Progress Tracking Sheet-Piping Erection

Material at Pipe Full welding Non Destructive Pipe Support Final


Preparation
Site laying execution Examination Erection Inspection

Work Pack

Weighting

Individual
(Dia-inch)

Man hour

Progress
Progress
Drawing

Overall
Project

Quantity
Area
Item

5% 20% 20% 35% 5% 10% 5%

1 ISO-011 A WP-001 20.0 267 0.03 100% 100% 100% 100% 100% 100% 100% 100% 0.027
2 ISO-012 A WP-001 30.0 400 0.04 100% 100% 100% 100% 100% 100% 100% 100% 0.040
3 ISO-013 A WP-001 20.0 267 0.03 100% 100% 100% 100% 100% 100% 100% 100% 0.027
4 ISO-014 A WP-001 10.0 133 0.01 100% 100% 100% 100% 100% 100% 100% 100% 0.013
5 ISO-015 A WP-001 6.0 80 0.01 100% 100% 100% 100% 100% 100% 100% 100% 0.008
6 ISO-016 A WP-001 40.0 533 0.05 100% 100% 100% 100% 100% 100% 100% 100% 0.053
7 ISO-017 A WP-02 60.0 800 0.08 100% 100% 100% 100% 100% 100% 100% 100% 0.080
8 ISO-018 A WP-02 54.0 720 0.07 100% 100% 100% 100% 100% 100% 100% 100% 0.072
9 ISO-019 A WP-02 40.0 533 0.05 100% 100% 100% 100% 100% 100% 100% 100% 0.053
10 ISO-020 A WP-02 20.0 268 0.03 100% 100% 100% 100% 100% 100% 100% 100% 0.027
11 ISO-021 B WP-02 73.0 973 0.10 100% 100% 100% 100% 100% 100% 100% 100% 0.097
12 ISO-022 B WP-02 60.0 800 0.08 100% 100% 100% 100% 100% 100% 100% 100% 0.080
13 ISO-023 B WP-02 30.0 400 0.04 100% 100% 100% 100% 100% 100% 100% 100% 0.040
14 ISO-024 B WP-02 60.0 800 0.08 100% 100% 100% 100% 100% 100% 100% 100% 0.080
15 ISO-025 B WP-03 55.0 733 0.07 100% 100% 100% 100% 100% 100% 100% 100% 0.073
16 ISO-026 B WP-03 40.0 533 0.05 100% 100% 100% 100% 100% 100% 100% 100% 0.053
17 ISO-027 B WP-03 50.0 667 0.07 100% 100% 100% 100% 100% 100% 100% 100% 0.067
18 ISO-028 B WP-03 6.0 80 0.01 100% 100% 100% 100% 100% 100% 100% 100% 0.008
19 ISO-029 B WP-03 15.0 200 0.02 100% 100% 100% 100% 100% 100% 100% 100% 0.020
20 ISO-030 B WP-04 35.0 467 0.05 100% 100% 100% 100% 100% 100% 100% 100% 0.047
21 ISO-031 B WP-04 6.0 80 0.01 100% 100% 100% 100% 100% 100% 100% 100% 0.008
22 ISO-032 B WP-04 20.0 268 0.03 100% 100% 100% 100% 100% 100% 100% 100% 0.027

Progress Summary by Project Area-Piping Erection Progress Summary by Work Pack-Piping Erection

Work Pack)
Weighting(
Work Pack
Weighting
(Dia-inch)

Man hour

Progress

Progress
Progress

Progress
Enter % complete

by Work
by Area
Project

Overall

Overall
Quantity

Pack
Area

for each work step

A 300 4000 0.40 100% 40.0% WP-001 0.168 100% 17%


B 450 6000 0.60 100% 60.0% WP-02 0.529 100% 53%
WP-03 0.221 100% 22%
WP-04 0.081 100% 8%
Total 750 10000 1.00 100.0% 1.00 100%