You are on page 1of 24

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT

Summary

Preliminaries and General (18% of total cost)

Excavation $ 14,669.20

Concrete Work $ 58,620.80

Reinforcing Steel $ 8,023.20

Concrete Blockwork $ 67,760.00

Carpentry $ 93,479.73

Roofing $ 21,249.90

Door and Window $ 9,550.97

Solid Plaster $ 7,950.68

Painting $ 22,018.39

Subtotal $ 303,322.87

Labor (40%) $ 121,329.15

Preliminaries and General (18% of total cost) $ 54,598.12

Subtotal $ 479,250.14

Profit 10% $ 47,925.01

Subtotal $ 527,175.15

Tax 7.5% $ 39,538.14


AMOUNT OF TENDER $ 566,713.29
BOQ FOR PROPOSED 2 STORY BUILING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS/WORKS QTY UNIT RATE AMOUNT


1 Preliminaries and General
Refer to the drawings and Specification for full details and
1 descriptions of materials and workmanship

Refer to the General and Special Conditions of contract


2 and Tender and to the Preliminary and General section of
the Specification
The scope of this Contract consists of the construction of a
3 new 2 storey building at XXX location.

This Bill of Quantities has been prepared generally in


accordance with NZS 4202:1995 Standard Method of
4 measurement of Building Works, but no deviation from
same shall form the basis of a claim
Refer to the General Rules of the NZS 4202:1995 Standard
5 Method of Measurement of Building Works
The following metric abbreviations for units have been
6 used:
m3 : Cubic Metres
m2 : Square Metres
m : Linear Metres
mm : Millimetres
no : Number
kg : Kilogram
MPa : Megapascal
The Bills of Quantities are not to be used as a basis for
7 ordering materials, nor as a basis for dimensions of
manufacture

Site works
Supervision
Allowance for full-time supervision of the works by a
8 suitable qualified and experienced individual as named and
detailed within the tender document
Additional Items
9 The contractor should read and familiarise himself with the 1
preliminaries section of the tender document item
Site Clearance
10 Allowance for site Clearance 1 item $ 1,500.00
Landscaping
11 Allow a provisional sum for landscaping to site 1 item $ 500.00
Sewerage Work
12 Allow the provisional sum of SBD$1000 for sewage 1
connection inclusive of all excavation,backfilling etc item $ 1,500.00
Water Connection
13 Allowance for connecting water to the local mains water 1
supply item $ 2,500.00
14 Allowance for providing and maintaining First Aid Kit and 1
all necessary safety equipment item $ 250.00
BOQ FOR PROPOSED 2 STORY BUILING AT XXX LOCATION

AMOUNT OF PRELIMINARIES AND SITE WORKS


CARRIED TO SUMMARY $ 3,750.00
BOQ FOR PROPOSED 2 STORY BUILING AT XXX LOCATION
BOQ FOR PROPOSED 2 STORY BUILING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


2 EXCAVATION

Clear Site and Surface Excavation


Clear site of all trees, shrubs etc.. And items
1 extract
Excavatestumps
topsoil 87 m² $ 75.00 $ 6,525.00
Foundation Excavation
Excavate 800mm x 800mm pad footing
0-0.900m deep, commencing from 9.9 m³ $ 90.00 $ 891.00
ground level
2
Excavate 400mm x 400mm pad footing
0-0.755 deep, commencing from ground 1.2 m³ $ 90.00 $ 108.00
level
3
Excavate 450mm x 200 SF 0-0.500m
deep, commencing from ground level 1.2 m³ $ 90.00 $ 108.00
4
Excavate 450mm x 200 RF 0-0.500m
deep, commencing from ground level 11 m³
5
Cartaway, Backfilling & Blinding
Approved backfill surplus excavated
materials to sides of footing and 25 m³ $ 250.00 $ 6,250.00
6
rammed as approved by Engineer
Filling
50mm thick sand blinding spread over
hardcore fill $ 12.50 $ 600.00
7 48 m²
Damp Proof membrane

