Professional Documents
Culture Documents
I EARTH WORK … … … 1 … 3
II MORTAR … … … 4 … 5
V BRICK … … … 14 … 16
VI STONE WORK … … … 17 … 18
X FLOORING … … … 35 … 39
XI WALLING … … … 40 … 44
XII CEILING … … … 45 … 47
XIII ROOFING … … … 48 … 54
XV FENCING … … … 63 … 65
XIX BRIDGES … … … 87 … 90
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
I. EARTH WORK
1 Site Clearing including Cutting Trees and
Bushes and Dressing
( For 100 Cft ) L.S … ( According to site condition )
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
8 Excavating in Medium Soil and Filling
and Forming Embankment,
Lead 100 Feet, Lift 5 Feet
( For 100 Cft )
Mastery No 1/8
Digger No 1 1/2
Worker for carrying No 1
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
16 Digging Post Holes Not Exceeding 12 Cft.
in Each Hole in Ordinary Soil Part
Return and Fill
( For Each Hole)
Digger No 1/7
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
II. MORTAR
1 Cement Mortar 1:2
( For 100 Cft )
Cement 46 Cft Lbs 4140
Sand Cft 92
Workers for Mixing No 4
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
9 Lime Mortar 1:1:1 For Small Work
( For 100 Cft )
Lime Cft 50
Sand Cft 50
Surkhi Cft 50
Workers for Mixing No 8
13 Mud Mortar
( For 100 Cft )
Selected Suitable Clay (Mud) Cft 100
Workers for Mixing No 2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
III. CONCRETE (HAND MIXED)
1 Cement Concrete with Stone Ballast 1½"
Gauge 1:3:6
( For 100 Cft )
Cement 16 Cft Lbs 1440
Stone Ballast 1 ½" Gauge Cft 96
Sand Cft 48
Mason No 1
Workers No 8
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
7 Cement Concrete 1:2:4 with Ironite 10% to
the Weight of Cement.
( For 100 Cft )
Cement 21 Cft Lbs 1890
Ironite Lbs 189
Stone or River Shingle ¼" To ¾" Gauge Cft 92
Sand Cft 46
Mason No 1
Workers No 10
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
13 Lime Concrete 1:2:6 with Gravel or Broken
Brick Aggregate
( For 100 Cft )
Gravel Cft 100
Lime Cft 17 1/2
Sand Cft 35
Mason No 1/2
Workers No 10
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
18 Mixing Only Granolithic Mix(1:2) with ¼"
Down Granite Chipping in Ordinary Cement
( For 100 Cft )
Cement Lbs 4320
Sand Cft 9
¼" Granite Chipping Cft 96
Mason No 1
Workers No 5
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
IV. REINFORCED CONCRETE (HAND MIXED)
1 Reinforced Concrete Work 1:2:4
( For 100 Cft )
Cement 23 Cft Lbs 2070
Coarse agg: ¼" to ¾" gauge Cft 92
Sand Cft 46
Mason No 2
Workers No 15
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Ballast ¼" to ¾" Gauge Cft 1.45
Sand Cft 0.72
Special Shuttering for Pipe L.S …
Masons No 1/8
Workers No 3/4
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
CONCRETE MIXED BY MACHINE
1 Mixing and Placing Cement Concrete 1:3:6 with
Stone Ballast or River Shingles or Brick Agg.
1½" Gauge Wheeled by Hand in Barrows
( For 100 Cft)
Cement 16 Cft Lbs 1440
Stone Ballast, Shingles or Brick Agg. 1½" Gauge Cft 96
Sand Cft 48
Fuel Gals 2
Mason No 1
Workers No 6
Machine Driver No 1/2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
5 Transporting Placing and Consolidating Cement
Concrete ( Not Reinforced )
Lead 100' and 15' Above or Below Mixer
( For 100 Cft)
(a) Foundations and Floors
Masons No 1
Workers No 5
(b) Walls
Masons No 1
Workers No 7
(b) Walls
Masons No 1
Workers No 8
(b) Walls
Masons No 2
Workers No 8
(c) Columns
Masons No 2
Workers No 9
(b) Walls
Masons No 2
Workers No 9
(c) Columns
Masons No 2
Workers No 10
pg-14
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
V. BRICK WORK
1 Brick Work 1st Class in Composite Mortar 1:1:6
( For 100 Cft)
1st Class Brick 9"x4 3/8"x2¾" No 1350 Allowed 2 more
Cement Lbs 372 workers for each
Lime Cft 4 1/8 additional story
Sand Cft 24 3/4 of the Bldg. Allow
Mason No 4 Extra for Scaffolding
Workers No 6 for each storey
Scaffolding and Sundries L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
7 9" Thick Honey-Comb Brick Work with 1st Class
in 1:3 Cement Mortar
( For 100 Sft)
1st Class Brick 9"x4 3/8"x2¾" No 700
Cement Lbs 564
Sand Cft 19
Mason No 3 1/2
Workers No 3 1/2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
13 Brick Work 1st Class in Lime Mortar 1:1
( For 100 Cft)
st
1 Class Brick 9"x4 3/8"x2¾" No 1350
Lime Mortar 1:1:1 Cft 26
Masons for Laying & Cutting No 4
Workers No 5
