEN FIELD Development
Document Title:
Inspection & Test Plan for Piping Fabrication & Erection
(Topsides & Bridges)
Document Number: WHP01-PMC1-ASYYY-23-182002-0001 Date: 24-Sep-2019 Rev.: 02
TABLE OF CONTENT
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Ref#erence should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-MPQA-FOR-000004_Rev00 Dated 09/06/2018
3 of 23 Page 3 of 7
Block 5 - AL SHAHEEN FIELD Development
Document Title:
Inspection & Test Plan for Piping Fabrication & Erection
(Topsides & Bridges)
Document Number: WHP01-PMC1-ASYYY-23-182002-0001 Date: 24-Sep-2019 Rev.: 02
1.0 PURPOSE
This Plan establishes the work process sequence, inspections and tests that are to be executed, documented with
involvement of CONTRACTOR, COMPANY & CERTIFYING AUTHORITY.
2.0 SCOPE
This document serves as a guideline for inspection of process piping fabrication which applied to Topsides and
Bridges of GALLAF project.
3.0 REFERENCES
SD-NOC-PVV-142 Valves
SD-NOC-PVV-145 Flanges
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Ref#erence should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-MPQA-FOR-000004_Rev00 Dated 09/06/2018
4 of 23 Page 4 of 7
Block 5 - AL SHAHEEN FIELD Development
Document Title:
Inspection & Test Plan for Piping Fabrication & Erection
(Topsides & Bridges)
Document Number: WHP01-PMC1-ASYYY-23-182002-0001 Date: 24-Sep-2019 Rev.: 02
WHP01-PMC1-ASYYY-24-302007-0001 Levelling & Dimension Control Procedure for Topsides & Bridges
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Ref#erence should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-MPQA-FOR-000004_Rev00 Dated 09/06/2018
5 of 23 Page 5 of 7
Block 5 - AL SHAHEEN FIELD Development
Document Title:
Inspection & Test Plan for Piping Fabrication & Erection
(Topsides & Bridges)
Document Number: WHP01-PMC1-ASYYY-23-182002-0001 Date: 24-Sep-2019 Rev.: 02
CONTRACTOR (CTR) PTSC MECHANICAL & CONSTRUCTION CO., LTD (PTSC M&C)
QC QUALITY CONTROL
RT RADIOGRAPHIC TESTING
SS STAINLESS STEEL
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Ref#erence should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-MPQA-FOR-000004_Rev00 Dated 09/06/2018
6 of 23 Page 6 of 7
Block 5 - AL SHAHEEN FIELD Development
Document Title:
Inspection & Test Plan for Piping Fabrication & Erection
(Topsides & Bridges)
Document Number: WHP01-PMC1-ASYYY-23-182002-0001 Date: 24-Sep-2019 Rev.: 02
“Review Point” is specified for all documents and data outputs (including
inspections and/or tests results) required to be submitted for review by
REVIEW POINT (R)
CTR to CPY and/ or the CA, before executing the relevant task or part of
work or operations.
6.0 RECORD
All inspection documents and QC Summary sheets shall be complied by project Quality Management Department
ongoing basis to maintain for final documentation.
7.0 APPENDICES
The information contained in this document is the proprietary to North Oil Company. It must not be reproduced, stored, disclosed to any third party or used for any purpose not authorized by North
Oil Company. Printed documents are uncontrolled and considered as "for information only". Ref#erence should always be made to the on-line EDMS for the updated version
Major Projects Template MAJOR-ASY-MPQA-MPQA-FOR-000004_Rev00 Dated 09/06/2018
7 of 23 Page 7 of 7
Block 5 - AL SHAHEEN FIELD Development APPENDIX I
DOCUMENTATION
• Welding machines,
Equipments baking ovens, quivers • Equipment Calibration and Maintenance
Calibration • Inspection tools & Procedure (WHP01-PMC1-ASYYY-23- H M/R R Equipment list register
QC- P3 equipments 302006-0001)
• NDE equipments
8 of 23
Block 5 - AL SHAHEEN FIELD Development APPENDIX I
9 of 23
Block 5 - AL SHAHEEN FIELD Development APPENDIX I
PRE-FABRICATION / ERECTION
10 of 23
Block 5 - AL SHAHEEN FIELD Development APPENDIX I
• Spool number&Joint
number
• Approved WPS
• Root gap
• Bevel angle
• Steel piping fabrication (SD-NOC-PVV-171)
• Alignment
• Approved WPS
• Tack weld
• Approved isometric drawings Welding Summary Report
• Dimension
QC-P8 Fit-up • ASME B31.3 H M/R M for Piping (Refer to
• Edge preparation
• Piping Fabrication & Erection Procedure Appendix III)
• Heat number
(WHP01-PMC1-ASYYY-19-302011-0001)
• Angle of Elbow
• Flange squareness
• Flange orientation
• Surface cleaning
• Flange raised face
protection
11 of 23
Block 5 - AL SHAHEEN FIELD Development APPENDIX I
• WPS
• Welding consumbales
• Equipment calibration
• Preheat/ interpass
• Steel piping fabrication (SD-NOC-PVV-171)
temperature.
