LUCCAHEALTH MEDICAL

SPECIALITY CENTER –
EAST LEGON
Weekly Progress Summary
27th November, 2019

www.smec.com
Issued: 29-Nov-19

1. Basement
The work done at the Basement include

1. Blockwork and Concrete work at the


washrooms.
2. The stair up the washrooms has been done.
3. Floor screeding at the washrooms has started
4. Studs for the Dry walls
5. The Blockwork at the main stairwell (near the
Lift)
6. Central Cable tray along the line of the central
columns
7. Block work and plastering for the Gas Structure
Fig. 1.1: Main Cable Tray in Basement Done at the storage area has been done
8. Electrical conduiting has begun at the
basement

Fig. 1.2: Cutting in the washroom for installation of foul


drainage at the Basement

Fig. 1.3: Blockwork and plastering of the Gas Structure in


the storage room at the Basement

SMEC-CONSAR – LuccaHealth Clinic, East Legon – Weekly Progress Summary Page 1 of 4


Issued: 29-Nov-19

Outstanding Works at the Basement Level Includes

1. Floor Finishing
2. Vinyl Flooring Finish/Carpet
3. Plaster board/Cement board in dry walls (which is behind schedule)
4. First Coat Painting (behind schedule)
5. Doors and Windows
6. Ceiling Works (fixing of acoustic and plasterboard) which is also behind schedule
7. Internal Painting of Walls, Ceiling and partitions
The activities below are delayed in the start dates (refer appendix A for details of delayed activities)

1. Connection of foul drainage to the mains


2. Installation of water supply system
3. Installation of sanitary appliances
4. First Coat Painting which depends on completion of drywall partitions
5. Ceiling Works (fixing of acoustic and plasterboard)

SMEC-CONSAR – LuccaHealth Clinic, East Legon – Weekly Progress Summary Page 2 of 4


Issued: 29-Nov-19

2. Second Floor
The activities below are completed
1. Block Work
2. Plastering
3. Installation of Electrical board
4. Installation of Electrical Conduits
5. Electric wiring and cabling
6. Installation of refrigerated network

The following activities are in progress at the Second-Floor level

1. Installation of foul drainage


2. Installation of water supply system (progress is on track)
3. Wall Partition (behind schedule)
4. First Coat Painting (behind schedule)
Fig. 2.1: Refrigeration network outlets
at the Second Floor

The following works are outstanding


1. Floor Finishing
2. Vinyl Flooring Finish/Carpet
3. Plaster board/Cement board in dry walls (which is behind
schedule)
4. First Coat Painting (behind schedule)
5. Doors and Windows
6. Ceiling Works (fixing of acoustic and plasterboard) which is also
behind schedule
7. Internal Painting of Walls, Ceiling and partitions

Fig. 2.2: Water Supply Distribution


Lines Installed

Fig. 2.3: Drywall Partition to Exam Rooms

SMEC-CONSAR – LuccaHealth Clinic, East Legon – Weekly Progress Summary Page 3 of 4


Issued: 29-Nov-19

3. Third Floor
The following activities are currently in
progress
1. Installation of foul drainage (behind schedule)
2. Installation of water supply system (behind
schedule)
3. Blockwork at the CSSD
4. Wall Partition (behind schedule)
5. First Coat Painting (behind schedule)
6. Installation of electrical conduits
7. Electric wiring and cabling

Fig. 3.2: Running of Refrigeration network at the Third-


Floor

The activities below are delayed in the start dates (refer appendix A for details of delayed activities)
1. Installation of sanitary appliances
2. Installation of firefighting system
3. Life Care Panels
4. Ceiling Finish
5. Installation of refrigerated network
6. Ducts installation
7. Installation of extraction fans

Fig. 3.4: Water Supply Pipe Lines Installation at the Third


Floor

Fig. 3.3: Foul drainage from the Third Floor to the inside
of the ceiling of Second Floor

SMEC-CONSAR – LuccaHealth Clinic, East Legon – Weekly Progress Summary Page 4 of 4