Scaffolding and Sundries L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
VI. STONE WORK
1 Coursed Rubble Dry Stone Masonry
( For 100 Cft)
Rubble Stone Cft 125
Masons No 2
Workers No 2
Scaffolding and Sundries L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
7 Coursed Rubble Stone Masonry in Lime
Mortar 1:1:1
( For 100 Cft)
Rubble Stone (Selected) Cft 125
Lime Mortar Cft 34
Masons No 9
Workers No 6
Scaffolding and Sundries L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
VII. PLASTERING & POINTING
1 Plastering with Damp Proof Cement Mortar ¾"
Thick 1:2
( For 100 Sft)
Cement 3.6 Cft Lbs 324
Pudlo (5% by Weight of Cement ) Lbs 16.2
Sand Cft 7.2
Mason No 1
Workers No 3
Sundries L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
8 Plastering with Lime Mortar ½" Thick (2:3:1)
( For 100 Sft)
Lime Mortar for Plaster (2:3:1) Cft 5
Masons No 1
Workers No 2
Sundries L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
14 Pointing with 1:2:6 Composite Mortar
( For 100 Sft)
Cement 0.32 Cft Lbs 29
Lime Cft 0.64
Sand Cft 1.92
Masons No 1
Workers No 2
Sundries L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
VIII. WOOD WORK
1 Thitya, Ingin, Pyingado Wood Work Wrought
and Fixed
( For 50 Cft)
Thitya, Ingin, Pyingado Cft 55 10% Wastage
Nails & Spikes Lbs 14
Carpenters No 12
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
7 Stair Case 2nd Class Without Hand railing
(Other than Teak)
( For 30 Sft) (10'x3')
Stringers 2 x 10' x 10" x 3" Cft 4.59 10% Wastage
Treads, 6 x 2 5/6" x 9" x 1½" Cft 2.47 15% Wastage
Risers 6 x 3' x 9" x ½" Cft
Nails Lbs 2
Carpenters No 4
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
12 Eaves & Facia Boards 12" x 1" Plank
( For 100 Rft )
Planks 100'x12"x1" Cft. 9.58 15% Wastage
Nails & Screws Lbs. 2
Carpenters No. 4
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
19 3" x ½" Wrought Inn Facia Boards Fixed
Complete Including Earth Oiling 2 Coats
( For 100 Rft )
3" x ½" Inn Plank Cft. 1.2 15% Wastage
Nails & Screws Lbs. 1
Carpenters No. 1 1/4
Earth Oiling 2 Coats Sft 33.5
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
IX. DOOR AND WINDOW
1 1½" Thick Teak Paneled Door 1st Class for
7' x 3½' (Double Leaf)
( For 24.5 Sft )
Styles 4 x 7' x 4" x 1½" Cft.
Top and Bottom Rails 4 x 1 5'/8 x 4" x 1½" Cft. 2.4 15% Wastage
Lock Rails 4 x 1 5'/8 x 8" x 1½" Cft.
Panels 6 x 1 5'/8 x 1¼' x 1" Cft. 1.32 15% Wastage
Nails & Glue L.S ...
Carpenters No 5
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
5 Corrugated Iron Doors and Windows for
7' x 3½' Double Leaf
( For 24.5 Sft )
Corrugated Iron 2 x 7' x 1¾' sht 2
Styles 4 x 7 1'/12 x 3¾" x 1½" Cft.
Top & Bottom Rails 4 x 1½' x 3¾" x 1½" Cft.
2.26 15% Wastage
Diagonal Rails, 4 x 3¼' x 3¾" x 1½" Cft.
Lock Rails 2 x1½' x 3¾" x 1½" Cft.
Nails, etc. lb 1/2
Carpenters No 1 1/2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
9 1½" Thick Teak Glazed Window, 1st Class,
4' x 3' ( Double Leaf)
( For 12 Sft )
21 oz Sheet Window Glass Panes Sft 9.05 50% Wastage
Styles 4 x 4'-0" x 4" x 1½" Cft.
Top and Bottom Rails 4 x 1'-6'' x 4" x 1½" Cft. 1.16 15% Wastage
Sash Bars 6 x 1' x 1½" x 1½" Cft.
Nails and Glue lb 1/4
Carpenters No 3
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
13 1½" Thick Venetianed And Glazed Window
5'-1" x 4'-1" Double Leaf.
( For 20.75 Sft )
21 oz Sheet Window Glass Panes Sft 6.6 50% Wastage
Styles 4 x 5'-2" x 3½" x 1½" Cft.
Top Rails 2 x 2'-1" x 4½" x 1½" Cft.
Bottom Rails 2 x 2'-1" x 5" x 1½" Cft.
Middle Rails 2 x 2'-1" x 4" x 1½" Cft.
Sash Bars 2 x3'-1½" x 1½" x 1½" Cft. 2.6 15% Wastage
Sash Beads 2 x 12' x ½" x ½" Cft.
5
Venetian Flaps, 20 x 1 /8' x 4" x ¾" Cft.
Venetian Rods, 2 x 2½' x 2" x ¾" Cft.
Venetian Beadings, 4 x 2½' x 1" x 1" Cft.
Nails and Glue L.S ...
Carpenters No 7
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
17 J Wood Verandah Gate With 3" x 1½" And
2" x ½" Batten Fixed Complete
(Double Leaf) 4' x 3'
( For 12 Sft )
J Wood Scantling Cft. 0.86 15% Wastage
½" Thick J Wood Plank Cft. 0.28 15% Wastage
1/16" Hoop Iron Catch No 1
4" Butt Hinges No 4
Nails and Glue Lb 1/4
Carpenters No 1
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
22 1" Thick Trellis Door With 3" x 1" Frame
(Single Leaf) 2'-9" x 6'-3"
( For 17.19 Sft )
Styles, 2 x 6'-3" x 3" x 1" Cft.
0.5 15% Wastage
Rails, 3 x 2'-9" x 3" x 1" Cft.
