Professional Documents
Culture Documents
T6497 KERINCI
PG I14314 Training
Caution
The reproduction, transmission or use of this document or its We have checked the contents of this manual for agreement
contents is not permitted without express written authority. with the hardware and software described. However,
Offenders will be liable for damages. deviations cannot be precluded entirely. Therefore we cannot
All rights, including rights created by patent grant or accept any guarantee for complete agreement. The data in
registration of a utility model or design, are reserved. this manual are reviewed regularly and any necessary
corrections included in subsequent editions.
Suggestions for improvement are welcome.
Table of contents
1 General Information 5
3 Turbine plant 16
3.1 Turbine 16
PG I1434 Training
3
© Siemens AG 2007
Preventive Maintenance General Information
1
1 General Information
Introduction
The availability of the turbine plant and, hence, in particular, the operating
reliability, depends on trouble-free operation and response of the control,
protective and monitoring equipment and the associated plant items, such as
pumps, etc. The section "Maintenance" therefore contains the essential
testing, maintenance and servicing activities which guarantee and/or restore
the operating reliability of the turbine plant. In addition, the current status can
also be assessed simultaneously with regard to requisite measures
concerning inspections and overhauls, or for establishing the
inspection/overhaul date.
All lubricants and control media used in the plant must fulfill the specified
requirements for purity and inherent properties. Of particular importance is
ensuring that adequate quantities of media are available for refilling to
prevent any faults due to the operating level of the media being too low.
Test Instructions
Performing tests
PG I14314 Training
5
© Siemens AG 2007
General Information Preventive Maintenance
1
When testing control, nonautomatic extraction and isolating devices with the
turbine at standstill, it is imperative that steam vapor be prevented from
flowing into the hot turbine, as this could result in single-sided or excessively
rapid cooling of turbine items. If the corresponding steam systems are not
depressurized the movability of control and stop valves can be tested one
after the other under some circumstances.
Evaluation of tests
Maintenance instructions
PG I14314 Training
6
© Siemens AG 2007
Preventive Maintenance General Information
1
Repair instructions
The repair instructions include measures designed to restore the turbine and
plant items to their specified condition. The necessary preparations for
performing these repairs, such as design calculation, scheduling, provision
of personnel and spare parts, are not included in these instructions, but must
be coordinated with our Service Center where required. This applies in
particular to stocking of spare parts.
Inspections/Overhauls
In the course of an inspection and overhaul, the turbine plant and all
associated plant items are checked and overhauled and, where required or
meaningful, wear parts replaced.
The inspection intervals and the type and scope of the inspections to be
conducted are described in the section "Inspection and Overhaul of Steam
Turbines".
PG I14314 Training
7
© Siemens AG 2007
Maintenance and inspection instructions Preventive Maintenance
2 Structure and overview
Protective devices shut down the turbine itself or parts of its equipment as
soon as operating conditions occur which may put the turbine at risk and
which cannot be kept within the permissible limits by the limiting devices.
Limiting devices are designed and adjusted such that they act before the
corresponding protective devices and, where possible, prevent protective
devices being tripped, thereby causing an outage.
The summary below therefore lists the test intervals for important equipment
and components, and other tests that need to be carried out.
For organizational reasons this list may also include components and
equipment which do not belong in the scope of supply for a turbine plant.
Actual practice Practical experience shows that it is best to perform the test as the turbine is
being shut down, as at this point the operating conditions correspond to
those for long-term operation. In addition, faults leading to malfunctions may
be corrected in the subsequent outage period.
PG I14314 Training
8
© Siemens AG 2007
Preventive Maintenance Maintenance and inspection instructions
Test/Inspection and maintenance intervals
2
Inspection date/test
Test/Inspection data and the associated criteria
Successful completion of test/inspection
Trip value, where this can be determined
Setting value
Column 2 indicates the plant section , the item of equipment or the measurement point.