APPENDIX A
Issued: 29-Nov-19

PROGRESS TRACKING

Duration Planned Start Planned % Work


Remarks
(Days) Date Finish Date Done

Third Floor 03-10-19 12-12-19

Third Floor Plumbing Works 19 05-10-19 26-10-19

A1670 Installation of foul drainage 7 14-10-19 21-10-19 95 16 days late

A1680 Installation of piped supply system 11 05-10-19 17-10-19 90 20 days late

A1690 Installation of sanitary appliances 7 18-10-19 25-10-19 0 19 days late

A1700 Installation of firefighting system 9 17-10-19 26-10-19 0 20 days late

Third Floor Internal Works 53 03-10-19 25-11-19

A1055 Floor Finishing 2 08-11-19 09-11-19 0 Not due

A1056 Vinyl Flooring Finish 7 11-11-19 18-11-19 0 Not due

A1060 Wall Partition (Except the Corridor) 7 03-10-19 10-10-19 80 27 days late

A1061 Life Care Panels 12 11-10-19 24-10-19 0 26 days late

A1062 Corridor Partition 5 24-10-19 30-10-19 0 13 days late


Issued: 29-Nov-19

A1063 First Coat Painting 2 11-10-19 14-10-19 80 23 days late

A1240 Ceiling Finish 3 29-10-19 01-11-19 0 8 day late

A1241 Doors and Windows (Some from the Client) 3 15-11-19 19-11-19 0 Not due

A1250 Internal Painting of Walls, Ceiling and partitions 7d 16 7 16-11-19 25-11-19 0 Not due

HVAC Installations 45 21-10-19 12-12-19

A1790 Installation of refrigerated network 9 21-10-19 30-10-19 0 16 days late

A1800 Installation of flow water chillers 9 02-12-19 12-12-19 0 Not due

A1810 Ducts installation 9 21-10-19 30-10-19 0 16 days late

A1820 Installation of air treatment unit 5 02-12-19 07-12-19 0 Not due

A1830 Installation of extraction fans 7 25-10-19 01-11-19 0 12 days late

A1840 Installation of indoor and outdoor air condition equipment 7 31-10-19 07-10-19 0 Not due
Issued: 29-Nov-19

Electrical Installations 48 09-10-19 03-12-19

A1970 Installation of pipes 19 09-10-19 30-10-19 90 7 days late

A1980 Connection of Earthing System 5 09-10-19 14-10-19 0 28 days late

A1990 Electric wiring and cabling 19 09-10-19 30-10-19 90 7 days late

A2000 Installation of light fixtures 10 20-11-19 30-11-19 0 Not due

A2010 Installation of Electrical board 38 21-10-19 03-12-19 100 Done

Second Floor 57 12-10-19 07-12-19

Second Floor Plumbing Works 29 21-10-19 22-11-19

A1710 Installation of foul drainage 9 21-10-19 30-10-19 70 7 days late

A1720 Installation of piped supply system 11 21-10-19 01-11-19 80 Finish date not due

A1730 Installation of sanitary appliances (Some from the Client) 7 15-11-19 22-11-19 0 Not due

A1740 Installation of firefighting system 10 25-10-19 05-11-19 0 5 days late


Issued: 29-Nov-19

Second Floor Internal Works 45 12-10-19 26-11-19

A1040 Block Work 2 25-10-19 26-10-19 100 Done

A1045 Floor Finishing 2 09-11-19 11-11-19 0 Not due

A1075 Plastering 1 12-11-19 12-11-19 100 Done

A1095 Ceiling Finish 7 04-11-19 11-11-19 0 Not due

A1105 Vinyl Flooring Finish 7 12-11-19 19-11-19 0 Not due

A1175 Wall Partition 7 12-10-19 19-10-19 60 18 days late

A1176 First Coat Painting 2 20-10-19 22-10-19 10 15 days late

A1185 Doors and Windows 3 16-11-19 20-11-19 0 Not due

A1270 internal Painting of Walls, Ceiling and partitions 7 18-11-19 26-11-19 0 Not due