Zallies, 2 x 6'-3" x 3" x½" Cft.
Zallies, 3 x 2'-9" x 3"x ½" Cft. 1.07 15% Wastage
Diagonals, 17.19/100x600'x2"x½" Cft.
Nails Lb 3
Carpenters No 2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
25 1" Thick Fly Proof Door Complete With
Fly Proof Mesh ( Double Leaf ) 7' x 3'
( For 21 Sft )
Teak Planks 3" x 1" Cft. 0.96
15% Wastage
Teak Beadings 3" x ½" Cft. 0.48
Fly Proof Mesh Sft 23 10% Wastage
Nails Lb 1/4
Screws Gross 1/4
Carpenters No 3
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
F 5"x2" Cft. 8 15% Wastage
Nails Lb 2
Carpenters No 6
Note : (1)For
Rebating in
Fanlight, Allow
One More
(2) For Every
Additional
Rebating , Allow
One More
Carpenter for
100 Rft
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
32 Teak Swing Door of 1½" Thick Styles Rails
and Braces Including ½" P.T.G Teak
Planks for 3½' x 3' = 10.5 Sft
( For 10.5 Sft )
Teak Scantling Cft. 1.1 15% Wastage
Teak ½" P.T.G Cft. 0.34
Nails and Screws L.S
4" Spring Hinges No 4
Carpenters No 1 3/4
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
X. FLOORING
1 Brick on Edge Flooring in Lime Mortar And
Pointed With Cement Mortar 1:2
( For 100 Sft )
1st Class Bricks 9" x 4 3/8" x 2 ¾" No 550
Lime Mortar 1:1:1 Cft. 12
Cement Mortar 1:2 Cft. 1
Masons No 2
Workers No 4 1/2
Sundries L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
7 18" x 18"x1" Polished Marble Flooring Laid in
Cement Mortar 1:3
( For 100 Sft )
18"x18"x1" Marble Slab No 47 7% Wastage
Cement Lb 135
Sand Cft. 4.5
Masons No 2 1/2
Workers No 2 1/2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
12 1" Thick P.C.C 1:2:4 Floor Using Medium
Fine Stone or River Shingle Aggregate
( For 100 Sft )
Cement Concrete (1:2:4) Cft. 8 1/3
Battens And Sundries L.S ...
Masons No 3/4
Workers No 1
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
19 Finishing and Laying Smooth 3/8" Thick
Terrazzo Floor 1:2 With ¼" Marble
Chipping On 3/8" Thick Average Screed
in Cement Mortar 1:3 ( Cast in Situ )
( For 100 Sft )
Terrazzo 1:2 Cft 3 1/8
Cement Mortar 1:3 Cft 3 1/8
Approved Metal Plastic Dividing Strip Rft 50
Mason No 1
Grinder Using Machine Day 1/2
Polisher Using Machine Day 1/4
Oxalic Acid Dresser Day 1/2
Carborundum Stone L.S ...
Wax Polish L.S ...
Oxalic Acid L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
24 1" Tongue and Grooved Plank Flooring
With 4" x 1" Planks
( For 100 Sft )
4"x1" T & G Plank Cft. 10.96 15% wastage
Nails Lb 2
Carpenters No 2
Workers No 1
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XI. WALLING
1 ½" Teak Or Pyingado T & G Plank Walling
Without Frames
( For 100 Sft )
T & G Planks 4" x ½" Cft. 5.29 15% Wastage
Nails Lb 2
Carpenter No 2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Bricks 9" x 4 3/8"x 2 ¾" No 350
Cement Lb 118
Sand Cft. 4
Masons No 1 1/2
Workers No 2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
11 Palisading Walling For Prisoners Cage
Including Rivets
( For 100 Sft )
3/8"ø Rivets 6½" Long No 88
Frames 4x10'x5"x4" Cft.
18.34 10% Wastage
Verticals 20 x 10' x 4" x 2" Cft.
Carpenter No 3
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
17 Fly Proof Mesh Fixed With 2" x 1" Teak
Fillets And 1½" x ½" Teak Beading
Complete
( For 100 Sft )
1½" x ½" Teak Beadings Cft 0.72 15% Wastage
2" x 1" Teak Fillets Cft 1.92 15% Wastage
Fly Proof Mesh (Wire) Sft 110
Nails Lb 1
Carpenters No 1 1/2
18 Bird Proof Wire Mesh Fixed With 2" x 1"
Teak Fillets And 1½" x ½" Teak Beading
Complete
( For 100 Sft )
½" Teak Plank Cft 0.72 15% Wastage
1" Teak Plank Cft 1.92 15% Wastage
Bird Proof Mesh (Wire) Sft 110
Nails Lb 1
Carpenters No 2 1/2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
23 Double Bamboo Mat Wall( Coarse Outside
and Fine Inside) With 2" x ½" Zallies But
Without Frames
( For 100 Sft )
½" Planks Cft 0.32 15% Wastage
Mat (Coarse Bamboo ) Sft 115
Mat (Fine Bamboo ) Sft 115
Wire Nails Lb 1 1/2
Carpenters No 1
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XII. CEILING
1 4" x ½" T & G Plank Ceiling With 4" x 2"
Joist at 2' Centres.
