You are on page 1of 166

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.

C
LOCATION: Dessie Break Down

LABOUR PRICE

Item Town Name Indexed hourly


No. Bahir Dar Type of Labour Per day cost Per Hour cost cost
1 Forman 195 24.38 29.25
2 Electrician 170 21.25 25.50
3 Welder 80 10.00 12.00
4 Crane operaator 320 40.00 48.00
5 Chiseler 80 10.00 12.00
6 Daily Labourer 60 7.50 9.00

EQUIPMENT PRICE
Item Town Name
No. Bahir Dar Type of Equipment Per day cost Per Hour cost
1 Hand Tools 30.00 3.75
2 Crane 10,000.00 1,250.00
3 Welding Machien 165.00 20.63
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Description Unit Fixed Price
1 Suplly and install Lighting Points:

Supply and install for Office flush mounted Light point fed
1.1 through 2 x 2.5 mm2 PVC insulated conductor inside
thermoplastic PVC conduit of ø 16mm complete with all
junction boxes with connection accessories. Pcs 290.05

Ditto, ai item 1 but for surface mounted lighting point for


1.2 office fed through 2 x 2.5 mm2 PVC insulated conductor
inside thermoplastic PVC Trunkate 16*16mm complete
with all junction boxes with connection accessories. Pcs 307.11

1.3 Ditto, as item 1 but for flush mounting lighting point for
Residence/Dormitry/, Aparetement. Pcs 230.04

1.4 Ditto, as item 1 but for flush mounting lighting point of


Work Shop /Store/. Pcs 565.18

Ditto, but Light point fed through 3 x 4 mm2 PVC insulated


1.5 conductor inside thermoplastic PVC conduit of ø 16mm
complete with all junction boxes with connection
accessories. Pcs 681.17

Ditto, but Light point fed through 5 x 6 mm2 PVC insulated


1.6 conductor inside thermoplastic PVC conduit of ø 16mm
complete with all junction boxes with connection
accessories. Pcs 1,443.12

Ditto, but Light point fed through 2 x 2.5 mm2 PVC


1.7 insulated conductor inside thermoplastic PVC conduit of ø
16mm and 1inche steel pipe complete with all junction
boxes with connection accessories. Pcs 744.39
2
Suplly and install Socket outlet Points of approved type:

Supply and install water heater point fed through 3 x 2.5


2.1 mm2 PVC insulated conductor inside thermoplastic PVC
conduit of ø 19mm complete with all junction boxes with
connection accessories. Pcs 451.80
Supply and install flush mounted (LEGRAND SALBEI)
2.2 socket outlet point 16A/1Ph with grounding through PVC
conductor of 3x2.5sq.mm wire, through conduits of 19mm
diameter and including with all accessories (For Office). Pcs 451.80

Page 2
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Description Unit Fixed Price

Supply and install flush mounted (LEGRAND SALBEI)


2.3 socket outlet point 16A/1Ph with grounding through PVC
conductor of 3x2.5sq.mm wire, through conduits of 19mm
diameter and including with all accessories (For Work
Shop and Store). 938.25

Ditto, but for flush mounted (LEGRAND SALBEI) Twin


2.4 socket outlet point 16A/1Ph with grounding through PVC
conductor of 3x2.5sq.mm wire, through conduits of 19mm
diameter and including with all accessories. (For Office). Pcs 512.55
2.5 Ditto, as item 2.2but for LEGRAND SALBEI) Surface
Mounted Socket outlet 16A with ground. Pcs 469.23
2.6 Ditto, as item 2.2but for (LEGRAND SALBEI) Table
Mounted Socket outlet 16A with ground. Pcs 542.25
2.7 Ditto, as item 2.2 but for Industrial type socket outlet
16A/1ph Legrand 0520 02. Pcs 643.50
2.8 Ditto, as item 2.2 but for Industrial type socket outlet
20A/1ph Legrand 0527 02. Pcs 625.28

Ditto, as item 2.2 but for Industrial type Legrand socket


outlet 16/3Ph 5 pin with interlocked isolator switch fed
2.9 through 5*4.0sq.mm PVC insulated and sheated power
cable of 0.6/1KV Euro cable insied PCV conduit of 21mm
dia. complete with all junction boxes with connection
accessories. (For Office) Pcs 1,678.95

Ditto, but for Industrial type Legrand socket outlet


16A/3ph fed through 5*4.0sq.mm PVC insulated and
2.10
sheated power cable of 0.6/1KV Euro cable insied PCV
conduit of 21mm dia. complete with all junction boxes with
connection accessories. (For Office) Pcs 1,597.95

Ditto, as item 2.2 but for Industrial type Legrand socket


outlet 32A/3ph fed through 5*6.0sq.mm PVC insulated
2.11
and sheated power cable of 0.6/1KV Euro cable insied PCV
conduit of 21mm dia. complete with all junction boxes with
connection accessories. (For Office) Pcs 2,212.65
3 Supply and Install Bell Call Point:
Suplly and install Bell call points fed through PVC
insulated conductor of 2 x 1mm2 inside thermo plastic
3.1
conduit of ø 13mm complete with all connection and fixing
accessories. Pcs 319.95

Page 3
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Description Unit Fixed Price
4 Suplly and install Switching Points for Office: Switch
must be approved type

Ditto, but for flush mounting Flush mounted single switch


4.1 (LEGRAND SALBEI) points fed through PVC insulated
conductor of 2 x 2.5mm² inside thermo plastic conduit of ø
16mm complete with all connection and fixing accessories. Pcs 214.99
4.2 Ditto, but for Flush mounted 2 gang single switch
(LEGRAND SALBEI) Pcs 247.39
4.3 Ditto, but for Flush mounted 2 gang two way switch
(LEGRAND SALBEI) Pcs 263.59
4.4 Ditto, but for Flush mounted two way switch (LEGRAND
SALBEI) Pcs 244.69
4.5 Ditto, but for flush mounting Intermediate switch
(LEGRAND SALBEI) Pcs 263.59
4.6 Ditto, but for flush mounting Tumbler 16A/1Ph switch
(LEGRAND SALBEI) Pcs 546.30
4.7 Ditto, but for flush mounting Dimmer switch (LEGRAND
SALBEI) Pcs 802.80

5 Suplly and install Switching Points for Work Shop and


store: Switch must be approved type

Ditto, but for flush mounting Flush mounted single switch


5.1 (LEGRAND SALBEI) points fed through PVC insulated
conductor of 2 x 2.5mm² inside thermo plastic conduit of ø
16mm complete with all connection and fixing accessories. Pcs 529.54
5.2 Ditto, but for Flush mounted 2 gang single switch
(LEGRAND SALBEI) Pcs 561.94
5.3 Ditto, but for Flush mounted 2 gang two way switch
(LEGRAND SALBEI) Pcs 578.14
5.4 Ditto, but for Flush mounted two way switch, (LEGRAND
SALBEI) Pcs 559.24
5.5 Ditto, but for flush mounting Intermediate switch
(LEGRAND SALBEI) Pcs 578.14
6 Supply and install Fan Outlet Point:

Ditto, but for flush mounted Rotary Fan switch of type


USHA 220V, 50Hz feed through PVC insulated conductors
6.1
0f 2x2.2sq.mm inside PVC conduit of 16mm diam.
including junction boxes with covers and insulating screw
cap connectors and all connection accessories. Pcs 893.70

Page 4
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Description Unit Fixed Price
7 Supply and Install Bell Call System:

Flush mounted Bell call system consisting of Indicator 18


7.1 digits with Transformer 220/12v/25vA and call canceling
master push button and buzzer Pcs 6,854.32
Ditto, but for Indicator 16 digits with Transformer
7.2 220/12v/25vA and call canceling master push button and
buzzer Pcs 6,375.07
Ditto, but for Indicator 6 digits with Transformer
7.3 220/12v/25vA and call canceling master push button and
buzzer Pcs 3,675.07
7 Supply and install TV Outlet Point:
Flush mounted fixed TV outlet outlet point fed through
7.1 coaxial cable inside thermoplastic PVC conduit of ø 16mm
complete with all junction boxes with connection
accessories. Pcs 336.25
8 Supply and install Tele/Data Outlet Point:

Ditto, but for flush mounted Tele outlet point fed through
8.1 TELE TERMINAL BOX 10 PAIR inside PVC Conduit of
Ø19mm complete with all connection accessories. Pcs 1,431.10
Ditto, but for RJ11 outlets type Legrand suno 7740 38 +
8.2 7740 41 or approved equivalent with 4 contacts (surface
mounted) Pcs 177.19

Ditto, but for RJ45 (Cat 6e) outlets type LEGRAND suno
8.3 74213 cat 6e or approved equivalent with 8 contacts
(surface mounted) Pcs 582.19
Ditto, but for category 6 UTP 4 pair data cable with RJ45
8.4 termination (3 meter patch cord and all necessary
accessories. ) Pcs 150.19
Ditto, but for 2x category 6 UTP 4 pair data cable with
8.5 RJ45 termination (3 meter patch cord and all necessary
accessories. ) Pcs 271.69

8.6 4x category 6 UTP 4 pair data cable with RJ45 termination


(3 meter patch cord and all necessary accessories. ) Pcs 514.69

8.7 8x category 6 UTP 4 pair data cable with RJ45 termination


(3 meter patch cord and all necessary accessories. ) Pcs 1,000.69

Page 5
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Description Unit Fixed Price
9 Supply and inatall light fitting of approved with
complete accessories
9.1 Mareco LUCE Iris 0750.101M with 1*FBT 18W E27 lamp
-65 Pcs 1,091.25
9.2 Mareco LUCE Barcellona Opal 1600.152W with 1*SE
70W E27 lamp IP-65 Pcs 6,113.25
9.3 Mareco LUCE Barcellona Eco1604.152W with 1*SE 70W
E27 lamp IP-65 Pcs 6,518.25
9.4 Mareco LUCE Sfera-Ura 400 2071.400T with 1*ST-SE
70W E27 lamp IP-65 Pcs 3,615.75
9.5 Philips TMS 012 with 1xTL-D 18W Lamp Pcs 377.10
9.6 Philips TCW 060 with 1xTL-D 36W Lamp Pcs 1,455.75
9.7 Philips TCW060 with 2xTL-D 36W Lamp Pcs 1,779.75
9.8 RZB 51060.963 +TC-D 18W LAMP Pcs 682.20
9.9 UNOLUX UX-CLASSIC ASN.NC LA T8 Pcs 2,306.25
9.10 UNOLUX UX-CLASSIC ASN.N PAR Pcs 2,873.25
9.11 UNOLUX UX-TUBUS 291 Pcs 2,090.25
9.12 RZB 90756.842 WITH 1XTC-T 18W TUBUS 291 Pcs 2,090.25
9.13 RZB 311070.842 WITH 1XTC-T 18W Pcs 1,989.00
9.14 RZB23643.002 with 1*E27 60W IP-40 Pcs 1,989.00
9.15 RZB211005.with 1*E27 60W IP-44 Pcs 1,989.00
9.16 MASSIVE 34041/11/10 1x GU10 | max. 35W Pcs 1,631.25
9.17 RZB 211006 WITH 1*TC-T 18W Lamp Pcs 1,658.25
9.18 RZB 211015 WITH 1*TC-T 18W Lamp Pcs 1,813.50
9.19 RZB50100.002 WITH 1*TC-D 13W Lamp Pcs 956.25
9.20 RZB 22143.913 WITH 1*TC-D 11W Lamp Pcs 969.75

9.21 RZB 45135.002 WITH SOCKET & SWITCH TC.26 15W


OMS MIRROR LIGHT Pcs 915.75
9.22 RZB 91152.002 WITH 1*QPAR20 60W LAMP IP-20 Pcs 652.50
9.23 PHILIPS TCW 012/1X36W Pcs 1,253.25
9.24 PHILIPS TMW 012/1X36W Pcs 1,253.25
9.25 PENDENT LIGHT MD 8180/3 Pcs 3,966.75
9.26 CANDELUX C12-9 HALF Pcs 1,039.95
9.27 Mareco LUCE SFERA 1080.201B with 1*FTB 20W E27
lamp. Pcs 1,654.20
9.28 PELSAN EXIT Pcs 3,757.50

Page 6
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Description Unit Fixed Price
9.29 RZB 10120.922.79 with 1*TC-DEL 13W IP-20 Pcs 821.25
9.30 PHILIPS SGS 102 SON-T 150W Pcs 5,708.25
9.31 PHILIPS SGS 101 SON-T 70W Pcs 3,980.25
9.32 Philips TMS 012 with 1xTL-D 36W Lamp Pcs 510.75
9.33 Philips TMS 012/236 IMK with 2xTL-D 36W Lamp Pcs 780.75
9.34 Philips TCW 196 with 1xTL-D 36W Lamp Pcs 1,239.75
9.35 Philips TCW196 with 2xTL-D 36W Lamp Pcs 2,049.75
9.36 Philips TCS 600 with 1xTL-S 36W Lamp Pcs 2,063.25
9.37 Philips TMS 600 with 2xTL-S 36W Lamp 2,738.25
9.38 Philips TCS 098/136 2xTL-D 36w lamp Pcs 2,670.75
9.40 Philips TCS 098/136 1xTL-D 36w lamp Pcs 1,995.75
9.41 Pelsan E.D.fiberglas bant + 1xTL-D 36w(TMW 065
Equivalent) Pcs 1,253.25
9.42 Pelsan E.D.fiberglas bant + 2xTL-D36w (TMW 065
Equivalent) Pcs 1,590.75

9.43 Incadscent Celling Glob type RZB 55154.00X with 1X25W


red dark room lamp Pcs 483.75
9.44 RZB 22141.923 with 1*TC-D 13W lamp Pcs 1,253.25
9.45 RZB 56220.003 with 1*TC-D 18W lamp Pcs 483.75
9.46 RZB 58030.962 with 1*TC-D 18w lamp Pcs 1,523.25
9.47 Massive 32005/31/10 with E27/max 60w Pcs 983.25
9.48 Gecem GCP 236L with 2xTL-D 36w Pcs 2,009.25
9.49 Philips TCS 098/218/ 2xTL-D 18w lamp Pcs 1,725.75
9.50 Legrand 400413 with 8w + 3hrs emergency kit. Pcs 3,818.25
9.51 Disano Ghost 323133-00 with FLC 70T/lamp or approved
equivalent. Pcs 3,413.25
9.52 Disano 1546 Globo 427236-00 with FLC 2x9 S lamp. Pcs 1,185.75
9.53 Massive 15254/45/10 with 3xE27 max 100w Pcs 3,953.25
9.54 Fumagali G40.121 M28.000.M80/max 80w Pcs 3,548.25
9.55 Philips HGS 101 with SON-H 250w lamp. Pcs 3,413.25

9.56 Philips post top lantern PMMA Ø40cm with SON-T 80w
lamp Pcs 6,113.25
Feal Luce light master 1000sqmm wide with MD/Jm
9.57
1000watt lamp. Pcs 34,530.75

Page 7
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Feal Luce JET 5 MT 400watt
Description
with MT/JM 400watt pole Unit Fixed Price
9.58 Feal
mounted
Lucetype.
MIRA PX 40470 CLI with SAP 250watt, pole Pcs 7,598.25
9.59 mounted type. Pcs 5,843.25
9.60 DISANO 920 Hydro T8 + FL 2*36watt lamp Pcs 1,725.75
9.61 DISANO 1601 Floor with diffuser, level finish with SAP
250watt lamp IP- 67 Pcs 6,653.25
9.62 LED pool light with 12volt, 25watt ratting and IP- 68 Pcs 10,568.25
9.63 RZB Perla 58131.922 with TC-D 18W lamp Pcs 1,361.25
9.64 Modus KV 1*36W lamp (prismatic) Pcs 1,725.75
9.65 Modus LL4*18 ALB ALMATE (louvered) Pcs 2,333.25
9.66 RZB linear 401000.912.79 with TC-EL 11W lamp Pcs 1,091.25
9.67 Modus KV 2*36W ALB ALMATE (prismatic) Pcs 2,063.25
9.68 MASSIVE 33012/17/10 with 2 x GU10 max 50W LAMP Pcs 1,455.75
9.69 MASSIVE 32005/31/10 withE27/max 60W LAMP Pcs 1,091.25
9.70 PHILIPS Pentura mini TCH128 with 1 x 28W Lamp. Pcs 1,523.25
9.71 Interior wall light fitting type RZB 25146.003 + A60 60W
LAMP Pcs 818.10
9.72 Exterior wall light fitting type RZB 22130.003 + A60
100W LAMP Pcs 1,193.40
9.73 Emergency light fitting type RZB 671467.752 with T16
8W/3h lamp and EXIT sign Pcs 5,026.05
9.74 RZB 921385.774 + 1XHIT-CE-P 150W LAMP Pcs 6,316.65
9.75 RZB 751097.773 + 1XHIT-CE 150W LAMP Pcs 2,444.85
9.76 RZB 581291.959 with 1xTCD 26W LAMP Pcs 1,806.30
9.77 RZB 33708.952 with 1xTCD 26W LAMP Pcs 2,268.00
9.78 MODUS BRKL 300+2XG23TC-S11WLAM Pcs 2,547.45
9.79 MODUS SB118EP+18W LAMPS Pcs 1,344.60
9.80 MODUS BRKL 375+2XG24TC-S18W LAMP Pcs 2,909.25
9.81 MODUS LLY 236 AL EP+T82X36W LAMP Pcs 3,893.40
9.81 MODUS LLY 236 KP EP+T82X36W LAMP Pcs 3,392.55

Supply and inatall Ventilation system Axial Ceiling,


10 false ceiling (Reccessed) and window Fan of approved
type with complete accessories
O.ERRE Axial fan STANDARD 12 with an ordering code
of 0015800 max dia of Hole Ø 120mm at 50Hz 220/240V,
10.1 max flow rate (m³/h) 125, max. press. 29Pa and max. power
demand of 13W.
Pcs 1,351.01

Page 8
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Description Unit Fixed Price
O.ERRE Axial fan STANDARD 15 with an ordering code
of 0016100 max dia of Hole Ø 150mm at 50Hz 220/240V,
10.2 max flow rate (m³/h) 230 max. press. 41Pa and max. power
demand of 30W.
Pcs 1,972.01
O.ERRE Axial fan VENTILOR 20/8 AR with an ordering
code of 0019000 max dia of Hole Ø 225-235mm at 50Hz
10.3 220/240V, max flow rate (m³/h) 450 max. press. 118Pa and
max. power demand of 50W.
Pcs 5,401.01
O.ERRE Axial fan VENTILOR 25/10 AR with an ordering
code of 0019200 max dia of Hole Ø275-285mm at 50Hz
10.4 220/240V, max flow rate (m³/h) 750, max. press. 59Pa and
max. power demand of 60W.
Pcs 6,751.01
O.ERRE Axial fan DIVERSO IN 240 with an ordering
code of 0083200 max dia of Hole Ø100mm at 50Hz
10.5 220/240V, max flow rate (m³/h) 270, max. press. 442Pa and
max. power demand of 80W.
Pcs 5,738.51
O.ERRE Axial fan AXIA MD 30 4M with an ordering code
of 0073003 IP-55 with single phase motor/4Pole RPM
10.6 1400 at 50/60Hz 230V, max flow rate (m³/h) 1800, max.
press. 135Pa and max. power demand of 100W.
Pcs 6,953.51
O.ERRE Axial fan AXIA MD 40 4M with an ordering code
of 0073007 IP55 with single phase motor/4Pole RPM 1350
10.7 at 50/60Hz 230V, max flow rate (m³/h) 3500, max. press.
155Pa and max. power demand of 170W.
Pcs 8,303.51
O.ERRE Ceiling Fan OASIS 3KR 140 with an ordering
code of 0024700 max dia of blades Ø 140mm at 50Hz
10.8
220/240V, max flow rate (m³/h) 16,000 and max. power
demand of 60W.
Pcs 3,848.51
11 Supply and install lighting protection system with
complet accessorie of approved quality.
11.1 AIR TERMINAL ROD 2.5M WITH MULTIPLE POINT
AND BASE Pcs 7,182.00

Page 9
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Description Unit Fixed Price

11.2 Ditto, but for Equipotential (Earthining) bonding copper bar


1500x50x10mm size with 7 bolted terminal Pcs 2,140.64

11.3 25X3MM LIGHTLY INSULATED COPEPR TAPE


2

INCLUDING CLIPS ETC. Ml 1,178.55


11.4 TEST CLAMP FOR 50/70 MM2 Pcs 905.85
11.5 TEST CLAMP FOR 25X3MM 2
Pcs 760.05
11.6 EARTH ROD 1200X16MM Pcs 517.62
11.7 AIR TERMINAL ROD 1.0M WITH MULTIPLE POINT
AND BASE Pcs 5,919.75
11.80 30x3.5mm galvanized steel ring earth termination net work. ML 2,103.30

12 Supply and install Bare Copper conductord of earthing


sysyem for buildings as per Electrical design/drawing
12.1 Diameter 16mm & 2400mm long copper earthing rod. Pcs 1,322.29
12.2 Diameter 16mm & 1500mm long copper earthing rod. Pcs 593.29
12.3 1x300mm. Sq. Bare copper bonding conductor ML 1,232.80
12.4 1x240mm. Sq. Bare copper bonding conductor ML 1,001.74
12.5 1x185mm. Sq. Bare copper bonding conductor ML 749.18
12.6 1x50mm. Sq. Bare copper bonding conductor ML 203.31
12.7 1x120mm. Sq. Bare copper bonding conductor ML 506.35
12.8 1x150mm. Sq. Bare copper bonding conductor ML 581.20
12.9 1x95mm. Sq. Bare copper bonding conductor ML 384.78
12.10 1x70mm. Sq. Bare copper bonding conductor ML 284.50
12.11 1x16mm. Sq. Bare copper bonding conducter ML 76.61
12.12 1x10mm. Sq. Bare copper bonding conducter ML 45.23
12.13 1x25mm. Sq. Bare copper bonding conductor ML 100.91
12.14 1x35mm. Sq. Bare copper bonding conductor ML 139.03
12.15 1x6mm. Sq. Bare copper bonding conductor ML 35.30
12.16 1x4mm. Sq. Bare copper bonding conductor ML 22.95
12.17 1x1.5 S Bare copper bonding conductor ML 7.67
12.18 1x2.5 S Bare copper bonding conductor ML 10.65
12.19 1x1.5 F Bare copper bonding conductor ML 8.23
12.20 1x2.5 F Bare copper bonding conductor ML 11.50
12.21 1x4 S Bare copper bonding conductor ML 22.95
12.22 1500x16mm copper earth road Pcs 593.29
12.23 Testing junction boxes at 1.5m above grade level. Pcs 934.88

Page 10
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Description Unit Fixed Price

Copper earth bar of 50x5mm (630-700A) and 500mm


12.24 length with holes every 50mm in three sections with
disconnecting link supporting brackets every 250mm
anchored to wall or floor for a minimum of 10 earthing
connections. Pcs 3,208.95

13 Supply and install PVC insulated Conductors in PVC


conduit (Euro cable or approved type)
13.1 1X1.5MM2 H97V-U 300/500V Ml 31.89
13.2 1X2.5MM2 " " Ml 38.97
13.3 1X4MM 2
" " Ml 49.61
13.4 1X6MM2 " " Ml 59.53
13.5 1X10MM2 H07V-K Ml 86.67
13.6 1X16MM 2
H07V-K Ml 125.18
13.7 1X25MM2 H07V-K Ml 150.11

14 Supply and install Power Cables (PVC sheated & PVC


insulated) (Euro cable or approved type)
14.1 1x70sqmm Cable NYY 0.6/1KV Ml 443.82
14.2 1x120sqmm Cable NYY 0.6/1KV Ml 890.32
Supply and install Power Cable PVC sheated & PVC
15 insulated Conductors in PVC conduit (NYY 0.6/1KV)
Euro cable or approved type
15.1 2X1.5MM2 Ml 39.66
15.2 3X1.5MM2 Ml 48.52
15.3 4X1.5MM2 Ml 64.18
15.4 2X2.5MM2 Ml 52.98
15.5 3X2.5MM2 Ml 62.00
15.6 4X2.5MM2 Ml 77.07
15.7 5X2.5MM2 Ml 110.38
15.8 2X4MM 2
Ml 68.39
15.9 3X4MM2 Ml 89.65
15.10 4X4MM2 Ml 113.84
15.11 5X4MM 3
Ml 135.95
15.12 2X6MM2 Ml 86.53
15.13 3X6MM2 Ml 120.08