Column 4 contains information about the measuring and test parameters that are to be
maintained and information about pertinent documentation, with:
Column 5 shows the frequency with which the tests and inspections are to be carried
out, where:
h = hourly
d = daily
w = weekly
m = monthly
PG I14314 Training
9
© Siemens AG 2007
Maintenance and inspection instructions Preventive Maintenance
2 Test/Inspection and maintenance intervals
y = annually
This column also shows whether tests are necessary on start up and
shutdown or, in special cases, during scheduled inspections:
A = on startup
S = on shutdown
R = during inspections/overhauls
B = Operating personnel
W = Maintenance personnel
K = PG I
PG I14314 Training
10
© Siemens AG 2007
Preventive Maintenance Maintenance and inspection instructions
Test/Inspection and maintenance intervals
2
PG I14314 Training
11
© Siemens AG 2007
Maintenance and inspection instructions Preventive Maintenance
2 Test/Inspection and maintenance intervals
PG I14314 Training
12
© Siemens AG 2007
Preventive Maintenance Maintenance and inspection instructions
Test/Inspection and maintenance intervals
2
PG I14314 Training
13
© Siemens AG 2007
Maintenance and inspection instructions Preventive Maintenance
2 Test/Inspection and maintenance intervals
PG I14314 Training
14
© Siemens AG 2007
Preventive Maintenance Maintenance and inspection instructions
Test/Inspection and maintenance intervals
2
PG I14314 Training
15
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 Turbine
3 Turbine plant
3.1 Turbine
Work to be performed
1. Check casing expansion at the indicator provided for this purpose.
Remarks, Notes
the sliding capability of the turbine casing can still be guaranteed and
whether
the casing supports also slide on the bearing pedestal along with the
casing without canting.
During startup and shutdown and during load changes the casing must not
make sudden jumps to its new position when sliding.
The paw support washers at the paw support bolts (connection between
turbine casing and bearing pedestal) must always be easily movable; the
clearance between the head of the bolt and the washer should be around
0.1 mm.
Work to be performed
1. Check shaft seal steam and the gland vapor stack
Remarks, Notes
PG I14314 Training
16
© Siemens AG 2007
Preventive Maintenance Turbine plant
Turbine
3
Risk of burns!
Do not touch the gland vapor stack when the turbine is hot.
DANGER
If the flow of escaping steam increases while all other conditions remain the
same, this usually indicates an increase in the seal strip clearances. Thrust
balancing can also be disrupted by an increase in the clearance in the
labyrinth seals on the balance piston, hence posing a risk to the thrust
bearing.
Work to be performed
1. Check the indication.
Remarks, notes
Work to be performed
PG I14314 Training
17
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 Turbine
Remarks, Notes
The vibration meter monitors the running condition of the turbine. Changes
over time can be ascertained using recorders.
In addition, deviation from the standard values and then the magnitude of
the measured value must be taken into account when evaluating the
vibration levels.
Work to be performed
1. Check the phase angle in conjunction with shaft vibration.
Remarks, Notes
With the keyphaser as the phase marking, the phase angle is defined as the
angle from the marking in the shaft to the first, positive peak value for
vibration amplitude.
To establish the phase angle precisely, you require an instrument that filters
out only the rotational-frequency components (1 x rpm) of the vibration
signal and measures and indicates the angle between the marking and the
maximum excursion on the shaft geometry.
Introduction
PG I14314 Training
18
© Siemens AG 2007
Preventive Maintenance Turbine plant
Turbine
3
Test recommendation
Additional friction losses between the rotating parts and the stationary parts
of the turbine result in shortening of the coast-down time. For this reason,
each time the turboset is shut down and each time the shaft assembly is
brought to a standstill from turning-gear operation, the relevant coast-down
time should be measured and compared with the corresponding values
given in the following table, which apply to the new condition.
Performance of measurement
Measurement of the speed characteristic with respect to time:
PG I14314 Training
19
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 Turbine
The following table lists possible causes and the measures which should be
taken in the event of deviation of the measured coast-down time from the
coast-down time on initial commissioning.
PG I14314 Training
20
© Siemens AG 2007
Preventive Maintenance Turbine plant
Turbine
3
From rated speed to turning- Condenser pressure or condenser- Check the condenser pressure
gear speed pressure change rate on coast-down is and the condenser-pressure
higher than normal. change rate;
On renewed coast-down, match
the condenser pressure to the
reproducibility conditions.