( For 100 Sft )
4" x ½" T & G Planks 331Rft Cft. 5.29 15% Wastage
Joist, 5½ x 10' x 4" x 2" Cft. 3.36 10% Wastage
Nails & Spikes Lb 2 1/2
Carpenter No 2 1/2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Teak Beading 1½" x ½" Cft 0.96 15% Wastage
1½" Wood Screws Gross 1 1/2
Nails Lb 1 1/2
Carpenters No 7 1/2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
12 X.P.M ¾" Mesh ¼" Thick Ceiling With
3" x ½" Beadings
( For 100 Sft )
X.P.M ¾" Mesh ¼" Thick Sft 110 10% Wastage
Beadings, 3" x ½" Cft 0.96 15% Wastage
Nails Lb 1 1/2
Carpenters No 2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XIII. ROOFING
1 Danyingon (Mangalore Pattern) Clay Tile
Roofing With 2" x 1" Battens And 4" x 2"
Common Rafters
( For 100 Sft )
Mangalore Pattern Clay Tiles No. 156 20% Wastage
2" x 1" Battens At 13" Centres Cft 1.76 15% Wastage
4" x 2" Common Rafters 2' Centres Cft 3.42 10% Wastage
Nails & Spikes Lb 2
Binding Wire L.S ...
Carpenter No 2
Workers No 2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
6 Galvd. C. I Roofing Laid on 1" Planking
( For 100 Sft )
Galvd. C. I Sheet, 7'- 10/3 No 7
G.I Roofing Nails Lb 1 1/2
1" Thick Planking Cft 9.58 15% Wastage
Nails Lb 2
Carpenters No 3
Workers No 1
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
11 Thatch Roofing With Bamboo Rafters
And Purlins
( For 100 Sft )
Bamboo Rafters 9" Centers 10' Long No 14
Bamboo Purlins 18" Centers 10' Long No 7
Bamboo Small Size For Lattice Work 10' Long No 20
Thatch ( 6 Nos to 1' ) No 120
Cane Ties L.S ...
Thatch Layer No 1
Workers No 1
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
15 Dhani, Thetke or Thatch Roofing Laid 6
Byits to a Foot With 6" Side Laps and
Including a Covering of Bamboo Lattice
Frames And 1½"ø Wind Ties At 4'
Centres
( For 160 Sft )
1½"ø Bamboo Rafters At 12" Centres No 11
1½"ø Bamboo For Lattice And Wind Ties No 15
Dhani, Thetke or Thatch (6 Nos to a Foot) No 120
Hnee Viss 1
G.I Binding Wire Lb 1/2
Dhani or Thatch Layer No 1
Workers No 1
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
21 Wooden Ridge And Hip Covers
( For 10 Rft )
Ridge Roll 1 x 10' x 4" x 3" Cft 0.92 10% Wastage
Boards, 2 x 10' x 9" x 1" Cft 1.44 15% Wastage
Nails Lb 1/4
Carpenters No 1/4
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
26 5 Lb Per Sft Flashing 18" Wide For 150 Sft
( For 100 Rft )
7' x 3' Lead Sheet 5 Lb/Sft Sht 9
Composite Mortar Cft 2.5
Mason No 2
Tin Smith No 2
Workers No 4
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
32 Corrugated A.C or Trafford Ridging With
½" Hook Bolts And Nuts And Washers
( For 100 Sft )
A.C Ridging Tile Rft 100 *To be included
¼"ø Bolts And Nuts and Washers Lb 22* only if the Ridging
Carpenters No 3 1/3 is Carried out
Workers No 1 Separately
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XIV. PAINTING AND WASHING
1 Coal Tarring One Coat (New Work)
( For 100 Sft )
Coal Tar Gal 3/4
Workers No 3/8
Sundries Including Brushes, Fuel, Etc. L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
9 Distemper One Coat
( For 100 Sft )
Distemper Lb 3
Painter No 1/4
Workers No 1/8
Sundries Including Brushes, Fuel, Etc. L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
17 Colour Washing One Coat
( For 100 Sft )
Strained Lime Cft 1/2
Yellow Powder Lb 1/8
Liquid Glue Lb 1/8
Painter No 1/8
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
22 Painting One Coat With Red Lead Ready
Mixed (New Work)
( For 1000 Sft )
*Red Lead Paint (Ready Mixed) Lb 30 *For Renewal
Putty Lb 4 20 Lb Only
Painter No 2 1/2
Workers No 2 1/2
Sundries Including Brushes L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
27 Painting One Coat With White Zinc Ready
Mixed (Renewal)
( For 1000 Sft )
White Zinc Ready Mixed Lb 28
Putty Lb 2
Painter No 2 1/2
Workers No 2 1/2
Sundries Including Brushes L.S ...