Page 11
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Description Unit Fixed Price
15.14 4X6MM2 Ml 154.66
15.15 5X6MM 3
Ml 196.24
15.16 2X10MM2 Ml 145.59
15.17 3X10MM2 Ml 213.09
15.18 4X10MM 2
Ml 260.81
15.19 5X10MM3 Ml 317.51
15.20 2X16MM2 Ml 198.91
15.21 3X16MM 2
Ml 345.13
15.22 4X16MM2 Ml 441.52
15.23 5X16MM3 Ml 552.08
15.24 3X25/16MM 2
Ml 751.95
15.25 3X35/16MM2 Ml 1,006.86
15.26 3X50/25MM2 Ml 1,222.90
15.27 3X70/35MM2 Ml 1,670.96
15.28 3X95/50MM 2
Ml 2,389.16
15.29 3X120/70MM2 Ml 2,925.79
15.30 3X150/70MM2 Ml 3,450.26

16 Price Of U.PVC is not included for those items. (Euro


cable or approved type)
16.1 3X185/95MM2 Ml 3,010.84
16.2 3X240/120MM2 Ml 3,777.71
16.3 3X300/150MM 2
Ml 4,935.80

Supply and install Octagonal (Imported type)


Galvanized steel lighting pole dia. 120mm at base, and
17 dia. 60mm at top with, 6mm & abovethick through out
its length including free fixed door for terminal box,
including removable panel with clamps for power
cables, protective fuse holder with 6A fuse.(2 flood
lights per pole).
17.1 Steel Pole Height 3M Pcs 5,966.33
17.2 Steel Pole Height 6M Pcs 12,121.65
17.3 Steel Pole Height 8M Pcs 16,826.40
17.4 Steel Pole Height 9M Pcs 20,491.65
17.5 Steel Pole Height 12M Pcs 23,866.65
17.6 Steel Pole Height 14M Pcs 26,971.65
17.7 Steel Pole Height 20M Pcs 43,162.20
Page 12
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Description Unit Fixed Price

18 Supply and install Generator that can operate


autonatically (power/supply turned off)
Smax .........................72 KVA
voltage .....................380volts, 50Hz, 3-ph
speed……………………… 1500rpm PF…… 0.8
cooling method……… water cooled
The generator shall be equipped with:
18.1
automatic voltage regulator (AVR)
automatic transfer switch (ATS)
HCB of 125A/3ph
ON/OFF switch, current, voltage and frequency measuring.
Price shall include all listed accessories. Pcs 844,630.20
19 Supply and install Transformer
LV, outdoor, oil immersed 315KVA, 15KV, 380/220V,
19.1 50HZ 3-ph pole mountable Transformer with all mounting
accessories Pcs 540,677.70
LV outdoor, oil immersed 100KVA, 15kv/380v, 220v, 3ph,
19.2 50Hz, 125A/3ph fuse, Dyn11 or Dyn5 configuration pole
mountable distribution transformer with all mounting
accessories Pcs 344,927.70
General Technical Data of the oil immersed and
hermetically sealed Transformer.
Protective degrees
HV compartment: IP43
Transfomer compartment: IP23
LV compartment: IP43
Type KTMU 18 HC 630
Rated Power, KVA 1000
Voltage ratio,V 15000+/-2x2.5%/400
19.3 Frequency,Hz 50
Vector Group Dyn 5
Standard IEC 76
Cooling ONAN
Insulation level windings, KV LI AC 38/LI_AC3
No load losses, W 1200
Load losses, W 56300
The LV part should be provided with
1600A, MCCB 3ph, 70KA
Provide all technical data with sketch and catalouge. Pcs 2,880,624.60

Page 13
ANRS BoIUD 2008 E.C 2nd. Qtr Electrical cost break down

PROJECT: Electrical Installation Cost Break Down 1st Quarter 2009 E.C
LOCATION: Dessie
Item
No. Description Unit Fixed Price
20 Supply and Install Cable Tray
Galvanized steel cable tray, and of 450x100mm section for
20.1 POWER, perforated type including ceiling support bracket
every 1.5m, and other fixing accessories. Ml 513.99

Galvanized steel T-SECTION of 450x450x450mm


20.2 including ceiling support brackets, bonding, and other
fixing accessories. Pcs 532.89

20.3 Galvanized steel ELBOW of 450mm including ceiling


support brackets, bonding, and other fixing accessories. Pcs 532.89
Galvanized steel cable tray, and of 300x100mm section for
20.4 DATA/TEL, perforated type including ceiling support
bracket every 1.5m, bends, and other fixing accessories. Ml 428.94

Galvanized steel T-SECTION of 300x300x300mm


20.5 including ceiling support brackets, bonding, and other
fixing accessories. Pcs 532.89

20.6 Galvanized steel ELBOW of 300mm including ceiling


support brackets, bonding, and other fixing accessories. Pcs 532.89
21 Supply and install Cable Ladder
Steel cable ladder, made of galvanized C-section metal,
21.1 with supports every 500mm, and of 600x100mm fixed
inside riser anchored to wall. Ml 910.89

22 Supply and Install Lighting Arrester and protection


system with complet accessorie of approved quality.
22.1 PREVENTOR P1 WITH 4.6M MAST Pcs 41,542.20
22.2 PREVENTOR P2 WITH 4.6M MAST Pcs 49,334.40
22.3 PREVENTOR P3 WITH 6M MAST Pcs 59,541.75
22.4 PREVENTOR P4 WITH 6M MAST Pcs 85,930.20

Page 14
Page 1
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Light point For Office EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 290.05 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (2x2.5mm2 ) Ml 7.70 12.00 92.40 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
PVC condute 16mm Ml 3.70 6.50 24.05 Electrician 1 1 25.50 25.50
Junction Box Pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Connector Pcs 2.00 4.20 8.40 DL 1 1 9.00 9.00

Total (1:-01) 129.85 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 129.85 Birr/Pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 214.85 Birr/Pc
Over Head : +
Profit Cost: 35% 75.20 Birr/Pc
Total Unit Cost : 290.05 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Surface Mounted Light point For Office EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 307.11 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (2x2.5mm 2)
Ml 7.70 12.00 92.40 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
PVC Trunkate of 16x16mm Ml 3.70 9.92 36.69 Electrician 1 1 25.50 25.50
Junction Box Pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Connector Pcs 2.00 4.20 8.40 DL 1 1 9.00 9.00

Total (1:-01) 142.49 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 142.49 Birr/Pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 227.49 Birr/Pc
Over Head : +
Profit Cost: 35% 79.62 Birr/Pc
Total Unit Cost : 307.11 Birr/Pc
Page 2
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Light point For Residence/Dormitry/, Aparetement EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 230.04 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (2x2.5mm2 ) Ml 4.70 12.00 56.40 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
PVC condute 16mm Ml 2.40 6.50 15.60 Electrician 1 1 25.50 25.50
Junction Box Pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Connector Pcs 2.00 4.20 8.40 DL 1 1 9.00 9.00

Total (1:-01) 85.40 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 85.40 Birr/Pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 170.40 Birr/Pc
Over Head : +
Profit Cost: 35% 59.64 Birr/Pc
Total Unit Cost : 230.04 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Light point For Work Shop /Store/ EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 565.18 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (2x2.5mm 2)
Ml 21.00 12.00 252.00 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
PVC condute 16mm Ml 10.50 6.50 68.25 Electrician 1 1 25.50 25.50
Junction Box Pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Connector Pcs 2.00 4.20 8.40 DL 1 1 9.00 9.00

Total (1:-01) 333.65 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 333.65 Birr/Pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 418.65 Birr/Pc
Over Head : +
Profit Cost: 35% 146.53 Birr/Pc
Total Unit Cost : 565.18 Birr/Pc
Page 3
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Light point(For Swimming Pool) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 744.39 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Power Cable NYY 0.6/1KV
(2x2.5mm2) Ml 7.70 24.40 187.88 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
PVC condute 16mm Ml 3.70 6.50 24.05 Electrician 1 1 25.50 15.00
Junction Box Pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Connector Pcs 2.00 4.20 8.40 DL 1 1 9.00 9.00
1.inch steel pipe Ml 3.7 70.83 262.07 Chiseler 0 1 - 0.00

Total (1:-01) 487.40 Total (1:02) 24.00 Total (1:03) 8.00

A= Materials Unit Cost 487.40 Birr/Pc B= Manpower Unit Cost 48.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 551.40 Birr/Pc
Over Head : +
Profit Cost: 35% 192.99 Birr/Pc
Total Unit Cost : 744.39 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Light point with power cable of 3x4mm sq. EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 681.17 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (3x4mm 2)
Ml 7.70 48.20 371.14 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
PVC condute 21mm Ml 3.70 8.33 30.83 Electrician 1 1 25.50 25.50
Junction Box Pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Connector Pcs 3.00 4.20 12.60 DL 1 1 9.00 9.00

Total (1:-01) 419.57 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 419.57 Birr/Pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 504.57 Birr/Pc
Over Head : +
Profit Cost: 35% 176.60 Birr/Pc
Total Unit Cost : 681.17 Birr/Pc
Page 4
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Light point with power cable of 5x6mm sq. EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 1,443.12 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (5x6mm2) Ml 7.70 112.40 865.48 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
PVC condute 50mm Ml 3.70 25.00 92.50 Electrician 1 1 25.50 25.50
Junction Box Pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Connector Pcs 5.00 4.20 21.00 DL 1 1 9.00 9.00

Total (1:-01) 983.98 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 983.98 Birr/Pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 1068.98 Birr/Pc
Over Head :
Profit Cost: 35% 374.14 Birr/Pc
Total Unit Cost : 1,443.12 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
Work Item: Flush mounted Socket outlet for Water heater EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM : 1 Pt RESULT: 451.80

MATERIAL COST (1:01) LABOUR COST Indexed


(1:02) EQUIPMENT COST (1:03)
cost per unit Labour by Hourly Hourly Type of Hourly
Type of material Unit Qty* Rate Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x2.5 mm2 Conductor ml 10.00 12.00 120.00 Electrician 1 1 25.50 25.50 Hand Tools 2 1.00 4.00 8.00
ø 19mm Conduit ml 5.00 7.33 36.67 D.Labourer 1 1 9.00 9.00
Water heater Socket outlet Pcs 1.00 88.00 88.00
Junction box Pcs 1 5.00 5.00

Total 249.67 Total 34.50 Total 8.00

A= Materials Unit Cost 249.67 Birr/Pc B= Manpower Unit Cost 69 Birr/Pc C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 334.67 Birr/Pc
Over Head : +
Profit Cost: 35% 117.13 Birr/Pc
Total Unit Cost : 451.80 Birr/Pc
Page 5
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Fan Outlet Point EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 893.70 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (2x2.5mm2 ) Ml 8.00 12.00 96.00 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
PVC condute 16mm Ml 4.00 6.50 26.00 Electrician 1 1 25.50 25.50
Junction Box Pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
USHA 220V, 50Hz Rotary
Speed adjusting On/Off fan
switch Pcs 1.00 450.00 450.00 DL 1 1 9.00 9.00

Total (1:-01) 577.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 577.00 Birr/Pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 662.00 Birr/Pc
Over Head : +
Profit Cost: 35% 231.70 Birr/Pc
Total Unit Cost : 893.70 Birr/Pc
Page 6
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.95 ml/hr
WORK ITEM: Cable try EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 513.99Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
ml 1.05 320.00 336.00 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Galvanized steel cable tray, and Electrician 1 1 25.50 25.50
of 450x100mm section for DL 1 1 9.00 9.00
POWER, perforated type
including ceiling support
bracket every 1.5m, and other
fixing accessories.
Total (1:-01) 336.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 336.00 Birr/ml B=Manpower Unit Cost 36.32 Birr/hr C=Equipment Unit Cost 8.42
Direct Cost of work item= A+B+C= 380.74 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 133.26 Birr/Pc
Total Unit Cost : 513.99 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.95 Pcs/hr
WORK ITEM: Cable try EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 532.89Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1 350.00 350.00 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Galvanized steel T-SECTION Electrician 1 1 25.50 25.50
of 450x450x450mm including
ceiling support brackets, DL 1 1 9.00 9.00
bonding, and other fixing
accessories.
Total (1:-01) 350.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 350.00 Birr/ml B=Manpower Unit Cost 36.32 Birr/hr C=Equipment Unit Cost 8.42
Direct Cost of work item= A+B+C= 394.74 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 138.16 Birr/Pc
Total Unit Cost : 532.89 Birr/Pc
Page 7
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.95 ml/hr
WORK ITEM: Cable try EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 532.89Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Galvanized steel ELBOW of Pcs 1 350.00 350.00 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
450mm including ceiling Electrician 1 1 25.50 25.50
support brackets, bonding, and DL 1 1 9.00 9.00
other fixing accessories.

Total (1:-01) 350.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 350.00 Birr/ml B=Manpower Unit Cost 36.32 Birr/hr C=Equipment Unit Cost 8.42
Direct Cost of work item= A+B+C= 394.74 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 138.16 Birr/Pc
Total Unit Cost : 532.89 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.95 ml/hr
WORK ITEM: Cable try EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 428.94Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
ml 1.05 260.00 273.00 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Galvanized steel cable tray, and Electrician 1 1 25.50 25.50
of 300x100mm section for DL 1 1 9.00 9.00
DATA/TEL, perforated type
including ceiling support
bracket every 1.5m, bends, and
other fixing accessories.
Total (1:-01) 273.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 273.00 Birr/ml B=Manpower Unit Cost 36.32 Birr/hr C=Equipment Unit Cost 8.42
Direct Cost of work item= A+B+C= 317.74 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 111.21 Birr/Pc
Total Unit Cost : 428.94 Birr/Pc
Page 8
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.95 Pcs/hr
WORK ITEM: Cable try EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 532.89Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1 350.00 350.00 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Galvanized steel T-SECTION Electrician 1 1 25.50 25.50
of 300x300x300mm including DL 1 1 9.00 9.00
ceiling support brackets,
bonding, and other fixing
accessories.

Total (1:-01) 350.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 350.00 Birr/ml B=Manpower Unit Cost 36.32 Birr/hr C=Equipment Unit Cost 8.42
Direct Cost of work item= A+B+C= 394.74 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 138.16 Birr/Pc
Total Unit Cost : 532.89 Birr/Pc
Page 9
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.95 Pcs/hr
WORK ITEM: Cable try EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 532.89Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1 350.00 350.00 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Galvanized steel ELBOW of Electrician 1 1 25.50 25.50
300mm including ceiling DL 1 1 9.00 9.00
support brackets, bonding, and
other fixing accessories.

Total (1:-01) 350.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 350.00 Birr/ml B=Manpower Unit Cost 36.32 Birr/hr C=Equipment Unit Cost 8.42
Direct Cost of work item= A+B+C= 394.74 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 138.16 Birr/Pc
Total Unit Cost : 532.89 Birr/Pc
Page 10
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.95 ml/hr
WORK ITEM: Cable Ladder EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 910.89Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Steel cable ladder, made of ml 1.05 600.00 630.00 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
galvanized C-section metal, Electrician 1 1 25.50 25.50
with supports every 500mm, DL 1 1 9.00 9.00
and of 600x100mm fixed inside
riser anchored to wall.

Total (1:-01) 630.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 630.00 Birr/ml B=Manpower Unit Cost 36.32 Birr/hr C=Equipment Unit Cost 8.42
Direct Cost of work item= A+B+C= 674.74 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 236.16 Birr/Pc
Total Unit Cost : 910.89 Birr/Pc
Page 11
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Bell call point EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 319.95 Birr/Pt

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
diam.16mm conduit Ml 2.40 6.50 15.60 E.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
twin flat of 2x1.5 sq.mm wire
for ball call Ml 4.70 12.00 56.40 Electrician 1 1 25.50 25.50
junction box Pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
spring loaded on/off bell call
push button Pcs 1.00 75.00 75.00 DL 1 1 9.00 9.00
0
Total (1:-01) 152.00 Total ( 1:02 ) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 152.00 Birr/Pt B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 237.00 Birr/Pt
Over head cost : +
Profit Cost: 35% 82.95 Birr/Pt
Total Unit Cost : 319.95 Birr/Pt
Page 12
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: Flush mounting Single switch Legrand type (for Office) EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pt RESULT: 214.99Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Flush mounted single switch
(Legrand) Pcs 1 66.00 66.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diam.16mm conduit Ml 2.40 6.50 15.60 Electrician 1 1 25.50 25.50
Conductor (2x2.5mm2) Ml 4.7 12.00 56.40 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 138.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 138.00 Birr/ml B=Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of work item= A+B+C= 159.25 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 55.74 Birr/Pc
Total Unit Cost : 214.99 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2 Pcs/hr
WORK ITEM: Flush mounted 2 gang single switch Legrand type (for Office) EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pt RESULT: 247.39Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Flush mounted 2 gang single
switch (Legrand) Pcs 1 90.00 90.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diam.16mm conduit Ml 2.40 6.50 15.60 Electrician 1 1 25.50 25.50
Conductor (2x2.5mm2) Ml 4.70 12.00 56.40 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 162.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 162.00 Birr/ml B=Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of work item= A+B+C= 183.25 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 64.14 Birr/Pc
Total Unit Cost : 247.39 Birr/Pc
Page 13
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: Flush mounted 2 gang two way switch Legrand type (for Office) EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pt RESULT: 263.59Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Flush mounted 2 gang two
way switch (Legrand) Pcs 1 102.00 102.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diam.16mm conduit Ml 2.40 6.50 15.60 Electrician 1 1 25.50 25.50
Conductor (2x2.5mm2) Ml 4.70 12.00 56.40 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 174.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 174.00 Birr/ml B=Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of work item= A+B+C= 195.25 Birr/Pc
Overhead Cost:+
Profit Cost: 35% 68.34 Birr/Pc
Total Unit Cost : 263.59 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: Flush mounted two way switch Legrand type (for Office) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 244.69 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)

**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Flush mounted two way switch
(Legrand) pcs 1.00 88.00 88.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diam.16mm conduit Ml 2.40 6.50 15.60 Electrician 1 1 25.50 25.50
Conductor (2x2.5mm2) Ml 4.70 12.00 56.40 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 160.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 160.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of Work Item = A+B+C = 181.25 Birr/pc
Over Head :+
Profit Cost: 35% 63.44 Birr/pc
Total Unit Cost : 244.69 Birr/pc
Page 14
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.88 Pcs/hr
WORK ITEM: Flush mounted Dimmer switch Legrand type (for Office) EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pt RESULT: 802.80Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost

Flush Dimmer switch (Legrand) Pcs 1 500.00 500.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diam.16mm conduit Ml 2.40 6.50 15.60 Electrician 1 1 25.50 25.50
Conductor (2x2.5mm2) Ml 4.70 12.00 56.40 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 572.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 572.00 Birr/ml B=Manpower Unit Cost 18.40 Birr/hr C=Equipment Unit Cost 4.27
Direct Cost of work item= A+B+C= 594.67 Birr/Pc
Overhead Cost:+
Profit Cost: 35% 208.13 Birr/Pc
Total Unit Cost : 802.80 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.88 Pcs/hr
WORK ITEM: Flush mounted Tumbler switch Legrand type (for Office) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 546.30 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Flush mounted 16A/1Ph
Tumbler switch (Legrand) pcs 1.00 310.00 310.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diam.16mm conduit Ml 2.40 6.50 15.60 Electrician 1 1 25.50 25.50
Conductor (2x2.5mm2) Ml 4.70 12.00 56.40 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 382.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 382.00 Birr/pc B= Manpower Unit Cost 18.40 Birr/hr C=Equipment Unit Cost 4.27
Direct Cost of Work Item = A+B+C = 404.67 Birr/pc
Over Head :+
Profit Cost: 35% 141.63 Birr/pc
Total Unit Cost : 546.30 Birr/pc
Page 15
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: Intermediate switch Legrand type (for Office) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 263.59 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Intermediate switch (Legrand) pcs 1.00 102.00 102.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diam.16mm conduit Ml 2.40 6.50 15.60 Electrician 1 1 25.50 25.50
Conductor (2x2.5mm2) Ml 4.70 12.00 56.40 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 174.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 174.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of Work Item = A+B+C = 195.25 Birr/pc
Over Head :
Profit Cost: 35% 68.34 Birr/pc
Total Unit Cost : 263.59 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.44 Pcs/hr
WORK ITEM: Controlling Switch (Rotary Switch) Legrand type EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 1,524.91 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost

Rotary switch to select phase pcs 1.00 1,100.00 1,100.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
voltage with 3 power indicator Electrician 1 1 25.50 25.50
lamps (pilot lamps) Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,100.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,100.00 Birr/pc B= Manpower Unit Cost 24.00 Birr/hr C=Equipment Unit Cost 5.57
Direct Cost of Work Item = A+B+C = 1129.57 Birr/pc
Over Head :
Profit Cost: 35% 395.35 Birr/pc
Total Unit Cost : 1,524.91 Birr/pc
Page 16
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.44 Pcs/hr
WORK ITEM: Controlling Switch (Mercury Float Switch) Legrand type EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 593.41 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Floating mercury switch pcs 1.00 410.00 410.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 410.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 410.00 Birr/pc B= Manpower Unit Cost 24.00 Birr/hr C=Equipment Unit Cost 5.57
Direct Cost of Work Item = A+B+C = 439.57 Birr/pc
Over Head :
Profit Cost: 35% 153.85 Birr/pc
Total Unit Cost : 593.41 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: Flush mounting Single switch Legrand type (for Work Shop & Store) EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pt RESULT: 529.54Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Flush mounted single switch
(Legrand) Pcs 1 66.00 66.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diam.16mm conduit Ml 24.40 6.50 158.60 Electrician 1 1 25.50 25.50
Conductor (2x2.5mm2) Ml 12.20 12.00 146.40 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 371.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 371.00 Birr/ml B=Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of work item= A+B+C= 392.25 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 137.29 Birr/Pc
Total Unit Cost : 529.54 Birr/Pc
Page 17
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2 Pcs/hr
WORK ITEM: Flush mounted 2 gang single switch Legrand type (for Work Shop & Store) EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pt RESULT: 561.94Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Flush mounted 2 gang single
switch (Legrand) Pcs 1 90.00 90.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diam.16mm conduit Ml 24.40 6.50 158.60 Electrician 1 1 25.50 25.50
Conductor (2x2.5mm2) Ml 12.20 12.00 146.40 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 395.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 395.00 Birr/ml B=Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of work item= A+B+C= 416.25 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 145.69 Birr/Pc
Total Unit Cost : 561.94 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: Flush mounted 2 gang two way switch Legrand type(for Work Shop & Store) EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pt RESULT: 578.14Pc/Birr

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Flush mounted 2 gang two
way switch (Legrand) Pcs 1 102.00 102.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diam.16mm conduit Ml 24.40 6.50 158.60 Electrician 1 1 25.50 25.50
Conductor (2x2.5mm2) Ml 12.20 12.00 146.40 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 407.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 407.00 Birr/ml B=Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of work item= A+B+C= 428.25 Birr/Pc
Overhead Cost:+
Profit Cost: 35% 149.89 Birr/Pc
Total Unit Cost : 578.14 Birr/Pc
Page 18
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: Flush mounted two way switch Legrand type (for Work Shop & Store) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 559.24 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Flush mounted two way switch
(Legrand) pcs 1.00 88.00 88.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diam.16mm conduit Ml 24.40 6.50 158.60 Electrician 1 1 25.50 25.50
Conductor (2x2.5mm2) Ml 12.20 12.00 146.40 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 393.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 393.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of Work Item = A+B+C = 414.25 Birr/pc
Over Head :+
Profit Cost: 35% 144.99 Birr/pc
Total Unit Cost : 559.24 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: Intermediate switch Legrand type (for Work Shop & Store) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 578.14 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Intermediate switch (Legrand) pcs 1.00 102.00 102.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diam.16mm conduit Ml 24.40 6.50 158.60 Electrician 1 1 25.50 25.50
Conductor (2x2.5mm2) Ml 12.20 12.00 146.40 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 407.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 407.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of Work Item = A+B+C = 428.25 Birr/pc
Over Head :
Profit Cost: 35% 149.89 Birr/pc
Total Unit Cost : 578.14 Birr/pc
Page 19
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.5 Pcs/hr
WORK ITEM: Flush mounted Socket Outlet point Legrand type (For Office) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 451.80 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (3x2.5mm 2)
Ml 10.00 12.00 120.00 Forman 0 0.25 0.00 0.00 tools 2 1.00 4.00 8.00
Conduit (19mm) Ml 5.00 7.33 36.67 Electrician 1 1 25.50 25.50
Junction Box pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Socket outlet Legrand SALBEI
with ground Pcs 1.00 88.00 88.00 DL 1 1 9.00 9.00

