INDEX

Schedule No. Name of Work Page

I EARTH WORK … … … 1 … 3

II MORTAR … … … 4 … 5

III CONCRETE (HAND MIXED) … … … 6 … 9

IV REINFORCED CONCRETE (HAND MIXED) … … 10 … 11

REINFORCED CONCRETE (MACHINE MIXED) … … 12 … 13

V BRICK … … … 14 … 16

VI STONE WORK … … … 17 … 18

VII PLASTERING AND POINTING … … … 19 … 21

VIII WOOD WORK … … … 22 … 25

IX DOOR AND WINDOW … … … 26 … 34

X FLOORING … … … 35 … 39

XI WALLING … … … 40 … 44

XII CEILING … … … 45 … 47

XIII ROOFING … … … 48 … 54

XIV PAINTING AND WASHING … … … 55 … 62

XV FENCING … … … 63 … 65

XVI IRON AND STEEL WORK … … … 66 … 69

XVII ROAD WORK … … … 70 … 77

XIII ROAD WORK ( BY MACHINE ) … … … 78 … 86

XIX BRIDGES … … … 87 … 90

MISCELLANEOUS NOTES … … … 91 … 100


pg-1

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
I. EARTH WORK
1 Site Clearing including Cutting Trees and
Bushes and Dressing
( For 100 Cft ) L.S … ( According to site condition )

2 Earth Work in Excavating Foundation in


Ordinary Soil to a Depth of 5 Ft. and
Removing the Excavated Materials as
Directed Within 100 Ft.
( For 100 Cft )
Workers No 1 1/2
Sundries L.S …

3 Earth Work in Excavating Foundation in


Medium Soil to a Depth of 5 Ft. and
Removing the Excavated Materials as
Directed Within 100 Ft.
( For 100 Cft )
Workers No 2
Sundries L.S …

4 Earth Work in Excavating Foundation in


Hard Soil to a Depth of 5 Ft. and
Removing the Excavated Materials as
Directed Within 100 Ft.
( For 100 Cft )
Workers No 3
Sundries L.S …

5 Earth Work in Ordinary Soil with


Excavated Earth Filling in 6" Layers
Watering and Ramming Within 100 Ft.
( For 100 Cft )
Worker No 1/2
Worker for carrying & ramming No 3/4
Worker for watering No 1/4
Sundries L.S …

6 Earth Work Over Areas in Ordinary


Ground in Cutting and Leveling Site
including Carrying away Surplus Spoils
Spreading and Leveling Within 100 Ft.
( For 100 Cft )
Workers No 1 1/4
Sundries L.S …

7 Earth Work in Excavation Over Areas in


Cutting and Leveling in Hard Soil
including Disposal of Surplus Spoil
not Exceeding 100 Feet.
( For 100 Cft )
Workers No 2 1/2
Sundries L.S …
pg-2

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
8 Excavating in Medium Soil and Filling
and Forming Embankment,
Lead 100 Feet, Lift 5 Feet
( For 100 Cft )
Mastery No 1/8
Digger No 1 1/2
Worker for carrying No 1
Sundries L.S …

9 Excavate and Filling and Forming


Embankment, Lead 100 Feet,
Lift 10 Feet
( For 100 Cft )
Mastery No 1/8
Digger No 1 1/2
Workers for carrying No 2
Sundries L.S …

10 Earth Work ( Items 2,3 & 4 ) Extra for


Every Additional 5 Feet Depth
( For 100 Cft )
Worker No 1/2

11 Earth Work ( Items 2,3 & 4 ) Extra for


Every Additional 100 Feet Lead
( For 100 Cft )
Worker No 1/2

12 Sand Filling, Watering and Ramming


( For 100 Cft )
Sand Cft 125
Worker for Carrying & Ramming No 1/2
Worker for Watering No 1/2
Sundries L.S …

13 Digging Post Holes Under 2 Feet Square


in Any Soil Average 2 Ft. Depth
( For Each Hole)
Digger No 1/8

14 Digging Post Holes Under 2 Feet Square


Not Exceeding 3 Ft. Depth in Each
Hole in Hard Soil Part Return and Fill
( For Each Hole)
Digger No 1/5

15 Digging Post Holes Not Exceeding 12 Cft.


in Each Hole in Medium Soil Part
Return and Fill
( For Each Hole)
Digger No 1/6
pg-3

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
16 Digging Post Holes Not Exceeding 12 Cft.
in Each Hole in Ordinary Soil Part
Return and Fill
( For Each Hole)
Digger No 1/7

17 Digging Post Holes Not Exceeding 10 Cft.


in Each Hole in Hard Soil
( For Each Hole)
Digger No 1/5
Worker No 1/8
Sundries L.S …

18 Digging Drain 1'-6" at Top 9" at Bottom


and Average Depth 12" ( Ordinary Soil )
( For 100 Rft )
Worker No 2
Sundries L.S …

19 Digging Drain 1'-6" at Top 9" at Bottom


and Average Depth 12" ( Hard Soil )
( For 100 Rft )
Worker No 3
Sundries L.S …

20 Digging Latrine Pit of Any Size up to


10 Ft. Depth in Hard Soil
( For 100 Cft )
Worker No 3 3/8
Sundries L.S …

21 Earth Work in Digging in Sand or Clay or


Laterite up to 10 Ft. Initial Depth
( For 100 Cft )
Worker No 3
Sundries L.S …

22 Earth Work Extra for Every Additional


5 Feet Lift
( For 100 Cft )
Worker No 1/2
pg-4

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
II. MORTAR
1 Cement Mortar 1:2
( For 100 Cft )
Cement 46 Cft Lbs 4140
Sand Cft 92
Workers for Mixing No 4

2 Cement Mortar 1:3


( For 100 Cft )
Cement 33 Cft Lbs 2970
Sand Cft 100
Workers for Mixing No 4

3 Cement Mortar 1:4


( For 100 Cft )
Cement 25 Cft Lbs 2250
Sand Cft 100
Workers for Mixing No 4

4 Composite Mortar for Plaster 1:1:6


( For 100 Cft )
Cement 16 2/3 Cft Lbs 1500
Lime Cft 16 2/3
Sand Cft 100
Workers for Mixing No 4

5 Damp Proof Cement Mortar 1:2 with 5%


Pudlo by Weight of Cement
( For 100 Cft )
Cement 48 Cft Lbs 4320
Pudlo Lbs 216
Sand Cft 96
Workers for Mixing No 4

6 Cement Mortar 1:6


( For 100 Cft )
Cement 16 2/3 Cft Lbs 1500
Sand Cft 100
Workers for Mixing No 4

7 Lime Mortar 1:2


( For 100 Cft )
Lime Cft 46
Sand Cft 92
Workers for Mixing No 4

8 Lime Mortar 1:1:1


( For 100 Cft )
Lime Cft 50
Sand Cft 50
Surkhi Cft 50
Workers for Mixing No 7
pg-5

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
9 Lime Mortar 1:1:1 For Small Work
( For 100 Cft )
Lime Cft 50
Sand Cft 50
Surkhi Cft 50
Workers for Mixing No 8

10 Lime Mortar 2:3:1 For Plaster


( For 100 Cft )
Lime Cft 50
Sand Cft 75
Surkhi Cft 25
Workers for Mixing No 7

11 Lime Mortar 2:3:1 For Plaster For Small Work


( For 100 Cft )
Lime Cft 50
Sand Cft 75
Surkhi Cft 25
Workers for Mixing No 8

12 Composite Mortar 1:2:6 For Plaster


( For 100 Cft )
Cement Lbs 1440
Lime Cft 32
Sand Cft 100
Workers for Mixing No 4

13 Mud Mortar
( For 100 Cft )
Selected Suitable Clay (Mud) Cft 100
Workers for Mixing No 2

14 Lime Mortar 1:1


( For 100 Cft )
Lime Cft 75
Sand Cft 75
Workers for Mixing No 4

15 Composite Mortar 1:½:4 For Plaster


( For 100 Cft )
Cement Cft 24.2
Lime Cft 12.1
Sand Cft 96.8
Workers for Mixing No 4
pg-6

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
III. CONCRETE (HAND MIXED)
1 Cement Concrete with Stone Ballast 1½"
Gauge 1:3:6
( For 100 Cft )
Cement 16 Cft Lbs 1440
Stone Ballast 1 ½" Gauge Cft 96
Sand Cft 48
Mason No 1
Workers No 8

2 Cement Concrete 1:2:4 with ¼" to ¾" Stone


Chipping or River Shingle Aggregate
( For 100 Cft )
Cement 23 Cft Lbs 2070
Stone Cft 92
Sand Cft 46
Mason No 1
Workers No 10

3 Mixing Only Cement Concrete 1:2:4 with ½"


to ¾" Gauge Stone Chipping or River
Shingle Aggregate
( For 100 Cft )
Mason No 1
Workers No 5

4 Cement Concrete with ¾" Stone Ballast or


River Shingle Aggregate 1:2½:5
( For 100 Cft )
Cement 19 Cft Lbs 1710
Stone Ballast ¾" Gauge Cft 94
Sand Cft 47
Mason No 1
Workers No 10

5 Cement Concrete 1:1½:3 with ¼" To ¾"


Stone or River Shingle Aggregate.
( For 100 Cft )
Cement Lbs 2790
Stone or River Shingle ¼" To ¾" Gauge Cft 92
Sand Cft 46
Mason No 1
Workers No 10

6 1½" Thick Cement Concrete 1:2:4 with 5%


Pudlo to the Weight of Cement for Damp
Proof Course.
( For 100 Sft )
Cement 2 ¾ Cft Lbs 248
Pudlo Lbs 12
Stone or River Shingle ¼" To ¾" Gauge Cft 12
Sand Cft 6
Mason No 1
Worker No 1
pg-7

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
7 Cement Concrete 1:2:4 with Ironite 10% to
the Weight of Cement.
( For 100 Cft )
Cement 21 Cft Lbs 1890
Ironite Lbs 189
Stone or River Shingle ¼" To ¾" Gauge Cft 92
Sand Cft 46
Mason No 1
Workers No 10

8 1" Thick Cement Concrete 1:2:4 with 5%


Pudlo to the Weight of Cement for Damp
Proof Course.
( For 100 Sft )
Cement Lbs 173
Pudlo Lbs 8 3/4
Stone or River Shingle ¼" To ¾" Gauge Cft 8
Sand Cft 4
Mason No 3/4
Workers No 3/4

9 Cement Concrete 1:6:12 using ¼" to ¾"


Stone or River Shingle Aggregate in Foundation
( For 100 Cft )
Cement Lbs 765
Stone or River Shingle ¼" To ¾" Gauge Cft 102
Sand Cft 51
Mason No 1
Workers No 10

10 Cement Concrete 1:4:8 with ¾" to 1½"


Stone or River Shingle Aggregate.
( For 100 Cft )
Cement Lbs 1170
Stone or River Shingle Aggregate Cft 104
Sand Cft 52
Mason No 1
Workers No 10

11 Lime Concrete 1:1:1:6 with Gravel Aggregate.


( For 100 Cft )
Gravel Cft 100
Lime Mortar 1:1:1 Cft 38
Mason No 1/2
Workers No 7
Sundries L/S …
12 Lime Concrete 1:1:4 in Foundation using
Medium Brick Aggregate
( For 100 Cft )
Lime Mortar Cft 34
Brick Bat Aggregate Cft 100
Mason No 1/2
Workers No 7
Sundries L.S …
pg-8

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
13 Lime Concrete 1:2:6 with Gravel or Broken
Brick Aggregate
( For 100 Cft )
Gravel Cft 100
Lime Cft 17 1/2
Sand Cft 35
Mason No 1/2
Workers No 10

14 Lime Concrete 1:1:1:6 with Broken Brick or


Stone Ballast
( For 100 Cft )
Lime Mortar 1:1:1 Cft 34
Stone or Brick Ballast 1½ Gauge Cft 100
Mason No 1/2
Workers No 7
Sundries L.S …

15 Composite Concrete with Stone Ballast, River


Shingle or Hill Gravel, 1:2:5:10
( For 100 Cft )
Cement 9 Cft Lbs 810
Stone Ballast ¾" Gauge, River Shingle
or Hill Gravel Cft 90
Lime Cft 18
Sand Cft 45
Mason No 1
Workers No 10

16 Cement Concrete (1:3:5) using Medium Fine


Fine Stone or River Shingle Aggregate
( For 100 Cft )
Cement Cft 17.9
Sand Cft 53.7
Stone or River Shingle Aggregate ¾" to 1½" Cft 89.5
Mason No 1
Workers No 10

17 Mixing Only Granolithic Mix(1:2½) with ¼"


Down Granite Chipping with Ordinary
Cement
( For 100 Cft )
Cement Lbs 3568
Sand Cft 7.5
¼" Granite Chipping Cft 104
Mason No 1
Workers No 5
pg-9

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
18 Mixing Only Granolithic Mix(1:2) with ¼"
Down Granite Chipping in Ordinary Cement
( For 100 Cft )
Cement Lbs 4320
Sand Cft 9
¼" Granite Chipping Cft 96
Mason No 1
Workers No 5

19 Mixing Only Terrazzo Mix(1:3) with ¼" Marble


Chipping in Coloured Cement
( For 100 Cft )
Colour-Crete Lbs 3240
¼" Marble Chipping Cft 108
Mason No 1
Workers No 5

20 Mixing Only Terrazzo Mix(1:2) with ¼" Down


Marble Chipping in Coloured Cement
( For 100 Cft )
Colour-Crete Lbs 4320
¼" Marble Chipping Cft 96
Mason No 1
Workers No 5

21 Timber Shuttering ( Form Work )


( For 100 Sft )
Timber Scantling Cft 15 (1) Add 1 More
Timber Planks 1" Sft 110 Carpenter for
Nails & Spikes Lbs 3 Beams, Lintels
M.S Bolt and Washer if Required ... ... Walls.
Carpenters Each 4 (2) Add 2 More
Workers Each 2 Carpenters for
Remark: Stairs and Columns.
(3) Add 2 More
Carpenters for
T & G Timber Work
(4) Add 1 More
Carpenter for
Each Additional
Storey Height
(5) Shuttering Can
be used a minimum
of 3 times.
(6) Add Timber
Planks 10 Sft for
T & G Work.
pg-10

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
IV. REINFORCED CONCRETE (HAND MIXED)
1 Reinforced Concrete Work 1:2:4
( For 100 Cft )
Cement 23 Cft Lbs 2070
Coarse agg: ¼" to ¾" gauge Cft 92
Sand Cft 46
Mason No 2
Workers No 15

2 R.C.C Work 1:2½:5, Mile, Furlong and Boundary


Posts for 91 Posts
( For 100 Cft )
Cement 19 Cft Lbs 1710
No.6 G.I Plain Wire Lbs 255
Coal Tar for filling in Letters Lbs 3
Ballast ¼" to ¾" Gauge Cft 94
Sand Cft 47
Shuttering Lump Sum Allowing Same Form to
be used several times L.S …
Masons No 3
Workers No 20

3 R.C.C 1:2:4, Intermediate Fence Posts


6' Long, 6" Sq. Base; 4" Sq. Top for 92 Posts
( For 100 Cft )
Cement 23 Cft Lbs 2070
3/8"Ø M.S Rods Lbs 872 5% Wastage
Binding Wire Lbs 80
Ballast ¼" to ¾" Gauge Cft 92
Sand Cft 46
Shuttering Lump Sum Allowing Same Form to
be used several times L.S …
Masons No 3
Workers No 20

4 R.C.C 1:2:4, Gate & Corner Posts 7' Long,


8" Sq. Base; 6" Sq. Top for 42 Posts
( For 100 Cft )
Cement 23 Cft Lbs 2070
3/8"Ø M.S Rods Lbs 464
Binding Wire Lbs 44
Ballast ¼" to ¾" Gauge Cft 92
Sand Cft 46
Shuttering Lump Sum Allowing Same Form to
be used several times L.S …
Masons No 3
Workers No 20

5 R.C.C Pipe for Culvert 12" Ø 2' Long, 2½"


Thick, 1:2:4 for One Pipe
( For 1.58 Cft )
Cement Lbs 32
Triangular Mesh RIF Style No.245 Sft 8
Binding Wire Lbs 0.2
pg-11

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Ballast ¼" to ¾" Gauge Cft 1.45
Sand Cft 0.72
Special Shuttering for Pipe L.S …
Masons No 1/8
Workers No 3/4

6 R.C.C Pipe 24" Ø 2' Long, 2½" Thick, 1:2:4 for


One Pipe
( For 2.90 Cft )
Cement 0.68 Cft Lbs 61
Triangular Mesh RIF Style, No.245 Sft 14.5
Binding Wire Lbs 0.2
Ballast ¼" to ¾" Gauge Cft 2.66
Sand Cft 1.34
Special Shuttering for Pipe L.S …
Masons No 1/4
Workers No 1 1/2

7 R.C.C Pipe 36" Ø 2' Long, 3½" Thick, 1:2:4 for


One Pipe
( For 6.3 Cft )
Cement Lbs 130
Triangular Mesh RIF Style No.245 Sft 22
Binding Wire Lbs 0.2
Ballast ¼" to ¾" Gauge Cft 5.8
Sand Cft 2.9
Special Shuttering for Pipe L.S …
Masons No 1
Workers No 2

8 R.C.C Pipe 48" Ø 2' Long, 5" Thick, 1:2:4 for


One Pipe
( For 11.66 Cft )
Cement 2.71 Cft Lbs 244
Triangular Mesh RIF Style No.365 Sft 29
Binding Wire Lbs 0.2
Ballast ¼" to ¾" Gauge Cft 10.8
Sand Cft 5.4
Special Shuttering L.S …
Masons No 1 1/2
Workers No 3

9 3" R.C.C (1:2:4) using Fine Stone or River


Shingle Aggregate and B.R.C No. 10
including use and waste of Forms and
Shuttering
( For 100 Sft)
R.C.C 1:2:4 Cft 25
B.R.C No.10 Fabric Fixed Sft 110
Shuttering Formwork ( Rate Reduced to Sft 110
1/6 for Reason of Repeated use.)
Masons No 3/4
Workers No 4
pg-12

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
CONCRETE MIXED BY MACHINE
1 Mixing and Placing Cement Concrete 1:3:6 with
Stone Ballast or River Shingles or Brick Agg.
1½" Gauge Wheeled by Hand in Barrows
( For 100 Cft)
Cement 16 Cft Lbs 1440
Stone Ballast, Shingles or Brick Agg. 1½" Gauge Cft 96
Sand Cft 48
Fuel Gals 2
Mason No 1
Workers No 6
Machine Driver No 1/2

2 Mixing only Cement Concrete 1:2:4, with ½" to


¾" Gauge Stone Chippings or River Shingle
Agg. Wheeled by Hand in Barrows
( For 100 Cft)
Cement 23 Cft Lbs 2070
Stone Ballast, Shingles or Brick Agg. 1½" Gauge Cft 92
Sand Cft 46
Fuel Gals 2
Mason No 1
Workers No 3
Machine Driver No 1/2

3 Mixing and Placing Cement Concrete 1:4:8 with


¾" to 1½" Gauge Stone Ballast or River
Shingle Agg. Wheeled by Hand in Barrows
( For 100 Cft)
Cement 13 Cft Lbs 1170
Stone Ballast, or River Shingle ¾" to 1½" Gauge Cft 104
Sand Cft 52
Fuel Gals 2
Mason No 1
Workers No 8
Machine Driver No 1/2

4 Mixing and Placing Cement Concrete 1:1½:3


with Stone Ballast or River Shingle Agg. ¼"
to ¾" Gauge Wheeled by Hand in Barrows
( For 100 Cft)
Cement 31 Cft Lbs 2790
Stone Ballast, or River Shingle ¾" to 1½" Gauge Cft 92
Sand Cft 46
Fuel Gals 2
Mason No 1
Workers No 8
Machine Driver No 1/2
pg-13

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
5 Transporting Placing and Consolidating Cement
Concrete ( Not Reinforced )
Lead 100' and 15' Above or Below Mixer
( For 100 Cft)
(a) Foundations and Floors
Masons No 1
Workers No 5

(b) Walls
Masons No 1
Workers No 7

Lead 100' and 30' Above or Below Mixer


( For 100 Cft)
(a) Foundations and Floors
Masons No 1
Workers No 6

(b) Walls
Masons No 1
Workers No 8

6 Transporting Placing and Consolidating Cement


Concrete ( Reinforced )

Lead 100' and 15' Above or Below Mixer


( For 100 Cft)
(a) Foundations and Floors
Masons No 2
Workers No 6

(b) Walls
Masons No 2
Workers No 8

(c) Columns
Masons No 2
Workers No 9

Lead 100' and 30' Above or Below Mixer


( For 100 Cft)
(a) Foundations and Floors
Masons No 2
Workers No 7

(b) Walls
Masons No 2
Workers No 9

(c) Columns
Masons No 2
Workers No 10
pg-14

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
V. BRICK WORK
1 Brick Work 1st Class in Composite Mortar 1:1:6
( For 100 Cft)
1st Class Brick 9"x4 3/8"x2¾" No 1350 Allowed 2 more
Cement Lbs 372 workers for each
Lime Cft 4 1/8 additional story
Sand Cft 24 3/4 of the Bldg. Allow
Mason No 4 Extra for Scaffolding
Workers No 6 for each storey
Scaffolding and Sundries L.S ...

2 Brick Work 1st Class in Composite Mortar 1:3


( For 100 Cft)
1st Class Brick 9"x4 3/8"x2¾" No 1350
Cement 8.67 Cft Lbs 780
Sand Cft 26
Mason No 4
Workers No 6

3 Brick Work 1st Class in Arches in 1:3


Cement Mortar
( For 100 Cft)
1st Class Brick 9"x4 3/8"x2¾" No 1350
Cement Lbs 780
Sand Cft 26
Mason No 5
Workers No 6
Scaffolding and Centering, etc. L.S ...

