You are on page 1of 7

Welcome to download the Newest 2passeasy PMP dumps

https://www.2passeasy.com/dumps/PMP/ ( New Questions)

Exam Questions PMP


Project Management Professional

https://www.2passeasy.com/dumps/PMP/

Passing Certification Exams Made Easy visit - https://www.2PassEasy.com


Welcome to download the Newest 2passeasy PMP dumps
https://www.2passeasy.com/dumps/PMP/ ( New Questions)

NEW QUESTION 1
- (Topic 1)
Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?

A. Project sponsor and project manager


B. Project sponsor and functional manager
C. Project manager and project team
D. Project team and functional manager

Answer: C

NEW QUESTION 2
- (Topic 1)
Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?

A. Build v
B. buy
C. Expert judgment
D. Alternatives identification
E. Product analysis

Answer: C

NEW QUESTION 3
- (Topic 1)
What is a hierarchically organized depiction of the identified project risks arranged by risk category?

A. Risk register
B. Risk breakdown structure (RBS)
C. Risk management plan
D. Risk category

Answer: B

NEW QUESTION 4
- (Topic 1)
Which statement is true about the project management body of knowledge?

A. Recognized by every project manager


B. Constantly evolving
C. The sum of all knowledge related to project management
D. A sum of knowledge that should be applied on every project

Answer: B

NEW QUESTION 5
- (Topic 1)
An element of the project scope statement is:

A. Acceptance criteria.
B. A stakeholder list.
C. A summary budget,
D. High-level risks.

Answer: A

NEW QUESTION 6
- (Topic 2)
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This
issue could have been avoided if they had created and followed a:

A. risk management plan


B. human resource management plan
C. scope management plan
D. procurement management plan

Answer: D

NEW QUESTION 7
- (Topic 2)
Which tool is used to develop technical details within the project management plan?

A. Expert Judgment
B. Project Management Methodology
C. Project Management Information

Passing Certification Exams Made Easy visit - https://www.2PassEasy.com


Welcome to download the Newest 2passeasy PMP dumps
https://www.2passeasy.com/dumps/PMP/ ( New Questions)

D. Project Selection Methods

Answer: A

NEW QUESTION 8
- (Topic 2)
The staffing management plan is part of the:

A. organizational process assets.


B. resource calendar.
C. human resource plan.
D. Develop Project Team process.

Answer: C

NEW QUESTION 9
- (Topic 2)
In the Plan Procurement Management process, which source selection criteria analyzes if the seller's proposed technical methodologies, techniques, solutions,
and services meet
the procurement documents requirements?

A. Technical approach
B. Technical capability
C. Business size and type
D. Production capacity and interest

Answer: A

NEW QUESTION 10
- (Topic 2)
Which is an output from Distribute Information?

A. Earned value analysis


B. Trend analysis
C. Project records
D. Performance reviews

Answer: C

NEW QUESTION 11
- (Topic 2)
Tools and techniques used for Plan Communications include the communication:

A. requirements analysis, communication technology, communication models, and communication methods.


B. methods, stakeholder register, communication technology, and communication models.
C. requirements, communication technology, communication requirements analysis, and communication methods.
D. management plan, communication technology, communication models, and communication requirements analysis.

Answer: A

NEW QUESTION 12
- (Topic 3)
The precedence diagramming method (PDM) is also known as:

A. Arrow Diagram.
B. Critical Path Methodology (CPM).
C. Activity-On-Node (AON).
D. schedule network diagram.

Answer: C

NEW QUESTION 13
- (Topic 3)
A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to
reevaluate the schedule?

A. What-if scenario analysis


B. Critical chain method
C. Schedule crashing
D. Resource leveling

Answer: C

NEW QUESTION 14
- (Topic 3)

Passing Certification Exams Made Easy visit - https://www.2PassEasy.com


Welcome to download the Newest 2passeasy PMP dumps
https://www.2passeasy.com/dumps/PMP/ ( New Questions)

Which illustrates the connection between work that needs to be done and its project team members?

A. Work breakdown structure


B. Network diagrams
C. Staffing management plan
D. Responsibility matrix

Answer: D

NEW QUESTION 15
- (Topic 4)
In Project Cost Management, which input is exclusive to the Determine Budget process?

A. Scope baseline
B. Organizational process assets
C. Project schedule
D. Resource calendars

Answer: D

NEW QUESTION 16
- (Topic 4)
Which process occurs within the Monitoring and Controlling Process Group?

A. Cost Control
B. Quality Planning
C. Quantitative Risk Analysis
D. Cost Budgeting

Answer: A

NEW QUESTION 17
- (Topic 4)
A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as
the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

A. budget at completion (BAC)


B. earned value management (EVM)
C. to-complete performance index
D. cost performance index

Answer: C

NEW QUESTION 18
- (Topic 4)
The following chart contains information about the tasks in a project.

Passing Certification Exams Made Easy visit - https://www.2PassEasy.com


Welcome to download the Newest 2passeasy PMP dumps
https://www.2passeasy.com/dumps/PMP/ ( New Questions)

Based on the chart, what is the cost performance index (CPI) for Task 2?

A. 0.8
B. 1
C. 1.25
D. 1.8

Answer: C

NEW QUESTION 19
- (Topic 4)
Cost of quality (COQ) refers to total cost of/to:

A. All efforts related to quality.


B. Product inspection activities.
C. Maintain plan quality.
D. Perform quality control.

Answer: B

NEW QUESTION 20
- (Topic 5)
Exhibit A is an example of which of the following types of Sequence Activities?

Passing Certification Exams Made Easy visit - https://www.2PassEasy.com


Welcome to download the Newest 2passeasy PMP dumps
https://www.2passeasy.com/dumps/PMP/ ( New Questions)

A. Activity-on-arrow diagramming
B. Precedence diagramming
C. Project schedule network diagramming
D. Mathematical analysis diagramming

Answer: B

NEW QUESTION 21
......

Passing Certification Exams Made Easy visit - https://www.2PassEasy.com


Welcome to download the Newest 2passeasy PMP dumps
https://www.2passeasy.com/dumps/PMP/ ( New Questions)

THANKS FOR TRYING THE DEMO OF OUR PRODUCT

Visit Our Site to Purchase the Full Set of Actual PMP Exam Questions With Answers.

We Also Provide Practice Exam Software That Simulates Real Exam Environment And Has Many Self-Assessment Features. Order the PMP
Product From:

https://www.2passeasy.com/dumps/PMP/

Money Back Guarantee

PMP Practice Exam Features:

* PMP Questions and Answers Updated Frequently

* PMP Practice Questions Verified by Expert Senior Certified Staff

* PMP Most Realistic Questions that Guarantee you a Pass on Your FirstTry

* PMP Practice Test Questions in Multiple Choice Formats and Updatesfor 1 Year

Passing Certification Exams Made Easy visit - https://www.2PassEasy.com


Powered by TCPDF (www.tcpdf.org)

You might also like