Total (1:-01) 249.67 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 249.67 Birr/pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 334.67 Birr/pc
Over Head :
Profit Cost: 35% 117.13 Birr/pc
Total Unit Cost : 451.80 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Flush mounted Socket Outlet point Legrand type (For Work Shop and Store) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 938.25 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (3x2.5mm 2)
Ml 33.00 12.00 396.00 Forman 0 0.25 0.00 0.00 tools 2 1.00 4.00 8.00
Conduit (19mm) Ml 16.50 7.33 121.00 Electrician 1 1 25.50 25.50
Junction Box pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00

Socket outlet Legrand SALBEI Pcs 1.00 88.00 88.00 DL 1 1 9.00 9.00
with ground
Total (1:-01) 610.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 610.00 Birr/pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 695.00 Birr/pc
Over Head :
Profit Cost: 35% 243.25 Birr/pc
Total Unit Cost : 938.25 Birr/pc
Page 20
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Surface mounted Socket Outlet point (For Office) Legrand type EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 469.23 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (3x2.5mm2) Ml 10.00 12.00 120.00 Forman 0 0.25 0.00 0.00 tools 2 4.00 8.00
PVC Trunckate 16*16mm Ml 5.00 9.92 49.58 Electrician 1 1 25.50 25.50
Junction Box pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Socket outlet Legrand SALBEI
with ground Pcs 1.00 88.00 88.00 DL 1 1 9.00 9.00

Total (1:-01) 262.58 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 262.58 Birr/pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 347.58 Birr/pc
Over Head :
Profit Cost: 35% 121.65 Birr/pc
Total Unit Cost : 469.23 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Table mounted Socket Outlet point (For Office) Legrand type EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 542.25 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (3x2.5mm2) Ml 10.00 12.00 120.00 Forman 0 0.25 0.00 0.00 tools 2 1.00 4.00 8.00
Conduit (19mm) Ml 5.00 7.33 36.67 Electrician 1 1 25.50 25.50
Junction Box pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Socket outlet Legrand SALBEI
with ground Pcs 1.00 155.00 155.00 DL 1 1 9.00 9.00

Total (1:-01) 316.67 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 316.67 Birr/pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 401.67 Birr/pc
Over Head :
Profit Cost: 35% 140.58 Birr/pc
Total Unit Cost : 542.25 Birr/pc
Page 21
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Flush mounted Twin Socket Outlet point Legrand type EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 512.55 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (3x2.5mm 2)
Ml 10.00 12.00 120.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit (19mm) Ml 5.00 7.33 36.67 Electrician 1 1 25.50 25.50
Junction Box pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Socket outlet Legrand SALBEI
with ground Pcs 1.00 133.00 133.00 DL 1 1 9.00 9.00

Total (1:-01) 294.67 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 294.67 Birr/pc B= Manpower Unit Cost 69.00 Birr/pc C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 379.67 Birr/pc
Over Head :
Profit Cost: 35% 132.88 Birr/pc
Total Unit Cost : 512.55 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Flush mounted IndutrialSocket outlet 20A/1P Legrand type EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 625.28 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (3x2.5mm 2)
Ml 10.00 12.00 120.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit (19mm) Ml 5.00 7.33 36.67 Electrician 1 1 18.75 18.75
Junction Box pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Socket outlet Legrand 0527 02 Pcs 1.00 230.00 230.00 DL 1 1 9.00 9.00

Total (1:-01) 391.67 Total (1:02) 27.75 Total (1:03) 8.00

A= Materials Unit Cost 391.67 Birr/pc B= Manpower Unit Cost 55.50 Birr/pc C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 463.17 Birr/pc
Over Head :
Profit Cost: 35% 162.11 Birr/pc
Total Unit Cost : 625.28 Birr/pc
Page 22
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Industrial type socket outlet 16A/1P Legrand type EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 643.50 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (3x2.5mm2) Ml 10.00 12.00 120.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit (19mm) Ml 5.00 7.33 36.67 Electrician 1 1 25.50 25.50
Junction Box pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Socket outlet Legrand 0520 02 Pcs 1.00 230.00 230.00 DL 1 1 9.00 9.00

Total (1:-01) 391.67 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 391.67 Birr/pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 476.67 Birr/pc
Over Head : +
Profit Cost: 35% 166.83 Birr/pc
Total Unit Cost : 643.50 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Industrial type socket outlet 16A/3P Legrand type EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 1597.95 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (5x4mm 2)
Ml 10.00 78.20 782.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit (21mm) Ml 5.00 8.33 41.67 Electrician 1 1 25.50 25.50
Junction Box pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Socket outlet Legrand Suno Pcs 1.00 270.00 270.00 DL 1 1 9.00 9.00

Total (1:-01) 1,098.67 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,098.67 Birr/pc B= Manpower Unit Cost 69.00 Birr/pc C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 1183.67 Birr/pc
Over Head : +
Profit Cost: 35% 414.28 Birr/pc
Total Unit Cost : 1,597.95 Birr/pc
Page 23
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Industrial type socket outlet 16/3Ph 5 pin with interlocked isolator switch Legrand type EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 1678.95 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (5*4mm2) Ml 10.00 78.20 782.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit (21mm) Ml 5.00 8.33 41.67 Electrician 1 1 25.50 25.50
Junction Box pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Socket outlet Legrand Suno Pcs 1.00 330.00 330.00 DL 1 1 9.00 9.00

Total (1:-01) 1,158.67 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,158.67 Birr/pc B= Manpower Unit Cost 69.00 Birr/pc C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 1243.67 Birr/pc
Over Head : +
Profit Cost: 35% 435.28 Birr/pc
Total Unit Cost : 1,678.95 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.50 Pcs/hr
WORK ITEM: Industrial type socket outlet 32A/3P Legrand type EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 2212.65 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (5*6.0mm 2)
Ml 10.00 112.40 1,124.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit (32mm) Ml 5.00 15.00 75.00 Electrician 1 1 25.50 25.50
Junction Box pcs 1.00 5.00 5.00 Ass. Elec 0 1 0.00 0.00
Socket outlet Legrand Suno Pcs 1.00 350.00 350.00 DL 1 1 9.00 9.00

Total (1:-01) 1,554.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,554.00 Birr/pc B= Manpower Unit Cost 69.00 Birr/pc C=Equipment Unit Cost 16.00
Direct Cost of Work Item = A+B+C = 1639.00 Birr/pc
Over Head : +
Profit Cost: 35% 573.65 Birr/pc
Total Unit Cost : 2,212.65 Birr/pc
Page 24
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.81 Pcs/hr
WORK ITEM: Bell Call System EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 6,854.32 Birr/Pt

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Buzzer Pcs 1.00 220.00 220.00 Forman 0.00 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Indicator 18 digits with call
canceling master push button Pcs 1.00 4,355.00 4,355.00 Electrician 1.00 1.00 25.50 25.50
Transformer 220/12v/25vA Pcs 1.00 450.00 450.00 Chisler 0.00 0.50 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 5,025.00 Total ( 1:02 ) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 5,025.00 Birr/Pt B= Manpower Unit Cost 42.44 Birr/hr C=Equipment Unit Cost 9.84
Direct Cost of Work Item = A+B+C = 5,077.28 Birr/Pt
Over head cost : +
Profit Cost: 35% 1,777.05 Birr/Pt
Total Unit Cost : 6,854.32 Birr/Pt

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.81 Pcs/hr
WORK ITEM: Bell Call System EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 6,375.07 Birr/Pt

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Buzzer Pcs 1.00 220.00 220.00 Forman 0.00 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Indicator 16digits with call
canceling master push button Pcs 1.00 4,000.00 4,000.00 Electrician 1.00 1.00 25.50 25.50
Transformer 220/12v/25vA Pcs 1.00 450.00 450.00 Chisler 0.00 0.50 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 4,670.00 Total ( 1:02 ) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 4,670.00 Birr/Pt B= Manpower Unit Cost 42.44 Birr/hr C=Equipment Unit Cost 9.84
Direct Cost of Work Item = A+B+C = 4,722.28 Birr/Pt
Over head cost : +
Profit Cost: 35% 1,652.80 Birr/Pt
Total Unit Cost : 6,375.07 Birr/Pt
Page 25
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.81 Pcs/hr
WORK ITEM: Bell Call System EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 3,675.07 Birr/Pt
**
Indexed
Material Cost (1:01) Cost per Labour by Labour (1:02)
Hourly Hourly Type of Equipment Cost (1:03)
Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Buzzer Pcs 1.00 220.00 220.00 Forman 0.00 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Indicator 6 digits with call
canceling master push button Pcs 1.00 2,000.00 2,000.00 Electrician 1.00 1.00 25.50 25.50
Transformer 220/12v/25vA Pcs 1.00 450.00 450.00 Chisler 0.00 0.50 0.00 0.00
Plasterer 0.00 0.25 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 2,670.00 Total ( 1:02 ) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,670.00 Birr/Pt B= Manpower Unit Cost 42.44 Birr/hr C=Equipment Unit Cost 9.84
Direct Cost of Work Item = A+B+C = 2,722.28 Birr/Pt
Over head cost : +
Profit Cost: 35% 952.80 Birr/Pt
Total Unit Cost : 3,675.07 Birr/Pt

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.84 Pcs/hr
WORK ITEM: TV Outlet Point EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 336.25 Birr/Pt

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
diam.21mm conduit Ml 4.00 8.33 33.33 Forman 0.00 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
RG 6 coaxial cable for tv line Ml 8.00 20.00 160.00 Electrician 1.00 1.00 25.50 25.50
junction box Pcs 1.00 5.00 5.00 Chisler 0.00 0.50 0.00 0.00
Plasterer 0.00 0.25 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 198.33 Total ( 1:02 ) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 198.33 Birr/Pt B= Manpower Unit Cost 41.19 Birr/hr C=Equipment Unit Cost 9.55
Direct Cost of Work Item = A+B+C = 249.08 Birr/Pt
Over head cost : +
Profit Cost: 35% 87.18 Birr/Pt
Total Unit Cost : 336.25 Birr/Pt
Page 26
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.84 Pcs/hr
WORK ITEM: Telephone Outlet Point EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pt RESULT: 1431.10 Birr/Pt

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
TELE TERMINAL BOX 10
PAIR Pcs 1.00 980.00 980.00 Forman 0.00 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø19mm Ml 4.00 7.33 29.33 Electrician 1.00 1.00 25.50 25.50
Chisler 0.00 0.50 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 1,009.33 Total ( 1:02 ) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,009.33 Birr/Pt B= Manpower Unit Cost 41.19 Birr/hr C=Equipment Unit Cost 9.55
Direct Cost of Work Item = A+B+C = 1060.08 Birr/Pt
Over head cost : +
Profit Cost: 35% 371.03 Birr/Pt
Total Unit Cost : 1431.10 Birr/Pt

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: RJ 11 outlet type LEGRAND surface mounted EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 177.19 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1.00 110.00 110.00 Forman 0.00 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1.00 1.00 25.50 25.50
RJ11 outlets type Legrand suno
7740 38 + 7740 41 or approved
equivalent with 4 contacts Ass. Elec 0.00 1.00 0.00 0.00
(surface mounted) DL 1.00 1.00 9.00 9.00

Total (1:-01) 110.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 110.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of Work Item = A+B+C = 131.25 Birr/pc
Over Head : +
Profit Cost: 35% 45.94 Birr/pc
Total Unit Cost : 177.19 Birr/pc
Page 27
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: RJ 45 outlet type LEGRAND surface mounted EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 582.19 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1.00 410.00 410.00 Forman 0.00 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
RJ45 (Cat 6e) outlets type
LEGRAND suno 74213 cat 6e Electrician 1.00 1.00 25.50 25.50
or approved equivalent with 8 Ass. Elec 0.00 1.00 0.00 0.00
contacts (surface mounted) DL 1.00 1.00 9.00 9.00

Total (1:-01) 410.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 410.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of Work Item = A+B+C = 431.25 Birr/pc
Over Head : +
Profit Cost: 35% 150.94 Birr/pc
Total Unit Cost : 582.19 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: RJ 45 outlet type LEGRAND surface mounted EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 150.19 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1.00 90.00 90.00 Forman 0.00 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
category 6 UTP 4 pair data Electrician 1.00 1.00 25.50 25.50
cable with RJ45 termination (3 Ass. Elec 0.00 1.00 0.00 0.00
meter patch cord and all
necessary accessories. ) DL 1.00 1.00 9.00 9.00

Total (1:-01) 90.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 90.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of Work Item = A+B+C = 111.25 Birr/pc
Over Head : +
Profit Cost: 35% 38.94 Birr/pc
Total Unit Cost : 150.19 Birr/pc
Page 28
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: RJ 45 outlet type LEGRAND surface mounted EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 271.69 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1.00 180.00 180.00 Forman 0.00 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
2x category 6 UTP 4 pair data
cable with RJ45 termination (3 Electrician 1.00 1.00 25.50 25.50
meter patch cord and all Ass. Elec 0.00 1.00 0.00 0.00
necessary accessories. ) DL 1.00 1.00 9.00 9.00

Total (1:-01) 180.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 180.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of Work Item = A+B+C = 201.25 Birr/pc
Over Head : +
Profit Cost: 35% 70.44 Birr/pc
Total Unit Cost : 271.69 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: RJ 45 outlet type LEGRAND surface mounted EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 514.69 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1.00 360.00 360.00 Forman 0.00 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
4x category 6 UTP 4 pair data
cable with RJ45 termination (3 Electrician 1.00 1.00 25.50 25.50
meter patch cord and all Ass. Elec 0.00 1.00 0.00 0.00
necessary accessories. ) DL 1.00 1.00 9.00 9.00

Total (1:-01) 360.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 360.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of Work Item = A+B+C = 381.25 Birr/pc
Over Head : +
Profit Cost: 35% 133.44 Birr/pc
Total Unit Cost : 514.69 Birr/pc
Page 29
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.00 Pcs/hr
WORK ITEM: RJ 45 outlet type LEGRAND surface mounted EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 1000.69 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1.00 720.00 720.00 Forman 0.00 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
8x category 6 UTP 4 pair data Electrician 1.00 1.00 25.50 25.50
cable with RJ45 termination (3
Ass. Elec 0.00 1.00 0.00 0.00
meter patch cord and all
necessary accessories. ) DL 1.00 1.00 9.00 9.00

Total (1:-01) 720.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 720.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of Work Item = A+B+C = 741.25 Birr/pc
Over Head : +
Profit Cost: 35% 259.44 Birr/pc
Total Unit Cost : 1000.69 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1091.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1 780.00 780.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Mareco LUCE Iris 0750.101M Electrician 1 1 25.50 25.50
with 1*FBT 18W E27 lamp -65 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 780.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 780.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 808.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 282.92 Birr/Pc
Total Unit Cost : 1,091.25 Birr/Pc
Page 30
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 6,113.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Mareco LUCE Barcellona Opal Pcs 1 4,500.00 4,500.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
1600.152W with 1*SE 70W Electrician 1 1 25.50 25.50
E27 lamp IP-65 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 4,500.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 4,500.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 4528.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1584.92 Birr/Pc
Total Unit Cost : 6,113.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 6,518.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Mareco Type
LUCEofBarcellona
Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Eco1604.152W with 1*SE 70W 1 4,800.00 4,800.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
E27 lamp IP-65 Electrician 1 1 25.50 25.50
Pcs Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 4,800.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 4,800.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 4828.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1689.92 Birr/Pc
Total Unit Cost : 6,518.25 Birr/Pc
Page 31
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 3,615.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Mareco LUCE Sfera-Ura 400 Pcs 1 2,650.00 2,650.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
2071.400T with 1*ST-SE 70W Electrician 1 1 25.50 25.50
E27 lamp IP-65 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,650.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,650.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 2678.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 937.42 Birr/Pc
Total Unit Cost : 3,615.75 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 377.10 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips TMS 012 with 1xTL-D Pcs 1 251.00 251.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
18W Lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 251.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 251.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 279.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 97.77 Birr/Pc
Total Unit Cost : 377.10 Birr/Pc
Page 32
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1455.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips TCW 060 with 1xTL-D
36W Lamp Pcs 1 1,050.00 1,050.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,050.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,050.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1078.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 377.42 Birr/Pc
Total Unit Cost : 1,455.75 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,779.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips TCW 060 with 2xTL-D
36W Lamp Pcs 1 1,290.00 1,290.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,290.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,290.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1318.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 461.42 Birr/Pc
Total Unit Cost : 1,779.75 Birr/Pc
Page 33
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 682.20 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 51060.963 +TC-D 18W Pcs 1 477.00 477.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
LAMP Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 477.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 477.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 505.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 176.87 Birr/Pc
Total Unit Cost : 682.20 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,306.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1 1,680.00 1,680.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
UNOLUX UX-CLASSIC - Electrician 1 1 25.50 25.50 0.00
ASN.NC LA T8 Lamp - Ass. Elec 0 1 0.00 0.00 0.00
- DL 1 1 9.00 9.00 0.00
0.00
Total (1:-01) 1,680.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,680.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1708.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 597.92 Birr/Pc
Total Unit Cost : 2,306.25 Birr/Pc
Page 34
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,873.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
UNOLUX UX-CLASSIC Pcs 1 2,100.00 2,100.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
ASN.N PAR Lamp
- Electrician 1 1 25.50 25.50
- Ass. Elec 0 1 0.00 0.00
- DL 1 1 9.00 9.00

Total (1:-01) 2,100.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,100.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 2128.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 744.92 Birr/Pc
Total Unit Cost : 2,873.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,090.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
UNOLUX UX-TUBUS Pcs 1 1,520.00 1,520.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
291GRID - Electrician 1 1 25.50 25.50
- Ass. Elec 0 1 0.00 0.00
- DL 1 1 9.00 9.00

Total (1:-01) 1,520.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,520.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1548.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 541.92 Birr/Pc
Total Unit Cost : 2,090.25 Birr/Pc
Page 35
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,090.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 90756.842 WITH 1XTC-T Pcs 1 1,520.00 1,520.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
18W TUBUS 291
- Electrician 1 1 25.50 25.50
- Ass. Elec 0 1 0.00 0.00
- DL 1 1 9.00 9.00

Total (1:-01) 1,520.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,520.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1548.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 541.92 Birr/Pc
Total Unit Cost : 2,090.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,989.00 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1 1,445.00 1,445.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
RZB 311070.842 WITH 1XTC-
T 18W Lamp. - Electrician 1 1 25.50 25.50
- Ass. Elec 0 1 0.00 0.00
- DL 1 1 9.00 9.00

Total (1:-01) 1,445.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,445.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1473.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 515.67 Birr/Pc
Total Unit Cost : 1,989.00 Birr/Pc
Page 36
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,989.00 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB23643.002 with 1*E27 Pcs 1 1,445.00 1,445.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
60W IP-40 LAMP - Electrician 1 1 25.50 25.50
- Ass. Elec 0 1 0.00 0.00
- DL 1 1 9.00 9.00

Total (1:-01) 1,445.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,445.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1473.33 Birr/Pc
Overhead Cost +:
Profit Cost: 35% 515.67 Birr/Pc
Total Unit Cost : 1,989.00 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1989.00 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB211005.with 1*E27 60W
IP-44 Lamp Pcs 1 1,445.00 1,445.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
- Electrician 1 1 25.50 25.50
- Ass. Elec 0 1 0.00 0.00
- DL 1 1 9.00 9.00