4 Brick Work 1st Class in 1:2 Cement Mortar


( For 100 Cft)
1st Class Brick 9"x4 3/8"x2¾" No 1350
Cement Lbs 1035
Sand Cft 23
Mason No 4
Workers No 6

5 Brick Work 1st Class in 1:4 Cement Mortar


( For 100 Cft)
1st Class Brick 9"x4 3/8"x2¾" No 1350
Cement Lbs 630
Sand Cft 28
Mason No 4
Workers No 6

6 Cornice 6" Deep 1st Class Brick Work in


1:3 Cement Mortar
( For 100 Cft)
1st Class Brick 9"x4 3/8"x2¾" No 275
Cement Lbs 150
Sand Cft 5
Mason s Laying & Cutting No 4
Workers No 3
pg-15

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
7 9" Thick Honey-Comb Brick Work with 1st Class
in 1:3 Cement Mortar
( For 100 Sft)
1st Class Brick 9"x4 3/8"x2¾" No 700
Cement Lbs 564
Sand Cft 19
Mason No 3 1/2
Workers No 3 1/2

8 4½" Thick Honey-Comb Brick Work with 1st


Class Brick in Cement Mortar 1:3
( For 100 Sft)
Brick No 350
Cement Lbs 300
Sand Cft 10
Mason No 2
Workers No 2

9 Brick Curb 4½"x3" in Cement Mortar 1:3 and


Plastered ½" Thick in the Same Mortar
( For 100 Rft)
Brick No 138
Cement Mortar 1:3 Cft 3
½" thick Cement Mortar Plastering Sft 87.5
Mason No 1/2
Workers No 1/3

10 Brick Work 1st Class in Lime Mortar 1:1:1


( For 100 Cft)
1st Class Brick 9"x4 3/8"x2¾" No 1350
Lime Mortar 1:1:1 Cft 26
Mason No 4
Workers No 5
Scaffolding and Sundries L.S ...

11 Brick Work 1st Class in Arches in Lime Mortar 1:1:1


( For 100 Cft)
1st Class Brick 9"x4 3/8"x2¾" No 1350
Lime Mortar 1:1:1 Cft 26
Mason No 5
Workers No 5
Scaffolding and Centering L.S ...

12 Brick Work 1st Class in Lime Mortar 1:2


( For 100 Cft)
1st Class Brick 9"x4 3/8"x2¾" No 1350
Lime Cft 12
Sand Cft 24
Mason No 4
Workers No 6
Scaffolding and Centering L.S ...
pg-16

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
13 Brick Work 1st Class in Lime Mortar 1:1
( For 100 Cft)
st
1 Class Brick 9"x4 3/8"x2¾" No 1350
Lime Mortar 1:1:1 Cft 26
Masons for Laying & Cutting No 4
Workers No 5
Scaffolding and Sundries L.S ...

14 Cornice 6" Deep 1st Class Brick Work in Lime


Mortar 1:1:1
( For 100 Rft)
1st Class Brick 9"x4 3/8"x2¾" No 275
Lime Mortar 1:1:1 Cft 5
Masons Laying & Cutting No 4
Workers No 3

15 Honey-Comb Work with Brick 1st Class and


Plastered One Coat 3/8" Lime Mortar
( For 100 Cft)
1st Class Brick 9"x4 3/8"x2¾" No 700
Lime Mortar 1:1:1 Cft 19
Masons No 9
Workers No 6

16 Brick Work in Mud with Sun Burnt Bricks


( For 100 Sft)
Sun Burnt Brick No 1350
Clay Cft 30
Masons No 3
Workers No 5
Scaffolding and Sundries L.S ...
pg-17

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
VI. STONE WORK
1 Coursed Rubble Dry Stone Masonry
( For 100 Cft)
Rubble Stone Cft 125
Masons No 2
Workers No 2
Scaffolding and Sundries L.S ...

2 Stone Pitching 12" or 18" Stone


( For 100 Cft)
Rubble Stone Cft 110
Masons No 2
Workers No 2

3 6" Spawls Under Stone Pitching


( For 100 Cft)
Stone Spawls Cft 100
Mason No 1/2
Workers No 1/2

4 Coursed Rubble Stone Masonry in Cement


Mortar 1:3
( For 100 Cft)
Rubble Stone (Selected) Cft 125
Cement Lbs 900
Sand Cft 30
Mason No 9
Workers No 6
Scaffolding and Sundries L.S ...

5 Coursed Rubble Stone Masonry in Cement


Mortar 1:3 in Arches
( For 100 Cft)
Rubble Stone (Selected) Cft 125
Cement 11 Cft Lbs 990
Sand Cft 33
Mason No 10
Workers No 8
Scaffolding and Centering, etc. L.S ...

6 Random Rubble Stone in Cement Mortar 1:3


Rough Dressed
( For 100 Cft)
Stone Roughly Dressed Cft 150
Cement Lbs 1180
Sand Cft 40
Mason No 4
Workers No 5
pg-18

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
7 Coursed Rubble Stone Masonry in Lime
Mortar 1:1:1
( For 100 Cft)
Rubble Stone (Selected) Cft 125
Lime Mortar Cft 34
Masons No 9
Workers No 6
Scaffolding and Sundries L.S ...

8 Random Rubble Stone in Lime Mortar 1:1:1


Rough Dressed
( For 100 Cft)
Stone Roughly Dressed Cft 150
Lime Mortar 1:1:1 Cft 40
Mason No 4
Workers No 5
Scaffolding and Sundries L.S ...

9 Coursed Rubble Stone Masonry in Lime Mortar


1:1:1 in Arches.
( For 100 Cft)
Rubble Stone (Selected) Cft 125
Lime Mortar 1:1:1 Cft 34
Mason No 10
Workers No 8
Scaffolding and Centering and Sundries L.S ...

10 Laterite Block Work with Dressed 16"x8"x6"


Blocks in Cement Mortar 1:4
( For 100 Cft)
Laterite Blocks No 222
Cement 5 Cft Lbs 450
Sand Cft 20
Mason No 3
Workers No 4
Scaffolding, Centering & Sundries L.S ...
pg-19

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
VII. PLASTERING & POINTING
1 Plastering with Damp Proof Cement Mortar ¾"
Thick 1:2
( For 100 Sft)
Cement 3.6 Cft Lbs 324
Pudlo (5% by Weight of Cement ) Lbs 16.2
Sand Cft 7.2
Mason No 1
Workers No 3
Sundries L.S ...

2 Plastering with 1:2 Cement Mortar ½" thick


( For 100 Sft)
Cement Lbs 225
Sand Cft 5
Masons No 1
Workers No 2

3 Plastering with 1:3 Cement Mortar ½" thick


( For 100 Sft)
Cement Lbs 150
Sand Cft 5
Masons No 1
Workers No 2

4 Plastering with 1:3 Cement Mortar ¾" thick


( For 100 Sft)
Cement Lbs 225
Sand Cft 7.5
Mason No 1 1/2
Workers No 3

5 Plastering with 1:4 Cement Mortar ½" thick


( For 100 Sft)
Cement Lbs 112.5
Sand Cft 5
Mason No 1
Workers No 2

6 Plastering ½" Thick with Lime Mortar 1:1


( For 100 Sft)
Lime Mortar 1:1 Cft 5
Masons No 1
Workers No 2
Sundries L.S ...

7 Plastering ½" Thick with Lime Mortar 1:2


( For 100 Sft)
Lime Cft 2.5
Sand Cft 5
Masons No 1
Workers No 2
pg-20

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
8 Plastering with Lime Mortar ½" Thick (2:3:1)
( For 100 Sft)
Lime Mortar for Plaster (2:3:1) Cft 5
Masons No 1
Workers No 2
Sundries L.S ...

9 Plastering with 1:2:6 Composite Mortar ½" Thick


( For 100 Sft)
Cement 0.8 Cft Lbs 72
Lime Cft 1.6
Sand Cft 4.8
Mason No 1
Workers No 2
Sundries L.S ...

10 Plastering with 1:1:6 Composite Mortar ½" Thick


( For 100 Sft)
Cement 0.83 Cft Lbs 75
Lime Cft 0.83
Sand Cft 5
Mason No 1
Workers No 2
Sundries L.S ...

11 Plastering ½" Thick Cement Mortar 1:3 with 5%


Pudlo by Weight of Cement
( For 100 Sft)
Cement Mortar 1:3 Cft 5
Pudlo Lbs 7.5
Masons No 1
Workers No 2
Sundries L.S ...

12 Mud Plastering ¼" Thick


( For 100 Sft)
Tempered Clay Chopped-Straw and Cow-Dung Cft 2.5
Mason No 1
Workers No 1

13 Pointing with 1:1:6 Composite Mortar


( For 100 Sft)
Cement Lbs 30
Lime Cft 0.33
Sand Cft 2
Masons No 1
Workers No 2
Sundries L.S ...
pg-21

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
14 Pointing with 1:2:6 Composite Mortar
( For 100 Sft)
Cement 0.32 Cft Lbs 29
Lime Cft 0.64
Sand Cft 1.92
Masons No 1
Workers No 2
Sundries L.S ...

15 Pointing with Cement Mortar 1:2


( For 100 Sft)
Cement Lbs 83
Sand Cft 2
Masons No 1
Workers No 2

16 Pointing with Cement Mortar 1:3 to full Depth


of Tiles, Marble Tiles, Marseilles Tiles,
Glazed Tiles, Etc.
( For 100 Sft)
Cement Lbs 15
Sand Cft 0.5
Masons No 1
Workers No 2
Colouring Matters and Sundries L.S ...

17 Pointing with Cement Mortar 1:3


( For 100 Sft)
Cement Lbs 60
Sand Cft 2
Masons No 1
Workers No 2

18 Pointing with 2:3:1 Lime Mortar


( For 100 Sft)
Lime Mortar for Plaster 2:3:1 Cft 2
Masons No 1
Workers No 2
Sundries L.S ...

19 Pointing with Lime Mortar 1:1


( For 100 Sft)
Lime Mortar 1:1 Cft 2
Masons No 1
Workers No 2
Sundries L.S ...
pg-22

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
VIII. WOOD WORK
1 Thitya, Ingin, Pyingado Wood Work Wrought
and Fixed
( For 50 Cft)
Thitya, Ingin, Pyingado Cft 55 10% Wastage
Nails & Spikes Lbs 14
Carpenters No 12

2 Jungle Wood Work Wrought And Fixed


( For 50 Cft)
Jungle Wood Scantling Cft 55 10% Wastage
Nails & Spikes Lbs 14
Carpenters No 10

3 Wood Work Wrought And Fixed In Fencing


And Bridges.
( For 50 Cft)
Scantling Cft 55 10% Wastage
Nails & Sikes Lbs 14
Carpenters No 7

4 Teak Hand Railing 1st Class Plain


( For 8 Rft)
Horizontal Top, 1 x 7 5/6' x 4" x 3" Cft. 2.61 10% Wastage
Horizontal Bottom, -Do- Cft.
Horizontal Inter, 2 x 7 5/6' x 3" x 2" Cft.
Post , 1 x 3 ¾' x 4" x 4" Cft.
Verticals 5 x 2 ¾' x 2" x 2" Cft. 1.31 15% Wastage
Diagonals 10 x 2 ¼' x 2" x 2" Cft.
Nails Lbs 1
Carpenters No 2

5 Hand Railing 2nd Class Plain


(Other Than Teak.)
( For 8 Rft)
Post , 1 x 3 ¾ ' x 4" x 4" Cft 1.18 10% Wastage
Horizontals, 2 x 7 5/6 ' x 3"x 2" Cft
Verticals, 3 x 2 5/6 ' x 2" x 1½" Cft 0.78 15% Wastage
Diagonals, 6 x 4' x 2" x 1½" Cft
Nails Lbs 0.5
Carpenters No 1 1/2

6 Teak Stair Case Without Hand Railing for 45 Sft


(10'x4' Clear Width)
( For 45 Sft)
Stringers 2 x 10' x 12" x 3" Cft 5.5 10% Wastage
Treads, 9 x 4 ¼ 'x 1 1/8' x 1¾" Cft 8.22 15% Wastage
Risers 9 x 4 ' x 7" x ½" Cft
Nails Lbs 2
Carpenters No 8
pg-23

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
7 Stair Case 2nd Class Without Hand railing
(Other than Teak)
( For 30 Sft) (10'x3')
Stringers 2 x 10' x 10" x 3" Cft 4.59 10% Wastage
Treads, 6 x 2 5/6" x 9" x 1½" Cft 2.47 15% Wastage
Risers 6 x 3' x 9" x ½" Cft
Nails Lbs 2
Carpenters No 4

8 Hard Wood Steps for Out Houses Without


Hand railing
( For 15 Sft) (5' x 3')
Stringers, 2 x 5' x 10" x 2" Cft 1.53 10% Wastage
Treads, 4 x 3' x 8" x 1" Cft 0.77 15% Wastage
Nails Lbs 0.5
Carpenters No 1 1/2

9 Providing Wrought Jungle Wood Steps With


10"x2" Stringers And 9"x1½" Treads
( For 15 Sft)
Jungle Wood Stringers Cft 1.53 10% Wastage
Treads Cft 1.3 15% Wastage
Nails Lbs 0.5
Carpenters No 1 1/2

10 Teak Gate 1st Class for 12' Wide

W.I Hinges, 2 x 4½ ' & 2 x 4' x 2" x ½" Lbs 28.9


1"ø Pintles, 4 Nos Lbs 12.6
½" bolts for hinges and hasps 17 Nos 4" long Lbs 3.72
Head & Nuts for bolts Lbs 0.29
Locking hasp 1 x 1¾' No 1
Top bar 2 x 6½' x 8½" x 3" Cft 8.79 10% Wastage
Bottom & centre rails 4 x 6' x 5" x 3" Cft
Diagonals, 2 x 6½' x 5" x 3" Cft
Outer stanchions, 2 x 5 1/8 ' x 5" x 3" Cft
Inner stanchions, 2 x 4 ' x 5" x 3" Cft
2"x1" battens Cft 1.3 15% Wastage
Nails Lbs 2
Carpenters No 5

11 Gate 2nd Class ( Other Than Teak )


( For 12' Wide )
W.I as above Item 10 Lbs 45.51
Locking hasp 1 x 1¾' No 1
Stanchions, 2 x 4½ ' x 4" x 2" Cft 4.03 10% Wastage
Stanchions, 2 x 4 ' x 4" x 2" Cft
Horizontal, 6 x 6 ' x 4" x 2" Cft
Diagonals, 2 x 6½' x 4" x 2" Cft
2"x1" battens Cft 2.04 15% Wastage
Nails Lbs 2
Carpenters No 3
pg-24

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
12 Eaves & Facia Boards 12" x 1" Plank
( For 100 Rft )
Planks 100'x12"x1" Cft. 9.58 15% Wastage
Nails & Screws Lbs. 2
Carpenters No. 4

13 Eaves & Facia Boards 10" x 1" Plank


( For 100 Rft )
Planks 100'x10"x1" Cft. 7.98 15% Wastage
Nails & Screws Lbs. 2
Carpenters No. 3 1/2

14 6" x 1" Teak Facia & Eave Boards


( For 100 Rft )
Teak 1" Plank Cft. 4.8 15% Wastage
Nails & Screws Lbs. 2
Carpenters No. 2

15 8" x 1" Thitya, Ingin, Pyingado Eave Board


Wrought & Fixed Including Earth Oiling
2 Coats
( For 100 Rft )
Thitya, Ingin, Pyingado 8" x 1" Plank Cft. 6.4 15% Wastage
Nails & Spikes Lbs. 2
Carpenters No. 3
Earth Oiling 2 Coats Sft 150

16 9" x 1" Thitya, Ingin, Pyingado Eave Board


Wrought & Fixed Including Earth Oiling
2 Coats
( For 100 Rft )
Thitya, Ingin, Pyingado 9" x 1" Plank Cft. 7.19 15% Wastage
Nails & Spikes Lbs. 2
Carpenters No. 3 1/4
Earth Oiling 2 Coats Sft 167

17 6" x 1" Pyingado Eave Board Wrought & Fixed


Complete Including Earth Oiling 2 Coats
( For 100 Rft )
Pyingado 6" x 1" Plank Cft. 4.8 15% Wastage
Nails & Spikes Lbs. 2
Carpenters No. 2
Earth Oiling 2 Coats Sft 117

18 3" x 1" Facia Boards Planed and Earth Oiling


2 Coats and Fixed Complete
( For 100 Rft )
3" x 1" Plank Cft. 2.4 15% Wastage
Nails & Spikes Lbs. 1
Carpenters No. 1 1/2
Earth Oiling 2 Coats Sft 42
pg-25

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
19 3" x ½" Wrought Inn Facia Boards Fixed
Complete Including Earth Oiling 2 Coats
( For 100 Rft )
3" x ½" Inn Plank Cft. 1.2 15% Wastage
Nails & Screws Lbs. 1
Carpenters No. 1 1/4
Earth Oiling 2 Coats Sft 33.5

20 18" Wide shelves with Brackets


( For 18 Rft )
Planks 1 x 18' x 18" x 1" Cft. 2.59 15% Wastage
Brackets Cft. 0.45
Nails & Spikes Lbs. 0.5
Carpenters No. 3/4

21 12" Wide shelves with Brackets


( For 20 Rft )
Planks 1 x 20' x 12" x 1" Cft. 1.92 15% Wastage
Brackets Cft. 0.22
Nails & Spikes Lbs. 0.5
Carpenters No. 3/4
pg-26

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
IX. DOOR AND WINDOW
1 1½" Thick Teak Paneled Door 1st Class for
7' x 3½' (Double Leaf)
( For 24.5 Sft )
Styles 4 x 7' x 4" x 1½" Cft.
Top and Bottom Rails 4 x 1 5'/8 x 4" x 1½" Cft. 2.4 15% Wastage
Lock Rails 4 x 1 5'/8 x 8" x 1½" Cft.
Panels 6 x 1 5'/8 x 1¼' x 1" Cft. 1.32 15% Wastage
Nails & Glue L.S ...
Carpenters No 5

2 1½" Thick 1/3 Paneled 2/3 Glazed Door


1st Class for 6½' x 3½' (Double Leaf)
( For 22.75 Sft )
21 oz. sheet glass pane Sft 11 50% Wastage
Styles 4 x 6½' x 4" x 1½" Cft.
Top and Bottom Rails 4 x 1¾' x 4" x 1½" Cft. 1.95 15% Wastage
Lock Rails 2 x 1 5'/8 x 8" x 1½" Cft.
Sash bars 2x 3 1'/8 x 1½" x 1½" Cft.
0.25 15% Wastage
Sash bars 6x 1¼' x 1½" x 1½" Cft.
Panels 2 x 1 1'/8 x 2 1'/8 x 1" Cft. 0.56 15% Wastage
Nails & Glue Lbs 0.5
Carpenters No 4 3/4

3 1½" Thick Teak Paneled Door 1st Class


for 6'-9½" x 2'-10" (Single Leaf)
( For 19.3 Sft )
Styles 2 x 6 7'/8 x 4½" x 1½" Cft.
Top and Middle Rails 2 x 2 7'/8 x 4½" x 1½" Cft. 15% Wastage
7' 1.79
Bottom and Lock Rails .2 x 2 /8 x 9" x 1½" Cft.
Vertical Rails, 1 x 2 ½' x 4" x 1½" Cft.
Panels 1 x 2¼' x 1' x ½" Cft.
1' 0.59 15% Wastage
Panels 2 x 2¼' x 1 /24 x ½" Cft.
Nails & Glue L.S ...
Carpenters No 5

4 1½" Thick Teak Ledged and Battened Door for


6½' x 3'.
( For 19.5 Sft )
Styles 4 x 6 ½' x 4" x 1½" Cft.
Rails 4 x 1 7'/12 x 6" x 1½" Cft. 1.93 15% Wastage
Lock Rails 2 x1 7'/12 x 6" x 1½" Cft.
T & G Planking 40' x 4" x ½" Cft. 0.65 15% Wastage
Nails & Glue L.S ...
Carpenters No 3 1/2
pg-27

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
5 Corrugated Iron Doors and Windows for
7' x 3½' Double Leaf
( For 24.5 Sft )
Corrugated Iron 2 x 7' x 1¾' sht 2
Styles 4 x 7 1'/12 x 3¾" x 1½" Cft.
Top & Bottom Rails 4 x 1½' x 3¾" x 1½" Cft.
2.26 15% Wastage
Diagonal Rails, 4 x 3¼' x 3¾" x 1½" Cft.
Lock Rails 2 x1½' x 3¾" x 1½" Cft.
Nails, etc. lb 1/2
Carpenters No 1 1/2

6 Single Course Bamboo Mat Doors and


Windows with 1" thick Battens Double Leaf
for 3'-1"x7'-½"
( For 21.71 Sft )
Styles 4 x 7'- ½" x 3" x 1" Cft.
Top Rails 2 x 1'-6½'' x 3" x 1" Cft.
Bracings, 6 x 2'-9" x 3" x 1" Cft. 1.44 15% Wastage
Bottom Rails 2 x 1'-6½'' x 4" x 1" Cft.
Lock Rails 2 x2 x 1'-6½" x4" x 1" Cft.
Covering Strips ½"(½ of Above) Cft. 0.72 15% Wastage
Bamboo Mats Sft 21
Nails lb 1/2
Carpenters No 1

7 Mat Door Double Leaf 3'-1" x 7'-½"


( For 21.71 Sft )
Styles 4 x 7'-½" x 3" x 1" Cft.
Top Rails 2 x 1'-6½'' x 3" x 1" Cft.
Bracings, 6 x 2'-9" x 3" x 1" Cft. 1.44 15% Wastage
Bottom Rails 2 x 1'-6½'' x 4" x 1" Cft.
Lock Rails 2 x2 x 1'-6½" x4" x 1" Cft.
Covering Strips ½"(½ of Above) Cft. 0.72 15% Wastage
Double Mat Best Quality Sft 42
Nails lb 1/2
Carpenters No 1

8 Mat Window Double Leaf 3'-1" x 4'-1"


( For 12.57 Sft )
Styles 4 x 4'-1" x 3" x 1" Cft.
Top and Bottom Rails 4 x 1'-6½'' x 3" x 1" Cft.
0.88 15% Wastage
Lock Rails 2 x 1'-6½" x4" x 1" Cft.
Bracings, 4 x 2'-6" x 3" x 1" Cft.
Covering Strips ½"(½ of Above) Cft. 0.44 15% Wastage
Double Mat Best Quality Sft 24
Nails lb 3/8
Carpenters No 5/8
pg-28