• Welding of pressure containing piping and
• Welders qualification
equipment (SD-NOC-PVV-611)
• Arc strikes
• Welding of duplex and super-duplex stainless
• Spatters
steel (SD-NOC-PVV-614) Monitoring Check List (if
QC-P9 Welding • Width of bead
• Approved WPS for piping require for Duplex and
• Welding Parameters
• Approved welder register M M/R M Super Duplex) – Appendix
• Weld identification
• ASME B31.3 II
• Welding sequences &
• Welding Control Procedure (WHP01-PMC1-
distortion
ASYYY-24-302004-0001
• Welding interruption
• Welding Consumable Control Procedure
• Color code (WHP01-PMC1-ASYYY-24-302005-0001)
• Monitoring check list for
DSS & SDSS
• Monitoring for CS Class
/ pre-heating
• WPS
• Visual request • Steel piping fabrication (SD-NOC-PVV-171-
Appendix I)
• Weld appearance
• Welding of pressure containing piping and
• Cracks
equipment (SD-NOC-PVV-611)
QC- • undercut Welding Summary Report
Visual • Approved WPS for piping
P10 • Spatters for Piping (Refer to
• ASME B31.3 H M/R M
• Arc strikes Appendix III)
• Leveling & Dimension Control Procedure for
• Distortion
Topsides & Bridges (WHP01-PMC1-
• Dimension check ASYYY-24-302007-0001)
• Spool identification
12 of 23
Block 5 - AL SHAHEEN FIELD Development APPENDIX I
• WPS
• Welding consumable • Steel piping fabrication (SD-NOC-PVV-171)
• Welder qualification • Welding of pressure containing piping and
QC- Welding
P11A Production test • Welding parameter equipment (SD-NOC-PVV-611) H M/R R Testing reports
• Visual inspection & • Welding Qualification Test Procedure
NDE (WHP01-PMC1-ASYYY-24-302001-0001)
• Mechanical testing
• WPS
• Steel piping fabrication (SD-NOC-PVV-171)
• Sketch
• ASME B31.3
• Film tracing
Welding repair • Approved WPS for repair
• Request
QC- (if any) • Weld Repair & Buttering Procedure NDE reports (for repair)
P12 Repeat from P9, • Defect removal H M/R M
(WHP01-PMC1-ASYYY-24-302003-0001)
• DPI prior welding
P10, P11 & P12 • Welding control procedure (WHP01-PMC1-
• Preheat & interpass
ASYYY-24-302004-0001)
temperature
• Distortion Control
• Welding of pressure containing piping and
equipment (SD-NOC-PVV-611)
• Piping and equipment subject to severe sour
QC- PWHT for CS • PWHT Equipment
service. Metallurgical and welding M/R M/R R PWHT report
P12A (if require) • Chart Recorder
requirement (SD-NOC-PVV-612)
• Post weld heat treatment Procedure (WHP01-
PMC1-ASYYY-19-302021-0001)
13 of 23
Block 5 - AL SHAHEEN FIELD Development APPENDIX I
QC- Ferrite • Weldments & base • Welding of duplex and super-duplex stainless
H M/R R Ferrite Report
P12D Measurement material (DSS & SDSS) steel (SD-NOC-PVV-614)
14 of 23
Block 5 - AL SHAHEEN FIELD Development APPENDIX I
• NDE status
• Internal cleanliness
Spool release for • Protection ( flange &
QC- blasting & pipe end) • Data control/NDE report Inspection Release note
H M/R -
P13 painting • Flange raised protection • Isometric drawing (Refer to Appendix IV)
• Identification
(drawing/spool)
• Painting system
• Painting & Coating System Qualification
Test Procedure for Topsides & Bridges
(WHP01-PMC1-ASYYY-12-302001-0001)
• Inspection activities as • ITP for External Blasting and Painting
Blasting &
QC- per ITP for blasting and (WHP01-PMC1-ASYYY-12-282001-0001) - - - Blasting & painting report
painting
P14
inspection.