Total (1:-01) 1,445.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,445.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1473.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 515.67 Birr/Pc
Total Unit Cost : 1,989.00 Birr/Pc
Page 37
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,658.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 211006 WITH 1*TC-T Pcs 1 1,200.00 1,200.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
18W Lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,200.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,200.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1228.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 429.92 Birr/Pc
Total Unit Cost : 1,658.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,631.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
MASSIVE 34041/11/10 1x Pcs 1 1,180.00 1,180.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
GU10 | max. 35W Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,180.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,180.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1208.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 422.92 Birr/Pc
Total Unit Cost : 1,631.25 Birr/Pc
Page 38
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,813.50 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1 1,315.00 1,315.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
RZB 211015 WITH 1*TC-T
Electrician 1 1 25.50 25.50
18W Lamp
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,315.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,315.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1343.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 470.17 Birr/Pc
Total Unit Cost : 1,813.50 Birr/Pc
Page 39
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 956.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB50100.002 WITH 1*TC-D Pcs 1 680.00 680.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
13W Lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 680.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 680.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 708.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 247.92 Birr/Pc
Total Unit Cost : 956.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 969.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 22143.913 WITH 1*TC-D Pcs 1 690.00 690.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
11W Lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 690.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 690.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 718.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 251.42 Birr/Pc
Total Unit Cost : 969.75 Birr/Pc
Page 40
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 915.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 45135.002 WITH Pcs 1 650.00 650.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
SOCKET & SWITCH 1*TC-26 Electrician 1 1 25.50 25.50
15W OMS MIRROR LIGHT Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 650.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 650.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 678.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 237.42 Birr/Pc
Total Unit Cost : 915.75 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 652.50 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 91152.002 WITH Pcs 1 455.00 455.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
1*QPAR20 60W LAMP IP-20 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 455.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 455.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 483.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 169.17 Birr/Pc
Total Unit Cost : 652.50 Birr/Pc
Page 41
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,253.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
PHILIPS TCW 012/1X36W Pcs 1 900.00 900.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 900.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 900.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 928.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 324.92 Birr/Pc
Total Unit Cost : 1,253.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Bahir Dar LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,253.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
PHILIPS TMW 012/1X36W Pcs 1 900.00 900.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 900.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 900.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 928.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 324.92 Birr/Pc
Total Unit Cost : 1,253.25 Birr/Pc
Page 42
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 3,966.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
PENDENT LIGHT MD 8180/3 Pcs 1 2,910.00 2,910.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,910.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,910.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 2938.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1028.42 Birr/Pc
Total Unit Cost : 3,966.75 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,039.95 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
CANDELUX C12-9 HALF Pcs 1 742.00 742.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 742.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 742.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 770.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 269.62 Birr/Pc
Total Unit Cost : 1,039.95 Birr/Pc
Page 43
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,654.20 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Mareco LUCE SFERA Pcs 1 1,197.00 1,197.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
1080.201B with 1*FTB 20W Electrician 1 1 25.50 25.50
E27 lamp. Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,197.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,197.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1225.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 428.87 Birr/Pc
Total Unit Cost : 1,654.20 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 3,757.50 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
PELSAN EXIT Pcs 1 2,755.00 2,755.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,755.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,755.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 2783.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 974.17 Birr/Pc
Total Unit Cost : 3,757.50 Birr/Pc
Page 44
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 821.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 10120.922.79 with 1*TC- Pcs 1 580.00 580.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
DEL 13W IP-20 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 580.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 580.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 608.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 212.92 Birr/Pc
Total Unit Cost : 821.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 5,708.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
PHILIPS SGS 102 SON-T Pcs 1 4,200.00 4,200.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
150W Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 4,200.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 4,200.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 4228.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1479.92 Birr/Pc
Total Unit Cost : 5,708.25 Birr/Pc
Page 45
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 3,980.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
PHILIPS SGS 101 SON-T 70W Pcs 1 2,920.00 2,920.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,920.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,920.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 2948.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1031.92 Birr/Pc
Total Unit Cost : 3,980.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 510.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips TMS 012 with 1xTL-D Pcs 1 350.00 350.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
36W Lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 350.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 350.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 378.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 132.42 Birr/Pc
Total Unit Cost : 510.75 Birr/Pc
Page 46
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 780.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips TMS 012/236 IMK Pcs 1 550.00 550.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
with 2xTL-D 36W Lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 550.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 550.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 578.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 202.42 Birr/Pc
Total Unit Cost : 780.75 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,239.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips TCW 196 with 1xTL-D Pcs 1 890.00 890.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
36W Lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 890.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 890.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 918.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 321.42 Birr/Pc
Total Unit Cost : 1,239.75 Birr/Pc
Page 47
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,049.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips TCW196 with 2xTL-D Pcs 1 1,490.00 1,490.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
36W Lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,490.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,490.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1518.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 531.42 Birr/Pc
Total Unit Cost : 2,049.75 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,063.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips TCS 600 with 1xTL-S Pcs 1 1,500.00 1,500.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
36W Lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,500.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,500.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1528.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 534.92 Birr/Pc
Total Unit Cost : 2,063.25 Birr/Pc
Page 48
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,738.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips TMS 600 with 2xTL-S Pcs 1 2,000.00 2,000.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
36W Lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,000.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,000.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 2028.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 709.92 Birr/Pc
Total Unit Cost : 2,738.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,670.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips TCS 098/136 2xTL-D Pcs 1 1,950.00 1,950.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
36w lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,950.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,950.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1978.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 692.42 Birr/Pc
Total Unit Cost : 2,670.75 Birr/Pc
Page 49
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,995.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips TCS 098/136 1xTL-D Pcs 1 1,450.00 1,450.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
36w lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,450.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,450.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1478.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 517.42 Birr/Pc
Total Unit Cost : 1,995.75 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,253.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pelsan E.D.fiberglas bant + Pcs 1 900.00 900.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
1xTL-D36w Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 900.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 900.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 928.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 324.92 Birr/Pc
Total Unit Cost : 1,253.25 Birr/Pc
Page 50
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,590.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pelsan E.D.fiberglas bant + Pcs 1 1,150.00 1,150.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
2xTL-D36w Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,150.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,150.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1178.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 412.42 Birr/Pc
Total Unit Cost : 1,590.75 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 483.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Incadscent Celling Glob type Pcs 1 330.00 330.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
RZB 55154.00X with 1X25W Electrician 1 1 25.50 25.50
red dark room lamp Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 330.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 330.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 358.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 125.42 Birr/Pc
Total Unit Cost : 483.75 Birr/Pc
Page 51
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,253.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 22141.923 with 1*TC-D Pcs 1 900.00 900.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
13W lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 900.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 900.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 928.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 324.92 Birr/Pc
Total Unit Cost : 1,253.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 483.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 56220.003 with 1*TC-D Pcs 1 330.00 330.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
18W lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 330.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 330.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 358.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 125.42 Birr/Pc
Total Unit Cost : 483.75 Birr/Pc
Page 52
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,523.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 58030.962 with 1*TC-D Pcs 1 1,100.00 1,100.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
18w lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,100.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,100.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1128.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 394.92 Birr/Pc
Total Unit Cost : 1,523.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 983.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Massive 32005/31/10 with Pcs 1 700.00 700.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
E27/max 60w Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 700.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 700.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 728.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 254.92 Birr/Pc
Total Unit Cost : 983.25 Birr/Pc
Page 53
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,009.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Gecem GCP 236L with 2xTL-D Pcs 1 1,460.00 1,460.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
36w Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,460.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,460.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1488.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 520.92 Birr/Pc
Total Unit Cost : 2,009.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,725.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips TCS 098/218/ 2xTL-D Pcs 1 1,250.00 1,250.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
18w lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,250.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,250.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1278.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 447.42 Birr/Pc
Total Unit Cost : 1,725.75 Birr/Pc
Page 54
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 3,818.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Legrand 400413 with 8w + 3hrs Pcs 1 2,800.00 2,800.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
emergency kit. Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,800.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,800.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 2828.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 989.92 Birr/Pc
Total Unit Cost : 3,818.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 3,413.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Disano Ghost 323133-00 with Pcs 1 2,500.00 2,500.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
FLC 70T/lamp or approved Electrician 1 1 25.50 25.50
equivalent. Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,500.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,500.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 2528.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 884.92 Birr/Pc
Total Unit Cost : 3,413.25 Birr/Pc
Page 55
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,185.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Disano 1546 Globo 427236-00 Pcs 1 850.00 850.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
with FLC 2x9 S lamp. Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 850.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 850.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 878.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 307.42 Birr/Pc
Total Unit Cost : 1,185.75 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 3,953.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Massive 15254/45/10 with Pcs 1 2,900.00 2,900.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
3xE27 max 100w Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,900.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,900.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 2928.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1024.92 Birr/Pc
Total Unit Cost : 3,953.25 Birr/Pc
Page 56
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 3,548.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Fumagali G40.121 Pcs 1 2,600.00 2,600.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
M28.000.M80/max 80w Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,600.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,600.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 2628.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 919.92 Birr/Pc
Total Unit Cost : 3,548.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 3,413.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips HGS 101 with SON-H Pcs 1 2,500.00 2,500.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
250w lamp. Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,500.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,500.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 2528.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 884.92 Birr/Pc
Total Unit Cost : 3,413.25 Birr/Pc
Page 57
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 6,113.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Philips post top lantern PMMA Pcs 1 4,500.00 4,500.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø40cm with SON-T 80w lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 4,500.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 4,500.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 4528.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1584.92 Birr/Pc
Total Unit Cost : 6,113.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 34,530.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Feal Luce light master Pcs 1 25,550.00 25,550.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
1000sq.mm wide with MD/Jm Electrician 1 1 25.50 25.50
1000watt lamp. Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 25,550.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 25,550.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 25578.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 8952.42 Birr/Pc
Total Unit Cost : 34,530.75 Birr/Pc
Page 58
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 7,598.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Feal Luce JET 5 MT 400watt Pcs 1 5,600.00 5,600.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
with MT/JM 400watt pole Electrician 1 1 25.50 25.50
mounted type. Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 5,600.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 5,600.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 5628.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1969.92 Birr/Pc
Total Unit Cost : 7,598.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 5,843.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Feal Luce MIRA PX 40470 CLI Pcs 1 4,300.00 4,300.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
with SAP 250watt, pole Electrician 1 1 25.50 25.50
mounted type. Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 4,300.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 4,300.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 4328.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1514.92 Birr/Pc
Total Unit Cost : 5,843.25 Birr/Pc
Page 59
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,725.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
DISANO 920 Hydro T8 + FL
2*36watt lamp Pcs 1 1,250.00 1,250.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,250.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,250.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1278.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 447.42 Birr/Pc
Total Unit Cost : 1,725.75 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 6,653.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
DISANO 1601 Floor with Pcs 1 4,900.00 4,900.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
diffuser, level finish with SAP Electrician 1 1 25.50 25.50
250watt lamp IP- 67 Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 4,900.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 4,900.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 4928.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1724.92 Birr/Pc
Total Unit Cost : 6,653.25 Birr/Pc
Page 60
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 10,568.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
LED pool light with 12volt, Pcs 1 7,800.00 7,800.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
25watt ratting and IP- 68 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 7,800.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 7,800.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 7828.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 2739.92 Birr/Pc
Total Unit Cost : 10,568.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,361.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB Perla 58131.922 with TC- Pcs 1 980.00 980.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
D 18W lamp Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 980.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 980.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1008.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 352.92 Birr/Pc
Total Unit Cost : 1,361.25 Birr/Pc
Page 61
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,725.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Modus KV 1*36W lamp Pcs 1 1,250.00 1,250.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
(prismatic) Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,250.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,250.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1278.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 447.42 Birr/Pc
Total Unit Cost : 1,725.75 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,333.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Modus LL4*18 ALB ALMATE Pcs 1 1,700.00 1,700.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
(louvered) Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,700.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,700.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1728.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 604.92 Birr/Pc
Total Unit Cost : 2,333.25 Birr/Pc
Page 62
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,091.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB linear 401000.912.79 with Pcs 1 780.00 780.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
TC-EL 11W lamp Electrician 1 1 25.50 25.50 0.00
Ass. Elec 0 1 0.00 0.00 0.00
DL 1 1 9.00 9.00 0.00
0.00
Total (1:-01) 780.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 780.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 808.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 282.92 Birr/Pc
Total Unit Cost : 1,091.25 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,063.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Modus KV 2*36W ALB Pcs 1 1,500.00 1,500.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
ALMATE (prismatic) Electrician 1 1 25.50 25.50 0.00
Ass. Elec 0 1 0.00 0.00 0.00
DL 1 1 9.00 9.00 0.00
0.00
Total (1:-01) 1,500.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,500.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1528.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 534.92 Birr/Pc
Total Unit Cost : 2,063.25 Birr/Pc
Page 63
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,455.75 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
MASSIVE 33012/17/10 with 2 Pcs 1 1,050.00 1,050.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
x GU10 max 50W LAMP Electrician 1 1 25.50 25.50 0.00
Ass. Elec 0 1 0.00 0.00 0.00
DL 1 1 9.00 9.00 0.00
0.00
Total (1:-01) 1,050.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,050.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1078.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 377.42 Birr/Pc
Total Unit Cost : 1,455.75 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,091.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
MASSIVE 32005/31/10 Pcs 1 780.00 780.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
withE27/max 60W LAMP Electrician 1 1 25.50 25.50 0.00
Ass. Elec 0 1 0.00 0.00 0.00
DL 1 1 9.00 9.00 0.00
0.00
Total (1:-01) 780.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 780.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 808.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 282.92 Birr/Pc
Total Unit Cost : 1,091.25 Birr/Pc
Page 64
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,523.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
PHILIPS Pentura mini TCH128 Pcs 1 1,100.00 1,100.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
with 1 x 28W Lamp. Electrician 1 1 25.50 25.50 0.00
Ass. Elec 0 1 0.00 0.00 0.00
DL 1 1 9.00 9.00 0.00
0.00
Total (1:-01) 1,100.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,100.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.33
Direct Cost of work item= A+B+C= 1128.33 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 394.92 Birr/Pc
Total Unit Cost : 1,523.25 Birr/Pc
Page 65
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.84 Pcs/hr
WORK ITEM: Axial Ceiling, false ceiling (Reccessed) and window Fan EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,351.01 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
O.ERRE Axial fan Pcs 1 950.00 950.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
STANDARD 12 with an Electrician 1 1 25.50 25.50
ordering code of 0015800 max Ass. Elec 0 1 0.00 0.00
dia of Hole Ø 120mm at 50Hz
220/240V, max flow rate (m³/h) DL 1 1 9.00 9.00
125, max. press. 29Pa and max.
power demand of 13W.

Total (1:-01) 950.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 950.00 Birr/ml B=Manpower Unit Cost 41.19 Birr/hr C=Equipment Unit Cost 9.55
Direct Cost of work item= A+B+C= 1000.75 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 350.26 Birr/Pc
Total Unit Cost : 1,351.01 Birr/Pc
Page 66
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.84 Pcs/hr
WORK ITEM: Axial Ceiling, false ceiling (Reccessed) and window Fan EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,972.01 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
O.ERRE Axial fan Pcs 1 1,410.00 1,410.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
STANDARD 15 with an Electrician 1 1 25.50 25.50
ordering code of 0016100 max Ass. Elec 0 1 0.00 0.00
dia of Hole Ø 150mm at 50Hz
220/240V, max flow rate (m³/h) DL 1 1 9.00 9.00
230 max. press. 41Pa and max.
power demand of 30W.

Total (1:-01) 1,410.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,410.00 Birr/ml B=Manpower Unit Cost 41.19 Birr/hr C=Equipment Unit Cost 9.55
Direct Cost of work item= A+B+C= 1460.75 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 511.26 Birr/Pc
Total Unit Cost : 1,972.01 Birr/Pc
Page 67
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.84 Pcs/hr
WORK ITEM: Axial Ceiling, false ceiling (Reccessed) and window Fan EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 5,401.01 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
O.ERRE Axial fan VENTILOR Pcs 1 3,950.00 3,950.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 4.00 8.00
20/8 AR with an ordering code Electrician 1 1 25.50 25.50 0.00
of 0019000 max dia of Hole Ø Ass. Elec 0 1 0.00 0.00 0.00
225-235mm at 50Hz 220/240V,
max flow rate (m³/h) 450 max. DL 1 1 9.00 9.00 0.00
press. 118Pa and max. power
demand of 50W.

0.00
Total (1:-01) 3,950.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 3,950.00 Birr/ml B=Manpower Unit Cost 41.19 Birr/hr C=Equipment Unit Cost 9.55
Direct Cost of work item= A+B+C= 4000.75 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1400.26 Birr/Pc
Total Unit Cost : 5,401.01 Birr/Pc
Page 68
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.84 Pcs/hr
WORK ITEM: Axial Ceiling, false ceiling (Reccessed) and window Fan EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 6,751.01 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
O.ERRE Axial fan VENTILOR Pcs 1 4,950.00 4,950.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
25/10 AR with an ordering code Electrician 1 1 25.50 25.50
of 0019200 max dia of Hole Ass. Elec 0 1 0.00 0.00
Ø275-285mm at 50Hz
220/240V, max flow rate (m³/h) DL 1 1 9.00 9.00
750, max. press. 59Pa and max.
power demand of 60W.

Total (1:-01) 4,950.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 4,950.00 Birr/ml B=Manpower Unit Cost 41.19 Birr/hr C=Equipment Unit Cost 9.55
Direct Cost of work item= A+B+C= 5000.75 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1750.26 Birr/Pc
Total Unit Cost : 6,751.01 Birr/Pc
Page 69
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.84 Pcs/hr
WORK ITEM: Axial Ceiling, false ceiling (Reccessed) and window Fan EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 5,738.51 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
O.ERRE Axial fan DIVERSO Pcs 1 4,200.00 4,200.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
IN 240 with an ordering code of Electrician 1 1 25.50 25.50
0083200 max dia of Hole Ass. Elec 0 1 0.00 0.00
Ø100mm at 50Hz 220/240V,
max flow rate (m³/h) 270, max. DL 1 1 9.00 9.00
press. 442Pa and max. power
demand of 80W.

Total (1:-01) 4,200.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 4,200.00 Birr/ml B=Manpower Unit Cost 41.19 Birr/hr C=Equipment Unit Cost 9.55
Direct Cost of work item= A+B+C= 4250.75 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1487.76 Birr/Pc
Total Unit Cost : 5,738.51 Birr/Pc
Page 70
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.84 Pcs/hr
WORK ITEM: Axial Ceiling, false ceiling (Reccessed) and window Fan EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 6,953.51 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
O.ERRE Axial fan AXIA MD Pcs 1 5,100.00 5,100.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
30 4M with an ordering code of Electrician 1 1 25.50 25.50
0073003 IP-55 with single Ass. Elec 0 1 0.00 0.00
phase motor/4Pole RPM 1400 at
50/60Hz 230V, max flow rate DL 1 1 9.00 9.00
(m³/h) 1800, max. press. 135Pa
and max. power demand of
100W.

Total (1:-01) 5,100.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 5,100.00 Birr/ml B=Manpower Unit Cost 41.19 Birr/hr C=Equipment Unit Cost 9.55
Direct Cost of work item= A+B+C= 5150.75 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1802.76 Birr/Pc
Total Unit Cost : 6,953.51 Birr/Pc
Page 71
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.84 Pcs/hr
WORK ITEM: Axial Ceiling, false ceiling (Reccessed) and window Fan EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 8,303.51 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
O.ERRE Axial fan AXIA MD Pcs 1 6,100.00 6,100.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
40 4M with an ordering code of Electrician 1 1 25.50 25.50
0073007 IP55 with single phase Ass. Elec 0 1 0.00 0.00
motor/4Pole RPM 1350 at
50/60Hz 230V, max flow rate DL 1 1 9.00 9.00
(m³/h) 3500, max. press. 155Pa
and max. power demand of
170W.

Total (1:-01) 6,100.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 6,100.00 Birr/ml B=Manpower Unit Cost 41.19 Birr/hr C=Equipment Unit Cost 9.55
Direct Cost of work item= A+B+C= 6150.75 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 2152.76 Birr/Pc
Total Unit Cost : 8,303.51 Birr/Pc
Page 72
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.84 Pcs/hr
WORK ITEM: Axial Ceiling, false ceiling (Reccessed) and window Fan EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 3,848.51 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
O.ERRE Ceiling Fan OASIS Pcs 1 2,800.00 2,800.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
3KR 140 with an ordering code Electrician 1 1 25.50 25.50
of 0024700 max dia of blades Ø Ass. Elec 0 1 0.00 0.00
140mm at 50Hz 220/240V, max
flow rate (m³/h) 16,000 and DL 1 1 9.00 9.00
max. power demand of 60W.

Total (1:-01) 2,800.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 2,800.00 Birr/ml B=Manpower Unit Cost 41.19 Birr/hr C=Equipment Unit Cost 9.55
Direct Cost of work item= A+B+C= 2850.75 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 997.76 Birr/Pc
Total Unit Cost : 3,848.51 Birr/Pc
Page 73
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 28.75 Ml/hr
WORK ITEM: 1x1.5 S bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 7.67 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x1.5 S Bare copper bonding
conductor Ml 1.05 4.00 4.20 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
Electrician 1.00 1.00 25.50 25.50
Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 4.20 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 4.20 Birr/ml B=Manpower Unit Cost 1.20 Birr/hr C=Equipment Unit Cost 0.28
Direct Cost of work item= A+B+C= 5.68 Birr/Ml
Overhead Cost: +
Profit Cost: 35% 1.99 Birr/Ml
Total Unit Cost : 7.67 Birr/Ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 28.75 Ml/hr
WORK ITEM: 1x2.5 S bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 10.65 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x2.5 S Bare copper bonding Ml 1.05 6.10 6.41 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
conductor Electrician 1.00 1.00 25.50 25.50
Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 6.41 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 6.41 Birr/ml B=Manpower Unit Cost 1.20 Birr/hr C=Equipment Unit Cost 0.28
Direct Cost of work item= A+B+C= 7.89 Birr/Ml
Overhead Cost: +
Profit Cost: 35% 2.76 Birr/Ml
Total Unit Cost : 10.65 Birr/Ml
Page 74
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 28.75 Ml/hr
WORK ITEM: 1x1.5 F bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 8.23 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x1.5 F Bare copper bonding
conductor Ml 1.05 4.40 4.62 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
Electrician 1.00 1.00 25.50 25.50
Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 4.62 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 4.62 Birr/ml B=Manpower Unit Cost 1.20 Birr/hr C=Equipment Unit Cost 0.28
Direct Cost of work item= A+B+C= 6.10 Birr/Ml
Overhead Cost: +
Profit Cost: 35% 2.13 Birr/Ml
Total Unit Cost : 8.23 Birr/Ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 28.75 Ml/hr
WORK ITEM: 1x2.5 F bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 11.50 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x2.5 F Bare copper bonding Ml 1.05 6.70 7.04 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
conductor Electrician 1.00 1.00 25.50 25.50
Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 7.04 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 7.04 Birr/ml B=Manpower Unit Cost 1.20 Birr/hr C=Equipment Unit Cost 0.28
Direct Cost of work item= A+B+C= 8.52 Birr/Ml
Overhead Cost: +
Profit Cost: 35% 2.98 Birr/Ml
Total Unit Cost : 11.50 Birr/Ml
Page 75
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 26.25 Ml/hr
WORK ITEM: 1x4 S bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 22.95 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x4 S Bare copper bonding
conductor Ml 1.05 14.65 15.38 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
Electrician 1.00 1.00 25.50 25.50
Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 15.38 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 15.38 Birr/ml B=Manpower Unit Cost 1.31 Birr/hr C=Equipment Unit Cost 0.30
Direct Cost of work item= A+B+C= 17.00 Birr/Ml
Overhead Cost: +
Profit Cost: 35% 5.95 Birr/Ml
Total Unit Cost : 22.95 Birr/Ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 26.25 Ml/hr
WORK ITEM: 1x4mm² bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 22.95 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x4mm. Sq. Bare copper Ml 1.05 14.65 15.38 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
bonding condacter Electrician 1.00 1.00 25.50 25.50
Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 15.38 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 15.38 Birr/ml B=Manpower Unit Cost 1.31 Birr/hr C=Equipment Unit Cost 0.30
Direct Cost of work item= A+B+C= 17.00 Birr/Ml
Overhead Cost: +
Profit Cost: 35% 5.95 Birr/Ml
Total Unit Cost : 22.95 Birr/Ml
Page 76
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 21.25 Ml/hr
WORK ITEM: 1x6mm2 bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 35.30 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x6mm. Sq. Bare copper
bonding condacter Ml 1.05 23.00 24.15 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
Electrician 1.00 1.00 25.50 25.50
Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 24.15 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 24.15 Birr/ml B=Manpower Unit Cost 1.62 Birr/hr C=Equipment Unit Cost 0.38
Direct Cost of work item= A+B+C= 26.15 Birr/Ml
Overhead Cost: +
Profit Cost: 35% 9.15 Birr/Ml
Total Unit Cost : 35.30 Birr/Ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 21.25 Ml/hr
WORK ITEM: 1x10mm2 bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 45.23 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x10mm. Sq. Bare copper Ml 1.05 30.00 31.50 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
bonding condacter Electrician 1.00 1.00 25.50 25.50
Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 31.50 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 31.50 Birr/ml B=Manpower Unit Cost 1.62 Birr/hr C=Equipment Unit Cost 0.38
Direct Cost of work item= A+B+C= 33.50 Birr/Ml
Overhead Cost: +
Profit Cost: 35% 11.73 Birr/Ml
Total Unit Cost : 45.23 Birr/Ml
Page 77
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 16.875 Ml/hr
WORK ITEM: 1x16mm2 bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 76.61 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Ml 1.05 51.65 54.23 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
1x16mm. Sq. Bare copper Electrician 1.00 1.00 25.50 25.50
bonding condacter Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 54.23 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 54.23 Birr/Pc B=Manpower Unit Cost 2.04 Birr/hr C=Equipment Unit Cost 0.47
Direct Cost of work item= A+B+C= 56.75 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 19.86 Birr/Pc
Total Unit Cost : 76.61 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 13.75 Ml/hr
WORK ITEM: 1x25mm2 bare copper conductor EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ML RESULT: 100.91 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x25mm. Sq. Bare copper Ml 1.05 68.25 71.66 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
bonding condacter Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 71.66 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 71.66 Birr/pc B= Manpower Unit Cost 2.51 Birr/hr C=Equipment Unit Cost 0.58
Direct Cost of Work Item = A+B+C = 74.75 Birr/pc
Over Head : +
Profit Cost: 35% 26.16 Birr/pc
Total Unit Cost : 100.91 Birr/pc
Page 78
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 13.125 Ml/hr
WORK ITEM: 1x35mm2 bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 139.03 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Ml 1.05 95.00 99.75 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
1x35mm. Sq. Bare copper Electrician 1.00 1.00 25.50 25.50
bonding condacter Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 99.75 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 99.75 Birr/Pc B=Manpower Unit Cost 2.63 Birr/hr C=Equipment Unit Cost 0.61
Direct Cost of work item= A+B+C= 102.99 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 36.05 Birr/Pc
Total Unit Cost : 139.03 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 8.75 Ml/hr
WORK ITEM: 1x50mm2 bare copper conductor EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ML RESULT: 203.31 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x50mm. Sq. Bare copper Ml 1.05 138.80 145.74 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
bonding condacter Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 145.74 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 145.74 Birr/pc B= Manpower Unit Cost 3.94 Birr/hr C=Equipment Unit Cost 0.91
Direct Cost of Work Item = A+B+C = 150.60 Birr/pc
Over Head : +
Profit Cost: 35% 52.71 Birr/pc
Total Unit Cost : 203.31 Birr/pc
Page 79
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 7.625 Ml/hr
WORK ITEM: 1x70mm2 bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 284.50 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Ml 1.05 195.40 205.17 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
1x70mm. Sq. Bare copper Electrician 1.00 1.00 25.50 25.50
bonding condacter Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 205.17 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 205.17 Birr/Pc B=Manpower Unit Cost 4.52 Birr/hr C=Equipment Unit Cost 1.05
Direct Cost of work item= A+B+C= 210.74 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 73.76 Birr/Pc
Total Unit Cost : 284.50 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.25 Ml/hr
WORK ITEM: 1x120mm2 bare copper conductor EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ML RESULT: 506.35 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x120mm. Sq. Bare copper Ml 1.05 349.50 366.98 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
bonding condacter Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 366.98 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 366.98 Birr/pc B= Manpower Unit Cost 6.57 Birr/hr C=Equipment Unit Cost 1.52
Direct Cost of Work Item = A+B+C = 375.08 Birr/pc
Over Head : +
Profit Cost: 35% 131.28 Birr/pc
Total Unit Cost : 506.35 Birr/pc
Page 80
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.25 Ml/hr
WORK ITEM: 1x150mm2 bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 581.20 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Ml 1.05 402.30 422.42 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
1x150mm. Sq. Bare copper Electrician 1.00 1.00 25.50 25.50
bonding condacter Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 422.42 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 422.42 Birr/Pc B=Manpower Unit Cost 6.57 Birr/hr C=Equipment Unit Cost 1.52
Direct Cost of work item= A+B+C= 430.52 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 150.68 Birr/Pc
Total Unit Cost : 581.20 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 4.25 Ml/hr
WORK ITEM: 1x185mm2 bare copper conductor EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ML RESULT: 749.18 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x185mm. Sq. Bare copper Ml 1.05 519.00 544.95 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
bonding condacter Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 544.95 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 544.95 Birr/pc B= Manpower Unit Cost 8.12 Birr/hr C=Equipment Unit Cost 1.88
Direct Cost of Work Item = A+B+C = 554.95 Birr/pc
Over Head : +
Profit Cost: 35% 194.23 Birr/pc
Total Unit Cost : 749.18 Birr/pc
Page 81
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 3.38 Ml/hr
WORK ITEM: 1x240mm2 bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 1001.74 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Ml 1.05 694.70 729.44 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
1x240mm. Sq. Bare copper Electrician 1.00 1.00 25.50 25.50
bonding condacter Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 729.44 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 729.44 Birr/Pc B=Manpower Unit Cost 10.22 Birr/hr C=Equipment Unit Cost 2.37
Direct Cost of work item= A+B+C= 742.03 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 259.71 Birr/Pc
Total Unit Cost : 1001.74 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 3.38 Ml/hr
WORK ITEM: 1x300mm2 bare copper conductor EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 ML RESULT: 1,232.80 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x300mm. Sq. Bare copper Ml 1.05 857.70 900.59 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
bonding condacter Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 900.59 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 900.59 Birr/pc B= Manpower Unit Cost 10.22 Birr/hr C=Equipment Unit Cost 2.37
Direct Cost of Work Item = A+B+C = 913.18 Birr/pc
Over Head : +
Profit Cost: 35% 319.61 Birr/pc
Total Unit Cost : 1,232.80 Birr/pc
Page 82
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 7.63 Ml/hr
WORK ITEM: 1x95mm2 bare copper conductor EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 384.78 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Ml 1.05 266.14 279.45 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 4.00 8.00
1x95mm. Sq. Bare copper Electrician 1.00 1.00 25.50 25.50
bonding condacter Ass. Elec 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 279.45 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 279.45 Birr/Pc B=Manpower Unit Cost 4.52 Birr/hr C=Equipment Unit Cost 1.05
Direct Cost of work item= A+B+C= 285.02 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 99.76 Birr/Pc
Total Unit Cost : 384.78 Birr/Pc
Page 83
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.48 Pcs/hr
WORK ITEM: Ø16mm diam. 2400 mm Long Copper Rod EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 1,322.29 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Diameter 16mm & 2400mm Pcs 1.00 890.00 890.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
long copper earthing rod. Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 890.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 890.00 Birr/pc B= Manpower Unit Cost 72.63 Birr/hr C=Equipment Unit Cost 16.84
Direct Cost of Work Item = A+B+C = 979.47 Birr/pc
Over Head : +
Profit Cost: 35% 342.82 Birr/pc
Total Unit Cost : 1,322.29 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.48 Pcs/hr
WORK ITEM: Ø16mm diam. 1500 mm Long Copper Rod EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 593.29 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Diameter 16mm & 1500mm Pcs 1.00 350.00 350.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
long copper earthing rod. Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 350.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 350.00 Birr/pc B= Manpower Unit Cost 72.63 Birr/hr C=Equipment Unit Cost 16.84
Direct Cost of Work Item = A+B+C = 439.47 Birr/pc
Over Head : +
Profit Cost: 35% 153.82 Birr/pc
Total Unit Cost : 593.29 Birr/pc
Page 84
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 Pcs/hr
WORK ITEM: Testing junction boxees EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 934.88 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Testing junction boxes at 1.5m Pcs 1.00 650.00 650.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
above grade level. Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 650.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 650.00 Birr/pc B= Manpower Unit Cost 34.50 Birr/hr C=Equipment Unit Cost 8.00
Direct Cost of Work Item = A+B+C = 692.50 Birr/pc
Over Head : +
Profit Cost: 35% 242.38 Birr/pc
Total Unit Cost : 934.88 Birr/pc
Page 85
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 Pcs/hr
WORK ITEM: Copper earth bar of 50x5mm (630-700A) EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 3208.95 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1.00 2,300.00 2,300.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 2 1 25.50 51.00
Copper earth bar of 50x5mm Ass. Elec 0 1 0.00 0.00
(630-700A) and 500mm length DL 2 1 9.00 18.00
with holes every 50mm in three
sections with disconnecting link
supporting brackets every
250mm anchored to wall or
floor for a minimum of 10
earthing connections.