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
9 1½" Thick Teak Glazed Window, 1st Class,
4' x 3' ( Double Leaf)
( For 12 Sft )
21 oz Sheet Window Glass Panes Sft 9.05 50% Wastage
Styles 4 x 4'-0" x 4" x 1½" Cft.
Top and Bottom Rails 4 x 1'-6'' x 4" x 1½" Cft. 1.16 15% Wastage
Sash Bars 6 x 1' x 1½" x 1½" Cft.
Nails and Glue lb 1/4
Carpenters No 3

10 1½" Thick Teak Glazed Fanlights, Supplied


and Fixed Complete and Including 18 Oz.
Glass and Glazing 5'-6" x 1'-8"
( For 9.16 Sft )
Teak Scantling Cft. 0.69 15% Wastage
Teak Plank (Sash) Cft. 0.08 15% Wastage
Wood Screw, Nails and Glue L.S ...
Pivot Hinges 2¼" x 7/8" Brass Pair 2
Safety Catch Brass Self Closing No 1
18 Oz. Glass sheet Sft 7.72 50% Wastage
Carpenters No 2

11 1½" Thick Teak Movable Venetian Window


1st Class Double Leaf 4'-0" x 3'-0"
( For 12 Sft )
Styles 4 x 4'-6" x 4" x 1½" Cft.
1.76 15% Wastage
Top and Bottom Rails 4 x 1'-6'' x 4" x 1½" Cft.
Venetian Flaps, 40 x 1 1'/12 x 4" x 2" Cft.
0.22 15% Wastage
Venetian Rods, 4 x 3 5/16' x 2" x 1" Cft.
7 '
Venetian Beadings, 4 x 3 /16 x 1" x 1" Cft.
1 ' 0.17 15% Wastage
Venetian Bars, 6 x 1 /6 x 1" x 1" Cft.
Nails and Glue lb 1/2
Carpenters No 6

12 1½" Thick Teak Paneled Venetianed And


Glazed Door 7'-7½" x 3'-7" Double Leaf.
( For 27.32 Sft )
21 oz Sheet Window Glass Panes Sft 5.63 50% Wastage
3 '
Styles 4 x 7 /8 x 4" x 1½" Cft.
5
Top Rails 2 x 1 /8' x 4½" x 1½" Cft.
15% Wastage
Middle Rails 2 x 1 5/8' x 4" x 1½" Cft.
Bottom & Lock Rails, 4 x 1 5/8' x 9" x 1½" Cft. 2.64
Panels 2 x 1¾' x 1 5/8' x ½" Cft.
Sash Bars, 2 x(13/8' + 13/8')) x 1½" x 1¼" Cft.
Sash Beads 22' x ½" x ½" Cft.
Venetian Flaps, 18 x 11/8' x 4" x ½" Cft.
Venetian Rods, 4½' x 2" x 1" Cft. 1.08 15% Wastage
Venetian Beadings, 4 x 2¼' x 1" x 1" Cft.
Nails and Glue lb 1/2
Carpenters No 8 1/2
pg-29

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
13 1½" Thick Venetianed And Glazed Window
5'-1" x 4'-1" Double Leaf.
( For 20.75 Sft )
21 oz Sheet Window Glass Panes Sft 6.6 50% Wastage
Styles 4 x 5'-2" x 3½" x 1½" Cft.
Top Rails 2 x 2'-1" x 4½" x 1½" Cft.
Bottom Rails 2 x 2'-1" x 5" x 1½" Cft.
Middle Rails 2 x 2'-1" x 4" x 1½" Cft.
Sash Bars 2 x3'-1½" x 1½" x 1½" Cft. 2.6 15% Wastage
Sash Beads 2 x 12' x ½" x ½" Cft.
5
Venetian Flaps, 20 x 1 /8' x 4" x ¾" Cft.
Venetian Rods, 2 x 2½' x 2" x ¾" Cft.
Venetian Beadings, 4 x 2½' x 1" x 1" Cft.
Nails and Glue L.S ...
Carpenters No 7

14 Palisading Door Pyingado or Engin 7' x 4'


( For 28 Sft )
Quartering, 6 x 2' x 5" x 3" Cft.
Palisadings, 8 x 7' x 4" x 2" Cft. 4.92 10% Wastage
Filling Pieces for bolts 1 x 2' x 4" x 2" Cft.
Carpenters No 1 1/2
M.S Bolts 6"x½"ø No 24

15 1" Thick Inn C.G.I Doors And Windows


(32 G) Fixed Complete With Iron Fitting
(3'-6" x 7')
( For 24.5 Sft ) Double Leaf
Inn 1" Planks Cft. 1.34 15% Wastage
C.G.I Sheets 32 G 7' No 2
Roofing Nails Lb 0.5
Carpenters No 1
4" Butt Hinges No 6 6" Tower Bolt
6" Hook and Eye No 2 1 No. & 9"
6" Tower Bolts No 2 Tower Bolt 1 No.
6" Hasp and Staples No 1 for Door
Carpenters No 1

16 1" Thick J Wood Battened Doors And


Windows Fixed Complete With Iron
Fittings (6½' x 3') Double Leaf
( For 19.5 Sft ) Double Leaf
J Wood 1" Planks Cft. 1.22 15% Wastage
J Wood ½" T & G Cft. 0.61 15% Wastage
Nails and Glue L.S ...
4" Butt Hinges No 6 *6" Tower Bolt
6" Hook and Eye No 2 1 No. & 9"
6" Tower Bolts No 2* Tower Bolt 1 No.
6" Hasp and Staples No 1 for Door
Carpenters No 4
pg-30

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
17 J Wood Verandah Gate With 3" x 1½" And
2" x ½" Batten Fixed Complete
(Double Leaf) 4' x 3'
( For 12 Sft )
J Wood Scantling Cft. 0.86 15% Wastage
½" Thick J Wood Plank Cft. 0.28 15% Wastage
1/16" Hoop Iron Catch No 1
4" Butt Hinges No 4
Nails and Glue Lb 1/4
Carpenters No 1

18 C.G.I Door for Garage With 5" x 2" Frames


And Bracings 8' x 8' ( Double Leaf )
( For 64 Sft )
C.G.I Sheet 8' x 10/3 No 4
Styles, 4 x 8' x 5" x 2" Cft.
Rails, 6 x 4' x 5" x 2" Cft. 6.23 15% Wastage
Diagonals, 4 x 5'-6" x 5" x 2" Cft.
Nails Lb 1½
Carpenters No 4

19 1½" Thick X.P.M Door or Sq. Mesh Doors


( 2'-9" x 6'-6")
( For 17.88 Sft )
X.P.M or Sq. Mesh, 1 x 2'-6" x 6'-3" Sft 17.19 10% wastage
Styles, 2 x 6'-6" x 3" x 1½" Cft.
Rails, 3 x 2'-9" x 3" x 1½" Cft.
1.02 15% Wastage
Beadings, 2 x 6'-6" x 3" x ½" Cft.
Beadings, 2 x 2'-9" x 3" x ½" Cft.
Nails Lb 1
Carpenters No 2 1/2

20 1" Thick Paneled Swing Door


(Double Leaf ) 3' x 3'-3"
( For 9.75 Sft )
Styles, 4 x 3'-9" x 3" x 1" Cft.
0.5 15% Wastage
Rails, 4 x 1'-6" x 3" x 1" Cft.
Panels Sft 10
Carpenters No 2

21 1½" Thick Paneled Swing Door


(Double Leaf ) 3' x 3'-3"
( For 9.75 Sft )
Styles, 4 x 3'-9" x 3" x 1½" Cft.
0.75 15% Wastage
Rails, 4 x 1'-6" x 3" x 1½" Cft.
Panels Sft 10
Carpenters No 2
pg-31

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
22 1" Thick Trellis Door With 3" x 1" Frame
(Single Leaf) 2'-9" x 6'-3"
( For 17.19 Sft )
Styles, 2 x 6'-3" x 3" x 1" Cft.
0.5 15% Wastage
Rails, 3 x 2'-9" x 3" x 1" Cft.
Zallies, 2 x 6'-3" x 3" x½" Cft.
Zallies, 3 x 2'-9" x 3"x ½" Cft. 1.07 15% Wastage
Diagonals, 17.19/100x600'x2"x½" Cft.
Nails Lb 3
Carpenters No 2

23 Trellis Door 4" x 1½" Teak Styles, Rails,


And Braces Covered With Including
2" x ½" Teak Battens, Fixed Complete
7' x 3' ( Double Leaf)
( For 21 Sft )
Teak Scantling Cft. 1.92
15% Wastage
Teak ½" Plank Cft. 1.01
Screws and Nails Lb 1/2
4" Steel Butt Hinges No 6
6" Hook And Eye No 2
6" Tower Bolts No 1
9" Tower Bolts No 1
4" Brass Bow Handle No 1
6" Hasp And Staples No 1
Carpenters No 3
24 Collapsible Iron Door With ¾" x 3/8"
Channels And ¾" x 1/8" Flats.
(One Leaf) for 4'-3" x 6'-9"
( For 28.69 Sft )
¾" x 3/8" Vertical Channels
22 x 6'-9" @ 0.532 Lb / Rft
2" x 1" Bottom Channels
1 x 4'-9" @ 6.80 Lb / Rft
¾" x 1/8" Flat Iron
3 x 4 x 1'-0" @ 0.314 Lb / Rft
3 x 18 x 2'-0" @ 0.314 Lb / Rft LB. 185.13 5% Wastage
2" x ½" Flat Iron Top Rail
1 x 4'-9" @ 3.4 Lb / Rft
¾" x ½" Flat Iron Bottom Guide Rail
1 x 4'-9" @ 1.28 Lb / Rft
Flat Iron For Lock Ring
1 x 3'-0" x 2" x ¼" @ 1.70 Lb / Rft
Rivets 3/16"ø x 2½" No 44
Rivets ¼"ø x 1½" No 33
Rivets ¼"ø x ¾" No 10
3/8"ø Steel Pipe Rft 5.5
¼"ø M.S Pin 1½" Long No 66
¾" Outside ø 1/16" Washers No 505
Door Handle No 2
Roller With Pin, 1¾" ø x ½" Bottom No 2
Roller With Pin, 2" ø x ½" Top No 3
Smith No 6
Workers No 5
pg-32

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
25 1" Thick Fly Proof Door Complete With
Fly Proof Mesh ( Double Leaf ) 7' x 3'
( For 21 Sft )
Teak Planks 3" x 1" Cft. 0.96
15% Wastage
Teak Beadings 3" x ½" Cft. 0.48
Fly Proof Mesh Sft 23 10% Wastage
Nails Lb 1/4
Screws Gross 1/4
Carpenters No 3

26 1½" Teak Door With Ply Wood on One


Side of Teak Styles And Rails
for 4' x 6'-6"
( For 26 Sft )
Teak 4" x 1½" Styles And Rails Cft. 2.01 15% Wastage
Ply Wood Sft 30
Wood Screws Gross 1/2
Carpenters No 3 1/2

27 Providing Teak Plywood (3 Ply) Flush Door


With 1½" Thick Teak Styles And Rails
Including Cost Of And Labour For Fixing
Iron Fitting 7' x 3'-2½"
( For 22.46 Sft )
Teak Scantling Cft. 2.04
15% Wastage
Teak Plywood (3 Ply) Sft 54
Wood Screw And Nails L.S ...
4" Butt Hinges No 3
6" Tower Bolts No 2
6" Hook and Eye No 1
4" Brass Bow Handle No 1
Carpenters No 3 3/4

28 Teak Door And Window Chowkets Planed


And One Side Rebated Including Fixing
Hold Fast, Etc.
( For 100 Rft )
A 3"x3" Cft. 7.19 15% Wastage
Nails Lb 2
Carpenters No 4
B 4"x2" Cft. 6.39 15% Wastage
Nails Lb 2
Carpenters No 4
C 4"x3" Cft. 9.58 15% Wastage
Nails Lb 2 1/2
Carpenters No 6
D 5"x3" Cft. 11.98 15% Wastage
Nails Lb 3
Carpenters No 7
E 6"x3" Cft. 14.38 15% Wastage
Nails Lb 3 1/2
Carpenters No 7
pg-33

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
F 5"x2" Cft. 8 15% Wastage
Nails Lb 2
Carpenters No 6
Note : (1)For
Rebating in
Fanlight, Allow
One More
(2) For Every
Additional
Rebating , Allow
One More
Carpenter for
100 Rft

29 1½" Thick Teak Flush Door With 3" x 1"


Frame And Ply Wood on Both Sides
including Cost of And Labour For Fixing
Iron Fittings 7' x 3' Single Leaf
( For 21 Sft )
Teak 3" x 1½" Styles And Rails Cft. 0.72 15% Wastage
3" x 1" Bracing Cft. 0.24
Ply Wood Sft 42 7'x3' 2 Nos
Wood Screws Gross 1/2
Carpenters No 4 1/4

30 C.G.I Door With 1½" x 4" Teak Styles And


Rails And Braces Covered With 32G.
C.G.I Sheet Size 7' x 3½' ( Double Leaf )
( For 24.5 Sft )
Corr. Iron Sheet 32G. 7' No 2
Teak Scantling Cft. 2.01 15% Wastage
Nails, Etc. L.S ...
Carpenters No 2
4" Butt Hinges No 6
6" Hook and Eye No 2
*6" Tower Bolts No 2 * 6"-1 No &
4" Brass Bow Handle No 1 9" - 1 No.
6" Hasp And Staple No 1

31 C.G.I Window of 1½" x 4" Teak Styles And


Rails And Braces Covered With 32G.
C.G.I Sheet ( Single Leaf ) for
( 3½' x 2½' )
( For 8.75 Sft )
Teak Scantling Cft. 0.7 15% Wastage
32G. C.G.I Sheet 7' No 1/2
Screw & Nails L.S ...
3" Butt Hinges No 4
6" Hook and Eye No 2
6" Tower Bolts No 1
4" Tower Bolts No 1
4" Brass Bow Handle No 1
Carpenters No 1
pg-34

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
32 Teak Swing Door of 1½" Thick Styles Rails
and Braces Including ½" P.T.G Teak
Planks for 3½' x 3' = 10.5 Sft
( For 10.5 Sft )
Teak Scantling Cft. 1.1 15% Wastage
Teak ½" P.T.G Cft. 0.34
Nails and Screws L.S
4" Spring Hinges No 4
Carpenters No 1 3/4

33 Fixed Louvres of ¼" Thick Opaque Glass


Blades Set in And Including 5"x2"
Wrought Teak Frames And 1½" x ½"
Teak Beadings, Supplied And Fixed
Complete Size 5' x 2'-6"
( For 12.5 Sft )
Teak Scantling Cft. 1.4 15% Wastage
Teak ½" P.T.G Cft. 0.05 15% Wastage
¼" Thick Opaque Glass Sft 17.5 50% Wastage
Nails L.S
Carpenters No 2
Glazier No 1/2

34 Fixed Doors And Windows of Any


Description Including Easing ( Labour
Only) Size of Door 7' x 3'
( For 21 Sft )
Carpenters No 1/2
pg-35

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
X. FLOORING
1 Brick on Edge Flooring in Lime Mortar And
Pointed With Cement Mortar 1:2
( For 100 Sft )
1st Class Bricks 9" x 4 3/8" x 2 ¾" No 550
Lime Mortar 1:1:1 Cft. 12
Cement Mortar 1:2 Cft. 1
Masons No 2
Workers No 4 1/2
Sundries L.S ...

2 Brick on Edge Flooring Laid in


Cement Mortar 1:3
( For 100 Sft )
1st Class Bricks 9" x 4 3/8" x 2 ¾" No 550
Cement Mortar 1:3 Cft. 12
Masons No 2
Workers No 3 1/2
Sundries L.S ...

3 Brick on Edge Flooring Laid in Composite


Mortar 1:1:6
( For 100 Sft )
1st Class Bricks 9" x 4 3/8" x 2 ¾" No 550
Composite Mortar 1:1:6 Cft. 12
Masons No 2
Workers No 3 1/2
Sundries L.S ...

4 Brick Laid Flat In Flooring in Cement


Mortar 1:3
( For 100 Sft )
1st Class Bricks 9" x 4 3/8" x 2 ¾" No 345
Cement Mortar 1:3 Cft. 8
Masons No 1 1/2
Workers No 1 1/2

5 Brick Laid Flat In Flooring in Composite


Mortar 1:1:6
( For 100 Sft )
1st Class Bricks 9" x 4 3/8" x 2 ¾" No 345
Composite Mortar 1:1:6 Cft. 8
Masons No 1 1/2
Workers No 1 1/2

6 6" x 6" Glazed Tiles Flooring Laid in


Cement Mortar 1:3
( For 100 Sft )
6"x6" Glazed Tiles No 420 5% Wastage
Cement Lb 135
Sand Cft. 4.5
Masons No 2 1/2
Workers No 2
pg-36

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
7 18" x 18"x1" Polished Marble Flooring Laid in
Cement Mortar 1:3
( For 100 Sft )
18"x18"x1" Marble Slab No 47 7% Wastage
Cement Lb 135
Sand Cft. 4.5
Masons No 2 1/2
Workers No 2 1/2

8 1½" Thick 1:2:4 Cement Concrete Flooring


Laid in Slab of 5' Square
( For 100 Sft )
Cement Lb 259 For All Cement
Sand Cft. 5.75 Rendering Work
Stone or River Shingle Aggregate Cft. 11.5 in Floors :-
Masons No ½ Add ¼ Mason for
Workers No 1 1/2 Each 100 Sft of
Sundries L.S ... Floor Area.

9 2" Thick 1:2:4 Cement Concrete Flooring


Using Stone or River Shingle Aggregate
( For 100 Sft )
Cement Lb 345
Sand Cft. 7.5
Stone or River Shingle Aggregate Cft. 15
Masons No 3/4
Workers No 2
Sundries L.S ...

10 3" Thick 1:2:4Cement Concrete Flooring


With River Shingle Aggregate
( For 100 Sft )
Cement Lb 518
Sand Cft. 11.5
River Shingle Aggregate Cft. 23
Masons No 3/4
Workers No 3
Battens And Sundries Cft. 1.5
Carpenter No 1/6

11 4½" Thick 1:2:4 Cement Concrete Flooring


Using Medium Fine Stone or River
Shingle Aggregate
( For 100 Sft )
Cement Lb 777
Sand Cft. 17.25
River Shingle Aggregate Cft. 34.5
Masons No 1
Workers No 4 1/2
Battens And Sundries Cft. 2.25
Carpenter No 1/6
pg-37

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
12 1" Thick P.C.C 1:2:4 Floor Using Medium
Fine Stone or River Shingle Aggregate
( For 100 Sft )
Cement Concrete (1:2:4) Cft. 8 1/3
Battens And Sundries L.S ...
Masons No 3/4
Workers No 1

13 3" Lime Concrete (1:2:6) Flooring Using


Stone, River Shingle or Brick Aggregate
( For 100 Sft )
Lime Cft. 4.37
Sand Cft. 8.74
Aggregate Cft. 25
Masons No 1/2
Workers No 3

14 4½" Lime Concrete (1:2:6) Flooring Using


Stone, River Shingle or Brick Aggregate
( For 100 Sft )
Lime Cft. 6.56
Sand Cft. 13.12
Aggregate Cft. 37.5
Masons No 1/2
Workers No 3

15 3" Lime Concrete (1:1:4) Under Lay for


Flooring Using Brick Aggregate
( For 100 Sft )
Lime Concrete (1:1:4) Cft. 25
Masons No 1/4
Workers No 2

16 ½" Thick Mastic Asphalt Flooring


( For 100 Sft )
Asphalt Lb 448
Coal Tar Lb 14
Sand Cft. 2 1/2
Firewood Cft. 6
Masons No 1
Workers No 4

17 6" Thick Gravel Flooring Well Watered And


Rammed
( For 100 Sft )
Gravel at Site Cft. 58
Workers No 1 1/2

18 6" Thick Earth Floor Well Watered And


Rammed
( For 100 Sft )
6" Earth Consolidated Cft. 58
Workers for Carrying, Laying & Ramming No 5/8
Workers for Watering No 1/4
pg-38

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
19 Finishing and Laying Smooth 3/8" Thick
Terrazzo Floor 1:2 With ¼" Marble
Chipping On 3/8" Thick Average Screed
in Cement Mortar 1:3 ( Cast in Situ )
( For 100 Sft )
Terrazzo 1:2 Cft 3 1/8
Cement Mortar 1:3 Cft 3 1/8
Approved Metal Plastic Dividing Strip Rft 50
Mason No 1
Grinder Using Machine Day 1/2
Polisher Using Machine Day 1/4
Oxalic Acid Dresser Day 1/2
Carborundum Stone L.S ...
Wax Polish L.S ...
Oxalic Acid L.S ...

20 Finishing and Laying Smooth ½" Thick


Granolithic Finish (1:2) With ¼" Granite
Chippings On 1" Thick Average Screed
in Cement Mortar 1:3 ( Cast in Situ )
( For 100 Sft )
Granolithic Ready Mixed Cft 4 1/6
Cement Mortar 1:3 Cft 8 1/3
Approved Metal Plastic Dividing Strip Rft 50
Mason No 1
Grinder Using Machine Day 1/4
Polisher Using Machine Day 1/2
Sodium Silicate Dresser Day 1/2
Carborundum Stone L.S ...
Sodium Silicate L.S ...

