Analysis of Rates

dk;Z dk uke& ftyk ;kstuk 2015&16 ds vUrZxr xzke lqDdh eas


rqdjk [kksbZ v[kksM esa lqj{kk nhokj A
Sr No Description Unit Cost Rs Remarks/
Input ref.
1 Excavation in Foundation for R/wall & B/wall in all type of soils and
rocks including lead, lift and disposal of surplus material as per
direction of engineer-in -charge.

Sor item No. 97511-16-1 Cum 291.20


Total :- 291.20 Per Cum
2 RR Stone Masonary laid in 1:6 Cement and sand mortar in
r/wall and b/wall etc. Including supply of all Materials,
Labours, T & P etc. Required for proper completion of the
works

Sor item No. 97515-16-5 3152.90


Total :- Cum 3152.90 Per cum
3 Random Rabble stone masonary laid dry in R/wall,B/ wall, Kharanja
etc. including supply of all material, labour T&P etc. required fo
proper completion of the work ( As per PWD Uttarakhand
specificatioin)

SOR item No. 97513-16-3 Cum 1985.00


Total 1985.00 Per Cum

J.E. A.E
DETAIL OF MEASUREMENT
dk;Z dk uke& ftyk ;kstuk 2015&16 ds vUrZxr xzke lqDdh eas
rqdjk [kksbZ v[kksM esa lqj{kk nhokj A
Sl. No. Item of work Unit No L. B. H/D Quantity
Excavation in Foundation for R/wall & B/wall in
all type of soils and rocks including lead, lift and
disposal of surplus material as per direction of
1 engineer-in -charge.

Cum 1 1/2 9.00 1.25 0.90 5.06


Cum 1 1/2 12.00 1.25 0.90 6.75
Total :- Cum 11.81

Random Rubble Stone Masonry laid in 1:6


cement and sand mortar, in breast walls,
retaining walls, parapets, scuppers, etc. including
supply of all material, labour, T&P and royaltiies
2 etc.(As per PWD Uttarakhand specifications)

Cum 1 1 9.00 (1.25+.60)/2 2.00 16.65


Total :- Cum 16.65
Random Rabble stone masonary laid dry in
R/wall,B/ wall, Kharanja etc. including supply of
all material, labour T&P etc. required fo proper
3 completion of the work ( As per PWD
Uttarakhand specificatioin)

Cum 1 1 12.00 (1.25+.60)/2 2.00 22.20


Total :- Cum 22.20

JUNIOR ENGINEER ASSITANT ENGINEER


P.D.P.W.D. BHATWARI P.D.P.W.D. BHATWARI
UTTARKASHI UTTARKASHI
BILL OF QUANTITY
dk;Z dk uke& ftyk ;kstuk 2015&16 ds vUrZxr xzke lqDdh eas rqdjk
[kksbZ v[kksM esa lqj{kk nhokj A
Si.No. Item of Works Quantity Unit Rate Amount
Excavation in Foundation for R/wall & B/wall in all
type of soils and rocks including lead, lift and disposal
of surplus material as per direction of engineer-in
1 -charge. 11.81 Cum 291.20 3439.80

Random Rubble Stone Masonry laid in 1:6 cement and sand


mortar, in breast walls, retaining walls, parapets, scuppers,
etc. including supply of all material, labour, T&P and
royaltiies etc.(As per PWD Uttarakhand specifications)
2 16.65 Cum 3152.90 52495.79

Random Rabble stone masonary laid dry in R/wall,B/


wall, Kharanja etc. including supply of all material,
labour T&P etc. required fo proper completion of the
work ( As per PWD Uttarakhand specificatioin)
3 22.20 Cum 1985.00 44067.00

Total :- 100002.59

JUNIOR ENGINEER ASSITANT ENGINEER


P.D.P.W.D.BHATWARI P.D.P.W.D.BHATWARI
UTTARKASHI UTTARKASHI
SUMMERY OF ESTIMATED COST

dk;Z dk uke& ftyk ;kstuk 2015&16 ds vUrZxr xzke lqDdh eas rqdjk [kksbZ
v[kksM esa lqj{kk nhokj A
Si. No. Item of Work Amount

1 ftyk ;kstuk 2015&16 ds vUrZxr xzke lqDdh eas


rqdjk [kksbZ v[kksM esa lqj{kk nhokj A 100002.59
Total :- 100002.59
Say :- 1.00 Lacs

JUNIOR ENGINEER ASSITANT ENGINEER EXECUTIVE ENGINEER


P.D.P.W.D. BHATWARI P.D.P.W.D. BHATWARI P.D.P.W.D.BHATWARI
UTTARKASHI UTTARKASHI UTTARKASHI
SCHEDULE - "B"
dk;Z dk uke& ftyk ;kstuk 2015&16 ds vUrZxr xzke lqDdh eas rqdjk [kksbZ v[kksM esa lqj{kk
nhokj A
Earnest Money :- Rs.4000.00 Date of Calling Tender :-
Cost of Tender Form :- Rs. 75.00+13.50% VAT Date of Receiving Tender :-
Validity of Tender :- Date of Opening Tender :-
Time of Completion :- :-

Rate
Sl No Item Of Work Qty Unit Per
In Figure In Words
1 Excavation in Foundation for R/wall & B/wall in
all type of soils and rocks including lead, lift and
disposal of surplus material as per direction of 11.81 Cum Cum 291.20
Rs.TwO hundred Fifty
engineer-in -charge. one only

2 Random Rubble Stone Masonry laid in 1:6 cement


and sand mortar, in breast walls, retaining walls,
parapets, scuppers, etc. including supply of all Rs. Two Thousand Eight
material, labour, T&P and royaltiies etc.(As per 16.65 Cum Cum 3152.90 Hundred Eighty seven
PWD Uttarakhand specifications)
only.

3 Random Rabble stone masonary laid dry in


R/wall,B/ wall, Kharanja etc. including supply of Rs. One Thousand Five
all material, labour T&P etc. required fo proper 22.20 Cum Cum 1985.00 Hundred Eighty nine
completion of the work ( As per PWD only.
Uttarakhand specificatioin)
4 #REF!
Rs. Six Hundred Eight
#REF! Cum Cum #REF! only.

1
I/we hereby agree to execute the above work..............……………….....................% above/below/at par the rates filled
as above.
2
I/We tender my/our rates as above after taking fully into consideration the specification, special condition of the department for
the above work and rate quoted above are inclusive of all leads, lifts, royalty, municipal and toll charges and other incidential
expenses.
3 I/ We give below my/ our permanent postal address, any change in the address shall be intimated by me/us time to
time in writing to the engineer in charge. We shall make necessary arrangement at all time to receive any notice,
orders and communications that will be issued and sent to me/ us at this address. If any letter, communication sent
to the contractor received back by department undelivered, it will be deemed to have been delivered to me/us and
the department will be free to take action in view of the same without intimating me/ us. For any claim whatsoever
on this account. .

Contractor
Permanent postal address
(Filled by the contractor)

Officer Inviting Officer Opening Officer Recommending Officer Accepting


Tender Tender Tender Tender