Total (1:-01) 2,300.00 Total (1:02) 69.00 Total (1:03) 8.00

A= Materials Unit Cost 2300.00 Birr/pc B= Manpower Unit Cost 69.00 Birr/hr C=Equipment Unit Cost 8.00
Direct Cost of Work Item = A+B+C = 2377.00 Birr/pc
Over Head : +
Profit Cost: 35% 831.95 Birr/pc
Total Unit Cost : 3208.95 Birr/pc
Page 86
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.5 Pcs/hr
WORK ITEM: Equipotential bar EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,140.64 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Equipotential (Earthining) bonding
copper bar 1500x50x10mm size
with 7 bolted terminal
Pcs 1 1,350.00 1,350.00 Electrician 1 1 25.50 25.50 Tools 2 1.00 3.75 7.50
RHS 40X20X2MM KG 0.50 27.40 13.81 Ass. Elec 0 1 0.00 0.00 Welding 1 1.00 20.63 20.63
ELECTODE Pcs 2 1.30 2.60 DL 1 1 9.00 9.00
Bolt & Nuts Pcs 7 10.00 70.00 Welder 1 1 12.00 12.00

Total (1:-01) 1,436.41 Total (1:02) 46.50 Total (1:03) 28.13

A= Materials Unit Cost 0.265957 1436.41 Birr/ml B=Manpower Unit Cost 93.00 Birr/hr C=Equipment Unit Cost 56.25
Direct Cost of work item= A+B+C= 1585.66 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 554.98 Birr/Pc
Total Unit Cost : 2,140.64 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.0375 Pcs/hr
WORK ITEM: AIR TERMINAL ROD 2.5M EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 7,182.00 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)

** Indexed
Cost per Labour by Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Hourly Cost Equipment No. UF Rental Hourly Cost
Copper Air termination rod of Pcs 1.00 4,200.00 4,200.00 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 3.75 7.50
2.5m with roof mounting bracket Electrician 1.00 1.00 25.50 25.50
and support accessories.
Elec.helper 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 4,200.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 4,200.00 Birr/pc B= Manpower Unit Cost 920.00 Birr/hr C=Equipment Unit Cost 200.00
Direct Cost of Work Item = A+B+C = 5320.00 Birr/pc
Over Head : +
Profit Cost: 35% 1862.00 Birr/pc
Total Unit Cost : 7,182.00 Birr/pc
Page 87
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 4.5 ml/hr
WORK ITEM: Install PVC sheated & PVC insulated Conductors 1x1.5mm² EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 31.89 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (1x1.5mm) Ml 1.05 7.00 7.35 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø16mm Ml 1.05 6.50 6.83 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 14.18 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 14.18 Birr/ml B=Manpower Unit Cost 7.67 Birr/hr C=Equipment Unit Cost 1.78
Direct Cost of work item= A+B+C= 23.62 Birr/ml
Overhead Cost: +
Profit Cost: 35% 8.27 Birr/ml
Total Unit Cost : 31.89 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 4.5 ml/hr
WORK ITEM: Install PVC sheated & PVC insulated Conductors 1x2.5mm² EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 38.97 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (1x2.5mm) Ml 1.05 12.00 12.60 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø16mm Ml 1.05 6.50 6.83 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 19.43 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 19.43 Birr/ml B=Manpower Unit Cost 7.67 Birr/hr C=Equipment Unit Cost 1.78
Direct Cost of work item= A+B+C= 28.87 Birr/ml
Overhead Cost: +
Profit Cost: 35% 10.10 Birr/ml
Total Unit Cost : 38.97 Birr/ml
Page 88
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 4.5 ml/hr
WORK ITEM: Install PVC sheated & PVC insulated Conductors 1x4mm² EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 49.61 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (1x4mm) NYY
0.6/1KV Ml 1.05 19.50 20.48 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø16mm Ml 1.05 6.50 6.83 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 27.30 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 27.30 Birr/ml B=Manpower Unit Cost 7.67 Birr/hr C=Equipment Unit Cost 1.78
Direct Cost of work item= A+B+C= 36.74 Birr/ml
Overhead Cost: +
Profit Cost: 35% 12.86 Birr/ml
Total Unit Cost : 49.61 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 4.5 ml/hr
WORK ITEM: Install PVC sheated & PVC insulated Conductors 1x6mm² EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 59.53 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (1x6mm) NYY
0.6/1KV Ml 1.05 26.50 27.83 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø16mm Ml 1.05 6.50 6.83 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 34.65 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 34.65 Birr/ml B=Manpower Unit Cost 7.67 Birr/hr C=Equipment Unit Cost 1.78
Direct Cost of work item= A+B+C= 44.09 Birr/ml
Overhead Cost: +
Profit Cost: 35% 15.43 Birr/ml
Total Unit Cost : 59.53 Birr/ml
Page 89
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 4.5 ml/hr
WORK ITEM: Install PVC sheated & PVC insulated Conductors 1x10mm² EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 86.67 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (1x10mm) NYY
0.6/1KV Ml 1.05 45.65 47.93 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø16mm Ml 1.05 6.50 6.83 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 54.76 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 54.76 Birr/ml B=Manpower Unit Cost 7.67 Birr/hr C=Equipment Unit Cost 1.78
Direct Cost of work item= A+B+C= 64.20 Birr/ml
Overhead Cost: +
Profit Cost: 35% 22.47 Birr/ml
Total Unit Cost : 86.67 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 4.5 ml/hr
WORK ITEM: Install PVC sheated & PVC insulated Conductors 1x16mm² EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 125.18 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (1x16mm) NYY
0.6/1KV Ml 1.05 71.98 75.58 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø19mm Ml 1.05 7.33 7.70 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 83.28 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 83.28 Birr/ml B=Manpower Unit Cost 7.67 Birr/hr C=Equipment Unit Cost 1.78
Direct Cost of work item= A+B+C= 92.72 Birr/ml
Overhead Cost: +
Profit Cost: 35% 32.45 Birr/ml
Total Unit Cost : 125.18 Birr/ml
Page 90
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 4.5 ml/hr
WORK ITEM: Install PVC sheated & PVC insulated Conductors 1x25mm² EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 150.11 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Conductor (1x25mm) NYY
0.6/1KV Ml 1.05 81.90 86.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø32mm Ml 1.05 15.00 15.75 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 101.75 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 101.75 Birr/ml B=Manpower Unit Cost 7.67 Birr/hr C=Equipment Unit Cost 1.78
Direct Cost of work item= A+B+C= 111.19 Birr/ml
Overhead Cost: +
Profit Cost: 35% 38.92 Birr/ml
Total Unit Cost : 150.11 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 6.25 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 2x1.5sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 39.66 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
2x1.5sqmm Cable NYY
0.6/1KV Ml 1.05 15.00 15.75 ELEc Forman 0 0.25 1.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø16mm Ml 1.05 6.50 6.83 Electrician 1 1 25.50 25.50
Ass. Elec 0 0 1.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 22.58 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 22.58 Birr/ml B=Manpower Unit Cost 5.52 Birr/hr C=Equipment Unit Cost 1.28
Direct Cost of work item= A+B+C= 29.38 Birr/ml
Overhead Cost: +
Profit Cost: 35% 10.28 Birr/ml
Total Unit Cost : 39.66 Birr/ml
Page 91
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 6.25 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x1.5sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 48.52 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x1.5sqmm Cable NYY
0.6/1KV Ml 1.05 21.25 22.31 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø16mm Ml 1.05 6.50 6.83 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 29.14 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 29.14 Birr/ml B=Manpower Unit Cost 5.52 Birr/ml C=Equipment Unit Cost 1.28
Direct Cost of work item= A+B+C= 35.94 Birr/ml
Overhead Cost: +
Profit Cost: 35% 12.58 Birr/ml
Total Unit Cost : 48.52 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 6.25 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 4x1.5sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 64.18 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
4x1.5sqmm Cable NYY
0.6/1KV Ml 1.05 32.30 33.92 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø16mm Ml 1.05 6.50 6.83 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 40.74 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 40.74 Birr/ml B=Manpower Unit Cost 5.52 Birr/ml C=Equipment Unit Cost 1.28
Direct Cost of work item= A+B+C= 47.54 Birr/ml
Overhead Cost: +
Profit Cost: 35% 16.64 Birr/ml
Total Unit Cost : 64.18 Birr/ml
Page 92
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 6.25 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 2x2.5sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 52.98 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
2x2.5sqmm Cable NYY
0.6/1KV Ml 1.05 24.40 25.62 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø16mm Ml 1.05 6.50 6.83 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 32.45 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 32.45 Birr/ml B=Manpower Unit Cost 5.52 Birr/hr C=Equipment Unit Cost 1.28
Direct Cost of work item= A+B+C= 39.25 Birr/ml
Overhead Cost: +
Profit Cost: 35% 13.74 Birr/ml
Total Unit Cost : 52.98 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.75 ml/hr
WORK ITEM: Feeder Cables (PVC sheated & PVC insulated) 3x2.5sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 62.00 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x2.5sqmm Cable NYY
0.6/1KV Ml 1.05 30.20 31.71 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø16mm Ml 1.05 6.50 6.83 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 38.54 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 38.54 Birr/ml B=Manpower Unit Cost 6.00 Birr/hr C=Equipment Unit Cost 1.39
Direct Cost of work item= A+B+C= 45.93 Birr/ml
Overhead Cost: +
Profit Cost: 35% 16.07 Birr/ml
Total Unit Cost : 62.00 Birr/ml
Page 93
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.75 ml/hr
WORK ITEM: Feeder Cables (PVC sheated & PVC insulated) 4x2.5sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 77.07 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
4x2.5sqmm Cable NYY
0.6/1KV Ml 1.05 40.00 42.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø19mm Ml 1.05 7.33 7.70 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 49.70 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 49.70 Birr/ml B=Manpower Unit Cost 6.00 Birr/ml C=Equipment Unit Cost 1.39
Direct Cost of work item= A+B+C= 57.09 Birr/ml
Overhead Cost: +
Profit Cost: 35% 19.98 Birr/ml
Total Unit Cost : 77.07 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.75 ml/hr
WORK ITEM: Feeder Cables (PVC sheated & PVC insulated) 5x2.5sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 110.38 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
5x2.5sqmm Cable NYY
0.6/1KV Ml 1.05 63.50 66.68 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø19mm Ml 1.05 7.33 7.70 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 74.38 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 74.38 Birr/ml B=Manpower Unit Cost 6.00 Birr/hr C=Equipment Unit Cost 1.39
Direct Cost of work item= A+B+C= 81.77 Birr/ml
Overhead Cost: +
Profit Cost: 35% 28.62 Birr/ml
Total Unit Cost : 110.38 Birr/ml
Page 94
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 6.00 ml/hr
WORK ITEM: Feeder Cables (PVC sheated & PVC insulated) 2x4sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 68.39 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost

2x4sqmm Cable NYY 0.6/1KV Ml 1.05 35.00 36.75 ELE.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø16mm Ml 1.05 6.50 6.83 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 43.58 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 43.58 Birr/ml B=Manpower Unit Cost 5.75 Birr/hr C=Equipment Unit Cost 1.33
Direct Cost of work item= A+B+C= 50.66 Birr/ml
Overhead Cost:
Profit Cost: 35% 17.73 Birr/ml
Total Unit Cost : 68.39 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.25 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x4sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 89.65 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost

3x4sq.mm Cable NYY 0.6/1KV Ml 1.05 48.20 50.61 ELE.Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø19mm Ml 1.05 7.33 7.70 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 58.31 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 58.31 Birr/ml B=Manpower Unit Cost 6.57 Birr/hr C=Equipment Unit Cost 1.52
Direct Cost of work item= A+B+C= 66.41 Birr/ml
Overhead Cost: +
Profit Cost: 35% 23.24 Birr/ml
Total Unit Cost : 89.65 Birr/ml
Page 95
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.25 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 4x4sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 113.84 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost

4x4sqmm Cable NYY 0.6/1KV Ml 1.05 62.60 65.73 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø25mm Ml 1.05 10.00 10.50 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 76.23 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 76.23 Birr/ml B=Manpower Unit Cost 6.57 Birr/hr C=Equipment Unit Cost 1.52
Direct Cost of work item= A+B+C= 84.33 Birr/ml
Overhead Cost: +
Profit Cost: 35% 29.51 Birr/ml
Total Unit Cost : 113.84 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.25 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 5x4sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 135.95 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost

5x4sqmm Cable NYY 0.6/1KV Ml 1.05 78.20 82.11 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø25mm Ml 1.05 10.00 10.50 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 92.61 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 92.61 Birr/ml B=Manpower Unit Cost 6.57 Birr/hr C=Equipment Unit Cost 1.52
Direct Cost of work item= A+B+C= 100.71 Birr/ml
Overhead Cost: +
Profit Cost: 35% 35.25 Birr/ml
Total Unit Cost : 135.95 Birr/ml
Page 96
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.25 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 2x6sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 86.53 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost

2x6sqmm Cable NYY 0.6/1KV Ml 1.05 46.00 48.30 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø19mm Ml 1.05 7.33 7.70 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 56.00 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 56.00 Birr/ml B=Manpower Unit Cost 6.57 Birr/hr C=Equipment Unit Cost 1.52
Direct Cost of work item= A+B+C= 64.10 Birr/ml
Overhead Cost: +
Profit Cost: 35% 22.43 Birr/ml
Total Unit Cost : 86.53 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.25 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x6sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 120.08 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost

3x6sqmm Cable NYY 0.6/1KV Ml 1.05 67.00 70.35 ELEc Forman 0 0.25 1.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø25mm Ml 1.05 10.00 10.50 Electrician 1 1 25.50 25.50
Ass. Elec 0 0 1.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 80.85 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 80.85 Birr/ml B=Manpower Unit Cost 6.57 Birr/ml C=Equipment Unit Cost 1.52
Direct Cost of work item= A+B+C= 88.95 Birr/ml
Overhead Cost: +
Profit Cost: 35% 31.13 Birr/ml
Total Unit Cost : 120.08 Birr/ml
Page 97
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.25 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 4x6sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 154.66 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost

4x6sqmm Cable NYY 0.6/1KV Ml 1.05 86.40 90.72 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø32mm Ml 1.05 15.00 15.75 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 106.47 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 106.47 Birr/ml B=Manpower Unit Cost 6.57 Birr/ml C=Equipment Unit Cost 1.52
Direct Cost of work item= A+B+C= 114.57 Birr/ml
Overhead Cost: +
Profit Cost: 35% 40.10 Birr/ml
Total Unit Cost : 154.66 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.25 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 5x6sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 196.24 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost

5x6sqmm Cable NYY 0.6/1KV Ml 1.05 112.40 118.02 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø35mm Ml 1.05 18.33 19.25 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 137.27 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 137.27 Birr/ml B=Manpower Unit Cost 6.57 Birr/hr C=Equipment Unit Cost 1.52
Direct Cost of work item= A+B+C= 145.37 Birr/ml
Overhead Cost: +
Profit Cost: 35% 50.88 Birr/ml
Total Unit Cost : 196.24 Birr/ml
Page 98
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 5.25 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 2x10sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 145.59 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
2x10sqmm Cable NYY
0.6/1KV Ml 1.05 85.00 89.25 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø25mm Ml 1.05 10.00 10.50 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 99.75 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 99.75 Birr/ml B=Manpower Unit Cost 6.57 Birr/ml C=Equipment Unit Cost 1.52
Direct Cost of work item= A+B+C= 107.85 Birr/ml
Overhead Cost: +
Profit Cost: 35% 37.75 Birr/ml
Total Unit Cost : 145.59 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 3.38 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x10sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 213.09 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x10sqmm Cable NYY
0.6/1KV Ml 1.05 120.00 126.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø35mm Ml 1.05 18.33 19.25 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 145.25 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 145.25 Birr/ml B=Manpower Unit Cost 10.22 Birr/ml C=Equipment Unit Cost 2.37
Direct Cost of work item= A+B+C= 157.84 Birr/ml
Overhead Cost: +
Profit Cost: 35% 55.24 Birr/ml
Total Unit Cost : 213.09 Birr/ml
Page 99
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 3.38 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 4x10sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 260.81 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
4x10sqmm Cable NYY
0.6/1KV Ml 1.05 147.00 154.35 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø50mm U.PVC Ml 1.05 25.00 26.25 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 180.60 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 180.60 Birr/ml B=Manpower Unit Cost 10.22 Birr/ml C=Equipment Unit Cost 2.37
Direct Cost of work item= A+B+C= 193.19 Birr/ml
Overhead Cost: +
Profit Cost: 35% 67.62 Birr/ml
Total Unit Cost : 260.81 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 3.38 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 5x10sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 317.51 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
5x10sqmm Cable NYY
0.6/1KV Ml 1.05 187.00 196.35 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø50mm U.PVC Ml 1.05 25.00 26.25 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 222.60 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 222.60 Birr/ml B=Manpower Unit Cost 10.22 Birr/ml C=Equipment Unit Cost 2.37
Direct Cost of work item= A+B+C= 235.19 Birr/ml
Overhead Cost: +
Profit Cost: 35% 82.32 Birr/ml
Total Unit Cost : 317.51 Birr/ml
Page 100
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 3.38 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 2x16sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 198.91 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
2x16sqmm Cable NYY
0.6/1KV Ml 1.05 110.00 115.50 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Conduit Ø35mm Ml 1.05 18.33 19.25 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 134.75 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 134.75 Birr/ml B=Manpower Unit Cost 10.22 Birr/ml C=Equipment Unit Cost 2.37
Direct Cost of work item= A+B+C= 147.34 Birr/ml
Overhead Cost: +
Profit Cost: 35% 51.57 Birr/ml
Total Unit Cost : 198.91 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x16sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 345.13 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x16sqmm Cable NYY
0.6/1KV Ml 1.05 178.00 186.90 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø50mm U.PVC Ml 1.05 25.00 26.25 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 213.15 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 213.15 Birr/ml B=Manpower Unit Cost 34.50 Birr/ml C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 255.65 Birr/ml
Overhead Cost: +
Profit Cost: 35% 89.48 Birr/ml
Total Unit Cost : 345.13 Birr/ml
Page 101
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 4x16sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 441.52 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
4x16sqmm Cable NYY
0.6/1KV Ml 1.05 231.00 242.55 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø80mm U.PVC Ml 1.05 40.00 42.00 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 284.55 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 284.55 Birr/ml B=Manpower Unit Cost 34.50 Birr/ml C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 327.05 Birr/ml
Overhead Cost: +
Profit Cost: 35% 114.47 Birr/ml
Total Unit Cost : 441.52 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 5x16sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 552.08 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
5x16sqmm Cable NYY
0.6/1KV Ml 1.05 284.00 298.20 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø110mm U.PVC Ml 1.05 65.00 68.25 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 366.45 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 366.45 Birr/ml B=Manpower Unit Cost 34.50 Birr/hr C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 408.95 Birr/ml
Overhead Cost: +
Profit Cost: 35% 143.13 Birr/ml
Total Unit Cost : 552.08 Birr/ml
Page 102
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x25+16sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 751.95 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x25+16sqmm Cable NYY
0.6/1KV Ml 1.05 425.00 446.25 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø110mm U.PVC Ml 1.05 65.00 68.25 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 514.50 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 514.50 Birr/ml B=Manpower Unit Cost 34.50 Birr/hr C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 557.00 Birr/ml
Overhead Cost: +
Profit Cost: 35% 194.95 Birr/ml
Total Unit Cost : 751.95 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x35+16sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 1006.86 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x35+16sqmm Cable NYY
0.6/1KV Ml 1.05 552.50 580.13 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø125mm U.PVC Ml 1.05 117.33 123.20 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 703.33 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 703.33 Birr/ml B=Manpower Unit Cost 34.50 Birr/ml C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 745.83 Birr/ml
Overhead Cost: +
Profit Cost: 35% 261.04 Birr/ml
Total Unit Cost : 1006.86 Birr/ml
Page 103
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x50+25sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 1,222.90 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x50+25sqmm Cable NYY
0.6/1KV Ml 1.05 637.00 668.85 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø160mm U.PVC Ml 1.05 191.67 201.25 Electrician 1 1 18.75 18.75
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 870.10 Total (1:02) 27.75 Total (1:03) 8.00