21 Laterite Or Kankar Filling in Floor Spread


And Consolidated in 6" Layers To Line
And Level Surface Including Watering
And Consolidating
( For 100 Cft )
Laterite Or Kankar Cft. 116
Workers for Carrying, Laying & Consolidating No 2
Workers for Watering No 1/4

22 4" Thick Laterite Or Kankar Well Watered


And Rammed
( For 100 Sft )
Laterite Or Kankar Cft. 38
Workers for Carrying, Laying & Ramming No 1/4
Workers for Watering No 1/8

23 6" Thick Laterite Or Kankar Well Watered


And Rammed
( For 100 Sft )
Laterite Or Kankar Cft. 58
Workers for Watering & Ramming No 1 1/2
pg-39

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
24 1" Tongue and Grooved Plank Flooring
With 4" x 1" Planks
( For 100 Sft )
4"x1" T & G Plank Cft. 10.96 15% wastage
Nails Lb 2
Carpenters No 2
Workers No 1

25 1" Butt Joint Plank Flooring With 4" x 1"


Planks
( For 100 Sft )
4"x1" Butt Joint Plank, 345 Rft Cft. 9.6 15% wastage
Nails Lb 2
Carpenters No 1 1/2
Workers No 1

26 Parquet Flooring Teak Blocks 9"x3"x1½"


Wax Polished
( For 100 Sft )
Coal Tar Gal 2
Asphalt Gal 7
Turpentine Pint 2
Teak Blocks, 9" x 3" x 1½" No 580
Fuel Cft 4
Bees Wax Lb 2
Carpenters No 6
Workers No 8
Sundries L.S ...
pg-40

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XI. WALLING
1 ½" Teak Or Pyingado T & G Plank Walling
Without Frames
( For 100 Sft )
T & G Planks 4" x ½" Cft. 5.29 15% Wastage
Nails Lb 2
Carpenter No 2

2 6" x ½" weather Board Walling Without


Frames
( For 100 Sft )
6" x ½" Planks Allowing 1½" Lap Cft. 6.48 15% Wastage
Vertical Strips 1½" x 3" Cft. 0.72
Nails Lb 1
Carpenter No 2 1/2

3 ½" Butt Jointed Plank Walling Without


Frames But With 2" x ½" Splints
( For 100 Sft )
6" x ½" Planks 200' Cft.
6.39 15% Wastage
2" x ½" Planks 200' Cft.
Nails Lb 2
Carpenter No 2 1/2

4 Trellis Work 2" Mesh With 2" x ½" Battens


And Zallies 40' x 2" x ½"
( For 100 Sft )
Filling Pieces 20' x 2' x ½" Cft.
Zallies 40' x 2" x ½" Cft. 5.27 15% Wastage
Diagonals 600' x 2" x ½" Cft.
Nails & Spikes Lb 6
Carpenter No 2

5 Galvanized C.I Sheet 8/3 Corrugation


Walling 4½" Lap Without Frames
( For 100 Sft )
Gal. C.I Sheet 8/3 Corrugation 7' No 9
G.I Roofing Nails With Washers Lb 1 1/2
Carpenters No 3/4
Workers No 1/2

6 Galvanized C.I Sheet Walling 4½" Lap


Without Frames
( For 100 Sft )
Gal. C.I Sheet 10/3 Corrugation 7' No 6
G.I Roofing Nails With Washers Lb 1 1/2
Carpenters No 3/4
Workers No 1/2

7 3" Thick Reinforced Brick Wall in Cement


Mortar 1:3 Reinforced at Every 4th
Course
( For 100 Sft )
Reinforcement ( X-Met 2½" Wide) Rft 105
pg-41

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Bricks 9" x 4 3/8"x 2 ¾" No 350
Cement Lb 118
Sand Cft. 4
Masons No 1 1/2
Workers No 2

8 4½" Thick Reinforced Brick Wall in


Cement Mortar 1:3 Reinforced at Every
4th Course
( For 100 Sft )
Reinforcement ( X-Met 2½" Wide) Rft 115
Bricks 9" x 4 3/8" 2 ¾" No 550
Cement Lb 297
Sand Cft. 10
Masons No 2
Workers No 3

8(A) 4½" Thick Brick Nogged Walling in Cement


Mortar 1:3 With 6"x3" Frames
( For 100 Sft )
Reinforcement ( X-Met 2½" Wide) Rft 115
Bricks 9" x 4 3/8" 2 ¾" No 550
Cement Lb 297
Sand Cft. 10
Frames 4x10'x6"x3" Cft. 5.5 10% Wastage
Beadings ¾" x ¾" x 4 x 4 x 10' + 2 x 10' Cft. 0.81 15% Wastage
Screw Gross 3/4
Coal Tar Lb 1
Nail And Spike Lb 1
Masons No 2
Carpenters No 1 1/4
Workers No 3

9 3" Thick Reinforced Brick Wall in Cement


Mortar 1:2 Reinforced at Every 3rd
Course
( For 100 Sft )
Reinforcement ( X-Met 2½" Wide) Rft 105
Bricks 9" x 4 3/8" 2 ¾" No 350
Cement Mortar Lb 4
Masons No 1 1/2
Workers No 2

10 4½" Thick Reinforced Brick Wall in Lime


Mortar 1:1:1 And With Reinforcement
at Every 4th Course Set In Cement
Mortar 1:2
( For 100 Sft )
Reinforcement ( X-Met 2½" Wide) Rft 115
Bricks 9" x 4 3/8"x 2 ¾" No 550
Lime Mortar 1:1:1 Cft. 7.5
Cement Mortar 1:2 Cft. 2.5
Masons No 2
Workers No 3
pg-42

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
11 Palisading Walling For Prisoners Cage
Including Rivets
( For 100 Sft )
3/8"ø Rivets 6½" Long No 88
Frames 4x10'x5"x4" Cft.
18.34 10% Wastage
Verticals 20 x 10' x 4" x 2" Cft.
Carpenter No 3

12 1½" Thick Expanded Metal Lath (No.26)


Walling in Cement Mortar 1:2
( For 100 Sft )
Expanded Metal Lathing ( No. 26) Sft 110 10% Wastage
Cement Mortar Cft. 12
Masons No 2
Workers No 2

13 X.P.M or Square Mesh Walling Without


Frames But With 2" x ½" Covering Strips
And secured with Screws
( For 100 Sft )
X.P.M or Square Mesh Sft 110 10% Wastage
Covering Strips 8 x 10' x 2" x ½" Cft. 0.64 15% Wastage
Screw Gross 1/2
Nails Lb 1
Carpenters No 1

14 ¼" Thick 2" Sq. Mesh Walling With And


Including 2" x ½" Teak Wrought Beading
And Including 4" x 2" Teak Without
Frames
( For 100 Sft )
2" Sq. Mesh 2"x2"x 7 S.W.G Sft 110 10% Wastage
2"x½" Teak Beadings Cft. 0.48 15% Wastage
Teak Wall Frames Cft. 3.7 10% Wastage
Nails And Wood Screws Gross 1 1/2
Carpenters No 2

15 Square Mesh Window guard With And


Including 2"x½" Thick Teak Beading
( For 25.18 Sft )
2" Sq. Mesh 2"x2"x 3/16 S.W.G Sft 27.7 10% Wastage
2"x½" Teak Beadings Cft 0.2 15% Wastage
Nails And Wood Screws L.S ...
Carpenters No 5/8
16 ½" Mesh Galvd. Iron Wire Netting With
Battens And Zallies
( For 100 Sft )
½" Mesh Galvd. Wire Netting 3' Wide Rft 42
Battens, Horizontal 1x80'x2"x1" Cft
Vertical 24x1¼'x2"x1" Cft
3.28 15% Wastage
Covering Strips 2x80'x2"x½" Cft
Covering Strips 24x1¼'x2"x½" Cft
Nails Lb 1
Carpenters No 1 1/2
pg-43

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
17 Fly Proof Mesh Fixed With 2" x 1" Teak
Fillets And 1½" x ½" Teak Beading
Complete
( For 100 Sft )
1½" x ½" Teak Beadings Cft 0.72 15% Wastage
2" x 1" Teak Fillets Cft 1.92 15% Wastage
Fly Proof Mesh (Wire) Sft 110
Nails Lb 1
Carpenters No 1 1/2
18 Bird Proof Wire Mesh Fixed With 2" x 1"
Teak Fillets And 1½" x ½" Teak Beading
Complete
( For 100 Sft )
½" Teak Plank Cft 0.72 15% Wastage
1" Teak Plank Cft 1.92 15% Wastage
Bird Proof Mesh (Wire) Sft 110
Nails Lb 1
Carpenters No 2 1/2

19 4" x ½" Fixed Venetian Walling With 4" x 2"


Frames
( For 100 Sft )
Frames 7 x 10' x 4" x 2" Cft 4.28 15% Wastage
Venetian, 74 x 10' x 4" x ½" Cft 11.82 15% Wastage
Nails Lb 1
Carpenters No 16

20 4" x ½" Movable Venetian Walling With


4" x 2" Frames
( For 100 Sft )
Frames 7 x 10' x 4" x 2" Cft 4.28 10% Wastage
Venetian Flaps, 74 x 10' x 4" x ½" Cft 11.82 15% Wastage
Venetian Bars Cft 1.28 15% Wastage
Venetian Hooks No 150
Carpenters No 19

21 Asbestos Sheet Walling Without Frames


But With 1½" x ½" Moulded Beadings
Complete With Screws On Frames
( For 144 Sft )
Asbestos Sheet Sft 158 10% Wastage
Beading 1½" x ½" x 110' Cft 0.66 15% Wastage
Nails Lb 1/4
Screws No 104
Carpenters No 1
Workers No 2

22 Single Rough Bamboo Mat Walling Without


Frames But with 3" x ½" Covering Strips
( For 144 Sft )
Covering Strips, 4 x 10' x 3" x ½" Cft 0.48 15% Wastage
Bamboo Mat Sft 115
Nails Lb 1 1/2
Carpenters No 1
pg-44

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
23 Double Bamboo Mat Wall( Coarse Outside
and Fine Inside) With 2" x ½" Zallies But
Without Frames
( For 100 Sft )
½" Planks Cft 0.32 15% Wastage
Mat (Coarse Bamboo ) Sft 115
Mat (Fine Bamboo ) Sft 115
Wire Nails Lb 1 1/2
Carpenters No 1

24 Single Bamboo Mat Walling Without


Frames But with 3" x ½" Covering Strips
( For 100 Sft )
Covering Strips, 4 x 10' x 4" x ½" Cft 0.64 15% Wastage
Bamboo Mat Sft 115
Wire Nails 2" Lb 1 1/2
Carpenters No 1
25 Double Bamboo Mat Walling Without
Frames But with Covering Strips
( For 100 Sft )
Covering Strips, 4 x 10' x 4" x ½" Cft 0.64 15% Wastage
Bamboo Mat (Coarse) Sft 115
Bamboo Mat (Fine) Sft 115
Wire Nails Lb 1 1/2
Carpenters No 1
26 Providing Movable Plywood Partition Wall
Fixed on Both sides And Including
2"x 1½" Frames And Runners.
( For 100 Sft )
Scantlings Cft 5.5 10% Wastage
Planks Cft 1.92 15% Wastage
Plywood Sft 230 15% Wastage
4" Brass Bow Handle No 4
Nails and Wood screws Lb 2
Carpenters No 10
27 Providing of Plywood Walling Without
Frames
( For 100 Sft )
Plywood Sft 115 15% Wastage
Nails and Spike Lb 1 1/2
Carpenters No 2
28 Providing of Plywood(5Ply) Walling With
And Including 4" x 2" frames
( For 100 Sft )
Plywood (5 Ply) Sft 115 15% Wastage
Wall Frames 4"x2" Cft 2.44 10% Wastage
Nails and Spike Lb 2
Carpenters No 2
29 Scaffolding not include in original
( For 100 Sft )
Bamboo (Wahya 1½"ø to 2" ø) Sft 48 15% Wastage
Coinyan Viss 2.75
Carpenters No 4
Workers No 4
pg-45

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XII. CEILING
1 4" x ½" T & G Plank Ceiling With 4" x 2"
Joist at 2' Centres.
( For 100 Sft )
4" x ½" T & G Planks 331Rft Cft. 5.29 15% Wastage
Joist, 5½ x 10' x 4" x 2" Cft. 3.36 10% Wastage
Nails & Spikes Lb 2 1/2
Carpenter No 2 1/2

2 ½" Thick T & G Ceiling Without Ceiling


Joists
( For 100 Sft )
4" x ½" T & G Planks 331Rft Cft. 5.29 15% Wastage
Nails & Spikes Lb 1 1/2
Carpenter No 1 1/2

3 4" x ½" Butt Jointed Plank Ceiling Without


Frames But With 2" x ½" Splints And
4" x 2" Joists At 2' Centres
( For 100 Sft )
4" x ½" Planks, 10' x 10' x ½" Cft.
7.19 15% Wastage
Splints, 30 x 10' x 2" x ½" Cft.
Joist, 5½ x 10' x 4" x 2" Cft. 3.36 10% Wastage
Nails And Spike Lb 2 1/2
Carpenter No 2 1/2

4 Asbestos Cement Ceiling With 4" x 2" Joists


At 2' Centres
( For 256 Sft )
4'x4' Asbestos Cement Sheet Sft 282 10% Wastage
Beading 1½" x ½" Cft 0.96 15% Wastage
Joists, 4" x 2" Cft 8.8 10% Wastage
1½" Wood Screws No 216 =1.5 gross
Nails Lb 1 1/2
Carpenters No 7 1/2

5 Asbestos Sheet Ceiling With 3" x 2" Joists


At 2' Centres And 1½" x ½" Beadings
( For 256 Sft )
A.C Plain Sheets Sft 282 10% Wastage
Joists, 3" x 2" Cft 6.6 10% Wastage
Beading 1½" x ½" Cft 0.96 15% Wastage
1½" Wood Screws Gross 1 1/2
Nails Lb 1 1/2
Carpenters No 6 1/2

6 Asbestos Sheet Ceiling With 4" x 2" Joists


At 4' Centres And 2" x 2" Cross Joists At
2' Centres Complete With 2" x ½"
Teak Beadings
( For 256 Sft )
A.C Plain Sheets Sft 282 10% Wastage
Joists, 4" x 2" Cft 4.89 10% Wastage
Joists, 2" x 2" Cft 4.6 15% Wastage
pg-46

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Teak Beading 1½" x ½" Cft 0.96 15% Wastage
1½" Wood Screws Gross 1 1/2
Nails Lb 1 1/2
Carpenters No 7 1/2

7 A.C Plain Sheet Ceiling With 3" x 2" Joists


At 4' Centres And 2" x 2" Cross Joists
At 2' Centres Complete With 2" x ½"
Teak Beadings
( For 256 Sft )
4' x 4' A.C Plain Sheets Sft 282 10% Wastage
Joists, 3" x 2" Cft 3.67 10% Wastage
Joists, 2" x 2" Cft 4.6 15% Wastage
Teak Beading 1½" x ½" Cft 1.28 15% Wastage
1½" Wood Screws Gross 1 1/2
Nails Lb 1 1/2
Carpenters No 7

8 A.C Plain Sheet Ceiling With 1½" x ½"


Teak Beadings But Without Ceiling Joists
( For 256 Sft )
4' x 4' A.C Plain Sheets Sft 282 10% Wastage
Teak Beading 1½" x ½" Cft 0.96 15% Wastage
1½" Wood Screws Gross 1 1/2
Nails Lb 1/2
Carpenters No 3 1/2
9 Bamboo Mat Ceiling with Covering Strips
But Without Joists
( For 100 Sft )
Bamboo Mat, Single Layer Sft 115
Covering Strips, 4" x ½" Cft 1.28 15% Wastage
Nails Lb 2
Carpenters No 1
10 Single Fine Bamboo Mat Ceiling with
3" x 2" Joists At 4' Centres And 2" x 2"
Cross Joists At 2' Centres With 2" x ½"
Beading
( For 100 Sft )
Fine Mat (Bamboo) Sft 295 15% Wastage
Scantling 3" x 2" Cft 3.67 10% Wastage
Scantling 2" x 2" Cft 4.6 15% Wastage
Beadings, 2" x ½" Cft 1.28 15% Wastage
Nails Lb 5
Carpenters No 5
Workers No 1 1/2

11 X.P.M Ceiling With 3" x ½" Beadings


Without Ceiling Joists
( For 100 Sft )
X.P.M Sft 110 10% Wastage
Beadings, 3" x ½" Cft 0.96 15% Wastage
Nails Lb 1 1/2
Carpenters No 2
pg-47

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
12 X.P.M ¾" Mesh ¼" Thick Ceiling With
3" x ½" Beadings
( For 100 Sft )
X.P.M ¾" Mesh ¼" Thick Sft 110 10% Wastage
Beadings, 3" x ½" Cft 0.96 15% Wastage
Nails Lb 1 1/2
Carpenters No 2

13 Square Mesh Ceiling With 4" x 2" Joists At


2' Centres And 2" x ½" Beadings
( For 100 Sft )
4" x 2" Scantling Cft 3.67 10% Wastage
Beadings, 2" x ½" Cft 0.48 15% Wastage
Sq. Mesh Sft 110 10% Wastage
Nails Lb 1 1/2
Carpenters No 2 1/2

14 Providing Ply Wood Ceiling With 3" x 2"


Ceiling Joists At 2' Centres.
( For 256 Sft )
Plywood Sft 295 15% Wastage
3" x 2" Scantling Cft 6.6 10% Wastage
Nails Lb 2
Wood Screws Gross 2
Carpenters No 6 1/2

15 Providing 3 Ply Wood Ceiling Complete


With 3" x 1½" Ceiling Joists At 2'
Centres (Both Ways) And 2" x ½"
Beadings
( For 256 Sft )
Plywood ( 3 Ply) Sft 295 15% Wastage
Scantling Cft 10.35 15% Wastage
½" Beading Cft 2.3 15% Wastage
Nails Lb 3
Wood Screws Gross 2
Carpenters No 7 1/2
pg-48

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XIII. ROOFING
1 Danyingon (Mangalore Pattern) Clay Tile
Roofing With 2" x 1" Battens And 4" x 2"
Common Rafters
( For 100 Sft )
Mangalore Pattern Clay Tiles No. 156 20% Wastage
2" x 1" Battens At 13" Centres Cft 1.76 15% Wastage
4" x 2" Common Rafters 2' Centres Cft 3.42 10% Wastage
Nails & Spikes Lb 2
Binding Wire L.S ...
Carpenter No 2
Workers No 2

2 Danyingon (Mangalore Pattern) Clay Tile


Roofing With 2" x 1" Close Battens And
4" x 2" Common Rafters
( For 100 Sft )
Mangalore or Marseilles Tiles No. 156 20% Wastage
2" x 1" Close Battens Cft 9.58 15% Wastage
1½" x 1" Ordinary Battens Above Close Batten Cft 1.32 15% Wastage
4" x 2" Common Rafters 2' Centres Cft 3.42 10% Wastage
Wire Nails & Spikes Lb 5
Carpenter No 3
Workers No 3

3 Danyingon (Mangalore Pattern) Clay Tile


Roofing With 2" x 1" Battens But
Without Rafters
( For 100 Sft )
Mangalore or Marseilles Tiles No. 156 20% Wastage
2" x 1" Battens At 13" Centres Cft 1.76 15% Wastage
Wire Nails & Spikes Lb 1 1/2
Binding Wire Lb 1/2
Carpenter No 1 1/2
Workers No 2

4 Danyingon (Mangalore Pattern) Clay Tile


Roofing Without Battens
( For 100 Sft )
Mangalore Tiles No. 156 20% Wastage
Wire Nails & Spikes L.S ...
Binding Wire Lb 1/2
Carpenter No 1 1/4
Workers No 1 1/2

5 Galvd. C. I Roofing 24 or 30 B.W.G


7' x 10/3
( For 100 Sft )
Galvd. C. I Sheet, 7' x 10/3 No 7
G.I Roofing Nails Lb 1 1/2
Carpenters No 1 1/2
Workers No 1
pg-49

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
6 Galvd. C. I Roofing Laid on 1" Planking
( For 100 Sft )
Galvd. C. I Sheet, 7'- 10/3 No 7
G.I Roofing Nails Lb 1 1/2
1" Thick Planking Cft 9.58 15% Wastage
Nails Lb 2
Carpenters No 3
Workers No 1

7 Roofing of 32 G. C.G.I Sheets Supplied


And Fixed
( For 100 Sft )
32G. C.G.I Sheets No 9
G.I Roofing Nails Lb 1 1/2
Carpenters No 1 1/2
Workers No 1

8 Wind Ties For Corrugated Iron Roofing


( For 100 Sft )
Flat Iron 1¼"x¼" With Necessary Bolt Holes Lb 128
3/8" Hook Bolts 12" Long With Heads & Nuts No 25
Carpenters No 1
Smith No 3
Workers No 1

9 Teak Shingle Roofing With 2" x 1" Battens


And 3" x 2"Common Rafters At 2'
Centres
( For 100 Sft )
Teak Shingles, 15" x 15" No 600 15% Wastage
2" x 1" Battens At 5" Centres Cft 4 10% Wastage
3" x 2" Common Rafters 2' Centres Cft 2.52
Nails And Spikes Lb 5
Earth Oil Gal 4
Fuel L.S ...
Carpenters No 2 1/2
Workers No 4

10 Teak Shingle Roofing With 2" x 1" Close


Battens
( For 100 Sft )
Teak Shingles, 15" x 5" No 600 15% Wastage
2" x 1" Battens Cft 9.58 10% Wastage
Nails Lb 9
Earth Oil Gal 4
Fuel L.S ...
Carpenters No 3
Workers No 4
pg-50

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
11 Thatch Roofing With Bamboo Rafters
And Purlins
( For 100 Sft )
Bamboo Rafters 9" Centers 10' Long No 14
Bamboo Purlins 18" Centers 10' Long No 7
Bamboo Small Size For Lattice Work 10' Long No 20
Thatch ( 6 Nos to 1' ) No 120
Cane Ties L.S ...
Thatch Layer No 1
Workers No 1

12 Wagat Roofing With Bamboo Rafters


And Purlins
( For 100 Sft )
Bamboo Rafters 2' Apart 10' Long No 6
Bamboo Purlins 18" Centers 10' Long No 7
Bamboo Small Size For Lattice Work 10' Long No 20
Wagat ( 6 Nos to 1' ) No 120
Cane Ties L.S ...
Wagat Layer No 1
Workers No 1 1/4
Earth Oil Gal 1
Fuel L.S ...

13 Wagat Roof With Bamboo Common


Rafters 1'-0" Centres And Whole Wind
Ties Complete
( For 100 Sft ) Wind Ties At
1½" to 2" ø Bamboo No 20 2½' Centres
Hnee (Fine Bamboo) Viss 1
Wagat ( 6 Nos to 1' ) No 120
Binding Wire Lb 1/4
Wagat Layer No 1
Workers No 1 1/4
Earth Oil Gal 1
Fuel L.S ...