HVAC Installations 12 30-10-19 12-11-19

A1850 Installation of refrigerated network 9 30-10-19 08-11-19 0 6 days ate

A1890 Installation of extraction fans 7 30-10-19 06-11-19 0 Due to finish today. Late

A1900 Installation of indoor and outdoor air condition equipment 7 05-11-19 12-11-19 0 2 days late
Issued: 29-Nov-19

Electrical Installations 46 16-10-19 07-12-19

A2020 Installation of pipes 22 16-10-19 09-11-19 100 Done

A2030 Installation of Earthing System 5 16-10-19 21-10-19 0 23 days late

A2040 Electric wiring and cabling 22 16-10-19 09-11-19 100 Done

A2050 Installation of light fixtures 10 27-11-19 07-12-19 0 Not due

A2060 Installation of Electrical board 38 21-10-19 03-12-19 100 Done

Roof Slab 10 25-10-19 05-11-19

A1260 Concrete Plinth for HVAC with associated formwork 3 25-10-19 28-10-19 0 12 days late

A1280 Neuce and Waterproofing 7 29-10-19 05-11-19 0 8 day late

Basement 45 16-10-19 29-11-19


Issued: 29-Nov-19

Basement Plumbing Works 15 24-10-19 09-11-19

A1750 Connection of foul drainage to the mains 4 30-10-19 02-11-19 0 7 days late

A1760 Installation of piped supply system 4 25-10-19 29-10-19 0 12 days late

A1770 Installation of sanitary appliances (Some from the Client) 7 24-10-19 31-10-19 0 13 days late

A1780 Installation of firefighting system 8 01-11-19 09-11-19 0 6 days late

Basement Internal Works 39 16-10-19 23-11-19

A1065 Concrete casting including steel mesh at the Washrooms 5 31-10-19 05-11-19 100 Done

A1066 Blockwork at the Washrooms 3 05-11-19 07-11-19 100 Done

A1070 Floor Finishing 4 08-11-19 12-11-19 0 Not due

A1300 Vinyl Flooring Finish/Carpet 7 13-11-19 20-11-19 0 Not due

A1310 Wall Partition 7 16-10-19 23-10-19 20 14 days late

A1311 First Coat Painting 2 24-10-19 26-10-19 0 13 days late

A1320 Doors and Windows 3 18-11-19 21-11-19 0 Not due

A1330 Ceiling Works (fixing of acoustic and plasterboard) 14 28-10-19 13-11-19 0 9 days late

A1340 Internal Painting of Walls, Ceiling and partitions 5 18-11-19 23-11-19 0 Not due
Issued: 29-Nov-19

HVAC Installations 14 09-11-19 25-11-19

A1910 Installation of refrigerated network 8 14-11-19 22-11-19 0 Not due

A1930 Ducts installation 8 09-11-19 18-11-19 0 Not due

A1940 Installation of air treatment unit 5 16-11-19 22-11-19 0 Not due

A1950 Installation of extraction fans 7 15-11-19 22-11-19 0 Not due

A1960 Installation of indoor and outdoor air condition equipment 7 18-11-19 25-11-19 0 Not due

Electrical Installations 35 21-10-19 29-11-19

A2070 Installation of pipes 8 09-11-19 18-11-19 0 Not due

A2080 Installation of Earthing System 5 09-11-19 14-11-19 0 Not due

A2090 Electric wiring and cabling 8 09-11-19 18-11-19 0 Not due

A2100 Installation of light fixtures 12 19-11-19 29-11-19 0 Not due

A2110 Installation of Electrical board 35 21-10-19 29-11-19 0 16 days late


Issued: 29-Nov-19

General Cleaning 15 02-12-19 18-12-19

A1140 Cleaning of the Site 12 02-12-19 14-12-19 0 Not due

A1142 Installation of Furnitures 7 05-12-19 12-12-19 0 Not due

A1145 Handing over Works 1 18-12-19 18-12-19 0 Not due