:9548/999/GOG/M/001
Pre-Feasibility Report for REV. NO.: 1
Lara Super Thermal Power Project, Stage-II REV. DATE: 23.05.2018
(2x800 MW) Page 1 of 29
FOR
NTPC Limited
(A Government of India Enterprise)
May, 2018
DOC. NO.:9548/999/GOG/M/001
Pre-Feasibility Report for REV. NO.: 1
Lara Super Thermal Power Project, Stage-II REV. DATE: 23.05.2018
(2x800 MW) Page 2 of 29
TABLE OF CONTENTS
Water Requirement Make up water requirement for Lara-II (2x800 MW) project
and Availability: would be about 4080 m3/hr with ash water recirculation
system and about 5300 m3/hr with once through ash water
system.
WRD, Govt. of Chhattisgarh have accorded Water
availability confirmation of 45 MCM (5137 m3/hr) for Stage-
I (2x800 MW) and 68 MCM (7763 m3/hr) for Stage-II of
Lara STPP from Saradih Barrage on River Mahanadi.
A closed cycle cooling water system using Induced Draft
DOC. NO.:9548/999/GOG/M/001
Pre-Feasibility Report for REV. NO.: 1
Lara Super Thermal Power Project, Stage-II REV. DATE: 23.05.2018
(2x800 MW) Page 4 of 29
2.3 Need for the Project & Its Importance to the Country & Region
Power is one of the key infrastructural elements for the economic growth of a country.
Proposed Lara STPP, Stage-II, is envisaged as a base load station to meet the power
demand of Chhattisgarh and other States in Western Region.
Anticipated power supply position during 2017-18 to 2021-22 excluding Lara STPP
Stage-II (1600 MW)
All India (Table-1)
REGION UNITS 2017-18 2018-19 2019-20 2020-21 2021-22
PEAK AVAILABILTY MW 227586.1 240077.7 251534.3 263361 271912
PEAK LOAD MW 214093 229465 246068 264041 283470
SURPLUS/DEFICIT MW 13493.1 10612.7 5466.3 -680 -11558
SURPLUS/DEFICIT % 6.30 4.60 2.20 -0.30 -4.10
ENERGY AVAILABILTY MKWH 1638804.7 1736164.3 1826191.4 1873135.6 1972226.1
ENERGY REQUIREMENT MKWH 1450982 1552008 1660783 1778109 1904861
SURPLUS/DEFICIT MKWH 187822.7 184156.3 165408.4 95026.6 67365.1
SURPLUS/DEFICIT % 12.90 11.90 10.00 5.30 3.50
Western Region (Table-2)
REGION UNITS 2017-18 2018-19 2019-20 2020-21 2021-22
PEAK AVAILABILTY MW 81512.9 86220.7 88605.8 91718.5 92863.9
PEAK LOAD MW 65871 70383 75223 80441 86054
SURPLUS/DEFICIT MW 15641.9 15837.7 13382.8 11277.5 6809.9
SURPLUS/DEFICIT % 23.70 22.50 17.80 14.00 7.90
ENERGY AVAILABILTY MKWH 606119.3 645189.4 672789.9 687520.9 710125.5
ENERGY REQUIREMENT MKWH 417342 444735 474042 505534 539310
SURPLUS/DEFICIT MKWH 188777.3 200454.4 198747.9 181986.9 170815.5
SURPLUS/DEFICIT % 45.20 45.10 41.90 36.00 31.70
Chhattisgarh (Table-3)
REGION UNITS 2017-18 2018-19 2019-20 2020-21 2021-22
PEAK AVAILABILTY MW 15537.4 16236.6 16749 16862.8 17092.2
PEAK LOAD MW 5028 5385 5755 6162 6599
SURPLUS/DEFICIT MW 10509.4 10851.6 10994 10700.8 10493.2
SURPLUS/DEFICIT % 209.00 201.50 191.00 173.70 159.00
ENERGY AVAILABILTY MKWH 121543.6 131109.6 133750.6 133303.7 138568.4
ENERGY REQUIREMENT MKWH 25989 27833 29743 31850 34106
SURPLUS/DEFICIT MKWH 95554.6 103276.6 104007.6 101453.7 104462.4
SURPLUS/DEFICIT % 367.70 371.10 349.70 318.50 306.30
The studies have been carried out excluding capacity addition from renewable resources
during 12th and 13th Plan as the year wise renewable capacity addition plan is not available.
