Costing
Example 8.4:- Calculate the quantities of different items of the figure
shown in below
SEPTIC TANK
Detailed Estimates 100
S.No. Particulars of Items No. L B H Q Explanation
1 Earth work excation upto
3
G.L. 1 4.0 2.0 1.9 15.2m
3
2. C.C. (1:4:8)bed 1 4.0 2.0 0.3 2.4m
3. Brick masonary in CM
1:4 for side walls
3.7
1.7
0.3
1.4
2.0
0.15
1.85
1800
400
1400
4100
1600
300
1300
4750
225 0 1.60
150
4450
1950
4350 1x1
1850 1x1
160
100
500
1600 1000
700
1800
600
1600
Detailed Estimates 106
o. Particulars of Items No. L B H Q Explanation
1. Earth work excavation
in non cohesive soils
like sandy soils with an
intial lead & lift π
a) Soak pit 1 x1.62 3.86 7.76
4
b) side brick wall 1 π (2.06 2 −1.6 2 ) 1.16
1.53
4
Total 9.29
2. Brick work in CM (1:5)
with country bricks
including cost and
conveyance etc
complete alround the
pit
π
)
230 1600 230 1 4 (2.062 −1.62 0.9 1.19