JORDAN DISTRICT COOLING
CASE STUDY
www.araner.coM
1 ABOUT ABDALI AREA
www.araner.coM www.araner.coM
2 WHAT DID ABDALI NEED?
www.araner.coM
3 ARANER’S SOLUTION
The original solution considered in the early design stages The disadvantage of cooling towers is that they have a very
was a district cooling plant with centrifugal chillers and high water consumption. The original design concept would
cooling towers. Cooling towers are the traditional solution have implemented a grey water supply from the municipality
implemented in District Cooling plants in order to increase that would be treated in a water treatment plant inside the
the chiller's efficiency. District Cooling Plant. The problems with this solution were
threefold:
www.araner.coM
It is commonly understood that air cooled chillers are less
efficient than chillers with cooling towers, and this is true
for most design conditions. However, out of the design
conditions, the benefit of a cooling tower when compared
with an air cooled chiller is not that high and may not really
compensate for the additional water consumption. This is the
case in Amman where the temperature at night
decreases drastically and it is close to the wet bulb
temperature.
ARANER’s air cooled chillers are able to achieve almost the
same yearly average COP than a system based on cooling
towers but with zero water consumption. These incredible
results were achieved by implementing three products in
which ARANER has a high level of expertise.
www.araner.coM
4 PROJECT EXECUTION
The relationship between Araner and the Abdali District Heating and Cooling started in 2009 with the installation of a temporary
plant with a capacity of 2,500 Tons supplied by 2 chillers of 1,125 Tons each and 1 boiler of 5,000 KW. They could easily satisfy
the demand that the developers had at the early stages of the District.
www.araner.coM
5 years later, at the end of 2014, when most of the buildings had been occupied and the demands could no longer be satisfied
with temporary chillers, the construction of the final plant started. In order to be able to provide cooling and heating at the right
time, the project was defined by two key milestones:
MILESTONE 1:
• 2 New Chillers (2,500 Tons each)
• 2 Temporary Chillers (1,125 Tons each) 7,500 Ton Cooling
274 Calendar days
• 1 New Boiler (16MW) 21 MW Heating
• 1 Temporary Boiler (5MW)
MILESTONE 2:
• 4 Chillers (2,500 Tons each) 30,500 Ton Cooling
53 MW Heating 486 Calendar days
• TES Tank (20,500 Tons)
• 4 Boilers (3x16MW + 1x5 MW)
The main challenge of the project execution was to achieve these two deadlines within a tight framework, bearing in mind
that within 274 calendar days (9 months), only the skeleton of the building and half of the tank, where the electrical rooms
should be placed, would be erected.
www.araner.coM
In order to reach these targets, close coordination between in Spain in order to carry out maintenance and install all
civil, mechanical, electrical and control departments was the improvements that have been developed by Araner’s
undertaken to install all of the equipment with the required Engineering team during the last years.
quality and within a very tight schedule.
Changes to the discharge line, modifications in the oil
Araner’s experts from different departments were mobilized separator supports, rearrangement of the interior piping or
to the site to supervise the installation and commissioning of oil separator filters are just some of the modifications that
the main equipment. were applied in the compressor units in order to improve
their performance.
For milestone 2, the chillers installed in the temporary
plant were dismantled and delivered to Araner’s workshop
www.araner.coM
Thanks of the good quality of the different equipment installed Once we have all the equipment installed at site and due
in the compressor units and the good maintenance performed to the pre-installation being carried out to a high degree of
by Araner’s O&M team; the components were still in perfect precision, it took just 30 days from the plant being energized
condition after 6 years working. by the Local Electricity Authority (JEPCO) before we were able
to start supplying chilled water to the Network.
www.araner.coM
The following tests were performed; only with a professional
and multidisciplinary team like Araner would be possible to
reach these targets:
• MV Motors Commissioning
• FF & FA Commissioning
www.araner.coM
5 ARANER RESULTS
With ARANER products, the energy consumption all around the year is very similar to a system with cooling towers but the water
needs are eliminated. The high performance results of the final cooling plant with ARANER products have been certified by several
international consultants and by the Jordanian Royal Scientific Society.