Basic Formulas

Relaxation Contingency
SMV =Basic Time+ ( Basic Time x Allowance ) Observed Time Allowance
Rating Factor Allowance

BasicTime=Observed Time x Rating If Performed at a pace greater than standard pace

Observed Time=Total Cycle time/ No .of Cycles Earn Minutes


Efficiency= x 100
Observed Rating x Standard Rating Available Minutes
Rating= Basic Time
Standard Rating
Earn Minutes=No. of output x SMV Standard Time
Standard Time=Observerd time x Observed rating+ Allowances
Available Mins=Working Hours/ Manpower

60 60
Capacity= Target ( hr )= x Efficiency
Cycle time(mins) Operation SMV ( mins )

Line Output Line Output


Machine Productivity= Labor Productivity =
no of machines No . of Manpower (Line)

Total Manpower Line Output


Man−Machine Ratio= Machine Productivity =
Total Machine No . of Manpower (line)

Total working mins x No . of operators


Line Target = X Line Efficiency
Garment SMV

Actual Machine running time


Machine Utilization %= x 100
Time Available

Total cost incurred ∈Manpower


Cost Per Minute=
Total available working mins x No . of Manpower (line)

Total cost incurred ∈Production


Production Cost Per pcs (Day)=
Total Output

Total cost incurred ∈ prdn per machine


Cost of Production ( Day )= x Targeted Effieciency
Working Hours x 60