Polythene DPC over 30mm thick sand


blinding $ 3.90 $ 187.20
8 48 m²

AMOUNT OF EXCAVATION WORK


CARRIED TO SUMMARY $ 14,669.20
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT

3 CONCRETE
SUB-STRUCTURE
25 Mpa strength concrete as specified in
:
1 800x800 pad footing 3 m³ $ 1,800.00 $ 5,400.00
2 400x400 pad footing 0.5 m³ $ 1,800.00 $ 900.00
3 450x300 strip footing 3 m³ $ 1,800.00 $ 5,400.00
4 300x150 R footing 0.3 m³ $ 1,800.00 $ 540.00
5 90mm concrete slab 5 m³ $ 1,800.00 $ 9,000.00
6 250Ø column 15 m³ $ 1,800.00 $ 27,000.00

SUPERSTRUCTURE
7 300X160 suspended beam 1 m³ $ 1,800.00 $ 1,800.00

FORMWORK
SUBSTRUCTURE
8 sides of pad footing 11 m² $ 138.40 $ 1,522.40
9 sides of strip footing 39 m² $ 138.40 $ 5,397.60
10 sides of 250Ø column 12 m² $ 138.40 $ 1,660.80
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF CONCRETE CARRIED TO SUMMARY $ 58,620.80


BOQ FOR PROPOSES 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


5 CONCRETE BLOCKWORK
Ground floor external wall
1 150mm thick reinforced plastered blo sides 800 pcs $ 82.00 $ 65,600.00

CONCRETE FILLING
2 Fill all cell with 25mpa concrete 1.2 m³ $ 1,800.00 $ 2,160.00
BOQ FOR PROPOSES 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF CONCRETE BLOCKWORK


CARRIED TO SUMMARY $ 67,760.00
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOACTION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


4 STEEL ROD REINFORCEMENT
SUB-STRUCTURE
Column Pads
1 D12 bars 143 l/m $ 7.60 $ 1,086.80
2 R6 ties 31 l/m $ 2.60 $ 80.60
3 Galvanized Tie wire 30 kg $ 27.00 $ 810.00

STRIP FOOTING
4 D12 139 L/M $ 7.60 $ 1,056.40
5 R6 ties 54 L/M $ 2.60 $ 140.40
6 Galvanized Tie wire 25 kg $ 27.00 $ 675.00

RF
7 D12 19 L/M $ 7.60 $ 144.40
8 R6 ties 7 L/M $ 2.60 $ 18.20
9 Tie wire 10 kg $ 27.00 $ 270.00

CIRCULAR COLUMN
10 D12 106 l/m $ 7.60 $ 805.60
11 R6 ties 56 l/m $ 2.60 $ 145.60
12 Galvanized Tie wire 25 kg $ 25.00 $ 625.00

BLOCK WORK
13 D12 87 l/m $ 7.60 $ 661.20
14 Galvanized Tie wire 10 l/m $ 27.00 $ 270.00

SUSPENDED BEAM
15 D12 93 l/m $ 7.60 $ 706.80
16 R6 stirrup 47 l/m $ 2.60 $ 122.20
17 Galvanized Tie wire 15 kg $ 27.00 $ 405.00
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOACTION

AMOUNT OF REINFORCING STEEL


CARRIED TO SUMMARY $ 8,023.20
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


6 CARPENTRY
FIRST FLOOR WALLS FRAMING
External walls
1 100X50 timber studs 136 l/m $ 20.00 $ 2,720.00
2 100X50 top plate 29 l/m $ 20.00 $ 580.00
3 100x50 bottom plate 29 l/m $ 20.00 $ 580.00
4 100x50 noggings 72 l/m $ 20.00 $ 1,440.00

Internal walls
5 100x50 noggings 43 l/m $ 20.00 $ 860.00
6 100x50 top plate 14 l/m $ 20.00 $ 280.00
7 100x50 bottom plate 14 l/m $ 20.00 $ 280.00
8 100x50 stud 81 l/m $ 20.00 $ 1,620.00

