Eco-Sanctuary Precast Drawings Production Report Summary Update date: 07/07/20

Drawings Completion Tracker


Level, Block A Total Output for
Week of Status Report L1 L2 L3 -L11 Roof the past weeks

Dec 19 Dwgs Completed Status 0 0 0 0


Output for Past Weeks 0 0 0 0 0
Dec 26 Dwgs Completed Status 0 0 0 0 Summary of Delays
Output for Past Weeks 0 0 0 0 0 MS Revised Target Actual Delays
Jan 03 Dwgs Completed Status 0 0 0 0 Level Completion Date Weeks
Output for Past Weeks 0 0 0 0 0 L1 20/02/2015 07/07/20 -281
Jan 10 Dwgs Completed Status 0 0 0 0 L2 25/03/2015 07/07/20 -276
Output for Past Weeks 0 0 0 0 0 L3-L11 10/04/2015 07/07/20 -274
Jan 17 Dwgs Completed Status 0 0 0 0 roof 27/04/2015 07/07/20 -271
Output for Past Weeks 0 0 0 0 0
Jan 24 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Jan 31 Dwgs Completed Status 0 0 0 0 `
Output for Past Weeks 0 0 0 0 0
Feb 07 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Feb 14 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Feb 21 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Feb 28 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
No of Drawings For that Floor 17 66 116 40
Total % of Drawings Completed 0% 0% 0% 0%

Precast Framing plan Tracker Block A


Status L1 L2 L3-L8 roof
Scheduled 04/02/15 28/02/15 17/03/15 02/04/15
Actual 7/7/20 7/7/20 7/7/20 7/7/20
Delay (Days) -1980 -1956 -1939 -1923
Drawings Completion Tracker
Level, Block B Total Output for
Week of Status Report L1 L2 L3 -L8 Roof the past weeks

Summary of Delays
Dec 19 Dwgs Completed Status 0 0 0 0 MS Revised Target Actual Delays
Output for Past Weeks 0 0 0 0 0 Level Completion Date Weeks
Dec 26 Dwgs Completed Status 0 0 0 0 L1 07/05/2015 07/07/20 -270
Output for Past Weeks 0 0 0 0 0 L2 03/06/2015 07/07/20 -266
Jan 03 Dwgs Completed Status 0 0 0 0 L3-L8 19/06/2015 07/07/20 -264
Output for Past Weeks 0 0 0 0 0 roof 06/07/2015 07/07/20 -261
Jan 10 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Jan 17 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Jan 24 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Jan 31 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Feb 07 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Feb 14 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Feb 21 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Feb 28 Dwgs Completed Status 0 0 0 0
Output for Past Weeks 0 0 0 0 0
No of Drawings For that Floor 0 0 0 0
Total % of Drawings Completed #DIV/0! #DIV/0! #DIV/0! #DIV/0!

Precast Framing plan Tracker Block B


Status L1 L2 L3 -L8 L14
Scheduled 06/04/15 30/04/15 16/05/15 02/06/15
Actual 7/7/20 7/7/20 7/7/20 7/7/20
Delay (Days) -1919 -1895 -1879 -1862
Eco-Sanctuary Precast Drawings Production Report Summary

Overall Drawings Completion Tracker


Level, All Blks Total Output for
Week of Status Report B L1 L2-L12 L13 the past weeks

Dec 19 Dwgs Completed Status 0 0 0 0 0


Output for Past Weeks 0 0 0 0 0
Dec 26 Dwgs Completed Status 0 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Jan 03 Dwgs Completed Status 0 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Jan 10 Dwgs Completed Status 0 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Jan 17 Dwgs Completed Status 0 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Jan 24 Dwgs Completed Status 0 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Jan 31 Dwgs Completed Status 0 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Feb 07 Dwgs Completed Status 0 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Feb 14 Dwgs Completed Status 0 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Feb 21 Dwgs Completed Status 0 0 0 0 0
Output for Past Weeks 0 0 0 0 0
Feb 28 Dwgs Completed Status 0 0 0 0 0
Output for Past Weeks 0 0 0 0 0
No of Drawings For that Floor 17 66 116 40
Total % of Drawings Completed 0% 0% 0% 0%