From rated speed to turning- Temperature difference between the upper Determine the cause of the
gear speed part of the turbine housing and the lower temperature difference.
part is high => turbine housing distortion.
From rated speed to turning- Bearing temperature before shut down Determine the cause of the
gear speed extremely high => shaft displacement. high temperature.
From rated speed to turning- Bearing or shaft vibrations before shut Determine the cause of the
gear speed down were high => shaft distortion increase in vibration.
From turning-gear speed to Boundary conditions at coast-down are not Check the boundary conditions.
shaft standstill comparable, e.g. failure of the jacking oil
pump.
From turning-gear speed to The temperature difference between the Determine the cause of the
shaft standstill upper part of the turbine housing and the temperature difference.
lower part is high => turbine housing
distortion.
From rated speed to turning- Condenser pressure or condenser- Check the condenser pressure
gear speed pressure change rate on coast-down is and the condenser-pressure
lower than normal. change rate;
On renewed coast-down, match
the condenser pressure to the
reproducibility conditions.
PG I14314 Training
21
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 Turbine
From rated speed to turning- Emergency stop and control valves are Check the emergency stop and
gear speed leaking. control valves for leakage.
Standstill periods can result both in direct damage by corrosion and later
consequent faults due to corroded components. For example, damage to
blading components is possible after a standstill period of only a few days
after shutting down the turbine.
Precondition for conservation: No steam vapour or condensate may enter the turbine.
The plant should be isolated from the steam and condensate networks by
monitored check lines or blanking plates.
PG I14314 Training
22
© Siemens AG 2007
Preventive Maintenance Turbine plant
Turbine
3
We recommend that the emergency stop valve should not be inserted as the
second isolating device in the main steam line, in order to save a valve,
since otherwise it would be subjected to corrosion.
Protection measures In the case of steam turbine, there is a possibility that accumulation of water
by condensation will occur in spite of lines being closed by means of valves
or blanking plates. This is caused as a result of the daily fluctuations in
temperature in the powerhouse.
In the illustrative Figure it can be seen clearly that the temperature of the
casing and to an even greater extent that of the rotor are often lower than
that of the room air which has leaked in. The room air passes its heat energy
to the turbine components, so that, in conjunction with corresponding values
of relative air humidity, the temperature often falls below the dew point.
PG I14314 Training
23
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 Turbine
ϑR Room temperature
ϑW Casing wall temperature
ϑL Temperature of the enclosed air
Hot-air conservation Heated ambient air is blown into the turbine and as a result the relative air
humidity is lowered and at the same time the inner parts of the casing are
dried. This air takes up the moisture from inside the turbine and heats the
cold casing components to a temperature higher than that of the ambient air.
PG I14314 Training
24
© Siemens AG 2007
Preventive Maintenance Turbine plant
Turbine
3
The hot air should, where possible, be introduced at the lowest point of the
turbine and should be exhausted via the vapour ducts of the shaft seals and
via the opened drains.
In order to ensure that all parts of the turbine are at a higher level than the
ambient air temperature and that the temperature at no point within the
turbine casing falls below the dew point, the quantity and temperature
difference of the air introduced must be controlled so that the temperature of
the air exhausted is between 8 and 10 °C above the temperature of the
powerhouse even at the remotest point of the casing.
Dry-air conservation A better and more economic solution for conservation of the turbine casing is
achieved by introduction of air, which has been previously dried. This
method has the advantage that the plant can be conserved for any length of
time and can, moreover, be made ready for renewed operation within a very
short time.
PG I14314 Training
25
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 Turbine
The dry-air blower dehumidifies the air, which has been drawn in from the
atmosphere by means of a ventilator and filtered, in a rotating drying wheel
and supplies it to the turbine. That part of the drying wheel, which has taken
up the humidity is dried by a heated air flow through the regeneration
section, which is separate from the absorption section of the drying wheel.
1 Heater
2 Ventilator
3 Filter
4 Dry air
5 Drying wheel
6 Regeneration air
The humidity of the air leaving the air drier is very low. By this means it is
ensured that the air blown into the turbine, even after taking up the moisture
and being cooled down by colder turbine components, still remains below
the critical corrosion threshold of approx. 50 % relative air humidity.