A= Materials Unit Cost 870.10 Birr/ml B=Manpower Unit Cost 27.75 Birr/hr C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 905.85 Birr/ml
Overhead Cost: +
Profit Cost: 35% 317.05 Birr/ml
Total Unit Cost : 1,222.90 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x70+35sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 1,670.96 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x70+35sqmm Cable NYY
0.6/1KV Ml 1.05 780.00 819.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø220mm U.PVC Ml 1.05 358.33 376.25 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,195.25 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,195.25 Birr/ml B=Manpower Unit Cost 34.50 Birr/hr C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 1237.75 Birr/ml
Overhead Cost: +
Profit Cost: 35% 433.21 Birr/ml
Total Unit Cost : 1,670.96 Birr/ml
Page 104
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x95+50sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 2,389.16 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x95+50sqmm Cable NYY
0.6/1KV Ml 1.05 1,085.00 1,139.25 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø315mm U.PVC Ml 1.05 560.00 588.00 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,727.25 Total (1:02) 34.50 Total (1:03) 8.00

A= Materials Unit Cost 1,727.25 Birr/ml B=Manpower Unit Cost 34.50 Birr/hr C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 1769.75 Birr/ml
Overhead Cost: +
Profit Cost: 35% 619.41 Birr/ml
Total Unit Cost : 2,389.16 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x120+70sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 2,925.79 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x120+70sqmm Cable NYY
0.6/1KV Ml 1.05 1,370.00 1,438.50 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø450mm U.PVC Ml 1.05 660.00 693.00 Electrician 1 1 18.75 18.75
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,131.50 Total (1:02) 27.75 Total (1:03) 8.00

A= Materials Unit Cost 2,131.50 Birr/ml B=Manpower Unit Cost 27.75 Birr/hr C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 2167.25 Birr/ml
Overhead Cost: +
Profit Cost: 35% 758.54 Birr/ml
Total Unit Cost : 2,925.79 Birr/ml
Page 105
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated NYY0.6/1KV ) 3x150+70sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 3,450.26 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x150+70sqmm Cable NYY
0.6/1KV Ml 1.05 1,650.00 1,732.50 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø500mm U.PVC Ml 1.05 750.00 787.50 Electrician 1 1 18.75 18.75
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,520.00 Total (1:02) 27.75 Total (1:03) 8.00

A= Materials Unit Cost 2,520.00 Birr/ml B=Manpower Unit Cost 27.75 Birr/hr C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 2555.75 Birr/ml
Overhead Cost: +
Profit Cost: 35% 894.51 Birr/ml
Total Unit Cost : 3,450.26 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated NYY0.6/1KV ) 3x185+95sqmm Cable) EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 3,010.84 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x185+95sqmm Cable NYY
0.6/1KV Ml 1.05 2,090.00 2,194.50 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 18.75 18.75
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,194.50 Total (1:02) 27.75 Total (1:03) 8.00

A= Materials Unit Cost 2,194.50 Birr/ml B=Manpower Unit Cost 27.75 Birr/hr C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 2230.25 Birr/ml
Overhead Cost: +
Profit Cost: 35% 780.59 Birr/ml
Total Unit Cost : 3,010.84 Birr/ml
Page 106
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x240+120sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 3,777.71 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x240+120sqmm Cable NYY
0.6/1KV Ml 1.05 2,631.00 2,762.55 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 18.75 18.75
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,762.55 Total (1:02) 27.75 Total (1:03) 8.00

A= Materials Unit Cost 2,762.55 Birr/ml B=Manpower Unit Cost 27.75 Birr/hr C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 2,798.30 Birr/ml
Overhead Cost: +
Profit Cost: 35% 979.41 Birr/ml
Total Unit Cost : 3,777.71 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 3x300+150sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 4,935.80 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
3x300+150sqmm Cable NYY
0.6/1KV Ml 1.05 3,448.00 3,620.40 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 18.75 18.75
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 3,620.40 Total (1:02) 27.75 Total (1:03) 8.00

A= Materials Unit Cost 3,620.40 Birr/ml B=Manpower Unit Cost 27.75 Birr/hr C=Equipment Unit Cost 8.00
Direct Cost of work item= A+B+C= 3,656.15 Birr/ml
Overhead Cost: +
Profit Cost: 35% 1279.65 Birr/ml
Total Unit Cost : 4,935.80 Birr/ml
Page 107
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2.5 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 1x70sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 443.82 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x70sqmm Cable NYY
0.6/1KV Ml 1.05 234.48 246.20 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø110mm U.PVC Ml 1.05 65.00 68.25 Electrician 1 1 18.75 18.75
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 314.45 Total (1:02) 27.75 Total (1:03) 8.00

A= Materials Unit Cost 314.45 Birr/ml B=Manpower Unit Cost 11.10 Birr/hr C=Equipment Unit Cost 3.20
Direct Cost of work item= A+B+C= 328.75 Birr/ml
Overhead Cost: +
Profit Cost: 35% 115.06 Birr/ml
Total Unit Cost : 443.82 Birr/ml

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2 ml/hr
WORK ITEM: Power Cables (PVC sheated & PVC insulated) 1x120sqmm Cable EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 ML RESULT: 890.32 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
1x120sqmm Cable NYY
0.6/1KV Ml 1.05 419.40 440.37 ELE Forman 0 0.25 0.00 0.00 Tools 2 1.00 4.00 8.00
Ø160mm U.PVC Ml 1.05 191.67 201.25 Electrician 1 1 18.75 18.75
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 641.62 Total (1:02) 27.75 Total (1:03) 8.00

A= Materials Unit Cost 641.62 Birr/ml B=Manpower Unit Cost 13.88 Birr/hr C=Equipment Unit Cost 4.00
Direct Cost of work item= A+B+C= 659.50 Birr/ml
Overhead Cost: +
Profit Cost: 35% 230.82 Birr/ml
Total Unit Cost : 890.32 Birr/ml
Page 108
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS
PROJECT: Electrical Work LABOUR HOURLY OUTPUT: 0.25 Pc/Hr
WORK ITEM:Steel Light poles 14m height Polygonal Tapered mast with circular properly flanged arm EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs 1.00 Pc RESULT: 26971.65 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Steel light poles pcs 1 18,500.00 18,500.00 ELE Forman 0 1 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 18.75 18.75 Crane 1 0.25 1,187.50 296.88
operator 1 0.25 40.50 10.13
Plasterer 0 0.25 0.00 0.00
DL 4 1 9.00 36.00

Total (1:-01) 18,500.00 Total (1:02) 64.88 Total (1:03) 304.88

A= Materials Unit Cost 18,500.00 Birr/PC B=Manpower Unit Cost 259.50 Birr/hr C=Equipment Unit Cost 1219.50
Direct Cost of work item= A+B+C= 19979.00 Birr/PC
Overhead Cost:
Profit Cost: 35% 6992.65 Birr/PC
Total Unit Cost : 26,971.65 Birr/PC

PROJECT: Electrical Work LABOUR HOURLY OUTPUT: 0.25 Pc/Hr


WORK ITEM:Steel Light poles 9m height Polygonal Tapered mast with circular properly flanged arm EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs 1.00 Pc RESULT: 20,491.65 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Steel light poles pcs 1 13,700.00 13,700.00 ELEc Forman 0 1 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 18.75 18.75 Crane 1 0.25 1,187.50 296.88
operator 1 0.25 40.50 10.13
Plasterer 0 0.25 0.00 0.00
DL 4 1 9.00 36.00

Total (1:-01) 13,700.00 Total (1:02) 64.88 Total (1:03) 304.88

A= Materials Unit Cost 13,700.00 Birr/PC B=Manpower Unit Cost 259.50 Birr/hr C=Equipment Unit Cost 1219.50
Direct Cost of work item= A+B+C= 15179.00 Birr/PC
Overhead Cost:
Profit Cost: 35% 5312.65 Birr/PC
Total Unit Cost : 20,491.65 Birr/PC
Page 109
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Work LABOUR HOURLY OUTPUT: 0.25 Pc/hr.


WORK ITEM:Steel Light poles 3m height Polygonal Tapered mast with circular properly flanged arm EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 5966.33 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Steel light poles Pcs 1 4,200.00 4,200.00 ELEc Forman 0 1 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 18.75 18.75
operator 1 0.25 40.50 10.13
DL 2 1 9.00 18.00

Total (1:-01) 4,200.00 Total (1:02) 46.88 Total (1:03) 8.00

A= Materials Unit Cost 4,200.00 Birr/PC B=Manpower Unit Cost 187.50 Birr/hr C=Equipment Unit Cost 32.00
Direct Cost of work item= A+B+C= 4419.50 Birr/PC
Overhead Cost:
Profit Cost: 35% 1546.83 Birr/PC
Total Unit Cost : 5,966.33 Birr/PC

PROJECT: Electrical Work LABOUR HOURLY OUTPUT: 0.25 Pc/hr.


WORK ITEM:Steel Light poles 6m height Polygonal Tapered mast with circular properly flanged arm EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 12121.65 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Steel light poles pcs 1 7,500.00 7,500.00 ELEc Forman 0 1 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 18.75 18.75 Crane 1 0.25 1,187.50 296.88
operator 1 0.25 40.50 10.13
Plasterer 0 0.25 0.00 0.00
DL 4 1 9.00 36.00

Total (1:-01) 7,500.00 Total (1:02) 64.88 Total (1:03) 304.88

A= Materials Unit Cost 7,500.00 Birr/PC B=Manpower Unit Cost 259.50 Birr/hr C=Equipment Unit Cost 1219.50
Direct Cost of work item= A+B+C= 8979.00 Birr/PC
Overhead Cost:
Profit Cost: 35% 3142.65 Birr/PC
Total Unit Cost : 12,121.65 Birr/PC
Page 110
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Work LABOUR HOURLY OUTPUT: 0.25 Pc/hr.


WORK ITEM:Steel Light poles 8m height Polygonal Tapered mast with circular properly flanged arm EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 16,826.40 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Steel light poles pcs 1 11,000.00 11,000.00 ELEc Forman 0 1 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 18.75 15.00 Crane 1 0.25 1,187.50 296.88
operator 1 0.25 40.50 10.13
Plasterer 0 0.25 0.00 0.00
DL 4 1 9.00 36.00

Total (1:-01) 11,000.00 Total (1:02) 61.13 Total (1:03) 304.88

A= Materials Unit Cost 11,000.00 Birr/PC B=Manpower Unit Cost 244.50 Birr/hr C=Equipment Unit Cost 1219.50
Direct Cost of work item= A+B+C= 12464.00 Birr/PC
Overhead Cost:
Profit Cost: 35% 4362.40 Birr/PC
Total Unit Cost : 16,826.40 Birr/PC

PROJECT: Electrical Work LABOUR HOURLY OUTPUT: 0.25 Pc/hr.


WORK ITEM:Steel Light poles 12m height Polygonal Tapered mast with circular properly flanged armEQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 23,866.65 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Steel light poles pcs 1 16,200.00 16,200.00 ELEc Forman 0 1 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 18.75 18.75 Crane 1 0.25 1,187.50 296.88
operator 1 0.25 40.50 10.13
DL 4 1 9.00 36.00

Total (1:-01) 16,200.00 Total (1:02) 64.88 Total (1:03) 304.88

A= Materials Unit Cost 16,200.00 Birr/PC B=Manpower Unit Cost 259.50 Birr/hr C=Equipment Unit Cost 1219.50
Direct Cost of work item= A+B+C= 17679.00 Birr/PC
Overhead Cost:
Profit Cost: 35% 6187.65 Birr/PC
Total Unit Cost : 23,866.65 Birr/PC
Page 111

ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Work LABOUR HOURLY OUTPUT: 0.1875 Pc/hr.


WORK ITEM:Steel Light poles 20m height Polygonal Tapered mast with circular properly flanged arm EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 43,162.20 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Steel light poles pcs 1 30,000.00 30,000.00 ELEc Forman 1 1 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 18.75 18.75 Crane 1 0.25 1,187.50 296.88
operator 1 0.25 40.50 10.13
Plasterer 1 0.25 0.00 0.00
DL 4 1 9.00 36.00

Total (1:-01) 30,000.00 Total (1:02) 64.88 Total (1:03) 304.88

A= Materials Unit Cost 30,000.00 Birr/PC B=Manpower Unit Cost 346.00 Birr/hr C=Equipment Unit Cost 1626.00
Direct Cost of work item= A+B+C= 31972.00 Birr/PC
Overhead Cost:
Profit Cost: 35% 11190.20 Birr/PC
Total Unit Cost : 43,162.20 Birr/PC
Page 112
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Work LABOUR HOURLY OUTPUT: 0.125 Pc/hr.


WORK ITEM:Supply and install Generator that can operate autonatically (power/supply turned off) EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 844,630.20 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost

pcs 1 625,000.00 625,000.00 ELEc Forman 1 1 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 2 1 18.75 37.50
Smax .........................72 KVA operator 1 0.25 0.00 0.00
voltage .....................380volts,
50Hz, 3-ph Plasterer 1 0.25 0.00 0.00
speed………………………
1500rpm PF…… 0.8
cooling method……… water
cooled
The generator shall be equipped
with:
automatic voltage regulator
(AVR)
automatic transfer switch
(ATS)
HCB of 125A/3ph
ON/OFF switch, current,
voltage and frequency
measuring. Price shall include
all listed accessories. DL 4 1 9.00 36.00

Total (1:-01) 625,000.00 Total (1:02) 73.50 Total (1:03) 8.00

A= Materials Unit Cost 625,000.00 Birr/PC B=Manpower Unit Cost 588.00 Birr/hr C=Equipment Unit Cost 64.00
Direct Cost of work item= A+B+C= 625652.00 Birr/PC
Overhead Cost:
Profit Cost: 35% 218978.20 Birr/PC
Total Unit Cost : 844,630.20 Birr/PC
Page 113
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Work LABOUR HOURLY OUTPUT: 0.125 Pc/hr.


WORK ITEM: Supply and install Transformer EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 540,677.70 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
pcs 1 400,000.00 400,000.00 ELE. Forman 1 1 0.00 0.00 Tools 2 1.00 4.00 8.00
LV, outdoor, oil immersed Electrician 1 1 18.75 18.75
315KVA, 15KV, 380/220V,
50HZ 3-ph pole mountable operator 1 0.25 0.00 0.00
Transformer with all mounting Plasterer 1 0.25 0.00 0.00
accessories DL 4 1 9.00 36.00

Total (1:-01) 400,000.00 Total (1:02) 54.75 Total (1:03) 8.00

A= Materials Unit Cost 400,000.00 Birr/PC B=Manpower Unit Cost 438.00 Birr/hr C=Equipment Unit Cost 64.00
Direct Cost of work item= A+B+C= 400502.00 Birr/PC
Overhead Cost:
Profit Cost: 35% 140175.70 Birr/PC
Total Unit Cost : 540,677.70 Birr/PC
Page 114
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Work LABOUR HOURLY OUTPUT: 0.125 Pc/hr.


WORK ITEM: Supply and install Transformer EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 344,927.70 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
pcs 1 255,000.00 255,000.00 ELE. Forman 1 1 0.00 0.00 Tools 2 1.00 4.00 8.00
Electrician 1 1 18.75 18.75
operator 1 0.25 0.00 0.00
LV outdoor, oil immersed Plasterer 1 0.25 0.00 0.00
100KVA, 15kv/380v, 220v, DL 4 1 9.00 36.00
3ph, 50Hz, 125A/3ph fuse,
Dyn11 or Dyn5 configuration
pole mountable distribution
transformer with all mounting
accessories
Total (1:-01) 255,000.00 Total (1:02) 54.75 Total (1:03) 8.00

A= Materials Unit Cost 255,000.00 Birr/PC B=Manpower Unit Cost 438.00 Birr/hr C=Equipment Unit Cost 64.00
Direct Cost of work item= A+B+C= 255502.00 Birr/PC
Overhead Cost:
Profit Cost: 35% 89425.70 Birr/PC
Total Unit Cost : 344,927.70 Birr/PC
Page 115
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Work LABOUR HOURLY OUTPUT: 0.125 Pc/hr.


WORK ITEM:Supply and install Generator that can operate autonatically (power/supply turned off) EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,880,624.60 Birr/Ml

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
General Technical Data of the
oil immersed and hermetically
sealed Transformer. pcs 1 2,133,000.00 2,133,000.0 ELEc Forman 1 1 0.00 0.00 Tools 2 1.00 4.00 8.00
Protective degrees Electrician 2 1 18.75 37.50
HV compartment: IP43 operator 1 0.25 0.00 0.00
Transfomer compartment IP23 Plasterer 1 0.25 0.00 0.00
LV compartment: IP43 DL 6 1 9.00 54.00
Type KTMU 18 HC 630
Rated Power, KVA 1000
Voltage ratio,V
15000+/-2x2.5%/400
Frequency,Hz 50
Vector Group Dyn 5
Standard IEC 76
Cooling ONAN
Insulation level windings, KV
LI AC 38/LI_AC3
No load losses, W 1200
Load losses, W 56300

The LV part should be provided


with 1600A, MCCB 3ph, 70KA

Provide all technical data with


sketch and catalouge.

Total (1:-01) 2,133,000.0 Total (1:02) 91.50 Total (1:03) 8.00

A= Materials Unit Cost 2,133,000.00 Birr/PC B=Manpower Unit Cost 732.00 Birr/hr C=Equipment Unit Cost 64.00
Direct Cost of work item= A+B+C= 2,133,796 Birr/PC
Overhead Cost:
Profit Cost: 35% 746,828.60 Birr/PC
Total Unit Cost : 2,880,624.60 Birr/PC
Page 116
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2 Pcs/hr
WORK ITEM: Test Clamps EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 760.05 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1.00 542.00 542.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
TEST CLAMP FOR 25X3MM2 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 542.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 542.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 3.75
Direct Cost of Work Item = A+B+C = 563.00 Birr/pc
Over Head : +
Profit Cost: 35% 197.05 Birr/pc
Total Unit Cost : 760.05 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.0375 Pcs/hr
WORK ITEM: AIR TERMINAL ROD 1.0M EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 5,919.75 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)

** Indexed
Cost per Labour by Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Hourly Cost Equipment No. UF Rental Hourly Cost
Copper Air termination rod of Pcs 1.00 3,265.00 3,265.00 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 3.75 7.50
2.5m with roof mounting bracket Electrician 1.00 1.00 25.50 25.50
and support accessories.
Elec.helper 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 3,265.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 3,265.00 Birr/pc B= Manpower Unit Cost 920.00 Birr/hr C=Equipment Unit Cost 200.00
Direct Cost of Work Item = A+B+C = 4385.00 Birr/pc
Over Head : +
Profit Cost: 35% 1534.75 Birr/pc
Total Unit Cost : 5,919.75 Birr/pc
Page 117
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.48 Pcs/hr
WORK ITEM: Ø16mm diam. 1200 mm Long Copper Rod EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 517.62 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Diameter 16mm & 2400mm Pcs 1.00 295.00 295.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
long copper earthing rod. Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 295.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 295.00 Birr/pc B= Manpower Unit Cost 72.63 Birr/hr C=Equipment Unit Cost 15.79
Direct Cost of Work Item = A+B+C = 383.42 Birr/pc
Over Head : +
Profit Cost: 35% 134.20 Birr/pc
Total Unit Cost : 517.62 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2 Pcs/hr
WORK ITEM: Test Clamps EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 905.85 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
TEST CLAMP FOR 50/70 Pcs 1.00 650.00 650.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
MM2 Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 650.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 650.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 3.75
Direct Cost of Work Item = A+B+C = 671.00 Birr/pc
Over Head : +
Profit Cost: 35% 234.85 Birr/pc
Total Unit Cost : 905.85 Birr/pc
Page 118
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.06 Pcs/hr
WORK ITEM: Galvanized Steel Ring Earth Teminator EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 2,103.30 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
30x3.5mm galvanized steel ring ML 1.00 858.00 858.00 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 3.75 7.50
earth termination net work. Electrician 1.00 1.00 25.50 25.50
Elec.helper 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 858.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 858.00 Birr/pc B= Manpower Unit Cost 575.00 Birr/hr C=Equipment Unit Cost 125.00
Direct Cost of Work Item = A+B+C = 1558.00 Birr/pc
Over Head : +
Profit Cost: 35% 545.30 Birr/pc
Total Unit Cost : 2,103.30 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.0375 Pcs/hr
WORK ITEM: LIGHTINING ARRESTER EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 41,542.20 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)

** Indexed
Cost per Labour by Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Hourly Cost Equipment No. UF Rental Hourly Cost
PREVENTOR P1 WITH 4.6M Pcs 1.00 29,652.00 29,652.00 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 3.75 7.50
MAST Electrician 1.00 1.00 25.50 25.50
Elec.helper 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 29,652.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 29,652.00 Birr/pc B= Manpower Unit Cost 920.00 Birr/hr C=Equipment Unit Cost 200.00
Direct Cost of Work Item = A+B+C = 30772.00 Birr/pc
Over Head : +
Profit Cost: 35% 10770.20 Birr/pc
Total Unit Cost : 41,542.20 Birr/pc
Page 119
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.0375 Pcs/hr
WORK ITEM: LIGHTINING ARRESTER EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 49,334.40 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)

** Indexed
Cost per Labour by Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Hourly Cost Equipment No. UF Rental Hourly Cost
PREVENTOR P2 WITH 4.6M Pcs 1.00 35,624.00 35,624.00 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 0.00 0.00
MAST Electrician 1.00 1.00 25.50 25.50
Elec.helper 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 35,624.00 Total (1:02) 34.50 Total (1:03) 0.00

A= Materials Unit Cost 35,624.00 Birr/pc B= Manpower Unit Cost 920.00 Birr/hr C=Equipment Unit Cost 0.00
Direct Cost of Work Item = A+B+C = 36544.00 Birr/pc
Over Head : +
Profit Cost: 35% 12790.40 Birr/pc
Total Unit Cost : 49,334.40 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.0375 Pcs/hr
WORK ITEM: LIGHTINING ARRESTER EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 59,541.75 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)

** Indexed
Cost per Labour by Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Hourly Cost Equipment No. UF Rental Hourly Cost
PREVENTOR P3 WITH 6M Pcs 1.00 42,985.00 42,985.00 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 3.75 7.50
MAST Electrician 1.00 1.00 25.50 25.50
Elec.helper 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 42,985.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 42,985.00 Birr/pc B= Manpower Unit Cost 920.00 Birr/hr C=Equipment Unit Cost 200.00
Direct Cost of Work Item = A+B+C = 44105.00 Birr/pc
Over Head : +
Profit Cost: 35% 15436.75 Birr/pc
Total Unit Cost : 59,541.75 Birr/pc
Page 120
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 2 Pcs/hr
WORK ITEM: Test Clamps EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 1178.55 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Pcs 1.00 852.00 852.00 Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
25X3MM2 LIGHTLY Electrician 1 1 25.50 25.50
INSULATED COPEPR TAPE Ass. Elec 0 1 0.00 0.00
INCLUDING CLIPS ETC. DL 1 1 9.00 9.00

Total (1:-01) 852.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 852.00 Birr/pc B= Manpower Unit Cost 17.25 Birr/hr C=Equipment Unit Cost 3.75
Direct Cost of Work Item = A+B+C = 873.00 Birr/pc
Over Head : +
Profit Cost: 35% 305.55 Birr/pc
Total Unit Cost : 1178.55 Birr/pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 0.0375 Pcs/hr
WORK ITEM: LIGHTINING ARRESTER EQUIPEMENT:
TOTAL QANTITY OF WORK ITEM: 1 Pcs RESULT: 85,930.20 Birr/pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)