The government has set the target of capacity achievement from renewable sources till
2022 to be 175 GW. The capacity addition from renewable resources shall help in
mitigating power (Peak and Energy) shortages on all India basis.
DOC. NO.:9548/999/GOG/M/001
Pre-Feasibility Report for REV. NO.: 1
Lara Super Thermal Power Project, Stage-II REV. DATE: 23.05.2018
(2x800 MW) Page 8 of 29
Anticipated power supply position during 2017-18 to 2021-22 including Lara STPP
Stage-II (1600 MW)
All India (Table-4)
REGION UNITS 2017-18 2018-19 2019-20 2020-21 2021-22
PEAK AVAILABILTY MW 227586.1 240077.7 251534.3 263361 271912
PEAK LOAD MW 214093 229465 246068 264041 283470
SURPLUS/DEFICIT MW 13493.1 10612.7 5466.3 -680 -11558
SURPLUS/DEFICIT % 6.30 4.60 2.20 -0.30 -4.10
ENERGY AVAILABILTY MKWH 1638804.7 1736164.3 1826191.4 1873135.6 1972226.1
ENERGY REQUIREMENT MKWH 1450982 1552008 1660783 1778109 1904861
SURPLUS/DEFICIT MKWH 187822.7 184156.3 165408.4 95026.6 67365.1
SURPLUS/DEFICIT % 12.90 11.90 10.00 5.30 3.50
Western Region (Table-5)
REGION UNITS 2017-18 2018-19 2019-20 2020-21 2021-22
PEAK AVAILABILTY MW 81512.9 86220.7 88605.8 91718.5 93905.8
PEAK LOAD MW 65871 70383 75223 80441 86054
SURPLUS/DEFICIT MW 15641.9 15837.7 13382.8 11277.5 7851.8
SURPLUS/DEFICIT % 23.70 22.50 17.80 14.00 9.10
ENERGY AVAILABILTY MKWH 606119.3 645189.4 672789.9 687520.9 715616.4
ENERGY REQUIREMENT MKWH 417342 444735 474042 505534 539310
SURPLUS/DEFICIT MKWH 188777.3 200454.4 198747.9 181986.9 176306.4
SURPLUS/DEFICIT % 45.20 45.10 41.90 36.00 32.70
Chhattisgarh (Table-6)
REGION UNITS 2017-18 2018-19 2019-20 2020-21 2021-22
PEAK
AVAILABILTY MW 15537.4 16236.6 16749 16862.8 17705.1
PEAK LOAD MW 5028 5385 5755 6162 6599
SURPLUS/DEFICIT MW 10509.4 10851.6 10994 10700.8 11106.1
SURPLUS/DEFICIT % 209.00 201.50 191.00 173.70 168.30
ENERGY
AVAILABILTY MKWH 121543.6 131109.6 133750.6 133303.7 141798.3
ENERGY
REQUIREMENT MKWH 25989 27833 29743 31850 34106
SURPLUS/DEFICIT MKWH 95554.6 103276.6 104007.6 101453.7 107692.3
SURPLUS/DEFICIT % 367.70 371.10 349.70 318.50 315.80
From the above, it can be seen that there is overall peak deficit of 4.10% in the country
during 2021-22 excluding/ including Lara STPP, Stage-II (2x800 MW) which is planned to
be commissioned during 12th Plan period, is justified from demand supply consideration.
DOC. NO.:9548/999/GOG/M/001
Pre-Feasibility Report for REV. NO.: 1
Lara Super Thermal Power Project, Stage-II REV. DATE: 23.05.2018
(2x800 MW) Page 9 of 29
is carried out of the boiler along with the flue gas. The flue gas, after heat
recovery, is passed through the electrostatic precipitators, where the ash is trapped
by electrodes charged with high voltage electricity.