Any residual water is removed within a very short time and corrosion is
prevented with a high degree of safety. The connection conditions are
identical to those specified for hot-air conservation.
The area of the metallic surface to be conserved is the key parameter for
water removal and ventilation performance of the air dryer. Since this
parameter is difficult to calculate and the amount of residual water existing
on commencement of conservation can hardly be estimated, the air volume
of the plant to be conserved is generally taken as the basis in actual
practice. Thus an air change of once to twice an hour is provided for a
PG I14314 Training
26
© Siemens AG 2007
Preventive Maintenance Turbine plant
Turbine
3
volume which includes that of the condenser and of any other aggregates
plus a generously dimensioned factor of safety.
Nitrogen conservation In addition to hot-air and dry-air conservation, filling up of the turbine casing
with an insert gas, in this case nitrogen, has been proven in practice. Before
blowing in the nitrogen, the turbine has to be dried. The turbine must be
subsequently carefully made gas-tight. All steam and drainage connections
must be closed, the shaft bushings in the region of the sealing cups and the
valve spindle bushings should be sealing using "Densobinde".
Danger of suffocation
Human life is endangered by an excessively high nitrogen concentration.
For this reason, before restarting, it must be ensured that the oxygen
content in those plant sections, which are filled with nitrogen, is restored
DANGER to a normal value.
Conservation of the bearings No special measures must be taken for conservation of the control fluid and
and of the oil system lubricating oil system including the bearings, since the anti-corrosion additive
in the types of oil employed usually provides adequate protection against
corrosion. Care must only be taken to ensure that the parts exposed to oil
are constantly wetted. The oil circuit should therefore be put into service for
some hours every 2 to 4 weeks. In order to fully wet the spindle ends, the
turbine rotor and the jacking oil pump must be kept in operation. The oil
should be analysed with respect to its water content at regular intervals.
Bearing shells or bearing stubs of turbines, which are shutdown for long
periods of time in the assembled condition or whose rotors lie in the
bearings, should not be treated using conservation pastes or sprays.
NOTE Continuous low-level vibrations, which are transmitted to the turbine
through the foundation or via connection lines, cause destruction of the
thin oil protection film within a very short time under the high stress of
the inserted rotors and result in considerable damage due to friction
fretting. With oil conservation, the existing oil film prevents direct metallic
contact by continuous evaporation and constant reforming.
PG I14314 Training
27
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 Turbine
Protective coatings The internal parts of the turbine can be adequately protected against
corrosion by means of a protective coating only after opening the casing.
Generally available anti-corrosion protection agents are employed. Formerly
used compounds of linseed oil and turpentine should not be used on
account of the inadequate protection they afford.
In the case of turbines which are to be shutdown over longer time periods,
we recommend additional use of the following protection measures:
All the control elements (actuator cylinder, speed controller, etc.) should
be dismantled and carefully conserved. Please refer in this connection to
Section .
The bearings including all accessible parts (bearing housing, control
valve linkage, rotor up to the casing, etc.) should be carefully conserved.
It should be ensured in so doing that the conservation agent employed
forms a thin continuous film, since otherwise crevice corrosion can occur.
It should further be taken into account that the conservation agent must have
dried before the rotor is set down in the bearings.
Work to be performed
1. Check the white-metal temperature at the turbine axial bearing and the
turbine radial bearing.
For the commissioning and limit values, please refer to the Commissioning
report and the Function list 0-2020-TNo.-16.
PG I14314 Training
28
© Siemens AG 2007
Preventive Maintenance Turbine plant
Turbine
3
Remarks, notes
Visual inspection
Look through the sight glass to check the brush for wear. The indicator
points to "NEW" when the grounding brush is delivered (newly installed). The
marking "RPL" (replace) indicates that the brush must be replaced with a
new one. In designs with limit switches, the monitoring and replacement
times can be monitored by the instrumentation and control system.
If it is not possible to replace the brush at this time, check the condition of
the brush every day, as any absence of grounding can quickly result in
damage to the bearings and gearbox.