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
33 Painting Three Coats to Wood Work in
Posts, Chowkets, Facia Boards, Eave
Boards And Stringers With Ready Mixed
Paint of Any Approved Colour
( For 1000 Sft )
Ready Mixed Paint Lb 75
Putty Lb 4
Painter No 12 1/2
Workers No 10
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
40 Wood Oiling Two Coats
( For 100 Sft )
Wood Oil Lb 3
Workers No 3/4
Sundries Including Brushes L.S …
41 Bee's Waxing
( For 100 Sft )
Bees Wax Lb 1/4
Turpentine Pint 1/8
Painter No 1
Sundries Including Labour For Wood, L.S …
Dust Topping Cloth L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
48 Bengal Polishing Three Coats to
Wooden Wall
( For 100 Sft )
Methylated Spirit Gal 1 1/4
Shellac Lb 1 1/4
Sand Paper, Cotton Waste, Etc. L.S …
Polisher No 7
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XV. FENCING
1 Wooden Fencing With Posts 8 1/3 Centres
And Two Longitudinal Rails
( For 100 Rft )
Coal Tar, Two Coats Gal 4 1/4
Corner Post, 1 x 6½' x 5" x 5" Cft 10% Wastage
Cross Feet, 2 x 2' x 5" x 3" Cft For 24 Cft :-
Interposts, 11 x 6' x 5" x 3" Cft 24 4 Carpenters and
Cross Feet, 22 x 1½' x 5" x 2" Cft Coal Tarring 350
Longitudinal Rails, 2 x 100' x 4" x 2" Cft Sft, Workers for
Nails And Spikes Lb 7 12 Posts Holes
Carpenters No 4
Workers No 4
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
5 American Woven Wire Fencing With R.C
Posts 12½' Apart
( For 100 Rft )
American Woven Wire Rft 100
R.C Corner Posts At 200' Apart No 1/2
R.C InterPosts And One Strut No 8
Lime Concrete Foundation For Corner Post,
Cft 5
½ x 2' x 2' x 2½'
Straining Bolts 18" x ½" ø No 5
Binding Wire Staples Lb 1
Carpenters No 2
Workers No 2
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
8 Chain Link Fencing With 4" x 4" Timber
Post 8' Apart Embedded in 1:2:6 Lime
Concrete
( For 96 Rft )
5" x 5" Corner Posts, 1 x 8' x 5" x 5" Cft
4" x 4" Posts, 11 x 8' x 4" x 4" Cft
18.38 10% Wastage
Struts , 9x10'x4"x2" Cft
Battens, 13 x 6' x 2" x ½" Cft
Straining Wire, 3/8" Dia., 3 x 96' Rft 288
Chain Link, 6 x 96' Sft 576
Lime Cft 4.55
Sand Cft 9.1
Brick Aggregate Cft 27
Nails Lbs 1
Carpenters No 2
Workers No 4
pg-66
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XVI. IRON AND STEEL WORK
1 Hoisting And Fixing R.S Girder
(Over ½ Ton Weight)
( For 1 Cwt )
R.S Girder Cwt 1
Carriage to Site Cwt 1
Hoisting And Fixing Cwt 1
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
8 Mild Steel Bar Reinforcement 5/8" to 1"
Dia. Cut, Bend And Fixed in Columns
And Braces
( For 1 Cwt )
5/8" to 1" Dia. Bar Lbs 117.6 5% Wastage
14 S.W.G Binding Wire Lb 1
Smith (Steel Fixer) No 1
Workers No 1
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
FIXING ONLY STEEL FABRIC.
14 Fixing Steel Fabric or Mesh Reinforcement
in Beams, Floors And Walls, B.R.C
Expended Metal or Other Type, Including
All Straight Cutting And The Supply of
And Wiring as Necessary With 14G.
Wiring, Measured Nett No Allowance
For Laps
( For 100 Sft )
Sheet Weighting Under 4 Lbs Per Yard
Super
Smith or Steel Fixer No 1/2
Binding Wire(14 G.) L.S …
FIXING STEEL
15 Fixing Steel Fabric or Mesh Reinforcement
in Beams, Floors And Walls, B.R.C
Expended Metal or Other Type, Including
All Straight Cutting And Wiring as
Necessary With 14G. Wire, Measured
Nett And No Allowance For Laps
( For 100 Sft )
Sheet Weighting Under 4 Lbs Per Yard
Super
Smith or Steel Fixer No 3/4
Binding Wire(14 G.) L.S …
Sheet From 4 Lbs to 8 Lbs Per Yard
Super
Smith or Steel Fixer No 6/7
Binding Wire(14 G.) L.S …
Sheet Over 8 Lbs And Under 17 Lbs Per
Yard Super
Smith or Steel Fixer No 1 1/2
Binding Wire(14 G.) L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
17 Hasp And Staple 4" to 6" Fixed Complete
With Screws
( Each )
4" to 6" Hasp and Staple No 1
¾" wood Screws Gross 1/18
Carpenters No 1/50
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XVII. ROAD WORK
1 Earthwork in Excavation in Ordinary Soil
Either in Embankment or in Cutting With
an Initial Lead of 100 Feet And
Lift of 5 Feet
( For 1000 Cft )
Mastery No 1/2
Digger No 7 Tasks= 140 cft for
Workers For Carrying No 7 1 digger
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
6 Excavation in Hard Rock By Blasting
Including Removing Stones
( For 100 Cft )
Blasting Powder Lb 3
Charcoal Lb 10
Miner No 5
Workers No 5 1/2
Blacksmith No 1/4
Bellow Boy No 1/2
Hammer Man No 1/2
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
12 Collection And Conversion of Blasted
Debris to Metal At The Quarry Site
( For 100 Cft )
Labour
Hammer Man Man day 1 1/2
Workers Man day 3
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
19 Extraction of 1½" to 2" Stone Metal
Including Blasting And Breaking to Size
At The Quarry Site
( For 100 Cft )
Blasting Powder Lb 3
Charcoal Lb 10
Miner No 5
Blacksmith No 1/4
Bellows Boy No 1/4
Hammer Man No 1
Workers For Breaking And Stacking No 8
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
25 Collection of River Shingles Chippings
(½" to ¾") Within 2 Furlongs Lead
( For 100 Cft )
Workers For Collection No 4
Workers For Breaking And Stacking, Etc. No 6
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
31 Consolidation of 6" Soling By Steam Roller
After Hand Packing.
( For 1000 Cft )
Steam Roller Charges Day 1
Mastery No 1
Workers No 21
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Labour for Brushing Old Surface, Spraying,
Spreading, Etc. No 380
Rolling Charges Steam Roller Day 16
Hire for Boiler Sprayer, Etc. Day 12
Wire And Bristle Brushes L.S …
Miscellaneous Camber Board, Etc. L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
38 2" (Consolidated Thickness) Premix Carpet.
