SPECIALITY CENTER –
EAST LEGON
Weekly Progress Summary
27th November, 2019
www.smec.com
Issued: 29-Nov-19
1. Basement
The work done at the Basement include
1. Floor Finishing
2. Vinyl Flooring Finish/Carpet
3. Plaster board/Cement board in dry walls (which is behind schedule)
4. First Coat Painting (behind schedule)
5. Doors and Windows
6. Ceiling Works (fixing of acoustic and plasterboard) which is also behind schedule
7. Internal Painting of Walls, Ceiling and partitions
The activities below are delayed in the start dates (refer appendix A for details of delayed activities)
2. Second Floor
The activities below are completed
1. Block Work
2. Plastering
3. Installation of Electrical board
4. Installation of Electrical Conduits
5. Electric wiring and cabling
6. Installation of refrigerated network
3. Third Floor
The following activities are currently in
progress
1. Installation of foul drainage (behind schedule)
2. Installation of water supply system (behind
schedule)
3. Blockwork at the CSSD
4. Wall Partition (behind schedule)
5. First Coat Painting (behind schedule)
6. Installation of electrical conduits
7. Electric wiring and cabling
The activities below are delayed in the start dates (refer appendix A for details of delayed activities)
1. Installation of sanitary appliances
2. Installation of firefighting system
3. Life Care Panels
4. Ceiling Finish
5. Installation of refrigerated network
6. Ducts installation
7. Installation of extraction fans
Fig. 3.3: Foul drainage from the Third Floor to the inside
of the ceiling of Second Floor
PROGRESS TRACKING
A1060 Wall Partition (Except the Corridor) 7 03-10-19 10-10-19 80 27 days late
A1241 Doors and Windows (Some from the Client) 3 15-11-19 19-11-19 0 Not due
A1250 Internal Painting of Walls, Ceiling and partitions 7d 16 7 16-11-19 25-11-19 0 Not due
A1840 Installation of indoor and outdoor air condition equipment 7 31-10-19 07-10-19 0 Not due
Issued: 29-Nov-19
A1720 Installation of piped supply system 11 21-10-19 01-11-19 80 Finish date not due
A1730 Installation of sanitary appliances (Some from the Client) 7 15-11-19 22-11-19 0 Not due
A1270 internal Painting of Walls, Ceiling and partitions 7 18-11-19 26-11-19 0 Not due
A1890 Installation of extraction fans 7 30-10-19 06-11-19 0 Due to finish today. Late
A1900 Installation of indoor and outdoor air condition equipment 7 05-11-19 12-11-19 0 2 days late
Issued: 29-Nov-19
A1260 Concrete Plinth for HVAC with associated formwork 3 25-10-19 28-10-19 0 12 days late
A1750 Connection of foul drainage to the mains 4 30-10-19 02-11-19 0 7 days late
A1770 Installation of sanitary appliances (Some from the Client) 7 24-10-19 31-10-19 0 13 days late
A1065 Concrete casting including steel mesh at the Washrooms 5 31-10-19 05-11-19 100 Done
A1330 Ceiling Works (fixing of acoustic and plasterboard) 14 28-10-19 13-11-19 0 9 days late
A1340 Internal Painting of Walls, Ceiling and partitions 5 18-11-19 23-11-19 0 Not due
Issued: 29-Nov-19
A1960 Installation of indoor and outdoor air condition equipment 7 18-11-19 25-11-19 0 Not due