Electrical check
PG I14314 Training
29
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 Turbine
measuring point. The oscilloscope must cover the direct and alternating
current ranges to record both components.
Voltage is normally displayed as a sequence of almost vertical peaks on the
screen with a high level of noise. It is often the case that the rotational
frequency, or multiples thereof, are established. Establish the current
between the brush and ground as shown in Figure 1, while measuring the
voltage drop that occurs at this resistor with the oscilloscope. The current
can then be calculated from this voltage using the following equation:
I = Δ U R (V : Ω [A])
The ground switch can be closed when the calculated current and the
measured voltage remain within the limits specified in the following and
when no irregularities are discernible. If the current rises above 0.5 A
(measured peak to peak), you should perform troubleshooting to establish
PG I14314 Training
30
© Siemens AG 2007
Preventive Maintenance Turbine plant
Turbine
3
It can be assumed that the brush is in good condition if the measured values
for voltage and current remain approximately the same over a period of
weeks. The brush and the measuring equipment must be checked, however,
when measured values of zero are obtained.
Ohmmeter measurements
ATTENTION
PG I14314 Training
31
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 Turbine
1 Coupling 4 Ohmmeter
2 Grounding Brush 5 To ground
3 Ground switch 6 Shaft
Ensure that the measured value is around zero if the brush arm touches
the brush enclosure when lifting the machine brush to its outermost
position. Therefore, for this check, only lift the brush slightly off of the
NOTE shaft.
Voltage check
PG I14314 Training
32
© Siemens AG 2007
Preventive Maintenance Turbine plant
Turbine
3
Shaft voltage
The shaft voltage that is generated on the rotor due to various reasons can
be measured using the existing grounding brush and an auxiliary brush as
shown in Figure 3. The shaft voltage is measured with the ground switch
opened using an analog or digital voltmeter at the AC and DC settings.
Correct data concerning the voltage behavior is only obtained using an
oscilloscope however. Ground the oscilloscope to the bearing pedestal in
which the duty grounding brush is installed. The oscilloscope must be
potential free, i.e. there may be no connection between the measurement
inputs and the protective ground. It is imperative that this is ensured! If you
can not be sure of this, use a battery-powered oscilloscope.
ATTENTION
PG I14314 Training
33
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 I&C Systems
1 Coupling 4 AC / DC meter
2 Grounding Brush 5 To ground
3 Ground switch 6 Shaft
Monitoring
The condition and wear of the brush should be checked initially every hour
during commissioning; later, during satisfactory operation, weekly checks
should be performed and the results documented.
Work to be performed
Check for easy movement.
Check the alteration of the reference value
Check of leakage (tightness)
Tightening or installation of a new packing in the valve spindle cover.
PG I14314 Training
34
© Siemens AG 2007
Preventive Maintenance Turbine plant
I&C Systems
3
Remarks, notes
In spite of the applied steam pressure, the speed of the turbine rotor must
fall to zero after elapse of the coast-down time when the control valves are
closed.
In order to avoid hazard and unnecessary loss of steam, the valve spindle
packing should be either tightened or replaced as soon as possible. This
work can be carried out only in the depressurised state.
PG I14314 Training
35
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 I&C Systems
Work to be performed
1. Perform a visual inspection
Remarks, Notes
Work to do
1. Check the solenoid valves 2225, 2226, 2227 during operation
2. Check the emergency stop valves 2300, 2301 - partial stroke test - during
operation
PG I14314 Training
36
© Siemens AG 2007
Preventive Maintenance Turbine plant
I&C Systems
3
Mortal danger
Do not dismantle the emergency stop valve while the turbine is running
and/or hot.
DANGER The surrounding cover of the control block and the stroke indicator must
also not be removed until the turbine is at standstill and has cooled
down.
Risk of crushing and/or burns!