painting • Welded joint will follow: WHP01-PMC1-
ASYYY-19-302035-0001_rev02
Hydrotesting Testing Procedure & SD-NOC-
PVV-171 Rev.00_Steel Piping Fabrication
• Cleaning of piping and vessels (SD-NOC-
PVV-175)
• Surface cleanliness
• Pickling & Passivation for Stainless Steel &
QC- Pickling & • Identification Lines, Pickling/passivation report
Duplex Stainless Steel of Piping & Welding W M R
14A passivation system or spool (for line/system )
Joint Procedure (WHP01-PMC1-ASYYY-
• Tools & consumables
19-302013-0001)
• Isometric drawings
15 of 23
Block 5 - AL SHAHEEN FIELD Development APPENDIX I
16 of 23
Block 5 - AL SHAHEEN FIELD Development APPENDIX I
• Spool/valve
cleanliness/ correct type
& size
• Rise face clean
• Approved Isometric drawings
• Gasket, ring joint
• Approved P&ID
QC- • Bolt nut dimension
Bolt tightening • Flange management procedure (WHP01- H M/R R Bolt tightening certificate
P18 • Joint number
PMC1-ASYYY-19-302031-0001)
• Tighten equipment
• Check bolt/nuts has
been painted with prime
expoxy layer of P05
before installed
• Approved test package
• Piping fabrication & Erection procedure
• Approved test package Construction Punch List
QC- Line check prior (WHP01-PMC1-ASYYY-19-302011-0001)
• Inspection/line check H H R Red Mark-up Isometrics
P19 to hydrotesting • Approved P&ID drawings (SD-NOC-EC-602
• Welding summary Red Mark-up P&IDs
10.3.5)
• Approved isometric drawings
• Approved test package
• Piping fabrication & Erection procedure
QC-
NDE check • NDE clearance (WHP01-PMC1-ASYYY-19-302011-0001) H H R Welding summary report
P19A
• Approved P&ID drawings
• Approved isometric drawings
17 of 23
Block 5 - AL SHAHEEN FIELD Development APPENDIX I
18 of 23
Block 5 - AL SHAHEEN FIELD Development APPENDIX I
• Painting completed
• Insulation Procedure
QC- Insulation (if • Surface cleanliness
• Shop drawings M/R M/R R Inspection Report
P23 any) • Type & size
• P & ID drawing
• Insulation cladding
• Approved drawings
• Approved test package
• Project specifications ▪ Approved Test
• Welding summary Packages
QC- • All relevant documents
P24
Final • Material traceability ▪ NDE report
shall be verified
documentation • NDE report H H R ▪ RT film
• As built drawings
• Final documentation procedure (WHP01-
PMC1-ASYYY-23-302005-0001)
19 of 23
Appendix II
PTSC MECHANICAL & CONSTRUCTION
Thickness Correct?
WPS Correct?
Name:
Sign:
Date:
20 of 23
Block 5 - AL SHAHEEN FIELD Development APPENDIX III
PENALTY
FOR J8
PENALTY
FOR J8
PENALTY
J6,7
Note: Weld type: BW(Butt Welds), SW(Socket Weld), FW(Fillet Weld), BRW(Branch Weld)
21 of 23
Appendix IV Page 1 of 1
PTSC MECHANICAL AND CONSTRUCTION
INSPECTION RELEASE NOTES
PROJECT : RELEASE NO:
CLIENT : DATE:
CONTRACT NO. : INITIATOR:
PIPING:
PRIOR TO RELEASED FOR PAINTING
INDICATE BELOW ALL RELEVANT INSPECTION ACTIVITIES THAT HAVE BEEN COMPLETED BEFORE RELEASE
CLEARED
REMARKS:
PREPARED BY APPROVED BY
CONTRACTOR COMPANY
NAME NAME
SIGNATURE SIGNATURE
DATE DATE
22 of 23
Appendix 5: Sample of Piping Steel Traceability Record
10
11
12
13
14
Signature:
Name:
Date:
23 of 23