** Indexed
Cost per Labour by Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Grade No. UF Cost Hourly Cost Equipment No. UF Rental Hourly Cost
PREVENTOR P4 WITH 6M Pcs 1.00 62,532.00 62,532.00 Forman 0.00 0.25 0.00 0.00 Tools 2.00 1.00 3.75 7.50
MAST Electrician 1.00 1.00 25.50 25.50
Elec.helper 0.00 1.00 0.00 0.00
DL 1.00 1.00 9.00 9.00

Total (1:-01) 62,532.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 62,532.00 Birr/pc B= Manpower Unit Cost 920.00 Birr/hr C=Equipment Unit Cost 200.00
Direct Cost of Work Item = A+B+C = 63652.00 Birr/pc
Over Head : +
Profit Cost: 35% 22278.20 Birr/pc
Total Unit Cost : 85,930.20 Birr/pc
Page 121
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 818.10 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Interior wall light fitting type Pcs 1 578.00 578.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
RZB 25146.003 + A60 60W
LAMP Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 578.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 578.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.00
Direct Cost of work item= A+B+C= 606.00 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 212.10 Birr/Pc
Total Unit Cost : 818.10 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,193.40 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Exterior wall light fitting type Pcs 1 856.00 856.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
RZB 22130.003 + A60 100W Electrician 1 1 25.50 25.50
LAMP Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 856.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 856.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.00
Direct Cost of work item= A+B+C= 884.00 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 309.40 Birr/Pc
Total Unit Cost : 1,193.40 Birr/Pc
Page 122
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 5,026.05 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
Emergency light fitting type Pcs 1 3,695.00 3,695.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
RZB 671467.752 with T16
8W/3h lamp and EXIT sign Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 3,695.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 3,695.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.00
Direct Cost of work item= A+B+C= 3723.00 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1303.05 Birr/Pc
Total Unit Cost : 5,026.05 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 6,316.65 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 921385.774 + 1XHIT-CE- Pcs 1 4,651.00 4,651.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
P 150W LAMP Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 4,651.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 4,651.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.00
Direct Cost of work item= A+B+C= 4679.00 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1637.65 Birr/Pc
Total Unit Cost : 6,316.65 Birr/Pc
Page 123
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down Fo rDessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,444.85 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 751097.773 + 1XHIT-CE Pcs 1 1,783.00 1,783.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
150W LAMP Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,783.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 1,783.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.00
Direct Cost of work item= A+B+C= 1811.00 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 633.85 Birr/Pc
Total Unit Cost : 2,444.85 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,806.30 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 581291.959 with 1xTCD Pcs 1 1,310.00 1,310.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
26W LAMP Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,310.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 1,310.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.00
Direct Cost of work item= A+B+C= 1338.00 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 468.30 Birr/Pc
Total Unit Cost : 1,806.30 Birr/Pc
Page 124
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,268.00 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
RZB 33708.952 with 1xTCD
26W LAMP Pcs 1 1,652.00 1,652.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,652.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 1,652.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.00
Direct Cost of work item= A+B+C= 1680.00 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 588.00 Birr/Pc
Total Unit Cost : 2,268.00 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,547.45 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
MODUS BRKL Pcs 1 1,859.00 1,859.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
300+2XG23TC-S11WLAM Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 1,859.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 1,859.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.00
Direct Cost of work item= A+B+C= 1887.00 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 660.45 Birr/Pc
Total Unit Cost : 2,547.45 Birr/Pc
Page 125
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 1,344.60 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
MODUS SB118EP+18W
LAMPS Pcs 1 968.00 968.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 968.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 968.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.00
Direct Cost of work item= A+B+C= 996.00 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 348.60 Birr/Pc
Total Unit Cost : 1,344.60 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 2,909.25 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
MODUS BRKL Pcs 1 2,127.00 2,127.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
375+2XG24TC-S18W LAMP Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,127.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 2,127.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.00
Direct Cost of work item= A+B+C= 2155.00 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 754.25 Birr/Pc
Total Unit Cost : 2,909.25 Birr/Pc
Page 126
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 3,893.40 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
MODUS LLY 236 AL
EP+T82X36W LAMP Pcs 1 2,856.00 2,856.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,856.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 2,856.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.00
Direct Cost of work item= A+B+C= 2884.00 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 1009.40 Birr/Pc
Total Unit Cost : 3,893.40 Birr/Pc

PROJECT: Electrical Installation Cost Break Down For Dessie LABOUR HOURLY OUTPUT: 1.5 Pcs/hr
WORK ITEM: Light Fitting with Lamps EQUIPEMENT:
TOTAL QUANTITY OF WORK ITEM: 1 Pcs RESULT: 3,392.55 Birr/Pc

Material Cost (1:01) Labour (1:02) Equipment Cost (1:03)


**
Indexed
Cost per Labour by Hourly Hourly Type of Hourly
Type of Material Unit Qty * Rate Unit Trade No. UF Cost Cost Equipment No. UF Rental Hourly Cost
MODUS LLY 236 KP Pcs 1 2,485.00 2,485.00 ELEc Forman 0 0.25 0.00 0.00 Tools 2 1.00 3.75 7.50
EP+T82X36W LAMP Electrician 1 1 25.50 25.50
Ass. Elec 0 1 0.00 0.00
DL 1 1 9.00 9.00

Total (1:-01) 2,485.00 Total (1:02) 34.50 Total (1:03) 7.50

A= Materials Unit Cost 2,485.00 Birr/ml B=Manpower Unit Cost 23.00 Birr/hr C=Equipment Unit Cost 5.00
Direct Cost of work item= A+B+C= 2513.00 Birr/Pc
Overhead Cost: +
Profit Cost: 35% 879.55 Birr/Pc
Total Unit Cost : 3,392.55 Birr/Pc
Electrical Material Price List

TO: DESSIE Break Down 1st Quarter 2009

ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
1 Automatic circuit breaker type ABB -
ACB of 25A/1ph pcs 1 90.00 90.00
ACB of 10A/1ph pcs 1 90.00 90.00
ACB of 16A/1ph pcs 1 90.00 90.00
ACB of 20A/1ph pcs 1 90.00 90.00
ACB of 25A/3ph pcs 1 540.00 540.00
ACB of 32A/3ph pcs 1 650.00 650.00
ACB of 40A/3ph pcs 1 910.00 910.00
ACB of 63A/3ph pcs 1 1,560.00 1,560.00
ACB of 100A/3ph pcs 1 3,300.00 3,300.00
ACB of 150A/3ph pcs 1 4,250.00 4,250.00
ACB of 200A/3ph pcs 1 9,000.00 9,000.00
2 Switches FM type LEGRAND SALBEI 1 -
Single switches 10A pcs 1 66.00 66.00
Double (two gang single) switches 10A pcs 1 90.00 90.00
Two way switches 10A pcs 1 88.00 88.00
Two gang Two way switches 10A pcs 1 102.00 102.00
Intermediate Switches 10A pcs 1 102.00 102.00
Tumbler Switches 16A/1Ph pcs 1 310.00 310.00
Dimmer switch pcs 1 500.00 500.00
Rotary switch to select phase voltage with 3 power
indicator lamps (plot lamps) pcs 1 1,100.00 1,100.00
Floating mercury switch pcs 1 410.00 410.00
Sockets flush mounted LEGRAND SALBEI
3 socket outlet approved type -
Flush Mounted Socket outlet 16A with ground pcs 1 88.00 88.00
Surface Mounted Socket outlet 16A with ground pcs 1 88.00 88.00
Table Mounted Socket outlet 16A with ground pcs 1 155.00 155.00
Socket Outlet 25A with ground pcs 1 405.00 405.00
Flush Mounted socket out let water Heater socket pcs 1 88.00 88.00
with
Flushground Terminal
fixed R.J.11 16A/1 ph
Telephone socket out let pcs 1 105.00 105.00
Flush Mounted Twin Socket outlet 16A with ground pcs 1 133.00 133.00
Socket outlets- Legrand suno type -
16A/1p with earth contact water proof(774022
+774041) pcs 1 210.00 210.00
20A/1p with earth contact water proof(774022
+774041) pcs 1 450.00 450.00
25A/1p with earth contact water proof(774022
+774041) pcs 1 550.00 550.00

Page 147
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
20A/3p with earth contact water proof(774022
+774041) pcs 1 500.00
Euro Cable of PVC insulated condutor (Wire)
4 H97V-U 300/500V 1 -
1X1.5MM2 H97V-U 300/500V ml 1 7.00 7.00
1X2.5MM2 " " ml 1 12.00 12.00
1X4MM 2
" " ml 1 19.50 19.50
1X6MM 2
" " ml 1 26.50 26.50
1X10MM 2
H07V-K ml 1 45.65 45.65
1X16MM 2
H07V-K ml 1
1X25MM 2
H07V-K ml 1
5 PVC insulated Conductors of Ethio-cable 1 -
1X1.5MM2 ml 1 5.90 5.90
1X2.5MM2 ml 1 10.50 10.50
1X4MM2 ml 1 16.00 16.00
1X6MM2 ml 1 22.50 22.50
1X10MM2 ml 1 39.03 39.03
1X16MM2 ml 1 -
1X25MM2 ml 1 -
6 Junction Box and Acceseries 1 -
J-Box cover Dia 85 mm pcs 1 7.50 7.50
J-Box cover Dia 65 mm pcs 1 6.50 6.50
Flush mounted telephone Box size 15 Cm x 30 cm pcs 1 980.00 980.00
Flush jun box Tele 30x35x10cm pcs 1 980.00 980.00
Cooper earth road Dis 16mm length 1.5m pcs 1 350.00 350.00
Clamp Dia 32mm pcs 1 -
Surface mounted Jun. Bpx 15x20 cm pcs 1 250.00 250.00
Insulating Tape (Made in Japan) pcs 1 55.00 55.00
Plastic fisher Dia 8 mm pcs 1 -
Wood screw Dia 8 mm pcs 1
Bolts and Nuts pcs 1 10.00 10.00
9 Socket LEGRAND SALBEI 1 -
16, 1Ph with interlocked on/off switch pcs 1 122.00 122.00
20, 1Ph with interlocked on/off switch pcs 1 122.00 122.00
25,1ph with interlocked on/off switch pcs 1 122.00 122.00
20/1ph pcs 1 -
20/1ph gange pcs 1 -
25/1ph pcs 1 -
16/3ph pcs 1 -
20/3ph pcs 1 -
25/3ph pcs 1 -
FM+AM TV outlets pcs 1 410.00 410.00

Page 148
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
10 Industrial Sockets Legrand suno type 1 -
16A/1ph Legrand pcs 1 230.00 230.00
20A/1ph Legrand pcs 1 230.00 230.00
32A/1ph pcs 1 330.00 330.00
16/3Ph 5 pin with interlocked isolator switch 330.00
Legrand pcs 1 330.00
16A/3ph Legrand pcs 1 270.00 270.00
32A/3ph Legrand pcs 1 350.00 350.00
11 Tele Socket 1 -
RJ11 outlets type Legrand suno 7740 38 + 7740 41
or approved equivalent with 4 contacts (surface
mounted) pcs 1 110.00 110.00
RJ45 (Cat 6e) outlets type LEGRAND suno 74213
cat 6e or approved equivalent with 8 contacts
(surface mounted) pcs 1 410.00 410.00
Data pcs 1 -
50 pairs CAT 5 UTP telephone cable partly in PVC
dia.50mm (or equivalent pair as ETC standards) ml 1 -
fire resistant cable 3x1.5sq.mm ml 1 110.00 110.00
12 Junction box/scatolla/ 1 -
φ65 pcs 1 5.00 5.00
φ85 pcs 1 6.00 6.00
13 Flexibile conduit -
φ13 pcs 1 3.00 3.00
φ16 pcs 1 5.00 5.00
14 Rigide conduit -
φ13 ml 1 5.00 5.00
φ16 ml 1 6.50 6.50
φ19 ml 1 7.33 7.33
φ21 ml 1 8.33 8.33
φ25 ml 1 10.00 10.00
φ29 ml 1 12.67 12.67
φ32 ml 1 15.00 15.00
φ35 ml 1 18.33 18.33
15 UPVC Conduits -
φ50 ml 1 25.00 25.00
φ80 ml 1 40.00 40.00
φ110 ml 1 65.00 65.00
φ125 ml 1 117.33 117.33
φ150 ml 1 191.67 191.67
φ160 ml 1 191.67 191.67
φ200 ml 1 358.33 358.33
φ315 ml 1 560.00 560.00
φ450 ml 1 660.00 660.00
φ500 ml 1 750.00 750.00

Page 149
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
16 Galvanized Iron Pipe -
GIP φ1/2'' ml 1 36.83 36.83
GIP φ3/4'' ml 1 53.83 53.83
GIP φ1'' ml 1 70.83 70.83
GIP φ2'' ml 1 148.75 148.75
GIP φ4'' ml 1 400.00 400.00
Angle Iron -
Angle Iron 40*40*2 ml 1 27.40 27.40
Electrode 2.5mm diam pcs 1 1.30 1.30
17 Connector -
Connector Dia 9mm pcs 1 5.00 5.00
Connector cap Dia 7 mm pcs 1 4.20 4.20
18 CIRCUIT BREAKERS (MCB & MCCB) 1 -
2A/QP ACB Breaking capacity= 10KA pcs 1 250.00 250.00
6A/1P ACB ICU= 6KA pcs 1 160.00 160.00
10-32A/1P ACB ICU= 6KA pcs 1 160.00 160.00
40A/1P ACB " pcs 1 200.00 200.00
50A/1P ACB " pcs 1 220.00 220.00
63A/1P ACB " pcs 1 300.00 300.00
6A/3P ACB " pcs 1 650.00 650.00
10-25A/3P ACB " pcs 1 650.00 650.00
32A/3P ACB " pcs 1 750.00 750.00
40A/3P ACB " pcs 1 900.00 900.00
50A/3P ACB " pcs 1 1,500.00 1,500.00
63A/3P ACB " pcs 1 1,900.00 1,900.00
80A/3P MCCB ICU= 16KA pcs 1 2,800.00 2,800.00
100A/3P MCCB " pcs 1 3,500.00 3,500.00
125A/3P MCCB " pcs 1 4,100.00 4,100.00
160A/3P MCCB ICU= 36KA adjusteble pcs 1 5,600.00 5,600.00
200A/3P MCCB ICU= 25KA fixed pcs 1 8,400.00 8,400.00
250A/3P MCCB ICU= 36KA fixed pcs 1 10,500.00 10,500.00
315A/3P MCCB ICU= 36KA adjusteble pcs 1 12,000.00 12,000.00
315A/3P MCCB " pcs 1 12,000.00 12,000.00
400A/3P MCCB " pcs 1 16,500.00 16,500.00
500A/3P MCCB " pcs 1 21,000.00 21,000.00
630A/3P MCCB " pcs 1 27,500.00 27,500.00
800A/3P MCCB ICU= 50KA pcs 1 34,500.00 34,500.00
1000A/3P MCCB " pcs 1 50,214.00 50,214.00
1250A/3P MCCB " pcs 1 64,500.00 64,500.00
1600A/3P MCCB " electronic pcs 1 72,500.00 72,500.00

DB lockable with bus bar rating for steel sheet


19 meatal ABB type IP 65 floor or flush mounting 1 -
Up to 40A (12 spaces & 25% reserve pitch )/1ph pcs 1 900.00 900.00
Up to 63A (24 spaces & 25% reserve pitch)/3ph pcs 1 1,000.00 1,000.00

Page 150
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
Up to 80A (24 spaces & 25% reserve pitch)/3ph pcs 1 1,500.00 1,500.00
Up to 125A (12 spaces & 25% reserve pitch)/3ph pcs 1 4,500.00 4,500.00
Up to 630A ( 36 spaces & 25% reserve pitch)/3ph
12,000.00
170*90cm pcs 1 12,000.00
Up to 300A (24 spaces & 25% reserve pitch)/3ph
100*70cm pcs 1 5,000.00 5,000.00
20 DB lockable with bus bar rating for plastic 1 -
Up to 40A (12 spaces)/1ph pcs 1 900.00 900.00
Up to 125A (12 spaces)/3ph pcs 1 1,000.00 1,000.00
DIN rail mounted terminal blocks pcs 1 -

Surface mounted 500 pairs telephone terminal


blocks (telephone distrubution frame) or punch
down blocks with plastic cover of similar color to
the adjacent wall support structure complete
accessories pcs 1 -
TELE TERMINAL BOX 10 PAIR pcs 1 980.00 980.00
TV Terminal Box of 35x35x11 pcs 1 900.00 900.00
21 Surge arrestor 40KA pcs 1 2,800.00 2,800.00
Current transformer 630/5A pcs 1 900.00 900.00
Voltmeter 0-500V pcs 1 500.00 500.00
Ameter 0-600A pcs 1 500.00 500.00
22 Bare copper wire 1 -
1x150sq.mm ml 1 402.30 402.30
1x120sq.mm ml 1 349.50 349.50
1x70sq.mm ml 1 195.40 195.40
1x50sw.mm ml 1 138.80 138.80
1x16sw.mm ml 1 51.65 51.65
1x10sq.mm ml 1 30.00 30.00
1x6sq.mm ml 1 23.00 23.00
1x4sq.mm ml 1 14.65 14.65
23 Data, TV and Speaker cables
CAT5e STP cable ml 1 12.00 12.00
CAT6e Tele UTP cable ml 1 14.00 14.00
CAT7 LAN UTP cable ml 1 20.00 20.00
RG 6 coaxial cable ml 1 20.00 20.00
twin flat of 2x1.5 sq.mm wire for ball call ml 1 12.00 12.00
twin flat of 2x1 sq.mm wire for speaker ml 1 10.00 10.00
coaxial cable of 2x0.8 sq.mm for tv line ml 1 10.00 10.00
RG 6u coaxial cable for tv line ml 1 10.00 10.00
RG 59u coaxial cable for tv line ml 1 10.00 10.00

Page 151
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
category 6 UTP 4 pair data cable with RJ45
termination (3 meter patch cord and all necessary
accessories. ) pcs 1 90.00 90.00
2x category 6 UTP 4 pair data cable with RJ45
termination (3 meter patch cord and all necessary
accessories. ) pcs 1 180.00 180.00
4x category 6 UTP 4 pair data cable with RJ45
termination (3 meter patch cord and all necessary
accessories. ) pcs 1 360.00 360.00
8x category 6 UTP 4 pair data cable with RJ45
termination (3 meter patch cord and all necessary
accessories. ) pcs 1 720.00 720.00
Rack for wall mounted, 9U weight: Approx. 580g pcs 1 5,800.00 5,800.00
Mixer amplifier 250w and constant voltage 100v pcs 1 38,000.00 38,000.00
6w ceiling mounted speaker with fixing necessaries
access pcs 1 3,200.00 3,200.00
20W column speakers line voltage 100V dimensions
200(w)x80(H)x121(D)mm weight.App.7.7kg with
speaker stand fixture pcs 1 7,500.00 7,500.00

Wireless reciver carrier frequency range: 700-


900MHz, Receving system: Diversity reception,
Sensitivity<2micro volt(S/N-40dB),S/N
Ratio>=90dB, Distortion<=1% Frequency
Responset(+-3dB)50-14000 No complete. pcs 1 21,000.00 21,000.00
Ditto as item 38 but wirless transmitor all complete pcs 1 21,000.00 21,000.00

Desk-top type microphone with separate push


switches for momentary and locked use. Astrong
flexible 10" gooseneck securely fixed to the
aluminium die-cast base. Frequency response: 50-
15,000Hz sensitivity:2.5m V.PA, imedance:600-
OHM all complete pcs 1 7,000.00 7,000.00
Wireless hand held microphone frequency
response:50-15,000Hz,RF out out power
15mV(max), Dynamic range:100dB all complete pcs 1 21,000.00 21,000.00

Hand held micopone with extension cord cable 10m


and with all the necessary accessories all complete. pcs 1 4,500.00 4,500.00
Speaker stand adjustable height:1160-2040mm with
all the necessary accessories all complete pcs 1 4,500.00 4,500.00
fire alarm pcs 1 -
RG 6 coaxial cable pcs 1 11.00 11.00

Page 152
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
Fire alarm control panel with built in terminal
consisting of 1 -
Display and operating terminal 1 -
Microprocessor controlled main CPU 1 -
Detection for 1 loop control panel 1 -
48 hours stand by power supply unit wall mounted
cabinet pcs 1 -
Wall mounted cabinet 1 -
Input output module 1 -
250 AC/10A relay module all complete with the
necessay up-to-date accessories and gears for
automatic detection and operation according to
manufacturers installation instructions 1 -
ionisation smoke detector pcs 1 -
fire alarm addressable reset-able break glass push
button pcs 1 -
24 Bare copper -
1X1.5 S ml 1 4.00 4.00
1X2.5 S ml 1 6.10 6.10
1X1.5 F ml 1 4.40 4.40
1X2.5 F ml 1 6.70 6.70
1X4 S ml 1 14.65 14.65
1X16 ml 1 51.65 51.65
1X25 ml 1 68.25 68.25
1X35 ml 1 95.00 95.00
1X50 ml 1 138.80 138.80
1X70 ml 1 195.40 195.40
1X95 ml 1 266.14 266.14
1X120 ml 1 349.50 349.50
1X150 ml 1 402.30 402.30
1X185 ml 1 519.00 519.00
1X240 ml 1 694.70 694.70
1X300 ml 1 857.70 857.70
2X1.5 F ml 1 10.75 10.75
2X2.5 F ml 1 17.00 17.00
2X4 F ml 1 25.00 25.00
2X6 F ml 1 35.00 35.00
2X10 T ml 1 59.00 59.00
3X1.5 F ml 1 16.50 16.50
3X2.5 F ml 1 23.50 23.50
3X4 F ml 1 36.00 36.00
3X6 F ml 1 52.00 52.00

Page 153
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
3X25/16 ml 1 245.00 245.00
3X35/16 ml 1 320.00 320.00
3X50/25 ml 1 455.00 455.00
3X70/35 ml 1 640.00 640.00
3X95/50 ml 1 880.00 880.00
3X120/70 ml 1 1,104.00 1,104.00
3X150/70 ml 1 1,327.00 1,327.00
3X185/95 ml 1 1,660.00 1,660.00
3X240/120 ml 1 2,100.00 2,100.00
3X300/150 ml 1 2,670.00 2,670.00
4X1.5 F ml 1 18.00 18.00
4X2.5 F ml 1 30.00 30.00
4X4 F ml 1 48.00 48.00
4X6 F ml 1 67.00 67.00
4X10 F ml 1 116.00 116.00
4X16 F ml 1 187.00 187.00
5X4 F ml 1 61.00 61.00
5X6 F ml 1 91.00 91.00
5X10 F ml 1 151.00 151.00
5X16 F ml 1 236.00 236.00
Diameter 16mm& 2400mm long copper rod pcs 1 890.00 890.00
Diameter 16mm& 1500mm long copper rod pcs 1 350.00 350.00
Testing junction boxes at 1.5m above grade level. pcs 1 650.00 650.00

Copper earth bar of 50x5mm (630-700A) and


500mm length with holes every 50mm in three
sections with disconnecting link supporting brackets
every 250mm anchored to wall or floor for a
minimum of 10 earthing connections. pcs 1 2,300.00 2,300.00
Equipotential (Earthining) bonding copper bar
1500x50x10mm size with 7 bolted terminal pcs 1 1,350.00 1,350.00
Copper Air termination rod of 2.5m with roof
mounting bracket and support accessories. pcs 1 4,200.00 4,200.00
25 Bus bar -
Bus bar 63A/3P pcs 1 600.00 600.00
Bus bar 80A/3P pcs 1 1,200.00 1,200.00
Bus bar 100A/3P pcs 1 1,490.00 1,490.00
Bus bar 125A/3P pcs 1 1,800.00 1,800.00
Bus bar 160A/3P pcs 1 2,400.00 2,400.00
Bus bar 250A/3P pcs 1 4,500.00 4,500.00
Bus bar 320A/3P pcs 1 6,500.00 6,500.00
Bus bar 400A/3P pcs 1 7,200.00 7,200.00