(For 1 Mile x 12' = 63360 Sft)
Labour for Brushing Road Surface No 300
Main Coat
1" to 1¼" Stone 7670 Cft Cft 11500
¼" to ¾" Stone 3830 Cft
Bitumen at 3 Lb per Cft Ton 20.31 13% Wastage
Sand At 5% of Stone Cft 575
Bitumen For Sand at .25 Lb per Cft Ton 0.07 13% Wastage
Topping Course
¼" to ½" Chipping At 5 Cft Per 100 Sft Cft 3200
Bitumen at 4 Lb per Cft Ton 6.45
Wearing Course
¼" to ½" Chipping At 4.5 Cft Per 100 Sft Cft 2900
1/8" to ¼ Chipping
Bitumen at 25 Lb per %Sft Ton 8.00 13% Wastage
Sand For Final Coat At 3 Cft Per %Sft Cft 1300
Railway Freight For Bitumen Ton 34.83
Carriage to Site Ton 34.83
Wood Fuel Cft 1066
Labour for Spreading, Spraying, , Etc. No 1000
Road Roller Charges M Coat Day 25
Road Roller Charges Topping Course Day 4
Road Roller Charges W Coat Day 25
Wire And Bristle Brushes L.S …
Miscellaneous, Tools & Plant, Camber
Board, Etc. L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XVIII. ROAD WORK (BY MACHINE)
1 Earthwork in Excavation By Machine For
100 Ft. Average Haul in Ordinary Soil For
Level Excavation For 10000 Cft
Labour (A) For 1:10
Workers For Teak Cleaning, Etc. Man 1 Upgrade
Operator No 1 1/3 Dozing Allow
Fitter No 2/3 25% Increase
Machine Over Level
Bull Dozer ( D 8 ) Hour 5 1/3 Excavation
POLL For Operation (B) For 1:10
H.S.D Gal 20 Downgrade
Engine Oil Gal 1/3 Dozing Allow
Gear Oil Gal 1/3 25% Deduction
Hydraulic Oil Gal 2/3 Over Level
Grease Lb 1/3 Excavation
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Tools And Machine
Air Compressor Hour 8 Life- 200' Boring
Pneumatic Drill Hour 8
Drill Bit (10' Boring) Hour 1 x 1/20
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
7 Consolidation of Sand 4" Thick By Diesel
Roller
( For 2500 Cft )
Labour
Head Worker Man day 1 Whenever Roller
Worker Man day 25 is Required Over
Roller Driver Man day 1 Night One Night
Material Durwan Per
Sand Cft 2500 Night is Allowed
Machine in the Consolida-
Roller Hour 8 tion Item
P.O.L for Operation
H.S.D Gal 6
Engine Oil Gal 1/4
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Material
2" To 4" Metals Cft 1000
Machine
Roller Hour 8
P.O.L for Operation
H.S.D Gal 6
Engine Oil Gal 1/4
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
12 Working Expenses Of Diesel Roller Per
Day
Labour Employment of
Roller Driver Man day 1 mechanics, etc.
Night Durwan Man day 1 For Maintenance
Material And Tools of Mechanical
Water Cart No. of Day 1 Equipments To
For Operation Be Included In
H.S.D Gal 6 The Main
Engine Oil Gal 1/4 Estimate
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
17 Hot Bitumen 1½" Depth Grouting (Semi
Grout) Over Stone Metal Surface With
¼" to ¾" Chippings
( For 1 Mile x 12' = 63360 Sft )
Labour
Head Worker Man day 15 Based on 3"
Workers Man day 225 Compacted
Boiler Man day 15 Thickness
Materials
Bitumen Ton 23.96 13% Wastage
Chippings Cft 4000
Machine
Roller Day 15 Whenever Roller
Bitumen Heater Day 8 x 1½ is Required Over
Thermometer Day 8x1 Night One Night
Cotton Waste For Cleaning, Etc. L.S … Durwan Per
For Operation Night is Allowed
Fire Wood Ton 8.50 in the Consolida-
H.S D Gal 6 tion Work
Engine Oil Gal 1/4
Gear Oil Gal 15 x 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Workers Man day 200
Roller Driver Man day 15
Materials
Bitumen At 40 Lb Per % Sft Ton 13 13% Wastage
Chippings Cft 3600
Machine Whenever Roller
Roller Day 15 is Required Over
Bitumen Heater Day 8 x 1½ Night One Night
Thermometer Day 8x1 Durwan Per
For Operation Night is Allowed
Fire Wood Ton 5.12 in the Consolida-
H.S D Gal 6 tion Work
Engine Oil 1/4
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Machine And Tools
Roller Day 12 Whenever Roller
Bitumen Heater Day 8 x 1½ is Required Over
Thermometer Day 8x1 Night One Night
For Operation Durwan Per
Fire Wood Ton 3.20 Night is Allowed
H.S D Gal 6 in the Consolida-
Engine Oil 12 x 1/4 tion Work
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
24 Laying Only of Hot Mix Asphalts Concrete
of 1½" Thickness.
