COST ANALYSIS FOR ROAD SECTION

INPUT DATA

R.C.C PART WIDTH SEC. AREA LENGTH VOLUME RATE

4 0.874923 3 2.624769 9500


COSTING 24935.31
BRICK SOLING LENGTH WIDTH AREA RATE
4.305 3 12.915 25

COSTING 322.875

REBAR WORK
U.W SPACING(X) SPACING(Y) NO OF RODTOTAL ,L WT RATE COST
DB10 0.666

DB12 0.888 0.15 0.15 27.666667 106.5167 94.5868 65 6148.142


21 90.3 80.1864 65 5212.116
DB16 1.456

SHUTTERING WORK

LENGTH 3
WIDTH 0.3

SURFACE AREA(SQFT) 36

VOLUME(CFT) 3
RATE 450
COST 1350

REBAR FOR EXPANSION JOINT


UNIT WT NO OF ROD LENGTH TOTAL .L WT RATE
DB16 1.456 6 0.6 3.6 5.2416 65

COST 340.704

CCNSTRUCTION OF EDGE BEAM


DB16 NO ROD NO BEAM LENGTH WT RATE COST
DB16 4 2 24 34.944 65 2271.36
DB10 21 2 34.44 22.93704 65 1490.908
SO.TOTAL COST FOR 1 METER LENGTH 14023.8