Page 154
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
Bus bar 500A/3P pcs 1 8,500.00 8,500.00
Bus bar 630A/3P pcs 1 8,900.00 8,900.00
Bus bar 800A/3P pcs 1 10,000.00 10,000.00
Bus bar 1000A/3P pcs 1 12,000.00 12,000.00
Bus bar 1250A/3P pcs 1 14,200.00 14,200.00
Bus bar 1600A/3P pcs 1 18,000.00 18,000.00
Bus bar 2000A/3P pcs 1 25,000.00 25,000.00
Bus bar 2500A/3P pcs 1 30,000.00 30,000.00
Bus bar 3000A/3P pcs 1 36,000.00 36,000.00
EURO POWER CABLE 0.6/1KV of approved
26 type Or (Equivalent Elsewedy). -
2X1.5MM2 ml 1 15.00 15.00
3X1.5MM 2
ml 1 21.25 21.25
4X1.5MM2 ml 1 32.30 32.30
2X2.5MM 2
ml 1 24.40 24.40
3X2.5MM2 ml 1 30.20 30.20
4X2.5MM 2
ml 1 40.00 40.00
5X2.5MM2 ml 1 63.50 63.50
2X4MM 2
ml 1 35.00 35.00
3X4MM2 ml 1 48.20 48.20
4X4MM 2
ml 1 62.60 62.60
5X4MM3 ml 1 78.20 78.20
2X6MM2 ml 1 46.00 46.00
3X6MM 2
ml 1 67.00 67.00
4X6MM2 ml 1 86.40 86.40
5X6MM 3
ml 1 112.40 112.40
2X10MM2 ml 1 85.00 85.00
3X10MM 2
ml 1 120.00 120.00
4X10MM2 ml 1 147.00 147.00
5X10MM 3
ml 1 187.00 187.00
2X16MM2 ml 1 110.00 110.00
3X16MM 2
ml 1 178.00 178.00
4X16MM 2
ml 1 231.00 231.00
5X16MM3 ml 1 284.00 284.00
3X25/16MM 2
ml 1 425.00 425.00
3X35/16MM2 ml 1 552.50 552.50
3X50/25MM 2
ml 1 637.00 637.00

Page 155
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
3X70/35MM2 ml 1 780.00 780.00
3X95/50MM 2
ml 1 1,085.00 1,085.00
3X120/70MM2 ml 1 1,370.00 1,370.00
3X150/70MM 2
ml 1 1,650.00 1,650.00
3X185/95MM2 ml 1 2,090.00 2,090.00
3X240/120MM 2
ml 1 2,631.00 2,631.00
3X300/150MM2 ml 1 3,448.00 3,448.00
1x16 " 1 71.98 71.98
1x25 " 1 81.90 81.90
1x70 " 1 234.48 234.48
1x120 " 1 419.40 419.40
27 PVC Data cable Tranckate -
10x15mm ml 1 5.10 5.10
10x20mm ml 1 7.08 7.08
16x16mm " 1 9.92 9.92
16x25mm " 1 11.33 11.33
25x40mm " 1 19.83 19.83
40x60mm " 1 34.00 34.00
50x80mm " 1 55.25 55.25
50x100mm " 1 90.67 90.67
100x60mm " 1 99.17 99.17
28 Power Cable Lugs -
Ø10mm pcs 1 6.60 6.60
Ø16mm " 1 10.80 10.80
Ø25mm " 1 15.60 15.60
Ø35mm " 1 21.60 21.60
Ø50mm " 1 33.60 33.60
Ø70mm " 1 49.20 49.20
Ø95mm " 1 66.00 66.00
Ø120mm " 1 93.60 93.60
Ø150mm " 1 114.00 114.00
Ø185mm " 1 144.00 144.00
Ø240mm " 1 180.00 180.00
Ø300mm " 1 240.00 240.00
29 Light Fitting of approved type -
Mareco LUCE Iris 0750.101M with 1*FBT 18W
E27 lamp -65 pcs 1 780.00 780.00
Mareco LUCE Barcellona Opal 1600.152W with
1*SE 70W E27 lamp IP-65 " 1 4,500.00 4,500.00
Mareco LUCE Barcellona Eco1604.152W with
1*SE 70W E27 lamp IP-65 " 1 4,800.00 4,800.00

Page 156
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
Mareco LUCE Sfera-Ura 400 2071.400T with
1*ST-SE 70W E27 lamp IP-65 " 1 2,650.00 2,650.00
Philips TMS 012 with 1xTL-D 18W Lamp " 1 251.00 251.00
Philips TCW 060 with 1xTL-D 36W Lamp " 1 1,050.00 1,050.00
Philips TCW060 with 2xTL-D 36W Lamp " 1 1,290.00 1,290.00
RZB 51060.963 +TC-D 18W LAMP " 1 477.00 477.00
UNOLUX UX-CLASSIC ASN.NC LA T8 " 1 1,680.00 1,680.00
UNOLUX UX-CLASSIC ASN.N PAR " 1 2,100.00 2,100.00
UNOLUX UX-TUBUS 291 " 1 1,520.00 1,520.00
RZB 90756.842 WITH 1XTC-T 18W TUBUS 291 " 1 1,520.00 1,520.00
RZB 311070.842 WITH 1XTC-T 18W " 1 1,445.00 1,445.00
RZB23643.002 with 1*E27 60W IP-40 " 1 1,445.00 1,445.00
RZB211005.with 1*E27 60W IP-44 " 1 1,445.00 1,445.00
MASSIVE 34041/11/10 1x GU10 | max. 35W " 1 1,180.00 1,180.00
RZB 211006 WITH 1*TC-T 18W Lamp PCS 1 1,200.00 1,200.00
RZB 211015 WITH 1*TC-T 18W Lamp " 1 1,315.00 1,315.00
RZB50100.002 WITH 1*TC-D 13W Lamp " 1 680.00 680.00
RZB 22143.913 WITH 1*TC-D 11W Lamp " 1 690.00 690.00
RZB 45135.002 WITH SOCKET & SWITCH
TC.26 15W OMS MIRROR LIGHT " 1 650.00 650.00
RZB 91152.002 WITH 1*QPAR20 60W LAMP IP-
20 " 1 455.00 455.00
PHILIPS TCW 012/1X36W " 1 900.00 900.00
PHILIPS TMW 012/1X36W " 1 900.00 900.00
PENDENT LIGHT MD 8180/3 " 1 2,910.00 2,910.00
CANDELUX C12-9 HALF " 1 742.00 742.00
Mareco LUCE SFERA 1080.201B with 1*FTB
20W E27 lamp. " 1 1,197.00 1,197.00
PELSAN EXIT " 1 2,755.00 2,755.00
RZB 10120.922.79 with 1*TC-DEL 13W IP-20 " 1 580.00 580.00
PHILIPS SGS 102 SON-T 150W " 1 4,200.00 4,200.00
PHILIPS SGS 101 SON-T 70W " 1 2,920.00 2,920.00
Philips TMS 012 with 1xTL-D 36W Lamp pcs 1 350.00 350.00
Philips TMS 012/236 IMK with 2xTL-D 36W pcs 1 550.00 550.00
Lamp
Philips TCW 196 with 1xTL-D 36W Lamp pcs 1 890.00 890.00
Philips TCW196 with 2xTL-D 36W Lamp pcs 1 1,490.00 1,490.00
Philips TCS 600 with 1xTL-S 36W Lamp pcs 1 1,500.00 1,500.00
Philips TMS 600 with 2xTL-S 36W Lamp pcs 1 2,000.00 2,000.00
Incandescent lamp holder pcs 1 16.00 16.00
Incandescent lamp 60 W CFL LAMP pcs 1 45.00 45.00
Philips TCS 098/136 2xTL-D 36w lamp pcs 1 1,950.00 1,950.00
Philips TCS 098/136 1xTL-D 36w lamp pcs 1 1,450.00 1,450.00

Page 157
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
Pelsan E.D.fiberglas bant + 1xTLD36w(TMW 065
Equivalent) pcs 1 900.00 900.00
Pelsan E.D.fiberglas bant + 2xTLD36w(TMW 065
Equivalent) pcs 1 1,150.00 1,150.00
Incadscent Celling Glob type RZB 55154.00X with
1X25W red dark room lamp pcs 1 330.00 330.00
RZB 22141.923 with 1*TC-D 13W lamp pcs 1 900.00 900.00
RZB 56220.003 with 1*TC-D 18W lamp pcs 1 330.00 330.00
RZB 58030.962 with 1*TC-D 18w lamp 1 1,100.00 1,100.00
Massive 32005/31/10 with E27/max 60w pcs 1 700.00 700.00
Gecem GCP 236L with 2xTL-D 36w pcs 1 1,460.00 1,460.00
Philips TCS 098/218/ 2xTL-D 18w lamp pcs 1 1,250.00 1,250.00
Legrand 400413 with 8w + 3hrs emergency kit. pcs 1 2,800.00 2,800.00
Disano Ghost 323133-00 with FLC 70T/lamp or
approved equivalent. pcs 1 2,500.00 2,500.00
Disano 1546 Globo 427236-00 with FLC 2x9 S
lamp. pcs 1 850.00 850.00
Massive 15254/45/10 with 3xE27 max 100w pcs 1 2,900.00 2,900.00
Fumagali G40.121 M28.000.M80/max 80w pcs 1 2,600.00 2,600.00
Philips HGS 101 with SON-H 250w lamp. pcs 1 2,500.00 2,500.00
Philips post top lantern PMMA Ø40cm with SON-T
80w lamp pcs 1 4,500.00 4,500.00
Feal Luce light master 1000sqmm wide with MD/Jm
1000watt lamp. Pcs 1 22,500.00 25,550.00
Feal Luce JET 5 MT 400watt with MT/JM 400watt
pole mounted type. Pcs 1 5,000.00 5,600.00
Feal Luce MIRA PX 40470 CLI with SAP 250watt,
pole mounted type. Pcs 1 4,300.00 4,300.00
DISANO 920 Hydro T8 + FL 2*36watt lamp Pcs 1 1,250.00 1,250.00
DISANO 1601 Floor with diffuser, level finish with
SAP 250watt lamp IP- 67 Pcs 1 4,900.00 4,900.00
LED pool light with 12volt, 25watt ratting and IP-
68 Pcs 1 7,800.00 7,800.00
RZB Perla 58131.922 with TC-D 18W lamp Pcs 1 980.00 980.00
Modus KV 1*36W lamp (prismatic) Pcs 1 1,250.00 1,250.00
Modus LL4*18 ALB ALMATE (louvered) Pcs 1 1,700.00 1,700.00
RZB linear 401000.912.79 with TC-EL 11W lamp Pcs 1 780.00 780.00
Modus KV 2*36W ALB ALMATE (prismatic) Pcs 1 1,500.00 1,500.00
MASSIVE 33012/17/10 with 2 x GU10 max 50W
LAMP Pcs 1 1,050.00 1,050.00

Page 158
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR

MASSIVE 32005/31/10 withE27/max 60W LAMP Pcs 1 780.00 780.00

Page 159
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
PHILIPS Pentura mini TCH128 with 1 x 28W
Lamp. Pcs 1 1,100.00 1,100.00
Interior wall light fitting type RZB 25146.003 +
A60 60W LAMP Pcs 1 578.00 578.00
Exterior wall light fitting type RZB 22130.003 +
A60 100W LAMP Pcs 1 856.00 856.00
Emergency light fitting type RZB 671467.752 with
T16 8W/3h lamp and EXIT sign Pcs 1 3,695.00 3,695.00
RZB 921385.774 + 1XHIT-CE-P 150W LAMP Pcs 1 4,651.00 4,651.00
RZB 751097.773 + 1XHIT-CE 150W LAMP Pcs 1 1,783.00 1,783.00
RZB 581291.959 with 1xTCD 26W LAMP Pcs 1 1,310.00 1,310.00
RZB 33708.952 with 1xTCD 26W LAMP Pcs 1 1,652.00 1,652.00
MODUS BRKL 300+2XG23TC-S11WLAM Pcs 1 1,859.00 1,859.00
MODUS SB118EP+18W LAMPS Pcs 1 968.00 968.00
MODUS BRKL 375+2XG24TC-S18W LAMP Pcs 1 2,127.00 2,127.00
MODUS LLY 236 AL EP+T82X36W LAMP Pcs 1 2,856.00 2,856.00
MODUS LLY 236 KP EP+T82X36W LAMP Pcs 1 2,485.00 2,485.00
Supply and install Lighting Steel Pole Of
30 Octagonal (Imported type) -
Steel Pole Height 3M Pcs 1 4,200.00 4,200.00
Steel Pole Height 6M Pcs 1 7,500.00 7,500.00
Steel Pole Height 8M Pcs 1 11,000.00 11,000.00
Steel Pole Height 9M Pcs 1 13,700.00 13,700.00
Steel Pole Height 12M Pcs 1 16,200.00 16,200.00
Steel Pole Height 14M Pcs 1 18,500.00 18,500.00
Steel Pole Height 20M Pcs 1 30,000.00 30,000.00
31 MAGNETIC SWITCH -
CONTACTOR 6/3P Pcs 1 1,250.00 1,250.00
CONTACTOR 10/3P Pcs 1 1,250.00 1,250.00
CONTACTOR 16/3P Pcs 1 1,700.00 1,700.00
CONTACTOR 25/3P Pcs 1 2,328.00 2,328.00
CONTACTOR 32/3P Pcs 1 2,987.00 2,987.00
CONTACTOR 40/3P Pcs 1 4,300.00 4,300.00
CONTACTOR 60/3P Pcs 1 6,300.00 6,300.00
CONTACTOR 90/3P Pcs 1 9,500.00 9,500.00
CONTRACTOR SINGLE PHASE Pcs 1 1,020.00 1,020.00
32 FUSED SWITCH -
63A/3P Pcs 1 2,950.00 2,950.00
125A/3P Pcs 1 3,500.00 3,500.00
250A/3P Pcs 1 4,560.00 4,560.00
400A/3P Pcs 1 6,895.00 6,895.00
630A/3P Pcs 1 8,574.00 8,574.00

Page 160
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
33 Controlling switches and connector -
Spring loaded on/off bell call push button Pcs 1 75.00 75.00
20A/1p on/off push button switch Pcs 1 650.00 650.00
Tumbler switch of 10A/1p Pcs 1 250.00 250.00
Photocell Assy. (mounting outside WPB) Pcs 1 980.00 980.00
Timer and coil Pcs 1 1,200.00 1,200.00
Contactor of 200-220V/1ph, 25A pcs 1 1,100.00 1,100.00
over load relay 9-13A pcs 1 1,000.00 1,000.00
USHA 220V, 50Hz Rotary Speed adjusting On/Off
fan switch pcs 1 450.00 450.00
34 Bell Call system

Indicator 18 digits with Transformer


220/12v/25vA, call canceling master push button
and buzzer " 1 4,355.00 4,355.00
Indicator 16 digits with Transformer
220/12v/25vA, call canceling master push button
and buzzer " 1 4,000.00 4,000.00
ditto,but for 6 digits indicator " 1 2,000.00 2,000.00
ditto, but for 4 digits indicator " 1 2,000.00 2,000.00
Transformer 220/12v/25vA " 1 450.00 450.00
Buzzer 220V-250V " 1 220.00 220.00
34 Ventilation System and Accessories -
O.ERRE Axial fan STANDARD 12 with an
ordering code of 0015800 max dia of Hole Ø
120mm at 50Hz 220/240V, max flow rate (m³/h)
125, max. press. 29Pa and max. power demand of
13W.
" 1 950.00 950.00
O.ERRE Axial fan STANDARD 15 with an
ordering code of 0016100 max dia of Hole Ø
150mm at 50Hz 220/240V, max flow rate (m³/h)
230 max. press. 41Pa and max. power demand of
30W. " 1 1,410.00 1,410.00
O.ERRE Axial fan VENTILOR 20/8 AR with an
ordering code of 0019000 max dia of Hole Ø 225-
235mm at 50Hz 220/240V, max flow rate (m³/h)
450 max. press. 118Pa and max. power demand of
50W.
" 1 3,950.00 3,950.00
O.ERRE Axial fan VENTILOR 25/10 AR with an
ordering code of 0019200 max dia of Hole Ø275-
285mm at 50Hz 220/240V, max flow rate (m³/h)
750, max. press. 59Pa and max. power demand of
60W. " 1 4,950.00 4,950.00

Page 161
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
O.ERRE Axial fan DIVERSO IN 240 with an
ordering code of 0083200 max dia of Hole Ø100mm
at 50Hz 220/240V, max flow rate (m³/h) 270, max.
press. 442Pa and max. power demand of 80W.
" 1 4,200.00 4,200.00
O.ERRE Axial fan AXIA MD 30 4M with an
ordering code of 0073003 IP-55 with single phase
motor/4Pole RPM 1400 at 50/60Hz 230V, max flow
rate (m³/h) 1800, max. press. 135Pa and max. power
demand of 100W.
" 1 5,100.00 5,100.00
O.ERRE Axial fan AXIA MD 40 4M with an
ordering code of 0073007 IP55 with single phase
motor/4Pole RPM 1350 at 50/60Hz 230V, max flow
rate (m³/h) 3500, max. press. 155Pa and max. power
demand of 170W.
" 1 6,100.00 6,100.00
O.ERRE Ceiling Fan OASIS 3KR 140 with an
ordering code of 0024700 max dia of blades Ø
140mm at 50Hz 220/240V, max flow rate (m³/h)
16,000 and max. power demand of 60W. " 1 2,800.00 2,800.00
35 Cable Tray -
Galvanized steel cable tray, and of 450x100mm
section for POWER, perforated type including
ceiling support bracket every 1.5m, and other fixing
accessories.
ml 1 320.00 320.00
Galvanized steel T-SECTION of 450x450x450mm
including ceiling support brackets, bonding, and
other fixing accessories. Pcs 1 350.00 350.00
Galvanized steel ELBOW of 450mm including
ceiling support brackets, bonding, and other fixing
accessories. Pcs 1 350.00 350.00
Galvanized steel cable tray, and of 300x100mm
section for DATA/TEL, perforated type including
ceiling support bracket every 1.5m, bends, and other
fixing accessories.
ml 1 260.00 260.00
Galvanized steel T-SECTION of 300x300x300mm
including ceiling support brackets, bonding, and
other fixing accessories. Pcs 1 350.00 350.00
Galvanized steel ELBOW of 300mm including
ceiling support brackets, bonding, and other fixing
accessories. Pcs 1 350.00 350.00

Page 162
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
36 Cable Ladder -
Steel cable ladder, made of galvanized C-section
metal, with supports every 500mm, and of
600x100mm fixed inside riser anchored to wall. ml 1 600.00 600.00
37 Oil Immersed Transformer
General Technical Data of the oil immersed and
hermetically sealed Transformer.
Protective degrees
HV compartment: IP43
Transfomer compartment: IP23
LV compartment: IP43
Type KTMU 18 HC 630
Rated Power, KVA 1000
Voltage ratio,V 15000+/-2x2.5%/400
Frequency,Hz 50
Vector Group Dyn 5
Standard IEC 76
Cooling ONAN
Insulation level windings, KV LI AC
38/LI_AC3
No load losses, W 1200
Load losses, W 56300
The LV part should be provided with
1600A, MCCB 3ph, 70KA

Provide all technical data with sketch and catalouge. pc 1 2,133,000.00 2,133,000.00

LV, outdoor, oil immersed 315KVA, 15KV,


380/220V, 50HZ 3-ph pole mountable Transformer pc 1 400,000.00 400,000.00
LV outdoor, oil immersed 100KVA, 15kv/380v,
220v, 3ph, 50Hz, 125A/3ph fuse, Dyn11 or Dyn5
configuration pole mountable distribution
transformer with all mounting accessories pc 1 255,000.00 255,000.00

Page 163
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
38 Generator of specified technical data -
Smax .........................72 KVA
voltage .....................380volts, 50Hz, 3-ph
speed……………………… 1500rpm PF…… 0.8
cooling method……… water cooled
The generator shall be equipped with:
automatic voltage regulator (AVR)
automatic transfer switch (ATS)
HCB of 125A/3ph
ON/OFF switch, current, voltage and frequency
measuring.

pc 1 625,000.00 625,000.00
(DB)distribution board steel enclosure flush
39 mounting with locable door -
consisting 1-4pcs ckt.brs with 20A/1ph bus bar &
25% reserve. pc 1 800 800.00
consisting 5-6pcs ckt.br with 20A/1ph bus bar &
25% reserve. pc 1 800 800.00
consisting 7-9pcs ckt.br with 20A/1ph bus bar &
25% reserve. pc 1 1000 1,000.00
consisting 7-9pcs ckt.br with 160A/3ph bus bar &
25% reserve. pc 1 1000 1,000.00
consisting 10-18pcs with 160A/3ph bus bar & 25%
reserve. pc 1 2500 2,500.00
consisting 10-18pcs with 40A/3ph bus bar & 25%
reserve. pc 1 1300 1,300.00
consisting 10-18pcs with 25A/3ph bus bar & 25%
reserve. pc 1 1300 1,300.00
consisting 19-27pcs with 32A/3ph bus bar & 25%
reserve. pc 1 2000 2,000.00
consisting 19-27pcs with 50A/3ph bus bar & 25%
reserve. pc 1 2000 2,000.00
consisting 19-27pcs with 63A/3ph bus bar & 25%
reserve. pc 1 2000 2,000.00
consisting 28-42pcs with 40A/3ph bus bar & 25%
reserve. pc 1 2500 2,500.00
consisting 28-42pcs with 100A/3ph bus bar & 25%
reserve. pc 1 4000 4,000.00
consisting 28-42pcs with 150A/3ph bus bar & 25%
reserve. pc 1 4000 4,000.00

Page 164
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
water proof box (WPB) steel enclosure, surface
mounting and wall mounting with lockable door
consisting 1-4pcs with 32A/3ph bus bar & 25%
reserve pc 1 500 500.00

(DB)distribution board plastic enclosure flush


40 mounting -
consisting 1-4pcs ckt.brs with 20A/1ph bus bar &
25% reserve. Pcs 1 200 200.00
consisting 5-6pcs ckt.br with 40A/1ph bus bar &
25% reserve. Pcs 1 250 250.00
consisting 7-9pcs ckt.br with 63A/1ph bus bar &
25% reserve. Pcs 1 300 300.00
consisting 10-18pcs ckt.br with 100A/3ph bus bar &
25% reserve. Pcs 1 350 350.00
flush mounting plastic enclosure 35cmx30cmx10cm
box can consisting of 1pcs 16A/1p breaker Pcs 1 690 690.00
flush mounting switch box(TSB-1) can consisting of
14pcs Pcs 1 2000 2,000.00
flush mounting switch box(TSB-3&4) which can
consist of 12pcs Pcs 1 1800 1,800.00
flush mounting switch box(TSB-2) which can
consist of 8pcs Pcs 1 1400 1,400.00
flush mounting switch box(TSB-R) which can
consist of 7pcs Pcs 1 1300 1,300.00
flush mounting switch box(TSB-L) which can
consist of 4pcs Pcs 1 1000 1,000.00
flush mounting switch box(TSB-L) which can
consist of 2pcs Pcs 1 800 800.00
flush mounting switch box(TSB-L) which can
consist of 1pcs Pcs 1 690 690.00
Surface mounting Data Terminal Box or Patch
(PP24P/C2960S) Pcs 1 8450 8,450.00
TV terminal Boxes (TVTB) Pcs 1 950 950.00
41 LIGHTINING ARRESTER -
PREVENTOR P1 WITH 4.6M MAST Pcs 1 29,652.00 29,652.00
PREVENTOR P2 WITH 4.6M MAST Pcs 1 35,624.00 35,624.00
PREVENTOR P3 WITH 6M MAST Pcs 1 42,985.00 42,985.00
PREVENTOR P4 WITH 6M MAST Pcs 1 62,532.00 62,532.00
25X3MM2 LIGHTLY INSULATED COPEPR
TAPE INCLUDING CLIPS ETC. Pcs 1 852.00 852.00
TEST CLAMP FOR 50/70 MM 2
Pcs 1 650.00 650.00

Page 165
ITEM U.PRICE
No DESCRIPTION UNIT Qty* BIRR TOTAL BIRR
TEST CLAMP FOR 25X3MM2 Pcs 1 542.00 542.00
EARTH ROD 1200X16MM Pcs 1 295.00 295.00
AIR TERMINAL ROD 1.0M WITH MULTIPLE
POINT AND BASE Pcs 1 3,265.00 3,265.00
30x3.5mm galvanized steel ring earth termination
net work. ML 1 858.00 858.00

Page 166

You might also like