( For 1200 Cft )
Labour Whenever Roller
Time Keeper Man day 2 is Required Over
Foreman Man day 2 Night One Night
Traxcavator Operator Man day 2 Durwan Per
Paver Operator Man day 2 Night is Allowed
Mixer Operator Man day 3 in the Consolida-
Air Compressor Operator Man day 1 tion Work
Head Workers 13% Wastage
For Paver Man day 1
For Mixer Man day 1
For General Works Man day 1
Workers
For Paver Man day 12
For Mixer Man day 14
For General Tar Boiling & Transporting Man day 11
Machine Working
Mixer (Hot) Millers 10 Ft. Capacity Day 1 Expenses To Be
Drier For Chips Day 1 Included. Cost Of
Tar Boilers 5 Nos Day 5 Material
12' Wide Barber Green Paver 1 No. Day 1 i.e. Coarse
Taden Roller 2 (6 Tons) Day 2 Aggregate, Fine
Tipper 5 Nos Day 1 Aggregate
Water Bowzer 1 No. Day 1 Fillers And
Traxcavator Grader 1 No. Day 1 Bitumen in The
Air Compressor Day 1 Varying Mixes
For Operation is To Be
H.S.D For Machines Gal 200 Included In The
Engine Oil Gal 4 Main Estimate.
Grease Lb 4
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XIX. BRIDGES
1 Labour For Driving 10" Diameter Timber
Piles In Ordinary Soil (With ½ Ton Drop
Hammer From Pulley Winch And Local
Trestle And Manually Operated)
Penetration Average 20 Feet.
Labour Cost of timber
Foreman Man day 1/4 piles according
Carpenter (1st Grade) Man day 1/2 to varying dia.
Carpenter (2nd Grade) Man day 1/2 with all necessary
Workers Man day 3 fittings is to be
Plants Included in the
Pile Driving Frame 1 No. Hour 4 Main Estimate
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
4 Labour For Pile Driving Reinforced Cement
Concrete Pile 14" x 14" x 40" In Ordinary
Soil (Using Drop Hammer With Winch
Operated By Machine). Penetration
Average 40'.
Labour
Foreman Man Day 1/2
Operator Man Day 1/2
Workers Man Day 8 Cost of R.C piles
Machine to be calculated
Pile Driving Machine 1 No. Hour 4 according to the
For Operation required size and
Diesel Oil Lb 4 included in the
Grease Oil Gal 1/4 main estimate.
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
8 Labour For Assembling And Launching of
C.H Bridge (22' Road Way)
Bolts And Nuts For All Steel Works
Complete 160' Span Double Depth.
Total Weight = 150 Tons
Labour
Bridge Foreman Man Day 45
Skilled Workers Man Day 315
Unskilled Workers Man Day 2385
Tools Required
Tool Kit 1 No.
One Hummer
Coil Rope 1"ø 200'
4 Ton Hand Winch 2 Nos
Bailey Roller 6 Nos
Jumper 10 Nos.
Wire Rope 5/8" ø = 750'
One Local Jip
Double Pulley 2 Nos
Single Pulley 1 No.
50 Ton Jack 2 Nos.
Sundries L.S …
Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Single Pulley 1 No
One Bellow
Two Dollys
Two Riveting Gun
One Compressor with two Nos, Hose Pipes 500'
Local Jip One No.
One Hammer
75 Tons Jacks 2 Nos.
Sundries L.S …
Standard Data For Working Out Rates Per Unit Quantity Of Items Of Work
Sr. No Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
MISCELLANEOUS NOTES
Allowing Wastage of Building Materials
1 The Quantities of Material Given Allow For
Ordinary Breakages, Wastage, Carriage,
Etc., Viz.
(a) Scantling ( All timber ) 10%
(b) Small Timber 2" x 2" cross section and below 15%
(c) and for doors and windows 15%
(d) X.P.M Wire Netting 10%
(e) Glass 50%
(f) Roofing Tiles
(i) Mangalore Pattern 20%
(ii) Cement Roof Tiles 10%
(iii) Asbastos Cement Sheets 10%
(g) Floor Tiles 5%
Marble Slabs 7%
(h) Plywood 15%
(i) Steel Rods 5%
2 Brick Work
(a) Brick work in lime mortar up to plinth 25 Cft per day
(b) Brick work in superstructure 25 Cft per day
(c) Brick work in arches in buildings 20 Cft per day
(d) Brick work in bridges 20 Cft per day
(e) Brick on edge in lime mortar 50 Cft per day
3 Stone Work
(a) Coursed rubble masonary (dressing) 20 Cft Each
pg-[92]
Standard Data For Working Out Rates Per Unit Quantity Of Items Of Work
Sr. No Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
(b) Coursed rubble masonary laying 25 Cft Each
(c) Random rubble stone masonary (dressing & laying) 25 Cft Each
(d) Random rubble stonedry as in retaining walls 50 Cft Each