14 Wagat Roofing With 2" x 1" Rafters 1'-0"


Centres And Bamboo Wind Ties Fixed At
2' Centres And Complete Including Earth
Oiling 2 Coats to Timber And
Impregnating Wagat With Earth Oil
( For 100 Sft )
2" x 1" Common Rafters No 1.75
1½" to 2" ø Bamboo No 8
Wagat ( 6 Nos to a Foot ) No 120
Nails Lb 1
Binding Wire Lb 1/4
Earth Oil Gal 1 1/3
Fuel L.S ..
Wagat Layer No 1
Carpenters No 1/3
Workers No 1 1/4
pg-51

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
15 Dhani, Thetke or Thatch Roofing Laid 6
Byits to a Foot With 6" Side Laps and
Including a Covering of Bamboo Lattice
Frames And 1½"ø Wind Ties At 4'
Centres
( For 160 Sft )
1½"ø Bamboo Rafters At 12" Centres No 11
1½"ø Bamboo For Lattice And Wind Ties No 15
Dhani, Thetke or Thatch (6 Nos to a Foot) No 120
Hnee Viss 1
G.I Binding Wire Lb 1/2
Dhani or Thatch Layer No 1
Workers No 1

16 Corrugated A.C Sheet Roofing With


¼"ø Hook Bolts And Washers
( For 100 Sft ) *Tilex-10½ Nos.
Trafford or Corrugated A.C Sheet 7'-0" Long No 5 (30" x 5'-0")
Hook Bolts And Washers Lb 5 *Burdex-
Carpenters No 2 15 Nos
Workers No 1 (22" x 5'-0")

17 Galvd. Iron Ridge And Hip Covers With


6" Lap
( For 7.5 Rft ) *When G.I Ridging
Galvd. Iron Ridge With G.I Screws Rft 8 and Hip Covering
Carpenters No 1/4 is to be used for
A.C Sheet Roofing
Allow One More
Carpenter for
Every 7½ Feet.
18 Ridging of G.I Plain Sheet 24" Girth With
9" End Laps Fixed Complete
( For 100 Rft )
G.I Plain Sheet Rft 112
G.I Roofing Nails With Washer Lb 1 1/2
Carpenters No 3 1/3

19 No. 24 G. G.I Plain Sheet Ridging 2'-6"


Girth 3" Roll Ends Laps Complete
( For 100 Rft )
7' G.I Plain Sheet 24G Rft 112
G.I Roofing Nails With Washer Lb 1 1/2
Carpenters No 3 1/3

20 Danyingon (Mangalore Pattern) Clay Tile


Ridge And Hip Covering Set in Cement
Mortar 1:4
( For 100 Rft )
Mangalore or Marseilles Ridge Tiles No 90
Cement Mortar Cft 2
Mason No 2
Workers No 2
pg-52

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
21 Wooden Ridge And Hip Covers
( For 10 Rft )
Ridge Roll 1 x 10' x 4" x 3" Cft 0.92 10% Wastage
Boards, 2 x 10' x 9" x 1" Cft 1.44 15% Wastage
Nails Lb 1/4
Carpenters No 1/4

22 20 B.W.G Zinc Valley Guttering 3' Wide


Laid on 12" x 1"Planks And 2" x 1" Fillets
( For 22½ Rft )
20 B.W.G 8' x 3' Zinc Sheet 9" Lap Sht 3
Planks, 2 x 25' x 2" x 1" Cft 4.79 15% Wastage
Fillets, 2 x 23' x 2" x 1" Cft 0.73 15% Wastage
Nails No 1/2
Carpenters No 1 1/2

23 G.I Valley Guttering 3' Wide Without


Planks
( For 22.5 Rft )
G.I Plain Sheet Sft 72
Nails No 1/4
Carpenters No 1

24 Valley Guttering With G.I Plain sheet 36"


Girth With 9" End Laps, Supported on 1"
Valley Boards And 2" x 1" Fillets
Including Earth Oiling 2 Coats
( For 22.5 Rft )
G.I Plain Sheet Rft 24
Planks, 6" x 1" Cft 6.47 15% Wastage
Fillets, 2" x 1" Cft 0.73 15% Wastage
Earth Oil Gal 1/2
Nails No 1/4
Carpenters No 1 3/4
Workers No 1/4

25 Valley Guttering of 32G. G.I Plain Sheet


24" Girth With 9" End Laps, Supported
on ½" Thick Valley Boards And
Complete With 2" x 1" Fillets Including
Earth Oiling 2 Coats
( For 100 Rft )
G.I Plain Sheet Rft 112
Planks, 6" x ½" Cft 9.58 15% Wastage
Fillets, 2" x 1" Cft 3.19 15% Wastage
Earth Oil Gal 1 1/2
Nails No 2 1/2
Carpenters No 5
Workers No 1 1/2
pg-53

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
26 5 Lb Per Sft Flashing 18" Wide For 150 Sft
( For 100 Rft )
7' x 3' Lead Sheet 5 Lb/Sft Sht 9
Composite Mortar Cft 2.5
Mason No 2
Tin Smith No 2
Workers No 4

27 Lead Flashing 18" Wide


( For 100 Rft )
Lead Sheet (7' x 3') Sht 9
Cement Lb 75
Sand Cft 2 1/2
Mason No 2
Tin Smith No 2
Workers No 4

28 5 Lb Per Sft Lead Flashing 20" Wide


For 167 Sft
( For 100 Rft )
5 Lb/Sft Lead Sheet Sft 189
Cement Mortar 1:3 Cft 2.5
Mason No 2
Tin Smith No 2
Workers No 4

29 G.I Plain Sheet Flashing 18" Width


( For 100 Rft )
G.I Plain Sheet (7' x 3') Sft 8
Cement Lb 75
Sand Cft 2 1/2
Mason No 2
Tin Smith No 2
Workers No 4

30 Zinc Flashing 18" Wide With 6" Lap


( For 13.5 Rft )
Zinc Sheet (7' x 3') Sft 1
Nails And Screws Lb 1
Carpenters No 1

31 G.I / C.I Rain Water Pipe


( For 100 Rft )
G.I / C.I Pipe Rft 100
Offsets And Bends L.S ...
Plumber No 3
Mate No 3
pg-54

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
32 Corrugated A.C or Trafford Ridging With
½" Hook Bolts And Nuts And Washers
( For 100 Sft )
A.C Ridging Tile Rft 100 *To be included
¼"ø Bolts And Nuts and Washers Lb 22* only if the Ridging
Carpenters No 3 1/3 is Carried out
Workers No 1 Separately

33 Diamond Shape Cement Tile Roofing With Note: to cover


2" x 1" Battens But Without Rafters edges the following
are available
( For 100 Sft ) 1.Horizontal Top
Diamond Shape Tile No 220 Half-Tile
2" x 1" Battens At 6" Centres Cft 3.52 2.Horizontal Bottom
Wire Nails Lb 3 Half-Tile
Carpenters No 2 3. R.H.S
Workers No 2 Half-Tile
4. L.H.S
Half-Tile

34 Cement Tile Ridging For Diamond Shape


Cement Tile Ridging For Diamond Shape
Cement Tile Roofing, Set in Cement
Mortar 1:3
( For 100 Rft ) Note: To Cover
Cement Tile Ridging Piece No 74 Edges the
Cement Mortar Cft 2 Following are
Mason No 2 Available.
Workers No 2 1. R.H.S End
Ridge Piece And
2. L.H.S End
Ridge Piece.
pg-55

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XIV. PAINTING AND WASHING
1 Coal Tarring One Coat (New Work)
( For 100 Sft )
Coal Tar Gal 3/4
Workers No 3/8
Sundries Including Brushes, Fuel, Etc. L.S ...

2 Coal Tarring Two Coats (New Work)


( For 100 Sft )
Coal Tar Gal 1 1/4
Workers No 3/4
Sundries Including Brushes, Fuel, Etc. L.S ...

3 Oiling With Boiled Linseed Oil


( For 100 Sft )
Linseed Oil, Boiled Gal 1/4
Workers No 1/4
Sundries Including Brushes, Fuel, Etc. L.S ...

4 Oiling With Boiled Linseed Oil Two Coats


( For 100 Sft )
Linseed Oil, Boiled Gal 7/16
Workers No 1/2
Sundries Including Brushes, Fuel, Etc. L.S ...

5 Earth Oiling to Roof With Red Ochre


( For 100 Sft )
Red Ochre Lb 1.5
Earth Oil Gal 0.5
Workers No 3/8
Sundries Including Brushes, Fuel, Etc. L.S ...

6 Earth Oiling with 5% Coal Tar


( For 100 Sft )
Coal Tar Lb 0.175
Earth Oil Gal 0.35
Workers No 3/8
Sundries Including Brushes, Fuel, Etc. L.S ...

7 Earth Oiling Plain One Coat


( For 100 Sft )
Earth Oil Gal 0.35
Workers No 3/8
Sundries Including Brushes, Fuel, Etc. L.S ...

8 Earth Oiling Plain Two Coats


( For 100 Sft )
Earth Oil Gal 0.6
Workers No 5/8
Sundries Including Brushes, Fuel, Etc. L.S ...
pg-56

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
9 Distemper One Coat
( For 100 Sft )
Distemper Lb 3
Painter No 1/4
Workers No 1/8
Sundries Including Brushes, Fuel, Etc. L.S ...

10 Distemper Two Coats


( For 100 Sft )
Distemper Lb 5
Painter No 3/8
Workers No 1/4
Sundries Including Brushes, Fuel, Etc. L.S ...

11 Distemper Three Coats


( For 100 Sft )
Distemper Lb 7
Painter No 1/2
Workers No 3/8
Sundries Including Brushes, Fuel, Etc. L.S ...

12 Painting With Solignum One Coat


( For 100 Sft )
Solignum Gal 3/8
Painter No 1/8
Sundries Including Brushes, Fuel, Etc. L.S ...

13 Painting With Solignum Two Coats


( For 100 Sft )
Solignum Gal 5/8
Painter No 1/4
Sundries Including Brushes, Fuel, Etc. L.S ....

14 White Washing One Coat


( For 100 Sft ) *Use Liquid of
Strained Lime Cft 1/2 Glue instead of
Rice Lb 1/8 Rice
Workers No 1/8
Sundries Including Brushes, Fuel, Etc. L.S ...

15 White Washing Two Coats


( For 100 Sft ) *Use Liquid of
Strained Lime Cft 3/4 Glue instead of
Rice Lb 1/4 Rice
Workers No 1/4
Sundries Including Brushes, Fuel, Etc. L.S ...

16 White Washing Three Coats


( For 100 Sft ) *Use Liquid of
Strained Lime Cft 1 Glue instead of
Rice Lb 3/8 Rice
Workers No 3/8
Sundries Including Brushes, Fuel, Etc. L.S ...
pg-57

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
17 Colour Washing One Coat
( For 100 Sft )
Strained Lime Cft 1/2
Yellow Powder Lb 1/8
Liquid Glue Lb 1/8
Painter No 1/8

18 Colour Washing Two Coats


( For 100 Sft )
Strained Lime Cft 3/4
Yellow Powder Lb 1/4
Liquid Glue Lb 1/4
Painter No 1/4

19 Colour Washing Three Coats


( For 100 Sft )
Strained Lime Cft 1
Yellow Powder Lb 3/8
Liquid Glue Lb 3/8
Painter No 3/8

20 Cement Washing One Coat


( For 1000 Sft )
Cement 1.73 Cft Lb 156
Maistry No 1
Workers No 2
Sundries Including Brushes, Fuel, Etc. L.S ...

21 White Lead Painting Three Coats Including


Priming Coat And Puttying
( For 100 Sft )
Priming Coat (Inside)
Red Lead Lb 1 1/4
White Lead Lb 16
Raw Linseed Oil Pint 6
Turpentine Pint 1/4
Drier Lb 1/8
Putty Lb 2
Second Coat
White Lead Lb 15 *Allow Extra for
Raw Linseed Oil Pint 3 1/2 Works to be
Turpentine Pint 1 1/2 Carried out in the
Drier Lb 1/2 2nd & 3rd
Third Coat Storeys
White Lead Lb 15
Raw Linseed Oil Pint 3 1/2
Turpentine Pint 1 1/2
Drier Lb 1/4
Painter No 10
Workers No 18
Sundries Including Brushes L.S ...
pg-58

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
22 Painting One Coat With Red Lead Ready
Mixed (New Work)
( For 1000 Sft )
*Red Lead Paint (Ready Mixed) Lb 30 *For Renewal
Putty Lb 4 20 Lb Only
Painter No 2 1/2
Workers No 2 1/2
Sundries Including Brushes L.S ...

23 Painting One Coat With White Zinc in


Renewal
( For 100 Sft )
White Zinc Paint Lb 2
Drier Lb 0.015
Linseed Oil Pint 1/4
Turpentine Pint 0.007
Putty Lb 1/2
Painter No 1
Workers No 1
Sundries Including Brushes L.S ...

24 Painting Two Coats With White Zinc in


Renewal
( For 100 Sft )
White Zinc Paint Lb 3 1/2
Drier Lb 0.03
Linseed Oil Pint 1/2
Turpentine Pint 0.014
Putty Lb 1/2
Painter No 2
Workers No 2
Sundries Including Brushes L.S ...

25 Painting Three Coats With White Zinc


in Ready Mixed
( For 1000 Sft )
Priming Coat Red Lead Lb 30
White Zinc Paint for 2nd and 3rd Coat Lb 45
Putty Lb 4
Painter No 10
Workers No 10
Sundries Including Brushes L.S ...

26 Painting Two Coats With White Zinc in


Ready Mixed (Renewal)
( For 1000 Sft )
White Zinc Ready Mixed for Two Coats Lb 48
Putty Lb 2
Painter No 5
Workers No 5
Sundries Including Brushes L.S ...
pg-59

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
27 Painting One Coat With White Zinc Ready
Mixed (Renewal)
( For 1000 Sft )
White Zinc Ready Mixed Lb 28
Putty Lb 2
Painter No 2 1/2
Workers No 2 1/2
Sundries Including Brushes L.S ...

28 Painting Two Coats With White Zinc Ready


Mixed (New Work)
( For 1000 Sft )
White Zinc Ready Mixed for Two Coats Lb 55
Putty Lb 2
Painter No 5
Workers No 5

29 Painting One Coat in Renewal Any Paint


Ready Mixed Red Oxide, Corrival,
Chocolate, Green, Black, Etc.
( For 1000 Sft )
Ready Mixed Paint Lb 20
Putty Lb 2
Painter No 2 1/2
Workers No 2 1/2
Sundries Including Brushes L.S ...

30 Painting Two Coats in New Work Any


Paint Ready Mixed Red Oxide, Corrival,
Chocolate, Green, Black, Etc.
( For 1000 Sft )
Ready Mixed Paint Lb 50
Putty Lb 2
Painter No 5
Workers No 5
Sundries Including Brushes L.S ...

31 Painting Ripolin Enamel Ready Mixed


One Coat
( For 1000 Sft )
Ripolin Enamel Paint Gal 1 2/3
Painter No 2 1/2
Workers No 2 1/2
Sundries Including Brushes L.S ...

32 Painting Three Coats (New Work) With


Ready Mixed Paint of Any Approved
Colour
( For 1000 Sft )
Ready Mixed Paint Lb 75
Putty Lb 4
Painter No 10
Workers No 10
Sundries Including Brushes L.S ...
pg-60

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
33 Painting Three Coats to Wood Work in
Posts, Chowkets, Facia Boards, Eave
Boards And Stringers With Ready Mixed
Paint of Any Approved Colour
( For 1000 Sft )
Ready Mixed Paint Lb 75
Putty Lb 4
Painter No 12 1/2
Workers No 10

34 Painting Iron Work With Collins Mixture


One Coat
( For 225 Sft )
Coal Tar Gal 1
Cement 1/50 Cft Lb 1.8
Kerosene Oil Gal 1/8
Fire Wood L.S …
Painter No 1/2
Workers No 1/2
Sundries Including Brushes L.S …

35 Painting With Bitumastic Solution One Coat


( For 100 Sft )
Bitumastic Solution Gal 1/4
Workers No 1/2
Sundries Including Brushes L.S …

36 Varnishing (Copal) One Coat


( For 100 Sft )
Copal Varnish Gal 1/4
Painter No 3/8
Sundries Including Brushes L.S …

37 Varnishing (Copal) Two Coats


( For 100 Sft )
Copal Varnish Gal 1/2
Painter No 1/2
Sundries Including Brushes L.S …

38 Varnishing (Copal) Three Coats


( For 100 Sft )
Copal Varnish Gal 5/8
Painter No 3/4
Sundries Including Brushes L.S …

39 Wood Oiling One Coat


( For 100 Sft )
Wood Oil Lb 2
Workers No 1/2
Sundries Including Brushes L.S …
pg-61

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
40 Wood Oiling Two Coats
( For 100 Sft )
Wood Oil Lb 3
Workers No 3/4
Sundries Including Brushes L.S …

41 Bee's Waxing
( For 100 Sft )
Bees Wax Lb 1/4
Turpentine Pint 1/8
Painter No 1
Sundries Including Labour For Wood, L.S …
Dust Topping Cloth L.S …

42 Removing Old Paint Entirely With Caustic


Soda
( For 100 Sft )
Caustic Soda Lb 3
Paint Remover Brushes L.S … *For Taking
Carpenters No 1/4 down and
Painter No 1/2 Rehanging Doors
Workers No 1/4 and Windows

43 Snowcem One Coat


( For 100 Sft )
Snowcem Lb 3 1/2
Painter No 1/4
Workers No 1/8

44 Snowcem Two Coats


( For 100 Sft )
Snowcem Lb 6
Painter No 3/8
Workers No 1/4

45 Plastic Emulsion Paint One Coat


( For 100 Sft )
Emulsion Paint Gal 1/5
Painter No 1/4

46 Plastic Emulsion Paint Two Coats


( For 100 Sft )
Emulsion Paint Gal 1/3
Painter No 1/2

47 Plastic Emulsion Paint Three Coats


( For 100 Sft )
Emulsion Paint Gal 1/2
Painter No 3/4
pg-62

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
48 Bengal Polishing Three Coats to
Wooden Wall
( For 100 Sft )
Methylated Spirit Gal 1 1/4
Shellac Lb 1 1/4
Sand Paper, Cotton Waste, Etc. L.S …
Polisher No 7

49 Bengal Polishing Three Coats to Wooden


Furniture
( For 100 Sft )
Methylated Spirit Gal 1 3/8
Shellac Lb 1 3/8
Sand Paper, Cotton Waste, Etc. L.S …
Polisher No 10 1/2
pg-63

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XV. FENCING
1 Wooden Fencing With Posts 8 1/3 Centres
And Two Longitudinal Rails
( For 100 Rft )
Coal Tar, Two Coats Gal 4 1/4
Corner Post, 1 x 6½' x 5" x 5" Cft 10% Wastage
Cross Feet, 2 x 2' x 5" x 3" Cft For 24 Cft :-
Interposts, 11 x 6' x 5" x 3" Cft 24 4 Carpenters and
Cross Feet, 22 x 1½' x 5" x 2" Cft Coal Tarring 350
Longitudinal Rails, 2 x 100' x 4" x 2" Cft Sft, Workers for
Nails And Spikes Lb 7 12 Posts Holes
Carpenters No 4
Workers No 4

2 Wooden Fencing With Posts 8 1/3 Centres


And Three Longitudinal Rails
( For 100 Rft )
Coal Tar, Two Coats Gal 5 1/2
Corner Post, 1 x 6½' x 5" x 5" Cft 10% Wastage
Cross Feet, 2 x 2' x 5" x 3" Cft For 30 Cft :-
Interposts, 11 x 6' x 5" x 3" Cft 30.11 5 Carpenters and
Cross Feet, 22 x 1½' x 5" x 2" Cft Coal Tarring 450
Longitudinal Rails, 3 x 100' x 4" x 2" Cft Sft, Workers for
Nails And Spikes Lb 8 12 Posts Holes
Carpenters No 5
Workers No 4

3 5 Strand Wire (No.5 Seven Ply) Fencing


With Wooden Posts 14' Apart
( For 98 Rft )
Coal Tar, Two Coats Gal 1
No.5 Seven Ply Wire Lb 49
Straining Bolts 18" x ½" No 5
Corner Post, 7' x 5" x 5" Cft
Cross Feet, 2 x 2' x 5" x 3" Cft
6.47 10% Wastage
Interposts, 6 x 6½' x 4" x 3" Cft
Cross Feet, 12 x 1½' x 4" x 2" Cft
Staples Lb 1/2
Carpenters No 1 1/2
Workers No 2

4 5 Strand Wire (No.5 Seven Ply) Fencing


With R.C Posts 14' Apart
( For 98 Rft )
R.C Corner Posts At 196' Apart No 1/2
R.C InterPosts And One Strut No 7
No.5 Seven Ply Wire Lb 49
Straining Bolts 18" x ½" ø No 5
Lime Concrete Foundation For Corner Post,
Cft 5
½ x 2' x 2' x 2½'
Binding Wire Staples Lb 1
Carpenters No 1
Workers No 2
pg-64

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
5 American Woven Wire Fencing With R.C
Posts 12½' Apart
( For 100 Rft )
American Woven Wire Rft 100
R.C Corner Posts At 200' Apart No 1/2
R.C InterPosts And One Strut No 8
Lime Concrete Foundation For Corner Post,
Cft 5
½ x 2' x 2' x 2½'
Straining Bolts 18" x ½" ø No 5
Binding Wire Staples Lb 1
Carpenters No 2
Workers No 2

6 Bamboo Fencing With Wooden Posts 10'


Apart
( For 100 Rft )
Corner Posts, 1 x 6½' x 5" x 5" Cft
Cross Feet, 2 x 2' x 5" x 3" Cft
9.95 10% Wastage
InterPost, 9 x 6' x 5" x 3" Cft
Cross Feet, 18 x 1½' x 5" x 2" Cft
Bamboo (Half Split) For Horizontal 10' Long No 15
Bamboo For Split Ver. (3" Dia.)10'Long No 75
Nails Lbs 2
Carpenters No 1 1/2
Workers No 3

