You are on page 1of 1

FODC-FIRST ORIENT DEVELOPMENT AND CONSTRUCTION CORP.

Project :Food Manufacturing and Distribution Center of No Bia,Inc.


Location : Carmona, Cavite
Subject : Nominated Specialty Contractor's Checklist

Signed
ITEM NO. DESCRIPTION Soft Copy Date Submitted Remarks
Hard Copy
I. Schedule of Deliveries
(Manufacturing Duration, Transport Duration,
Duration of Cleaning and Release from Port of Manila)

II. Project Schedule


a. S-curve
b. Milestone Dates
c. Contract Timetable

III. Manpower and Equipment Schedule

IV. Method Statement Construction Methodology/ Execution Plan

V. Quality Control Plan Program

VI. 3S Program ( Safety,Security and Sanitation)


Safety Methodology Approved by DOLE

VII. Table of Organization with Photos and Contact Details

VIII. Resume of Nominated Key Personnel

IX. Proposed Staging Area

X. Material Submittal Tracking Log (MSTL)

XI. For Construction Drawings and Specifications