Transcom Electronics Ltd

Work-Schedule for HVAC work for BGMEA University of Fashion & Technology(BUFT)-Tentative
Description Jan-16 Feb-16 Mar-16 Apr-16 May-15 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16

W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
Man & Tools Mobilization
Mock up(VRF & Chiller)
Ducting Works
Floor Marking
Duct Febrication
Duct Insulation
Duct Hanging
Air Terminal Installation
AHU/FCU Installation
AHU Connection
Electrical Works
Imported Materials
Piping Works
VRF AC Installation
Air cooled water Chiller Installation
Pump Installation
Plant Room Piping
Riser Piping
Floor Piping
VRF Piping Pressure Test
Pipe Insulation
Cladding on Pipe Insulation
Drain Piping
Fan Installation
Electric Works
Pump Flashing
Testing and Commissioning