7 Barbed Wire Fencing With 4" x 4" Timber


Post 8' Apart Embedded in 1:2:6 Lime
Concrete
( For 96 Rft )
5" x 5" Corner Posts, 1 x 8' x 5" x 5" Cft
4" x 4" Posts, 11 x 8' x 4" x 4" Cft 17.17 10% Wastage
Struts, 8 x 10' x 4" x 2" Cft
Barbed Wire, 10x 96' Rft
1200
Diagonals, 2 x 12 x 10' Rft
Lime Cft 4.55
Sand Cft 9.1
Brick Aggregate Cft 27
Nails Lbs 1
Carpenters No 2
Workers No 4
pg-65

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
8 Chain Link Fencing With 4" x 4" Timber
Post 8' Apart Embedded in 1:2:6 Lime
Concrete
( For 96 Rft )
5" x 5" Corner Posts, 1 x 8' x 5" x 5" Cft
4" x 4" Posts, 11 x 8' x 4" x 4" Cft
18.38 10% Wastage
Struts , 9x10'x4"x2" Cft
Battens, 13 x 6' x 2" x ½" Cft
Straining Wire, 3/8" Dia., 3 x 96' Rft 288
Chain Link, 6 x 96' Sft 576
Lime Cft 4.55
Sand Cft 9.1
Brick Aggregate Cft 27
Nails Lbs 1
Carpenters No 2
Workers No 4
pg-66

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XVI. IRON AND STEEL WORK
1 Hoisting And Fixing R.S Girder
(Over ½ Ton Weight)
( For 1 Cwt )
R.S Girder Cwt 1
Carriage to Site Cwt 1
Hoisting And Fixing Cwt 1

2 Hoisting And Fixing R.S Girder or Joist


(Below ½ Ton Weight)
( For 1 Cwt )
R.S Girder Cwt 1
Carriage to Site Cwt 1
Hoisting And Fixing Cwt 1

3 W.I Work in Tee, Bars, Angles, Round,


Etc.
( For 1 Cwt )
Tee, Bars, Angles, Round, Etc. Cwt 1
Carriage to Site Cwt 1
Smith No 2
Workers No 2

4 W.I Straps For Trusses, Posts, Etc. With


Bolts And Nuts, Etc.
( For 1 Lb )
Straps, Bolts And Nuts Lb 1
Carriage to Site L.S …
Smith No 1/30

5 Mild Steel Bar Reinforcement ½" Dia. Cut,


Bend And Fixed in Floors, Roof And
Beams
( For 1 Cwt )
½" Dia. Bar Lbs 117.6 5% Wastage
14 S.W.G Binding Wire Lb 1
Smith (Steel Fixer) No 1
Workers No 1

6 Mild Steel Bar Reinforcement ½" Dia. Cut,


Bend And Fixed in Columns And Braces
( For 1 Cwt )
½" Dia. Bar Lbs 117.6 5% Wastage
14 S.W.G Binding Wire Lb 1
Smith (Steel Fixer) No 1 1/2
Workers No 1 1/2
7 Mild Steel Bar Reinforcement 5/8" to 1"
Dia. Cut, Bend And Fixed in Floors,
Roofs And Beams
( For 1 Cwt )
5/8" to 1" Dia. Bar Lbs 117.6 5% Wastage
14 S.W.G Binding Wire Lb 1
Smith (Steel Fixer) No 3/4
Workers No 3/4
pg-67

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
8 Mild Steel Bar Reinforcement 5/8" to 1"
Dia. Cut, Bend And Fixed in Columns
And Braces
( For 1 Cwt )
5/8" to 1" Dia. Bar Lbs 117.6 5% Wastage
14 S.W.G Binding Wire Lb 1
Smith (Steel Fixer) No 1
Workers No 1

9 Mild Steel Bar Reinforcement ½" Dia. Cut,


Bend And Fixed in Walls
( For 1 Cwt )
½" Dia. Bar Lbs 117.6 5% Wastage
14 S.W.G Binding Wire Lb 1
Smith (Steel Fixer) No 1 1/4
Workers No 1 1/4

10 Mild Steel Bar Reinforcement 5/8" to 1" 10% Wastage


Dia. Cut, Bend And Fixed in Walls
( For 1 Cwt )
5/8" to 1" Dia. Bar Lbs 117.6 5% Wastage
14 S.W.G Binding Wire Lb 1
Smith (Steel Fixer) No 1
Workers No 1

11 Mild Steel Bar Reinforcement 1" to 1½"


Dia. Cut, Bend And Fixed in Columns
And Braces
( For 1 Cwt )
1" to 1½" Dia. Rods Lbs 117.6 5% Wastage
14 S.W.G Binding Wire Lb 1
Smith (Steel Fixer) No 3/4
Workers No 3/4

12 Mild Steel Bar Reinforcement ¼" Dia.


Stirrups, Spacers Cut, Bend And Fixed
in Floors, Roofs and Beams
( For 1 Cwt )
¼" Dia. Rods Lbs 117.6 5% Wastage
14 S.W.G Binding Wire Lb 1
Smith (Steel Fixer) No 2 1½ No. for 3/8"Ø
Workers No 2 1½ No. for 3/8"Ø

13 Mild Steel Bar Reinforcement 1" to 1½"


Dia. Cut, Bend And Fixed in Floors,
Roofs And Beams
( For 1 Cwt )
1" to 1½" Dia. Rods Lbs 117.6 5% Wastage
14 S.W.G Binding Wire Lb 1
Smith (Steel Fixer) No 5/8
Workers No 5/8
pg-68

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
FIXING ONLY STEEL FABRIC.
14 Fixing Steel Fabric or Mesh Reinforcement
in Beams, Floors And Walls, B.R.C
Expended Metal or Other Type, Including
All Straight Cutting And The Supply of
And Wiring as Necessary With 14G.
Wiring, Measured Nett No Allowance
For Laps
( For 100 Sft )
Sheet Weighting Under 4 Lbs Per Yard
Super
Smith or Steel Fixer No 1/2
Binding Wire(14 G.) L.S …

Sheet From 4 Lbs to 8 Lbs Per Yard


Super
Smith or Steel Fixer No 4/7
Binding Wire(14 G.) L.S …

Sheet Over 8 Lbs And Under 17 Lbs Per


Yard Super
Smith or Steel Fixer No 1
Binding Wire(14 G.) L.S …

FIXING STEEL
15 Fixing Steel Fabric or Mesh Reinforcement
in Beams, Floors And Walls, B.R.C
Expended Metal or Other Type, Including
All Straight Cutting And Wiring as
Necessary With 14G. Wire, Measured
Nett And No Allowance For Laps
( For 100 Sft )
Sheet Weighting Under 4 Lbs Per Yard
Super
Smith or Steel Fixer No 3/4
Binding Wire(14 G.) L.S …
Sheet From 4 Lbs to 8 Lbs Per Yard
Super
Smith or Steel Fixer No 6/7
Binding Wire(14 G.) L.S …
Sheet Over 8 Lbs And Under 17 Lbs Per
Yard Super
Smith or Steel Fixer No 1 1/2
Binding Wire(14 G.) L.S …

16 Hinges Butt Stout Pressed 3" to 4" Fixed


Complete With Screws
( Each )
3" to 4" Butt Hinges No 1
1" wood Screws Gross 1/18
Carpenters No 1/25
pg-69

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
17 Hasp And Staple 4" to 6" Fixed Complete
With Screws
( Each )
4" to 6" Hasp and Staple No 1
¾" wood Screws Gross 1/18
Carpenters No 1/50

18 Tower Bolts Japanned Plate With Bright


Sheet 6" to 9" Fixed Complete With
Screws
( Each )
6" to 9" Tower Bolt No 1
¾" wood Screws Gross 1/18
Carpenters No 1/25

19 Hook And Eye 6" Fixed Complete


( Each )
6" Hook And Eye No 1
Carpenters No 1/50

20 Provide 2" x ¼" W.I Hold Fast 12" Over All


Length And Fixed to Chowkets With
Bolts And Nuts And Washers Complete
And Including Coal Tarring 2 Coats
( Each )
M.S Flat Iron 2" x ¼" x 12" Lb 1.7
Carriage to Site L.S …
3/8" Dia. 3" Long Bolts And Nuts Lb 0.167
Coal Tarring 2 Coats Sft 3/8
Smith No 1/50
Carpenters No 1/50
Workers No 1/50
pg-70

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XVII. ROAD WORK
1 Earthwork in Excavation in Ordinary Soil
Either in Embankment or in Cutting With
an Initial Lead of 100 Feet And
Lift of 5 Feet
( For 1000 Cft )
Mastery No 1/2
Digger No 7 Tasks= 140 cft for
Workers For Carrying No 7 1 digger
Sundries L.S …

2 Earthwork in Excavation in Soft Lateritic


Gravelling or Kanker Soil Either in
Embankment or in Cutting With an Initial
Lead of 100 Feet And Lift of 5 Feet
( For 1000 Cft )
Mastery No 1/2
Digger No 10 Tasks= 100 cft for
Workers For Carrying No 7 1 digger
Sundries L.S …

3 Earthwork in Excavation in Average


Lateritic Gravelling or Kanker Soil Either
in Embankment or in Cutting With an
Initial Lead of 100 Feet And Lift
of 5 Feet
( For 1000 Cft )
Mastery No 5/8
Digger No 14
Workers For Carrying No 8
Sundries L.S …

4 Earthwork in Excavation in Hard Lateritic


Gravelling or Kanker Soil Either in
Embankment or in Cutting With an Initial
Lead of 100 Feet And Lift of 5 Feet
( For 1000 Cft )
Mastery No 3/4
Digger No 21
Workers For Carrying No 10
Sundries L.S …

5 Excavation in Soft Rock Including Carriage


of Stone For 50 Feet
( For 100 Cft )
Miner No 1
Workers For Carrying No 4 1/2
Smith No 1/4
Bellow Boy No 1/4
Sundries L.S …
pg-71

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
6 Excavation in Hard Rock By Blasting
Including Removing Stones
( For 100 Cft )
Blasting Powder Lb 3
Charcoal Lb 10
Miner No 5
Workers No 5 1/2
Blacksmith No 1/4
Bellow Boy No 1/2
Hammer Man No 1/2
Sundries L.S …

7 Collection of Soling Stones (Local) At The


Quarry Site
( For 100 Cft )
Hammer Man No 1
Workers (Collection And Stacking) No 5
Sundries L.S …

8 Collection of Soling Stones (Kanker) At


The Quarry Site
( For 100 Cft )
Hammer Man No 1
Workers (Collection And Stacking) No 4
Sundries L.S …

9 Collection of Soling Stones (Laterite


Boulders) At The Quarry Site
( For 100 Cft )
Hammer Man No 1
Workers No 4
Sundries L.S …

10 Breaking Metal from Boulders (1½" to 2")


At The Quarry Site
( For 100 Cft )
Hammer Man No 1
Workers For Getting Out Boulder No 2 Male Workers
Workers For Breaking No 7
Sundries L.S …

11 Collection And Conversion of Blasted


Debris to 6" to 9" Soling Stones At
The Quarry Site
( For 100 Cft )
Labour
Hammer Man Man day 1
Workers Man day 2
Sundries L.S …
pg-72

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
12 Collection And Conversion of Blasted
Debris to Metal At The Quarry Site
( For 100 Cft )
Labour
Hammer Man Man day 1 1/2
Workers Man day 3
Sundries L.S …

13 Breaking Metal (2" - 4") from Boulders At


The Quarry Site Including Boxing
( For 100 Cft )
Labour
Hammer Man Man day 2
Workers For Boxing Man day 1
Sundries L.S …

14 Breaking And Boxing 1½" to 2" From 2" to


4" Metal At The Quarry Site
( For 100 Cft )
Labour
Workers For Breaking And Boxing Man day 2
Sundries L.S …

15 Breaking And Boxing ¼" to ¾" Chippings


From 1½" to 2" Metal At The Quarry Site
( For 100 Cft )
Labour
Workers For Breaking And Boxing Man day 15
Sundries L.S …

16 Breaking ¼" to ¾" Chippings From 2" to


4"Metal At The Quarry Site
( For 100 Cft )
Labour
Workers For Breaking And Boxing Man day 17
Sundries L.S …

17 Collection of Kanker or Laterite Gravel At


The Quarry Site
( For 100 Cft )
Labour
Workers For Digging , Boxing, Etc. Man day 3
Sundries L.S …

18 Collection of Hall Gravel At The Quarry


Site (Screened)
( For 100 Cft )
Labour
Workers For Digging , Boxing, Etc. Man day 4
Sundries L.S …
pg-73

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
19 Extraction of 1½" to 2" Stone Metal
Including Blasting And Breaking to Size
At The Quarry Site
( For 100 Cft )
Blasting Powder Lb 3
Charcoal Lb 10
Miner No 5
Blacksmith No 1/4
Bellows Boy No 1/4
Hammer Man No 1
Workers For Breaking And Stacking No 8

20 Laterite Metal 2½" Gauge At Quarry Site


( For 100 Cft )
Workers For Quarrying No 2
Hammer Man No 1
Workers For Breaking And Stacking No 5

21 Extraction of ¾" to 1" Gauge Stone Metal


Including Blasting And Breaking to Size
At The Quarry Site
( For 100 Cft )
Blasting Powder Lb 3
Charcoal Lb 10
Miner No 5
Blacksmith No 1/4
Bellows Boy No 1/4
Hammer Man No 1
Workers For Breaking And Stacking No 11

22 Extraction of Stone Chipping ¼" to ¾"


Gauge Including Blasting And Breaking
to Size At The Quarry Site
( For 100 Cft )
Blasting Powder Lb 3
Charcoal Lb 10
Miner No 5
Blacksmith No 1/4
Bellows Boy No 1/4
Hammer Man No 1
Workers For Breaking And Stacking No 16

23 Collection of Boulders From River Bed For


Soling Within 2 Furlongs
( For 100 Cft )
Workers For Collection And Stacking No 6

24 Breaking Metal 1½" to 2" Gauge River


Shingles Within 2 Furlongs
( For 100 Cft )
Workers For Collection No 3
Workers For Breaking And Stacking, Etc. No 4
Sundries L.S …
pg-74

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
25 Collection of River Shingles Chippings
(½" to ¾") Within 2 Furlongs Lead
( For 100 Cft )
Workers For Collection No 4
Workers For Breaking And Stacking, Etc. No 6
Sundries L.S …

26 Breaking Brick into 1½" to 2"Aggregate


( For 100 Cft )
Jama Bricks No 1000
Workers For Breaking And Stacking, Etc. No 5
Sundries L.S …

27 Collection of Sand Within One Mile Lead


( For 100 Cft )
Bullock Cart With Driver No 1
Workers For Loading And Unloading No 2
Sundries L.S …

28 Collection of Gravel Within One Mile Lead


( For 100 Cft )
Bullock Cart With Driver No 1
Workers For Digging, Carrying, Loading
No 4
And Unloading
Sundries L.S …

29 Working Expenses For a Steam Roller Per Wood Fuel


Day Required For a
Lubricating Oil, Cotton Waste, Kerosene, Steam Roller for
Soap, Asbestos Pacing, Etc. L.S … 1 Day work is 1/6
Fire Wood Cft 36 Fathom or 36 Cft
Driver No 1 =10 Cwt.or 1120
Fireman No 1 lb. If Coal is used
Night Durwan No 1 5 Cwt. Or 560 Lb.
Cart for Carrying Fuel And Water No 2 is Necessary.
Repairs to Chain And Roller L.S …
Washing out Boiler And Cleaning Engine L.S …
Sundries L.S …

30 Working Expenses For a Motor Roller Per


Day.
Petrol Gal 1/6
Kerosene Oil Gal 6
Lubricating Oil, Cotton Waste L.S …
Engine Driver No 1
Cleaning And Rest L.S …
Night Durwan No 1
Water Cart No 1
Sundries L.S …
pg-75

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
31 Consolidation of 6" Soling By Steam Roller
After Hand Packing.
( For 1000 Cft )
Steam Roller Charges Day 1
Mastery No 1
Workers No 21
Sundries L.S …

32 Consolidation of Stone Metal With Steam


Including Sand Blinding (4½" Coat)
( For 1000 Cft )
Steam Roller Charges Day 1
Sand For Blinding Cft 133
Mastery No 1
Workers No 14
Sundries L.S …

33 Scarifying Old Metal 2" Deep, 12' Wide,


Screening, Respreading And Rolling with
Roller Including Sand Blinding
( For 3300 Cft )
Steam Roller Charges Day 1
Sand For Blinding Cft 137
Mastery No 1
Workers No 19
Sundries L.S …

34 2" Thick Hot Bitumen Grouting Blinded


With ¼" to ½" Stone Chippings
(For 1 Mile x 12' = 63360 Sft)
Bitumen at 100 Lb per % Sft Ton 32* N.B.1. A Roller
Railway Freight on Above Ton 32 Can Deal With
Carriage to Site Ton 32 4000 Sft/Day.
½" to ¾" Chipping Cft 4000 2. One Ton of
Wood Fuel Cft 922 Coal or 2 Tons of .
Labour for Brushing Old Surface, Spraying, 380 Fire Wood Reqd
No
Spreading, Etc. to Heat up 5 Tons
Rolling Charges Steam Roller Day 16 or 1000 Gal. of
Hire for Boiler Sprayer, Etc. Day 12 Bitumen
Wire And Bristle Brushes L.S … 3. One Fathom of
Miscellaneous Camber Board L.S … Fire Wood Weight
3 Tons.
*Normal Wastage
3% + Leakage 10%

35 Hot Bitumen Surface Dressing (1st Coat)


Blinded With ¼" to ½" Stone Chippings
(For 1 Mile x 12' = 63360 Sft)
Bitumen at 40 Lb per % Sft Ton 12.79 13% Wastage
Railway Freight on Above Ton 12.79
Carriage to Site Ton 12.79
½" to ¾" Chipping Cft 4000
Wood Fuel Cft 369
pg-76

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Labour for Brushing Old Surface, Spraying,
Spreading, Etc. No 380
Rolling Charges Steam Roller Day 16
Hire for Boiler Sprayer, Etc. Day 12
Wire And Bristle Brushes L.S …
Miscellaneous Camber Board, Etc. L.S …

36 Hot Bitumen Surface Dressing (2nd Coat)


Blinded With ¼" to ½" Stone Chippings
(For 1 Mile x 12' = 63360 Sft)
Bitumen at 25 Lb per % Sft Ton 8 13% Wastage
Railway Freight on Above Ton 8
Carriage to Site Ton 8
Grit ¼" to ½" Cft 2650
Wood Fuel Cft 230
Labour for Brushing Old Surface, Spraying,
Spreading, Etc. No 320
Rolling Charges Steam Roller Day 16
Hire for Boiler Sprayer, Etc. Day 12
Wire And Bristle Brushes L.S …
Miscellaneous Camber Board, Etc. L.S …

37 1" (Consolidated Thickness) Premix Carpet.


(For 1 Mile x 12' = 63360 Sft)
Labour for Brushing Road Surface No 330
Printing Coat
Bitumen at 20 Lb per % Sft Ton 6.40 13% Wastage
Main Carpet
½" to ¾" Stone 3400 Cft Cft 5100
3/8" to ½" Stone 1700 Cft
Bitumen at 4 Lb per Cft Ton 10.29 13% Wastage
Sand At 5% of Stone Cft 255.00
Bitumen at 4 Lb per Cft Ton 0.03 13% Wastage
Wearing Course
¼" to ½" Chips At 3 Cft Per 100 Sft Cft 1900
1/8" to ¼ Chips
Bitumen at 35 Lb per %Sft Ton 11.19 13% Wastage
Sand For Final Coat At 2 Cft Per %Sft Cft 1300
Railway Freight For Bitumen Ton 27.91
Carriage to Site Ton 27.91
Wood Fire Cft 804
Labour for Spreading, Spraying, , Etc. No 500
Road Roller Charges M Coat Day 16
Road Roller Charges W Coat Day 4
Hire for Boiler, Etc. Day 16
Wire And Bristle Brushes L.S …
Miscellaneous, Tools & Plant, Camber Board, L.S …
pg-77

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
38 2" (Consolidated Thickness) Premix Carpet.
(For 1 Mile x 12' = 63360 Sft)
Labour for Brushing Road Surface No 300
Main Coat
1" to 1¼" Stone 7670 Cft Cft 11500
¼" to ¾" Stone 3830 Cft
Bitumen at 3 Lb per Cft Ton 20.31 13% Wastage
Sand At 5% of Stone Cft 575
Bitumen For Sand at .25 Lb per Cft Ton 0.07 13% Wastage
Topping Course
¼" to ½" Chipping At 5 Cft Per 100 Sft Cft 3200
Bitumen at 4 Lb per Cft Ton 6.45
Wearing Course
¼" to ½" Chipping At 4.5 Cft Per 100 Sft Cft 2900
1/8" to ¼ Chipping
Bitumen at 25 Lb per %Sft Ton 8.00 13% Wastage
Sand For Final Coat At 3 Cft Per %Sft Cft 1300
Railway Freight For Bitumen Ton 34.83
Carriage to Site Ton 34.83
Wood Fuel Cft 1066
Labour for Spreading, Spraying, , Etc. No 1000
Road Roller Charges M Coat Day 25
Road Roller Charges Topping Course Day 4
Road Roller Charges W Coat Day 25
Wire And Bristle Brushes L.S …
Miscellaneous, Tools & Plant, Camber
Board, Etc. L.S …

39 Liquid Seal Coat


(For 1 Mile x 12' = 63360 Sft)
Bitumen For Liquid Seal Coat at ¼ Lb per Ton 9.25 13% Wastage
Sq. Yard At 215 Gallons a Ton. 1760
Gallons And Wastage
Freight on Bitumen Ton 9.25
Carriage on Bitumen Ton 9.25
Wood Fuel For Heating Bitumen Cft 267
Labour For Spraying No 90
3/8" Grit or Coarse Sand For Blinding Cft 1800
Labour For Spreading Sand No 40
Steam Road Roller Charges Day 10
Hire For Boiler For Heating Bitumen Day 6
Incidental Charges Such As Brushers,
Pouring Can, Oil, Etc. L.S …
pg-78

