DAILY PROGRESS REPORT

Project: OSTT- SSJetty Submarine Pipeline,

Location:SS Jetty, SALPG, Durga Beach, Visakhapatnam


REPORT - DPR/OSTT-SSJ pipeline/HPCL/340 Date :10/01/2019
A) HIGHLIGHTS OF THE DAY
in ostt jetty 2" drain lines piping joints 4 no's fitup & welding done
in ss jetty station piping painting works on going
in ss jetty receiver station cable try supports installation is on going

B) QA/QC ACTIVITIES OF THE DAY


weld visuals and NDT works for completed joints
reports preparation for welded joints

0
C) SAFETY HIGHLIGHTS
Pre-start work meeting ( tool Box talk); briefed about the work and hazards invovled.

D) AREA OF CONCERN

E) ACTIVITIES PLANNED FOR NEXT 24 hrs


welding in ss jetty on piping joints
welding in ostt jetty on piping joints

F) (i)MANPOWER DETAILS
OCS-Infinite EPC
working crew 28
Staff 10
(ii)EQUIPMENT compressure 1
excavator
Hydra
JCB

G) REMARKS

OCS INFINITE EPC Client Representative( DAPPOLONIA/HPCL)

OCS-INFINITEEPC/006/OPR/001 Rev0 OCS-INFINITE EPC