(e) Coursed stone arched work
4 Wood Work
(a) Sawing hard wood ( Pyingado or Engin ) 40 Sft ( one pair of sawyers)
(b) Sawing soft wood 60 Sft ( one pair of sawyers)
(c) Chawkets Hard Wood 1 Cft Each
(d) Chawkets Soft Wood 1½ Cft Each
(e) Door battened and planed (teak) 6 Sft Each
(f) Door battened and planed (Engin) 6 Sft Each
(g) Door panelled and glazed (teak) 5 Sft Each
(h) Door panelled and glazed (other timber) 6 Sft Each
(i) Window fulley glazed (teak) 4 Sft Each
5 Roofing
(a) Mangalore tiles 50 Sft Each
(b) C.I Sheets 70 Sft Each
(c) Wagat 100 Sft Each
(d) Thatch 100 Sft Each
(e) Shingle 40 Sft Each
MEANS OF TRANSPORT
1" 0.213 0.425 0.638 0.85 1.28 1.7 2.13 2.55 2.98 3.4
1½" 0.319 0.638 0.956 1.28 1.91 2.55 3.19 3.83 4.46 5.1
2" 0.425 0.85 1.28 1.4 2.55 3.4 4.25 5.1 5.95 6.8
2½" 0.531 1.06 1.59 2.13 3.19 4.25 5.31 6.38 7.44 8.5
3 0.638 1.28 1.91 2.55 3.83 5.1 6.38 7.65 8.93 10.2
3½" 0.744 1.49 2.23 2.98 4.46 5.95 7.44 8.93 10.41 11.9
4 0.85 1.7 2.55 3.4 5.1 6.8 8.5 10.2 11.9 43.6
4½" 0.956 1.91 2.87 3.83 5.74 7.65 9.56 11.48 13.39 15.3
5½" 1.17 2.34 3.51 4.68 7.01 9.35 11.69 14.03 16.36 18.7
6 1.28 2.55 3.83 5.1 7.65 10.2 12.75 15.3 17.85 20.4
6½" 1.38 2.76 4.14 5.53 8.29 11.05 13.81 16.58 19.34 22.1
7 1.49 2.98 4.46 5.95 8.93 11.9 14.88 17.85 20.83 23.8
7½" 1.59 3.19 4.78 6.38 9.56 12.75 15.94 19.12 22.31 25.5
8½" 1.81 3.61 5.42 7.25 10.84 14.45 18.06 21.68 25.29 28.9
9 1.91 3.83 5.74 7.65 11.48 15.3 19.13 22.95 26.78 30.6
9½" 2.02 4.04 6.06 8.08 12.11 16.15 20.19 24.23 28.26 32.3
10½" 2.23 4.46 6.7 8.93 13.39 17.85 22.31 26.75 31.24 35.7
11 2.34 4.68 7.01 9.35 14.03 18.7 23.38 28.05 32.73 37.4
11½" 2.44 4.89 7.32 9.78 14.66 19.55 24.44 29.33 34.21 39.1
12 2.55 5.1 7.65 10.2 15.3 20.4 25.5 30.6 35.7 40.8
¼" 0.052 0.105 0.159 0.213 0.319 0.425 0.531 0.638 0.744 0.85
¾" 0.158 0.319 0.477 0.638 0.956 1.275 1.594 1.913 2.231 2.55
Pg-[96]
Weight in lbs of shenderd bolts and nuts Hexagonal head and nuts
Width Thickness in inches
in
inches 1/4" 3/8" 1/2" 5/8" 3/4" 7/8" 1" 1 1/8" 1 1/4" 1 1/2"
1" 0.042 0.106 0.222 0.376 0.612 … … … … …
1½" 0.049 0.122 0.25 0.419 0.675 0.986 1.394 … … …
2" 0.056 0.38 0.278 0.463 0.737 1.072 1.505 2.036 2.671 …
2½" 0.063 0.153 0.305 0.506 0.8 1.157 1.616 2.177 2.845 …
3 0.069 0.169 0.333 0.549 0.862 1.242 1.727 2.318 3.019 4.766
3½" 0.075 0.185 0.361 0.593 0.925 1.327 1.838 2.459 3.193 5.016
4 0.082 0.2 0.389 0.637 0.988 1.412 1.95 2.6 3.367 5.267
4½" 0.089 0.216 0.417 0.68 1.05 1.497 2.061 2.74 3.541 5.517
5 0.096 0.232 0.445 0.724 1.113 1.583 2.172 2.881 3.714 5.767
5½" 0.103 0.247 0.472 0.767 1.175 1.667 2.283 3.022 3.888 6.018
6 0.11 0.263 0.5 0.81 1.238 1.753 2.394 3.163 4.062 6.268
6½" 0.117 0.279 0.528 0.854 1.3 1.838 2.506 3.303 4.236 6.518
7 0.124 0.294 0.556 0.897 1.363 1.923 2.617 3.444 4.41 6.769
7½" 0.13 0.31 0.584 0.941 1.425 2.008 2.728 3.585 4.584 7.019
8 0.138 0.326 0.612 0.984 1.488 2.094 2.839 3.726 4.757 7.27
8½" … 0.341 0.639 1.028 1.55 2.179 2.95 3.867 4.931 4.52
9 … 0.357 0.667 1.071 1.613 2.264 3.062 4.008 4.105 7.77
9½" … … 0.695 1.115 1.676 2.349 3.173 4.149 5.279 8.021
10 … … 0.723 1.158 1.739 2.434 3.284 4.29 5.453 8.271
10½" … … … 1.202 1.801 2.519 3.396 4.43 5.627 8.521
11 … … … 1.245 1.863 2.605 3.507 4.57 5.8 8.772
11½" … … … … 1.926 2.689 3.618 4.71 5.974 9.022
12 … … … … 1.989 2.775 3.729 4.853 6.148 9.272
Weight of round and square M.S rods Weight of round washer per 100 Nos
Dia. Of side in inches Round Square Dia. of round washers Weight in lbs per 100 Nos.
¼" 0.167 0.213 ½" dia. 2½
5/16" 0.261 0.478 5/8" dia. 4
3/8" 0.376 0.849 ¾" dia. 5½
½" 0.668 1.328 7/8" dia. 7½
5/8" 1.043 1.912 1" dia. 14
¾" 1.502 2.603 1 1/8" dia. 17
7/8" 2.044 3.4 1¼" dia. 21½
1" 2.67 5.312 1 3/8" dia. 26
1¼" 4.172 7.65 1½" dia. 30½
1½" 6.008 2" dia. 64
3" dia. 21.4
Pg-[99]
B.R.C No. Lbs per sq. yd. Lbs per sq. ft. Lbs per 100 sft
7 6.57 0.74 74
8 5.67 0.63 63
9 4.71 0.523 52.3
10 3.94 0.438 43.8
12 2.72 0.302 30.2
14 1.83 0.203 20.3