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XVIII. ROAD WORK (BY MACHINE)
1 Earthwork in Excavation By Machine For
100 Ft. Average Haul in Ordinary Soil For
Level Excavation For 10000 Cft
Labour (A) For 1:10
Workers For Teak Cleaning, Etc. Man 1 Upgrade
Operator No 1 1/3 Dozing Allow
Fitter No 2/3 25% Increase
Machine Over Level
Bull Dozer ( D 8 ) Hour 5 1/3 Excavation
POLL For Operation (B) For 1:10
H.S.D Gal 20 Downgrade
Engine Oil Gal 1/3 Dozing Allow
Gear Oil Gal 1/3 25% Deduction
Hydraulic Oil Gal 2/3 Over Level
Grease Lb 1/3 Excavation
Sundries L.S …

2 Blasting Hard Rocks Including Removing


Debris For 100 Cft At Quarry Site
(Drilling By Manual Labour)
Labour
Miner Man day 1/10
Driller Man day 1/2
Drill Helper Man day 1/2
Worker Man day 1
Tools
Hand Drill Hour 8 Life- 60 Rft
Drill Bit (10' Boring) Hour 1 x 1/6 Life- 120 Days
Hammer (14 Lb) Hour 1 x 1/120
For Operation
Explosives Lb 1 1/2
Safety fuse Ft 10
Detonator No 2
Sundries L.S …

3 Blasting Hard Rocks Including Removing


Debris For 100 Cft At Quarry Site
Pneumatic Drill
Labour
Operator For Air Compressor Man day 1/7
Miner Man day 1/10
Driller Man day 1/7
Helper Man day 1/7
Worker For Removing Debris Man day 1
For Operation
Explosives Lb 1 1/2
Safety fuse Ft 10
H.S.D Gal 1
Engine Oil Gal 1/2
Detonator No 2
pg-79

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Tools And Machine
Air Compressor Hour 8 Life- 200' Boring
Pneumatic Drill Hour 8
Drill Bit (10' Boring) Hour 1 x 1/20
Sundries L.S …

4 Crushing of 500 Cft of Boulders to


Different Size of Road Metals By Stone
Crusher
Labour
Head Worker Man day 1
Worker Man day 14
Operator Man day 1
Night Durwan Man day 1
Materials
6" to 9" Boulders Cft 500
Machine
Stone Crusher (600 Cft. Capacity) Hour 8
For Operation
H.S.D Gal 3
Engine Oil Gal 1/4
Grease Lb 1/8
Rosin Lb 1/4
Sundries L.S …
Note
Different Size of Out Turned Road
Metals Depends on The Size And
Adjustment of Crushing Jaws

5 Conversion of 4" to 6" Boulder By 450 Cft


Capacity Granulator Per Day.
Labour Metal Converted
Operator Man day 1 2 5/8" = 60 Cft
Workers Man day 20 1 1/2" = 80 Cft
Materials Used Chips = 410 Cft
4" to 6" Boulders Cft 450 Total = 550 Cft
For Operation of Machine
H.S.D Gal 4
Engine Oil Gal 1/8
Grease Lb 3/4
Machine
Granulator No 1
Sundries L.S …

6 Collection of Sand Within 1 Mile Lead


( For 1000 Cft )
Labour
Workers for Loading And Unloading Man day 8
Machine
Tipper Hour 8
Sundries L.S …
pg-80

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
7 Consolidation of Sand 4" Thick By Diesel
Roller
( For 2500 Cft )
Labour
Head Worker Man day 1 Whenever Roller
Worker Man day 25 is Required Over
Roller Driver Man day 1 Night One Night
Material Durwan Per
Sand Cft 2500 Night is Allowed
Machine in the Consolida-
Roller Hour 8 tion Item
P.O.L for Operation
H.S.D Gal 6
Engine Oil Gal 1/4
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …

8 Laying And Hand Packing of Soling Stones


6"~9" And Consolidated By Road Roller
( For 1000 Cft )
Labour
Head Worker Man day 1 Whenever Roller
Worker Man day 20 is Required Over
Roller Driver Man day 1 Night One Night
Material Durwan Per
6" To 9" Soling Stones Cft 1000 Night is Allowed
Machine in the Consolida-
Roller Hour 6 tion Item
P.O.L for Operation
H.S.D Gal 4 1/2
Engine Oil Gal 3/16
Gear Oil Gal 1/8
Grease Lb 1/2
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …
Hammer Man Man day 2
Workers For Boxing Man day 1
Sundries L.S …

9 Laying of 2" to 4" Stone Metals For 4"


Uncompacted Thickness And
Consolidated By Road Roller Laying of
2" to 4" Stone Metals For 4"
Uncompacted Thickness And
Consolidated By Road Roller
( For 1000 Cft )
Labour
Head Worker Man day 1
Worker Man day 14
Roller Driver Man day 1
pg-81

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Material
2" To 4" Metals Cft 1000
Machine
Roller Hour 8
P.O.L for Operation
H.S.D Gal 6
Engine Oil Gal 1/4
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …

10 Laying of 1½"" to 2" Metals For 4½"


Uncompacted Thickness And
Consolidated By Road Roller
( For 1000 Cft )
Labour Whenever Roller
Head Worker Man day 1 is Required Over
Worker Man day 12 Night One Night
Roller Driver Man day 1 Durwan Per
Material Night is Allowed
1½" To 2" Metals Cft 1000 in the Consoli-
Machine dation Item
Roller Hour 8
P.O.L for Operation
H.S.D Gal 6
Engine Oil Gal 1/4
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …

11 Laying of Kanker or Lateriate For 6"


Uncompacted Thickness And
Consolidated By Road Roller
( For 1000 Cft )
Labour Whenever Roller
Head Worker Man day 1 is Required Over
Worker Man day 10 Night One Night
Roller Driver Man day 1 Durwan Per
Material Night is Allowed
Kanker Cft 1000 in the Consoli-
Machine dation Item
Roller Hour 8
P.O.L for Operation
H.S.D Gal 6
Engine Oil Gal 1/4
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …
pg-82

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
12 Working Expenses Of Diesel Roller Per
Day
Labour Employment of
Roller Driver Man day 1 mechanics, etc.
Night Durwan Man day 1 For Maintenance
Material And Tools of Mechanical
Water Cart No. of Day 1 Equipments To
For Operation Be Included In
H.S.D Gal 6 The Main
Engine Oil Gal 1/4 Estimate
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …

13 Working Expenses Of Diesel Tipper Per


Day
Labour
Driver Man day 1
For Operation
H.S.D Gal 8
Engine Oil Gal 1/4
Gear Oil Gal 1/8
Grease Lb 1/10

14 Working Expenses Of Petrol Tipper Per


Day
Labour Employment of
Driver Man day 1 mechanics, etc.
For Operation For maintenance
H.S.D Gal 10 of mechanical
Engine Oil Gal 1/4 equipments to
Gear Oil Gal 1/8 be included in
Grease Lb 1/10 the main estimate

15 Working Expenses Of Diesel Water


Bowzer Per Day
Labour Employment of
Driver Man day 1 mechanics, etc.
For Operation For maintenance
H.S.D Gal 8 of mechanical
Engine Oil Gal 1/4 equipments to
Gear Oil Gal 1/8 be included in
Grease Lb 1/10 the main estimate
Sundries L.S …

16 Working Expenses Of Petrol Water


Bowzer Per Day (Russian)
Labour Employment of
Driver Man day 1 mechanics, etc.
For Operation For maintenance
Petrol Gal 12 of mechanical
Engine Oil Gal 1/2 equipments to
Gear Oil Gal 1/2 be included in
Grease Lb 1 the main estimate
pg-83

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
17 Hot Bitumen 1½" Depth Grouting (Semi
Grout) Over Stone Metal Surface With
¼" to ¾" Chippings
( For 1 Mile x 12' = 63360 Sft )
Labour
Head Worker Man day 15 Based on 3"
Workers Man day 225 Compacted
Boiler Man day 15 Thickness
Materials
Bitumen Ton 23.96 13% Wastage
Chippings Cft 4000
Machine
Roller Day 15 Whenever Roller
Bitumen Heater Day 8 x 1½ is Required Over
Thermometer Day 8x1 Night One Night
Cotton Waste For Cleaning, Etc. L.S … Durwan Per
For Operation Night is Allowed
Fire Wood Ton 8.50 in the Consolida-
H.S D Gal 6 tion Work
Engine Oil Gal 1/4
Gear Oil Gal 15 x 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …

18 Hot Bitumen 1" Depth Grouting Over Stone


Metal Surface With ¼" to ¾" Chippings
For 1 Mile x 12' = 63360 Sft (Semi Grout)
Labour
Head Worker Man day 15 Based on 3"
Workers Man day 225 Compacted
Boiler Man day 15 Thickness
Materials
Bitumen Ton 15.82 13% Wastage
Chippings Cft 4000
Machine Whenever Roller
Roller Day 15 is Required Over
Bitumen Heater Day 8 x 1½ Night One Night
Thermometer Day 8x1 Durwan Per
Night is Allowed
For Operation in the Consolida-
Fire Wood Ton 6.40 tion Work
H.S D Gal 6
Engine Oil Gal 1/4
Gear Oil Gal 15 x 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …

19 Hot Bitumen Surface Dressing Over Stone


Metal Surface With ¼" to ¾" Chippings
For 1 Mile x 12' = 63360 Sft
Labour
Head Worker Man day 15.00
pg-84

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Workers Man day 200
Roller Driver Man day 15
Materials
Bitumen At 40 Lb Per % Sft Ton 13 13% Wastage
Chippings Cft 3600
Machine Whenever Roller
Roller Day 15 is Required Over
Bitumen Heater Day 8 x 1½ Night One Night
Thermometer Day 8x1 Durwan Per
For Operation Night is Allowed
Fire Wood Ton 5.12 in the Consolida-
H.S D Gal 6 tion Work
Engine Oil 1/4
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …

20 Hot Bitumen Surface Dressing Over Stone


Metal Surface With ¼" to ¾" Chippings
For 1 Mile x 12' = 63360 Sft (2nd Coat)
Labour
Head Worker Man day 15
Workers Man day 200
Roller Driver Man day 15
Materials
Bitumen At 25 Lb Per % Sft Ton 8 13% Wastage
Chippings Cft 3600
Machine
Roller Day 15 Whenever Roller
Bitumen Heater Day 8 x 1½ is Required Over
Thermometer Day 8x1 Night One Night
Durwan Per
For Operation Night is Allowed
Fire Wood Ton 3.20 in the Consolida-
H.S D Gal 6 tion Work
Engine Oil 15 x 1/4
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …

21 Hot Bitumen Seal Coat With Chippings 1/8"


To ½".
For 1 Mile x 12' = 63360 Sft
Labour
Head Worker Man day 12
Workers For Bitumen Heating, Spraying,
Stone Spreading, Etc. Man day 180
Roller Driver Man day 12
Materials
Bitumen Ton 8 13% Wastage
Chippings Cft 2800
pg-85

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Machine And Tools
Roller Day 12 Whenever Roller
Bitumen Heater Day 8 x 1½ is Required Over
Thermometer Day 8x1 Night One Night
For Operation Durwan Per
Fire Wood Ton 3.20 Night is Allowed
H.S D Gal 6 in the Consolida-
Engine Oil 12 x 1/4 tion Work
Gear Oil Gal 1/8
Grease Lb 3/4
Cotton Waste For Cleaning, Etc. L.S …
Sundries L.S …

22 Hot Bitumen Prime Coat Or Tack Coat


With Coarse Sands
For 1 Mile x 12' = 63360 Sft
Labour
Head Worker Man day 12
Workers Man day 80
Materials
Bitumen Ton 6.40 13% Wastage
Sand Cft 1800
Machines And Tools
Bitumen Heater Day 8x1
Thermometer Day 8x1
For Operation
Fire Wood Ton 2.60
Sundries L.S …

23 Laying of 1½" Thick (Consolidated) Premix


Carpet Including Priming Coat
(For 660' x 12' = 7920 Sft)
Labour Whenever Roller
Head Worker Man day 3 is Required Over
Workers Man day 54 Night One Night
Operator For Mixer Man day 3 Durwan Per
Roller Driver Man day 1 Night is Allowed
Tipper Driver Man day 1 in the Consolida-
Materials tion Work
Bitumen 80/100 Ton 2.83 13% Wastage
H.S.D Gal 25
Chippings ½" to ¾" Cft 1000
Machine
4 Cft Capacity Mixer (Miller) 24Hours 3 No
Roller 8 Hour 1 No
350 Gal Bitumen Heater 8 Hour 3 No
Tipper 8 Hour 1 No
Sundries L.S …
pg-86

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
24 Laying Only of Hot Mix Asphalts Concrete
of 1½" Thickness.
( For 1200 Cft )
Labour Whenever Roller
Time Keeper Man day 2 is Required Over
Foreman Man day 2 Night One Night
Traxcavator Operator Man day 2 Durwan Per
Paver Operator Man day 2 Night is Allowed
Mixer Operator Man day 3 in the Consolida-
Air Compressor Operator Man day 1 tion Work
Head Workers 13% Wastage
For Paver Man day 1
For Mixer Man day 1
For General Works Man day 1
Workers
For Paver Man day 12
For Mixer Man day 14
For General Tar Boiling & Transporting Man day 11
Machine Working
Mixer (Hot) Millers 10 Ft. Capacity Day 1 Expenses To Be
Drier For Chips Day 1 Included. Cost Of
Tar Boilers 5 Nos Day 5 Material
12' Wide Barber Green Paver 1 No. Day 1 i.e. Coarse
Taden Roller 2 (6 Tons) Day 2 Aggregate, Fine
Tipper 5 Nos Day 1 Aggregate
Water Bowzer 1 No. Day 1 Fillers And
Traxcavator Grader 1 No. Day 1 Bitumen in The
Air Compressor Day 1 Varying Mixes
For Operation is To Be
H.S.D For Machines Gal 200 Included In The
Engine Oil Gal 4 Main Estimate.
Grease Lb 4
Sundries L.S …

25 Scarifying Old Metal 2" Deep 12' Wide


Including Screening, Respreading, and
Rolling With a Road Roller For 1 Furlong.
Labour
Head Workers Man day 3
Workers Man day 30
Working Expenses of Roller Day 3
Sundries L.S …

26 Dressing Of Subgrade To Required Camber


By Manual Labour For Laying Of Soling
Stones (12' x 660') = 7920 Sft.
Labour
Head Workers Man day 3
Workers Man day 20
Sundries L.S …
pg-87

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
XIX. BRIDGES
1 Labour For Driving 10" Diameter Timber
Piles In Ordinary Soil (With ½ Ton Drop
Hammer From Pulley Winch And Local
Trestle And Manually Operated)
Penetration Average 20 Feet.
Labour Cost of timber
Foreman Man day 1/4 piles according
Carpenter (1st Grade) Man day 1/2 to varying dia.
Carpenter (2nd Grade) Man day 1/2 with all necessary
Workers Man day 3 fittings is to be
Plants Included in the
Pile Driving Frame 1 No. Hour 4 Main Estimate
Sundries L.S …

2 Labour For Driving 10" Diameter Timber


Piles In Ordinary Soil (With Pile Driving
Machine) Penetration Average 20 Feet.
Labour Cost of timber
Operator Man day 1/8 piles according
Foreman Man day 1/8 to varying dia.
Carpenter (1st Grade) Man day 1/2 with all necessary
Carpenter (2nd Grade) Man day 1/2 fittings is to be
Workers Man day 3 Included in the
For Operation Main Estimate
H.S.D Lb 2/3
Grease Ft 1/12
Plants
Pile Driving Frame 1 No. Hour 2/3
Sundries L.S …

3 Labour For Pile Driving Reinforced Cement


Concrete Pile 14" x 14" x 40" In Ordinary
Soil (With 40' Diesel Hammer).
Penetration Average 40'.
Labour
Foreman Man day 1/4
Pile Driving Machine Operator Man day 1/4
Pile Driving Machine Asst. Man day 1/4
Crane Operator Man day 1/4
Workers Man day 6
Tools Required
40' Rail Line Trollies For Transport Of Cost of R.C piles
Precast Pile … … … ... ... to be calculated
One Crane For Loading, Unloading, according to the
Erecting And Pitching of Precast Pile Hour 2 required size and
Pile Driving Machine 1 No. Hour 2 included in the
For Operation main estimate.
H.S.D For Pile Driving Machine Lb 1
H.S.D For Crane Gal 1 1/8
Engine Oil Gal 1 1/12
Sundries L.S …
pg-88

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
4 Labour For Pile Driving Reinforced Cement
Concrete Pile 14" x 14" x 40" In Ordinary
Soil (Using Drop Hammer With Winch
Operated By Machine). Penetration
Average 40'.
Labour
Foreman Man Day 1/2
Operator Man Day 1/2
Workers Man Day 8 Cost of R.C piles
Machine to be calculated
Pile Driving Machine 1 No. Hour 4 according to the
For Operation required size and
Diesel Oil Lb 4 included in the
Grease Oil Gal 1/4 main estimate.
Sundries L.S …

5 Labour For Launching Of R.S.JS. Over


Bridge Supports ( Using Two Pulleys And
Winch From The Other Side) 5 Nos x 44'
x 24" x 7½" At 95 Lbs Per Sft.
Total 9.3 Tons
Labour
Bridge Foreman Man Day 3
Workers Man Day 45
Sundries L.S …

6 Labour For Assembling And Launching Of


Bailey Bridge 100' Span D/S
Total Weight =24.9 Tons
Tools Required
Bailey Rollers = 0 No.
Bailey Jacks = 2 Nos
Jumpers 6 Nos
Sleepers or Bailey Clips 12 Nos.
One Hummer
Labour
Bridge Foreman Man Day 8
Workers Man Day 80
Sundries L.S …
7 Labour For Assembling of C.H. Bridge
(18' Road Way) on Scaffolding And
Fixing Bolts And Nuts For All Steel
Works Complete 60' Span Single Depth.
Total Weight =23.45 Tons
Tools Required
Tool Kit 1 No
One Hummer
Coil Rope 1"ø 200 Rft
25 Ton Jacks 2 Nos.
Labour
Bridge Foreman Man Day 10
Workers Man Day 80
Sundries L.S …
pg-89

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
8 Labour For Assembling And Launching of
C.H Bridge (22' Road Way)
Bolts And Nuts For All Steel Works
Complete 160' Span Double Depth.
Total Weight = 150 Tons
Labour
Bridge Foreman Man Day 45
Skilled Workers Man Day 315
Unskilled Workers Man Day 2385
Tools Required
Tool Kit 1 No.
One Hummer
Coil Rope 1"ø 200'
4 Ton Hand Winch 2 Nos
Bailey Roller 6 Nos
Jumper 10 Nos.
Wire Rope 5/8" ø = 750'
One Local Jip
Double Pulley 2 Nos
Single Pulley 1 No.
50 Ton Jack 2 Nos.
Sundries L.S …

9 Labour For Assembling of German Bridge


(11' Road Way) On Scaffoldings And
Lowering Down on Supports or
Launching 60' Span.
Total Weight = 17.87 Tons
Labour
Bridge Foreman Man Day 8
Workers Man Day 80
Tools Required
Bailey Jacks 2 No.
Bailey Roller 6 Nos
One Spanner
One Hummer
Sundries L.S …

10 Labour For Assembling of R.P.T. Bridge


On Scaffolds Including Riveting And
Lowering Down on Supports Complete
100' Span and 16' Road Way
Total Weight = 64.2 Tons
Labour
Bridge Foreman Man Day 36
Skilled Workers Man Day 126
Unskilled Workers Man Day 414
Tools Required
4 Ton Hand Winch
Wire Rope ½"ø = 1500'
Wire Rope 5/8"ø = 750'
Coil Rope 1"ø = 500'
Service Bolts
Double Pulley 2 Nos
pg-90

Standard Data for Working Out Rates Per Unit Quantity of Items of Work
Sr.
Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
No.
Single Pulley 1 No
One Bellow
Two Dollys
Two Riveting Gun
One Compressor with two Nos, Hose Pipes 500'
Local Jip One No.
One Hammer
75 Tons Jacks 2 Nos.
Sundries L.S …

11 Labour For Assembling And Launching of


R.P.T. Bridge After Riveting Complete
For All Steel Works 100' Span and
16' Road Way
Total Weight = 64.2 Tons
Labour
Bridge Foreman Man Day 41
Skilled Workers Man Day 138
Unskilled Workers Man Day 447
Tools Required
4 Ton Hand Winch
Wire Rope ½"ø = 1500'
Wire Rope 5/8"ø = 750'
Coil Rope 1"ø = 500'
Service Bolts
Double Pulley 2 Nos
Single Pulley 1 No
One Bellow
Dollys 2 Nos
Riveting Gun 2 Nos
One Compressor with two Nos, Hose Pipes 500'
Local Jip One No.
One Hammer
Bailey Rollers 6 Nos.
Jumpers 10 Nos
75 Tons Jacks 2 Nos.
Sundries L.S …
pg-[91]

Standard Data For Working Out Rates Per Unit Quantity Of Items Of Work
Sr. No Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
MISCELLANEOUS NOTES
Allowing Wastage of Building Materials
1 The Quantities of Material Given Allow For
Ordinary Breakages, Wastage, Carriage,
Etc., Viz.
(a) Scantling ( All timber ) 10%
(b) Small Timber 2" x 2" cross section and below 15%
(c) and for doors and windows 15%
(d) X.P.M Wire Netting 10%
(e) Glass 50%
(f) Roofing Tiles
(i) Mangalore Pattern 20%
(ii) Cement Roof Tiles 10%
(iii) Asbastos Cement Sheets 10%
(g) Floor Tiles 5%
Marble Slabs 7%
(h) Plywood 15%
(i) Steel Rods 5%

Task for an Average Artisan Per (8 hrs.) Day


1 Ballast
(a) Breaking brick ballast 1½" gauge 20 Cft per day
(b) Breaking brick ballast 1" gauge 15 Cft per day
(c) Breaking stone ballast 1½" gauge 12 ½ Cft per day
(d) Breaking stone ballast 1" gauge 10 Cft per day

2 Brick Work
(a) Brick work in lime mortar up to plinth 25 Cft per day
(b) Brick work in superstructure 25 Cft per day
(c) Brick work in arches in buildings 20 Cft per day
(d) Brick work in bridges 20 Cft per day
(e) Brick on edge in lime mortar 50 Cft per day

