DAILY SHIFT MDM & FM CONTRACTOR

MINUTES OF MEETING

Date: 05-05-2020

Attendance:

Maintenance:
1- Adnan Musawi MDM

Contractors:
1- Anil Shift Lead (PTB)
2- Vimal Supervisor (PTB)
3- Iqbal Supervisor (Cargo)
4- Anwer Technician (Cargo)

CM & PPM Figures


PPM CM of Previous Day
Area Previous Today Created Completed In Progress
Day Plan
PTB 62 64 17 14 3
Cargo 0 25 0 0 0

Other activities Conducted


S. no PTB Cargo
1 Log sheets updated for all major equipment as HVAC daily Log sheet filling work carried out
per agreed schedule
2 Attend today CM & PPM Plumbing system inspection carried out
3 Energy meter readings taken. Electrical daily log sheet filling work carried out.
4 Potable water meter readings taken. All toilet in cargo 320 checking work carried out.
5 BTU meter readings taken Recording Energy meter reading daily basis at
Incomer feeder.
6 PA weekly Checking 3 nos.
7 In progress counting the pending spare parts
requirement.

Page 1 of 2
Highlighted Issues
S. no PTB Cargo
1 Previous Day PPM 62nos all completed
(04-05-2020).
2 SMSB(E) Shut down activities done for
yearly ppm
3 Spare parts Process not clear

Remarks:

Note: conduct the meeting in shift wise for proper information

Page 2 of 2