You are on page 1of 1

Amps X 100 P2BBA02_U2 SWGR B (Nom. kV=11, Plot Ref.

kV=11)
.5 1 3 5 10 30 50 100 300 500 1K 3K 5K 10K
1K 1K

500 P2BBA02_U2 SWGR B 500

300
R_P2BBA02GH023_U2 SWGR B - P 300
OC1
AREVA
P141 (B/C/G)
CT Ratio 1000:1
100 IEC - Extremely Inverse 100
Pickup = 0.9 (0.08 - 4 xCT Sec)
Time Dial = 0.85
50 3x = 8.5 s, 5x = 2.83 s, 8x = 1.08 s 50
Inst = 10.4 (0.08 - 32 xCT Sec)
I.D.FAN MOTOR-2B-85% Time Delay = 0.3 s
30 30
I.D.FAN MOTOR-2B-Cold
I.D.FAN MOTOR-2B-100%
I.D.FAN MOTOR-2B-Hot
10 10
∆ 1.07 s

5 5

Seconds

Seconds
3 3
C_P2BBA02GH023_U2 SWGR B - P

R_P2BBD01GH001_AHS SWGR - P
1 OC1 1
AREVA
P141 (B/C/G)
.5 CT Ratio 1000:1 .5
IEC - Extremely Inverse
.3 Pickup = 0.9 (0.08 - 4 xCT Sec) .3
Time Dial = 0.85 C_P2BBA02GH021_U2 SWGR B - P
3x = 8.5 s, 5x = 2.83 s, 8x = 1.08 s
Inst = 3 (0.08 - 32 xCT Sec)
Time Delay = 0.27 s
.1 .1

.05 .05

.03 .03
P2BBD01_AHS SWGR B - Source PD Ia
P2BBA02_U2 SWGR B - Source PD Ia

.01 .01
.5 1 3 5 10 30 50 100 300 500 1K 3K 5K 10K

Amps X 100 P2BBA02_U2 SWGR B (Nom. kV=11, Plot Ref. ETAP


kV=11)Star 19.5.0D

Project: Mong Duong II 2 Date: 30-04-


Location: MONG DUONG, SN: DLR-E
Contract: Rev: Base
Engineer: Huy Doan Fault: Phase