You are on page 1of 3

Tunnels are artificial underground passages opened at both ends constructed for different

purposes. It is mostly required for highways, railways, sewerage, water supply, public
utilities and canals.
The choice of tunnelling method may be dictated by geological and hydrological conditions
such as
 Weak rock under high stresses leads to squeezing ground conditions.
 Brittle strong rock high stress conditions may lead to rockbursting.
 cross-section and length of continuous tunnel
 local experience and time/cost considerations (what is the value of time in the project)
limits of surface disturbance, and many others factors
 Choice of method depends upon nature of strata and geometry of tunnel section
Continued
Tunnelling methods
Rough classification of methods
 Excavation: An excavation process without removing the overlying rock or soil
• Steps: excavating-remove muck-supporting-lining- ventilation-draining
• Drill & Blast, hammer, roadheader
 Cut and cover: trenching to excavate and construct a tunnel, and then backfilling earth
over it.
 Immersed tunnel: lowering prefabricated tunnel elements into a dredged channel and
joining them up under water,
• Concrete
• Steel Continued
Classification of tunnelling method based on type of strata:
Methods divided into three categories
 Firm ground- reasonable time available for installing conventional support.
 Soft ground- Conventional support can not be installed.
 Rocks- Special treatment required before starting excavation

Tunnelling in Firm ground


 Traditional methods. Involving drilling and blasting
 Full Face Method. In firm soils where full face excavation can hold it self for
sufficient time to allow mucking and supporting operations.
 In the full-face method, workers excavate the entire diameter of the tunnel at the same
time.
 This is most suitable for tunnels passing through strong ground or for building smaller
tunnels. Continued
 Top Heading and benching.
 When full face excavation is not possible. Heading should be sufficient
distance ahead of benching.
 In this technique, workers dig a smaller tunnel known as a heading. Once the
top heading has advanced some distance into the rock, workers begin
excavating immediately below the floor of the top heading; this is a bench.
 One advantage of the top-heading-and-bench method is that engineers can use
the heading tunnel to gauge the stability of the rock before moving forward
with the project.
Tunnelling in Soft Ground
 Instantaneous support is required No drilling and blasting.
 Forepoling is done.
 Boards are driven ahead of the last ‘rib’, around periphery
 Forepoles act as cantilevers beyond breasting
 Soil is excavated after removing the breast board and new rib is erected Continued
 Because stand-up time is generally short when tunneling through soft ground, cave-
ins are a constant threat. To prevent this from happening, engineers use a special piece
of equipment called a shield.
 A shield is an iron or steel cylinder literally pushed into the soft soil. It carves a
perfectly round hole and supports the surrounding earth while workers remove debris
and install a permanent lining made of cast iron or precast concrete.
 When the workers complete a section, jacks push the shield forward and they repeat
the process.
Tunnelling in Rocks
 Tunnels are driven in rocks by drilling holes in the rock face, loading the holes with
explosives, blasting and removing the broken rock
 Each sequence full cross section of the tunnel may be excavated, or one or more drifts
may be there.
 Drilling pattern for holes of explosives may differ depending upon rock type, cross
section, experience expertise and type of explosive suggested.
 Methods are similar in principle like
 Full Face Method
 Top Heading and benching
 Drift Method Continued
 Tunneling through hard rock almost always involves blasting. Workers use a
scaffold, called a jumbo, to place explosives quickly and safely. The jumbo moves to
the face of the tunnel, and drills mounted to the jumbo make several holes in the rock.
The depth of the holes can vary depending on the type of rock, but a typical hole is
about 10 feet deep and only a few inches in diameter. Next, workers pack explosives
into the holes, evacuate the tunnel and detonate the charges. After vacuuming out the
noxious fumes created during the explosion, workers can enter and begin carrying out
the debris, known as muck, using carts. Then they repeat the process, which advances
the tunnel slowly through the rock.
 Fire-setting is an alternative to blasting. In this technique, the tunnel wall is heated
with fire, and then cooled with water. The rapid expansion and contraction caused by
the sudden temperature change causes large chunks of rock to break off. The stand-up
time for solid, very hard rock may measure in centuries. In this environment, extra
support for the tunnel roof and walls may not be required. However, most tunnels pass
through rock that contains breaks or pockets of fractured rock, so engineers must add
additional support in the form of bolts, sprayed concrete or rings of steel beams. In
most cases, they add a permanent concrete lining

You might also like