Work to be performed
1. Check solenoid valves 2225, 2226, 2227 during operation
2. Check turbine stop valve SSV 2300, 2301 during operation (part-lift test)
Work to be performed
1. Tests/Inspections during startup and shutdown phases
2. Tests/Inspections during operation (part-lift test)
3. Tests/Inspections during operation (full-lift test)
PG I14314 Training
37
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 I&C Systems
Remarks, Notes
You can open and close the turbine stop valves during startup and
shutdown and at standstill when the oil supply system is activated using
the startup control module in the turbine trip block and hence test these
valves for freedom of movement (monitor the indication).
During turbine operation, fault-free operation of the turbine stop valve can
be tested using the test device (part-lift test). This is done by actuating
the solenoid valves 1846, 1817.
Full-lift test
Full-lift testing can only be performed during turbine operation when
there are two turbine stop valves fitted and when a test gate valve is
fitted (not standard).
NOTE
Work to be performed
1. Check for freedom of movement of the nonreturn valves in the steam
system.
Remarks, Notes
PG I14314 Training
38
© Siemens AG 2007
Preventive Maintenance Turbine plant
I&C Systems
3
Steam and/or condensate may flow back into the turbine if the steam
pressure in the automatic or nonautomatic extraction lines is greater than the
steam pressure at the automatic or nonautomatic extraction point in the
turbine.
This returning steam, with a more or less high water content, can cause
negative thermal effects such as
or may influence the intercept reliability of the turbine during load changes.
Work to be performed
1. Check measuring accuracy
See Commissioning Data Record, design data and/or the list of functions for
the setpoint.
Remarks, Notes
Work to be performed
1. Check the accuracy.
Remarks, notes
PG I14314 Training
39
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 Pipework and fittings
Work to be performed
1. Check the keyphaser
Remarks, Notes
Work to be performed
1. Checking the vibration measuring equipment
Remarks, Notes
Work to do
1. Check drainage
2. Check the temperature drop in the main steam line
3. Check pipes, anchoring elements and expansion compensators etc.
Mortal danger
Do not work on hot and/or pressurized steam pipes.
Risk of burns
DANGER In the area of the steam pipes, there is a risk of burns on the hand
wheels of the valves.
PG I14314 Training
40
© Siemens AG 2007
Preventive Maintenance Turbine plant
Pipework and fittings
3
Over-expansion of screws
On flanges of high-pressure lines, screws must not be retightened during
operation.
ATTENTION
Steam lines through which there is not a constant flow, but which might
possibly suddenly contain hot steam, should not only be reliably drained on
a permanent basis but, as far as possible, should be protected against
thermal shocks by means of suitable operation and measures taken (sealing
steam systems, safety line and bypass stations).
This is why diaphragms with an inner diameter of less than 3 mm are not
suitable. Diaphragm in horizontal lines should be preceded by sludge traps.
All shut-off elements must seal tightly. Remedy any leaks discovered.
Check the perfect condition of all pipes, anchoring elements, pipe guiding
elements and expansion compensators in accordance with a defined plan to
ensure that no inadmissible expansion, additional stresses or vibrations will
occur during operation.
PG I14314 Training
41
© Siemens AG 2007
Turbine plant Preventive Maintenance
3 Shaft-gland sealing steam
Work to be performed
1. Check valve travel
2. Check for leak-tightness of valve stems
3. Check for proper air supply
4. Zero point check of the converter
Remarks, Notes
Risk of burns!
Risk of burns on the valve handwheels in the vicinity of the steam lines.
DANGER
1. The actual valve lift must correspond to the "Manual" setpoint indicator on
the control device; correct where required in accordance with the
operating instructions provided by the manufacturer.
2. Check for leak-tightness of valve stems. Slight tightening of the shaft
gland during operation eliminates any leaks which may be present.
3. Normally, the pneumatic control system devices are maintenance-free.
Proper function of these devices can, however, only be guaranteed when
supply of clean air to the system is maintained. The air filters and
reducing station must therefore be checked at regular intervals. In the
event of a drop in output, clean or replace the appropriate filter.
If the control module does not provide proper control, or if there is no
output signal, unscrew the preliminary throttle of the comparator and
PG I14314 Training
42
© Siemens AG 2007
Preventive Maintenance Turbine plant
Shaft-gland sealing steam
3
PG I14314 Training
43
© Siemens AG 2007
© Siemens AG PG I 2007 Data subject to change.