(5) The flue gases exiting from the Electrostatic Precipitators (ESPs) shall be treated
in Flue Gas Desulphurisation System and discharged through a tall chimney for
wider dispersal of remaining ash particles and gases. Suitable system for control
of NOx shall also be established. The ash collected in the ESP hoppers is
extracted in dry form and conveyed to dry ash storage silos from where it is
supplied to user industries.
(6) Any unused part of fly ash is mixed with water and conveyed to ash disposal area
in a slurry form.
(7) The steam, after passing through the turbines, is condensed back into water in
condensers and the same is re-used as a boiler feed water for making steam. The
reasons for condensing and reusing the steam are following: -
The cost of boiler feed water is very high as it is very pure demineralised
water hence reuse is economical.
The use of condenser lowers the temperature at the exit end and hence
increases the efficiency of the turbine.
(8) The condenser contains tubes through which cold water is constantly pumped. The
steam passing around the tubes of condenser loses heat and condenses as water.
During this process, the steam gets cooled while cooling water gets heated up (by
about 10oC). This hot water is cooled in a cooling tower and recycled for cooling.
However, in order to control dissolved solids, a certain amount of blow down is
required from the cooling towers, which is used in the plant for other usages such as
service water, coal dust suppression etc.
4 Site Analysis
4.1 Connectivity
The project site is approachable from NH-200 (Raigarh–Sarangarh) via Kondatarai
through State PWD Road. The nearest rail head Raigarh Railway Station (on South
East Central Railway, Howrah-Bilaspur Broad Gauge), is approximately 30 km from
the project site. The nearest commercial airport, Raipur is about 250 km from the
project site.
5 Brief Planning
5.1 Planning Concept
As discussed in Para 2.4 above, the planning of power projects is based on demand &
supply scenario of the country/ region, which is based on Electrical Power Survey
conducted by CEA. Once the necessity of the project, based on demand and supply
gap is established, the site for project is selected based on the following
considerations:
i. Availability of suitable and adequate land
ii. Availability of reliable source of water
iii. Distance from source of coal
iv. Road and railway access
v. Availability of infrastructural facilities
vi. Conformity of Environmental Guidelines
6 Proposed Infrastructure
6.1 Industrial Area
Major part of the project shall be developed as Industrial Area – consisting of main
plant area and ash disposal area. Major components of main power house complex are
o Main Plant Building
o Coal Handling & Storage Area
o Fuel Oil Handling & Storage Area
o Makeup Water System and Water Treatment Plant
o Cooling System with Cooling Towers
o Effluent Treatment Plant
o Electrostatic Precipitators, NOx Control System, FGD System and Chimney
o Ash Handling Plant
o Limestone and Gypsum Handling and Storage Area
o Switch Yard etc.
In addition, the project will have an ash disposal area connected with the main plant
area through service roads and ash pipelines.
Space provision have also been kept for lay-down and pre-assembly activities, stores,
contractor’s offices etc. Construction offices and storage sheds are located close to
the main approach road to the plant. Administration Building is proposed to be
located outside the plant boundary near the main approach road.
6.5 Connectivity
The site is having an excellent accessibility and communication facilities and it is well
connected through NH-200 (Raigarh–Sarangarh) via Kondatarai through State PWD
Road. The nearest rail head Raigarh Railway Station (on South East Central Railway,
Howrah-Bilaspur Broad Gauge), is approximately 30 km from the project site. The
nearest commercial airport, Raipur is about 250 km from the project site.
various purposes. Unused fly ash and bottom ash shall be disposed off in the ash
pond. A blanket of water shall be maintained over the entire ash pond to control
fugitive dust emission. After the ash pond is abandoned, it shall be reclaimed through
green vegetation.
7 Coal Transportation
Mode of coal transportation from the coal mines to the power plant is by MGR/ IR.
8 Power Evacuation
Lara STPP, Stage-II shall be the extension project of Lara STPP, Stage-I (2X800
MW) and would comprise of two (2) nos. of coal fired unit of capacity 800 MW each.