3 Stone Work
(a) Coursed rubble masonary (dressing) 20 Cft Each
pg-[92]

Standard Data For Working Out Rates Per Unit Quantity Of Items Of Work
Sr. No Particulars of Materials and Labour Unit Quantity Rate Per Amount Remarks
(b) Coursed rubble masonary laying 25 Cft Each
(c) Random rubble stone masonary (dressing & laying) 25 Cft Each
(d) Random rubble stonedry as in retaining walls 50 Cft Each
(e) Coursed stone arched work

4 Wood Work
(a) Sawing hard wood ( Pyingado or Engin ) 40 Sft ( one pair of sawyers)
(b) Sawing soft wood 60 Sft ( one pair of sawyers)
(c) Chawkets Hard Wood 1 Cft Each
(d) Chawkets Soft Wood 1½ Cft Each
(e) Door battened and planed (teak) 6 Sft Each
(f) Door battened and planed (Engin) 6 Sft Each
(g) Door panelled and glazed (teak) 5 Sft Each
(h) Door panelled and glazed (other timber) 6 Sft Each
(i) Window fulley glazed (teak) 4 Sft Each

5 Roofing
(a) Mangalore tiles 50 Sft Each
(b) C.I Sheets 70 Sft Each
(c) Wagat 100 Sft Each
(d) Thatch 100 Sft Each
(e) Shingle 40 Sft Each

6 Palstering and Painting


(a) Plastering ½" One Coat 100 Sft Each
(b) Plastering Fine Coat 100 Sft Each
(c) Painting 100 Sft Each
(d) White Washing One Coat 800 Sft Each
(e) Distempering One Coat 400 Sft Each
(f) Painting Doors And Windows 200 Sft Each
(g) Painting plain surfaces 400 Sft Each
(h) Painting Sheet Iron Roof 500 Sft Each
(i) Vanishing door and Windows 200 Sft Each
(j) Coal taring one coat 250 Sft Each
Pg- [93]

Weight and load various building materials


Double Lories Tipping
Lorry
Sr. No. Materials Unit Weight Bullock wagon
Tippers
Cart 15 Cwt 30 Cwt 3 Tons 27 Cft
1 Asphalt paving Ton Ton 0.6 0.6 1.25 2.5 0.7 2
2 Asphalt socony Ton Ton 0.6 0.6 1.25 2.5 0.7 2
3 Bricks 9" x 4 3/8" x 2¾" Each 7.5 Lb 200 200 425 850 250 650
4 Brick Ballast Cft 60 Lb 25 25 50 100 27 80
5 Broken stone metal Cft 110 Lb 18 15 30 60 20 50
6 Cement Ton Ton 0.75 0.75 1.5 3 0.9 2.5
7 Surkhi Cft 80 Lb 25 20 40 80 27 60
8 Exp. Metal (Av:) 8'x4' Sht 40 Lb 40 40 80 160 50 125
9 Fencing style No.949 220 yd(roll 415 Lb 4 4 8 16 5 12
10 Gravel Cft 110 Lb 20 15 30 60 23 50
11 Kanker Cft 72 Lb 25 22 45 90 27 70
12 Lime ordinary quick Cft 53 Lb 25 30 60 120 27 95
13 Ridging G.I 22G. 7' Each 22 Lb 75 75 150 300 100 240
14 Sand Cft 110 Lb 20 15 30 60 23 50
15 Sheet C.I 24G.7' 100 Sht Ton 75 75 150 300 80 240
16 Sheet zinc 22G. 8'x3' Each 25 Lbs 60 60 120 240 80 190
17 Shingles 15"x5" Each 1.25 Lb 1500 1250 2500 5000 1600 4000
18 Stone (building) Cft 110 Lb 18 18 37 75 20 60
19 Coal tar (5 gals. Drum) Each 63 Lb 25 25 50 100 30 80
20 Tiles, mangalore roofing Each 5.5 Lb 275 275 550 1100 300 900
21 Tiles, mangalore ridging Each 6 Lb 250 250 500 1000 300 800
22 Timber scantling (average) Ton Ton 0.6 0.6 1.2 2.4 … 1.9
23 Wire netting ½" mesh 50 yds 87 Lb 17 17 35 70 20 55
roll
24 Wire barbed 448 yd 112 Lb 12 12 25 50 16 40
roll
25 Wire stranded 7 ply 6 gauge 481 yds 112 Lb 12 12 25 50 16 40
26 6" thatch (covering capacity) Sft … 120 120 240 480 … 380
27 Bamboo large No. … 60 15 30 60 … 50
28 Bamboo mouli No. … 120 120 240 480 … 380
29 Bullies (average) No. … 9 9 18 36 … 30
30 Chattai (matting) Sft … 900 900 1800 3600 … 2900
31 4" pipping Rft … 120 120 240 480 … 380
Pg- [94]

MEANS OF TRANSPORT

(a) Motor Transport


One military 3 ton (chev) lorry should do the equivalent work of 100 miles daily and efficient loading will give
the folling equivalents. :-
Loading sand … 4 Miles, unlading sand … 3 Miles
Loading shingles … 6 Miles, unlading shingles … 4 Miles
Loading bricks … 12 Miles, unlading bricks … 8 Miles
Loading stones … 12 Miles, unlading stores … 8 Miles
Loading bamboos … 18 Miles, unlading bamboos … 4 Miles
e.g. Distance from shingle bed to job … say 12 miles
Distance … 24 Miles
One Trip Loading … 6 Miles
Unloading … 4 Miles
34 Miles
3 trips = 102 Miles

(b) Bullock Cart


One bullock cart load is equivalent to one quarter of the load carried by the average 3 ton (chev.) lorry.

(c) Railway Wagon


Approximate capacity of 10 ton metre gauge Railway wagon.
2,500 Nos. bricks
10 Tons coal dust
10 Tons cement
160 Nos. bullies
250 Cft. Sawn timber or logs
400 Nos. bamboo large
200 Cft. Boulders & stones ballast.
10 Tons steel.
35 Tons bitument or tar. (35 gals. Each).
Pg-[95]

Weight of flat rolled steel in lbs per linear foot

Width Thickness in inches


in
inches 1/16" 1/8" 3/16" 1/4" 3/8" 1/2" 5/8" 3/4" 7/8" 1"

1" 0.213 0.425 0.638 0.85 1.28 1.7 2.13 2.55 2.98 3.4

1½" 0.319 0.638 0.956 1.28 1.91 2.55 3.19 3.83 4.46 5.1

2" 0.425 0.85 1.28 1.4 2.55 3.4 4.25 5.1 5.95 6.8

2½" 0.531 1.06 1.59 2.13 3.19 4.25 5.31 6.38 7.44 8.5

3 0.638 1.28 1.91 2.55 3.83 5.1 6.38 7.65 8.93 10.2

3½" 0.744 1.49 2.23 2.98 4.46 5.95 7.44 8.93 10.41 11.9

4 0.85 1.7 2.55 3.4 5.1 6.8 8.5 10.2 11.9 43.6

4½" 0.956 1.91 2.87 3.83 5.74 7.65 9.56 11.48 13.39 15.3

5 1.06 2.13 3.19 4.25 6.38 8.5 10.63 12.75 14.88 17

5½" 1.17 2.34 3.51 4.68 7.01 9.35 11.69 14.03 16.36 18.7

6 1.28 2.55 3.83 5.1 7.65 10.2 12.75 15.3 17.85 20.4

6½" 1.38 2.76 4.14 5.53 8.29 11.05 13.81 16.58 19.34 22.1

7 1.49 2.98 4.46 5.95 8.93 11.9 14.88 17.85 20.83 23.8

7½" 1.59 3.19 4.78 6.38 9.56 12.75 15.94 19.12 22.31 25.5

8 1.7 3.4 5.1 6.8 10.2 13.6 17 20.4 23.8 27.2

8½" 1.81 3.61 5.42 7.25 10.84 14.45 18.06 21.68 25.29 28.9

9 1.91 3.83 5.74 7.65 11.48 15.3 19.13 22.95 26.78 30.6

9½" 2.02 4.04 6.06 8.08 12.11 16.15 20.19 24.23 28.26 32.3

10 2.13 4.25 6.38 8.5 12.75 17 21.25 25.5 29.75 34

10½" 2.23 4.46 6.7 8.93 13.39 17.85 22.31 26.75 31.24 35.7

11 2.34 4.68 7.01 9.35 14.03 18.7 23.38 28.05 32.73 37.4

11½" 2.44 4.89 7.32 9.78 14.66 19.55 24.44 29.33 34.21 39.1

12 2.55 5.1 7.65 10.2 15.3 20.4 25.5 30.6 35.7 40.8

Values of Additional Width of 1/4" and 3/4"

¼" 0.052 0.105 0.159 0.213 0.319 0.425 0.531 0.638 0.744 0.85

¾" 0.158 0.319 0.477 0.638 0.956 1.275 1.594 1.913 2.231 2.55
Pg-[96]

Weight in lbs of shenderd bolts and nuts Hexagonal head and nuts
Width Thickness in inches
in
inches 1/4" 3/8" 1/2" 5/8" 3/4" 7/8" 1" 1 1/8" 1 1/4" 1 1/2"
1" 0.042 0.106 0.222 0.376 0.612 … … … … …
1½" 0.049 0.122 0.25 0.419 0.675 0.986 1.394 … … …
2" 0.056 0.38 0.278 0.463 0.737 1.072 1.505 2.036 2.671 …
2½" 0.063 0.153 0.305 0.506 0.8 1.157 1.616 2.177 2.845 …
3 0.069 0.169 0.333 0.549 0.862 1.242 1.727 2.318 3.019 4.766
3½" 0.075 0.185 0.361 0.593 0.925 1.327 1.838 2.459 3.193 5.016
4 0.082 0.2 0.389 0.637 0.988 1.412 1.95 2.6 3.367 5.267
4½" 0.089 0.216 0.417 0.68 1.05 1.497 2.061 2.74 3.541 5.517
5 0.096 0.232 0.445 0.724 1.113 1.583 2.172 2.881 3.714 5.767
5½" 0.103 0.247 0.472 0.767 1.175 1.667 2.283 3.022 3.888 6.018
6 0.11 0.263 0.5 0.81 1.238 1.753 2.394 3.163 4.062 6.268
6½" 0.117 0.279 0.528 0.854 1.3 1.838 2.506 3.303 4.236 6.518
7 0.124 0.294 0.556 0.897 1.363 1.923 2.617 3.444 4.41 6.769
7½" 0.13 0.31 0.584 0.941 1.425 2.008 2.728 3.585 4.584 7.019
8 0.138 0.326 0.612 0.984 1.488 2.094 2.839 3.726 4.757 7.27
8½" … 0.341 0.639 1.028 1.55 2.179 2.95 3.867 4.931 4.52
9 … 0.357 0.667 1.071 1.613 2.264 3.062 4.008 4.105 7.77
9½" … … 0.695 1.115 1.676 2.349 3.173 4.149 5.279 8.021
10 … … 0.723 1.158 1.739 2.434 3.284 4.29 5.453 8.271
10½" … … … 1.202 1.801 2.519 3.396 4.43 5.627 8.521
11 … … … 1.245 1.863 2.605 3.507 4.57 5.8 8.772
11½" … … … … 1.926 2.689 3.618 4.71 5.974 9.022
12 … … … … 1.989 2.775 3.729 4.853 6.148 9.272

Weight 0.0134 … 0.0757 … 0.2164 … 0.4611 … 0.8511 …


in lbs of
1 nut … 0.0345 … 0.1394 … 0.3203 … 0.6379 … 1.391

Weight 0.0139 … 0.0557 … 0.1252 … 0.2225 … 0.3477 …


in lbs of
shank 1" … 0.0313 … 0.0869 … 0.1703 … 0.2817 … 0.5007
Weight
in lbs of 0.0035 … 0.0139 … 0.0313 … 0.0556 … 0.0869 …
shank
… 0.0078 … 0.0217 … 0.0426 … 0.0704 … 0.1252
¼"
Weight
in lbs of 0.0018 … 0.007 … 0.0157 … 0.0278 … 0.0435 …
shank
… 0.0039 … 0.0109 … 0.0213 … 0.0352 … 0.0626
1/8"
Pg-[97]

Weight of Unequal Angles


Lbs Lbs Lbs
Size of Angles Size of Angles Size of Angles
Per Rft Per Rft Per Rft
2" x 1½" x 5/16" 3.39 3½" x 2½" x 7/16" 8.28 4" x 3½" x 5/8" 14.61
2" x 1½" x ¼"" 2.76 3½" x 2½" x 3/8" 7.17 4" x 3½" x 9/16" 13.27
2" x 1½" x 3/16"" 2.11 3½" x 2½" x 5/16" 6.04 4" x 3½" x ½" 11.91
2½" x 1½" x 5/16" 3.92 3½" x 2½" x ¼" 4.89 4" x 3½" x 7/16" 10.51
2½" x 1½" x ¼"" 3.19 3½" x 3" x 9/16" 11.36 4" x 3½" x 3/8" 9.09
2½" x 1½" x 3/16"" 2.43 3½" x 3" x½" 10.2 4" x 3½" x 5/16" 7.64
2½" x 2" x 3/8" 5.26 3½" x 3" x 7/16" 9.02 5" x 3" x 9/16" 14.23
2½" x 2" x 5/16" 4.45 3½" x 3" x 3/8" 7.81 5" x 3" x ½" 12.75
2½" x 2" x ¼" 3.61 3½" x 3" x 5/16" 6.58 5" x 3" x 7/16" 11.25
2½" x 2" x 3/16" 2.75 3½" x 3" x ¼" 5.32 5" x 3" x 3/8" 9.73
3" x 2" x 3/8" 5.9 4" x 2½" x 7/16" 9.02 5" x 3" x 5/16" 8.17
3" x 2" x 5/16" 4.98 4" x 2½" x 3/8" 7.81 …
3" x 2" x ¼" 4.04 4" x 2½" x 5./16" 6.58 …
3" x 2" x 3/16" 3.07 4" x 2½" x ¼" 5.32 …
3" x 2½" x 7/16" 7.53 4" x 3" x ½" 11.05 …
3" x 2½" x 3/8" 6.54 4" x 3" x 7/16" 9.76 …
3" x 2½" x 5/16" 5.51 4" x 3" x 3/8" 8.45 …
3" x 2½" x ¼" 4.47 4" x 3" x 3/16" 7.11 …

Weight of Equal Angles


Lbs Lbs Lbs
Size of Angles Size of Angles Size of Angles
Per Rft Per Rft Per Rft
1¼" x 1¼" x ¼" 1.91 3" x 3" x 9/16" 10.4 4" x 4" x 3/4" 18.49
1¼" x 1¼" x 3/16" 1.47 3" x 3" x 1/2" 9.35 4" x 4" x 11/16" 17.1
1¼" x 1¼" x 1/8" 1.01 3" x 3" x 7/16" 8.28 4" x 4" x 5/8" 15.68
1½" x 1½" x 5/16" 2.85 3" x 3" x 3/8" 7.17 4" x 4" x 9/16" 14.23
1½" x 1½" x 1/4" 2.34 3" x 3" x 5/16" 6.04 4" x 4" x 1/2" 12.75
1½" x 1½" x 3/16" 1.79 3" x 3" x 1/4" 4.89 4" x 4" x 7/16" 11.25
2" x 2" x 3/8" 4.62 3½" x 3½" x 5/8" 13.55 4" x 4" x 3/8" 9.73
2" x 2" x 5/16" 3.92 3½" x 3½" x 9/16" 12.31 4" x 4" x 5/16" 8.17
2" x 2" x 1/4" 3.19 3½" x 3½" x 1/2" 11.05 6" x 6" x 7/8" 31.1
2" x 2" x 3/16" 2.43 3½" x 3½" x 7/16" 9.76 6" x 6" x 13/16" 30.9
2½" x 2½" x½" 7.65 3½" x 3½" x 3/8" 8.45 6" x 6" x 3/4" 28.69
2½" x 2½" x7/16" 6.79 3½" x 3½" x 5/16" 7.11 6" x 6" x 11/16" 26.44
2½" x 2½" x3/8" 5.9 3½" x 3½" x 1/4" 5.74 6" x 6" x 5/8" 24.17
2½" x 2½" x5/16" 4.98 6" x 6" x 9/16" 41.87
2½" x 2½" x1/46" 4.04 6" x 6" x 1/2" 19.55
6" x 6" x 7/16" 17.2
6" x 6" x 3/8" 14.82

Pg-[98]

Steel cup head rivets. Approximate weight in lbs of 100 Nos.


Diameters of rivets in inches
Length in inches Remarks
3/8" 1/2" 5/8" 3/4" 7/8" 1" 1½" 1 1/4"
1 4.58 9 … … … … … …
1¼ 5.37 .10.4 … … … … … …
1½ 6.15 11.8 19.7 30.4 … … … …
1¾ 6.93 13.1 21.9 33.5 … … … …
2 7.72 14.5 24.1 36.6 52.5 72 … …
2¼ 8.5 15.9 26.3 39.8 56.7 77.6 … …
2½ 9.28 17.3 28.4 42.9 61 83.1 110 141
2¾ 10.07 18.7 30.6 46 65.2 88.7 117 149
3 10.85 20.1 32.8 49.2 69.5 94.3 124 158
3¼ 11.63 21.5 35 52.3 73.8 100 131 167
3½ 12.42 22.8 37.1 55.4 78 105 138 175
3¾ 24.3 39.3 58.5 82.3 111 145 184
4 41.5 61.7 86.5 117 152 193
4¼ 43.6 64.8 90.8 122 159 202
4½ 45.8 67.9 95.1 128 166 210
4¾ 48 71.1 99 133 173 219
5 74.2 104 139 180 228
5¼ 77.3 108 144 187 236
5½ 80.4 112 150 194 245
5¾ 83.6 116 155 201 254
6 121 161 208 262
6¼ 125 167 215 271
6½ 129 172 222 280
6¾ 133 178 229 288
7 183 236 297
7¼ 189 243 306
7½ 194 250 315
7¾ 200 258 323
8 206 265 332
Approximate weight in lbs of 100
1.45 3.4 6.67 11.6 18.4 27.5 39.2 53.8
heads
Variation in weight of 100 rivets
3.13 5.56 8.69 12.5 17 221.3 28.2 34.8
per inch of length

Weight of round and square M.S rods Weight of round washer per 100 Nos
Dia. Of side in inches Round Square Dia. of round washers Weight in lbs per 100 Nos.
¼" 0.167 0.213 ½" dia. 2½
5/16" 0.261 0.478 5/8" dia. 4
3/8" 0.376 0.849 ¾" dia. 5½
½" 0.668 1.328 7/8" dia. 7½
5/8" 1.043 1.912 1" dia. 14
¾" 1.502 2.603 1 1/8" dia. 17
7/8" 2.044 3.4 1¼" dia. 21½
1" 2.67 5.312 1 3/8" dia. 26
1¼" 4.172 7.65 1½" dia. 30½
1½" 6.008 2" dia. 64
3" dia. 21.4
Pg-[99]

Weight of B.R.C Fabric

B.R.C No. Lbs per sq. yd. Lbs per sq. ft. Lbs per 100 sft

7 6.57 0.74 74
8 5.67 0.63 63
9 4.71 0.523 52.3
10 3.94 0.438 43.8
12 2.72 0.302 30.2
14 1.83 0.203 20.3

Weight of 100 ft. of wire of different materials


Gauge Iron Steel Brass Copper
S.W.G in nls in lbs in lbs in lbs
1 23.4 24 25.7 27.4
2 19.6 20.1 21.6 23.3
3 16.4 16.8 18.1 19.3
4 13.8 14.3 15.2 16.4
5 11.6 11.9 12.7 13.7
6 9.5 9.7 10.5 11.15
7 8 8.2 8.8 9.42
8 6.6 6.8 7.3 7.8
9 5.3 5.4 5.8 6.3
10 4.23 4.34 4.65 5.07
11 3.46 3.55 3.8 4.1
12 2.8 2.87 3.08 3.3
13 2.16 2.22 2.37 2.58
14 1.66 1.7 1.83 1.94
15 1.33 1.36 1.46 1.58
16 1.06 1.08 1.16 1.24
17 0.8 0.82 0.88 0.95
18 0.6 0.62 0.66 0.7
19 0.4 0.41 0.44 0.487
20 0.33 0.34 0.36 0.395
Pg-[100]

Weight of Zinc Sheet ( Plain )


Thickness Weight per sq. foot
Zinc Gauge
inches mm lbs oz. grms
5 0.01 0.291 … 5 11
6 0.011 0.297 … 6 11
7 0.013 0.337 7 12
8 0.015 0.386 8 14
9 0.018 0.45 10 5
10 0.02 0.5 11 7
11 0.023 0.53 13 5
12 0.026 0.66 15 2
13 0.029 0.74 1 0 15
14 0.032 0.82 1 2 12
15 0.038 0.95 1 5 12
16 0.043 1.08 1 8 12
17 0.048 1.21 1 11 11
18 0.058 1.34 1 14 11

Approximate number of Galvanized Corrugated Sheet per ton


Length in Feet
Thickness Corrugation
6 6½ 7 7½ 8 8½ 9 9½ 10
16 B.G. 8/3 58 54 50 47 44 41 39 37 35
16 B.G. 10/3 49 43 42 39 37 35 33 31 29
18 B.G. 8/3 74 68 64 59 56 52 49 46 44
18 B.G. 10/3 62 56 53 50 46 43 41 39 37
20 B.G. 8/3 95 88 81 76 71 67 63 60 57
20 B.G. 10/3 79 73 68 64 59 5 53 50 47
22 B.G. 8/3 116 107 99 93 87 82 77 73 69
22 B.G. 10/3 97 90 83 78 73 68 65 61 58
24 B.G. 8/3 140 130 120 112 105 98 93 88 84
24 B.G. 10/3 117 108 100 94 88 83 78 74 70
26 B.G. 8/3 186 172 159 149 139 131 124 117 111
26 B.G. 10/3 155 143 133 124 116 109 103 98 93
28 B.G. 8/3 200 185 185 161 150 141 133 126 120
28 B.G. 10/3 167 154 143 133 125 118 111 105 100
30 B.G. 8/3 240 222 206 192 180 170 160 151 144