You are on page 1of 1

Tag No.

Description.
System. Description.
SubSystem. Description.
Location. Drawings / Rev.
ITEM CHECK LIST OK N/A
1
Check cable tray / ladder is undamaged and installed against d rawings without clashes with pipe runs
or other equipment.  
2 Check cable tray / ladder is adequately supported against drawings (no excessive deflection).  
3 Check cables segregation in accordance with drawings.  
4 Check the capacity of cable tray / ladder (bunching , size of cables,etc…).  
5 Check insulation pads are adapted to stainless steel or aluminium cable tray /ladder.  
6 Check cable tray / ladder cleanness  
7 Check lids intallation (if any) against drawings,  
8 Check cable tray / ladder earthed and bonded against drawings.  
9 Produce marked-up layout drawing in accordance with installation.  
10 Produce a defects list for punch list issue.  
11 Punchlist raised - Yes  No  Punchlist No: Punchlist recorded in CSystem Database 
Remarks:

DATE NAME SIGNATURE

Carried Out by

Contractor
Accepted by

Company

Commisioning

Certifying Authority

Sheet 1 of 1