Step up/power evacuation voltage of Stage-I of the project is 400KV. Under Stage-I
of the project, provision of one no. 400 kV quad Double Circuit line up to Champa
pooling has been kept for connectivity and evacuation of power as finalized in
Western Region Standing Committee Meeting/LTA& Connectivity meeting.
Health Camps
Water Supply Provision of potable drinking water supply in affected villages
through wells, hand pumps, tankers etc
Awareness campaigns for water borne diseases, sanitation and
hygiene
Capacity Setting up new ITI with necessary infrastructure and machinery
Building
Sponsorship of PAPs/ wards
Short term courses for skill up gradation
Vocational training (dairy, poultry, bee keeping, sericulture)
Specific Programmes for Ladies (stitching, embroidery, tailoring
etc)
Infrastructure Construction of roads, drainage, community halls, school
Development buildings, health centres, street lighting, equipments to
educational institutions, public utilities, sanitation facilities,
Health centres etc in nearby and affected area
Sports and Regular Rural Sports
Culture
Facilitation/ Sponsorship to local talent
Promotion of local festivals
Participation of local community in national festivals
Preservation of culture and heritage
source of income for local people. With the implementation of the Stage-I of the
project, employment opportunities, communication, medical facilities, education and
skill up-gradation facilities etc. in the area have already improved.
Besides, there will be marked improvement for various facilities in the local areas as
shown below.
Improvement in medical and health care system.
Improvement in educational services.
Improvement of drinking water & sanitation facilities.
Vocational training facilities for local eligible youth of local community to enable
them to seek employment in suitable project operations and elsewhere.
Benefit to the State and the Central Governments through financial revenues from
this project directly and also indirectly.
Employment opportunities to local persons of different skills and trades.
Improvement in the socio-economic conditions of the inhabitants of the are
DOC. NO.:9548/999/GOG/M/001
Pre-Feasibility Report for REV. NO.: 1
Lara Super Thermal Power Project, Stage-II REV. DATE: 23.05.2018
(2x800 MW) Page 21 of 29
3. Boiler
Condensate
Steam Fly Ash 14. Dry Ash Storage
13. Cooling 12. Cooling
Silos
Tower System Steam
4. Turbine
Ash
Utilisation
15. Ash Disposal
5. Generator
Area
Cooling Tower Bottom Ash
Blow down Boiler Blow down
6. Transformer
7. Transmission
Towers
Exhibit-III: Schematic Representation of Thermal Power Generation in Coal Based Thermal Power Plant
DOC. NO.:9548/999/GOG/M/001
Pre-Feasibility Report for REV. NO.: 1
Lara Super Thermal Power Project, Stage-II REV. DATE: 23.05.2018
(2x800 MW) Page 24 of 29
Annexure-I
DOC. NO.:9548/999/GOG/M/001
Pre-Feasibility Report for REV. NO.: 1
Lara Super Thermal Power Project, Stage-II REV. DATE: 23.05.2018
(2x800 MW) Page 25 of 29
Annexure-II
DOC. NO.:9548/999/GOG/M/001
Pre-Feasibility Report for REV. NO.: 1
Lara Super Thermal Power Project, Stage-II REV. DATE: 23.05.2018
(2x800 MW) Page 26 of 29
DOC. NO.:9548/999/GOG/M/001
Pre-Feasibility Report for REV. NO.: 1
Lara Super Thermal Power Project, Stage-II REV. DATE: 23.05.2018
(2x800 MW) Page 27 of 29
DOC. NO.:9548/999/GOG/M/001
Pre-Feasibility Report for REV. NO.: 1
Lara Super Thermal Power Project, Stage-II REV. DATE: 23.05.2018
(2x800 MW) Page 28 of 29
Annexure-III
DOC. NO.:9548/999/GOG/M/001
Pre-Feasibility Report for REV. NO.: 1
Lara Super Thermal Power Project, Stage-II REV. DATE: 23.05.2018
(2x800 MW) Page 29 of 29