Topic 10 – Sloping Sites

02200 – Earthworks

Stepped Foundations

© Copyright : Davis Langdon & Seah Philippines Inc. SLOPE-7/1


Topic 10 – Sloping Sites

02200 – Earthworks

Stepped Foundations

Excavation of trenches

Plan of stepped
foundations

Profile of foundations

Method:

Calculate lengths of A, B and C

Then:

Length D = Center line of trench – (A+B+C)

* By doing this way trench excavation has been measured to the total girth of trench and any errors will be
reduced.

© Copyright : Davis Langdon & Seah Philippines Inc. SLOPE-7/2