External wall covering


9 140X50 external weather board cladding 234 l/m $ 32.12 $ 7,516.08

Internal wall finishes


10 90X20 wall linnings 1125 l/m $ 27.40 $ 30,825.00

FLOORING
11 90X20 T&G floor boards to main floor 580 l/m $ 27.14 $ 15,741.20
12 90x20 floor boards to verander 84 l/m $ 27.14 $ 2,279.76
13 90x20 floor boards to back door stair landing 15 l/m $ 27.14 $ 407.10
250x75 Bearer 28 l/m $ 95.82 $ 2,682.96
150x50 floor joist 146 l/m $ 20.00 $ 2,920.00
Z nails 63 pcs $ 3.50 $ 220.50
U nails 22 pcs $ 3.50 $ 77.00
ROOF FRAMING
14 75X50 purlin strap in position 131 l/m $ 28.46 $ 3,728.26
15 150x50 rafters 95 l/m $ 32.10 $ 3,049.50
16 Cyclone strap 118 pcs $ 19.40 $ 2,289.20

EXTERIOR FINISHES
17 200X35 fascia board 19 l/m $ 88.45 $ 1,680.55
18 200x35 badge board 12 l/m $ 88.45 $ 1,061.40

VERANDA
19 90X90 king post 8 l/m $ 17.09 $ 136.72
20 100mm Ø galvanized iron post 13 l/m $ 124.00 $ 1,612.00

STAIR
21 250mmx50mm stair stringers and treads 50 l/m $ 24.14 $ 1,207.00
22 100mmx50mm post 11 l/m $ 20.00 $ 220.00
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

23 75mmx50mm hand rail 20 l/m $ 23.30 $ 466.00


ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT
HARD WARE

24 Allow pc sum of $7000 (seven thousand dollars) $ 7,000.00


for supply and installation of all hardware
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF CARPENTRY CARRIED TO


SUMMARY $ 93,479.73
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


7 ROOFING
Roof shall be 0.48mm thick 24 gauge
steel roofing in single length sheets
fastened to purlins with 'U' way
roofing nails with total cyclonic
assembly, as:
Maximum 6.11m Above Ground Floor
Level
1 Roofing fixed to timber purlins 80 m² 198.18 15854.4
2 Extra value, for turn up 17 m 10.1 171.7
3 Extar value, for turn down 21 m 10.1 212.1
4 Ridge cap 10 l/m 88.45 884.5
0
INSULATION 0
Double sided sisilation 453 laid over
5 80 m²
wire mesh netting 38.32 3065.6
6 Bird wire netting 80 ²m 13.27 1061.6

BRACING
7 Strap bracing 26 l/m 0
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF ROOFING CARRIED


TO SUMMARY $ 21,249.90
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


8 PLASTER
EXTERIOR
15mm thick two coat 1:3 cement/sand plaster with an
approved plasticiser added, finished with a smooth and
wood float finish, as specified in :

1 Concrete blockwalls both sides 185 m² $ 35.18 $ 6,508.30

INTERIOR
10mm thick two coat 1:3 cement/sand plaster with an
approved plasticiser added, finished with a smooth and
wood float finish, as specified in :

2 Blockwork wall both sides 41 m² $ 35.18 $ 1,442.38


BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF SOLID PLASTER CARRIED TO


SUMMARY $ 7,950.68
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


9 PAINTING

EXTERIOR

Prepare and Apply 2 coats of finishing


1 coats to 140x20 external weather $ 60.00 m² $ 36.75 $ 2,205.00
boards on fisrt floor

2 Apply 3 coats of finishing coats to $ 6.20 m² $ 44.23 $ 274.23


200x35 fascia boards and badge board
3 Apply 3 coats of finishing coats to 90x90 $ 1.08 m² $ 25.20 $ 27.22
king posts

INTERIOR
Sand, prepare and apply three coats of
clear varnish to:
4 T&G flooring board $ 53.00 m² $ 368.15 $ 19,511.95
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF PAINTING CARRIED TO


SUMMARY $ 22,018.39
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


10 DOORS AND WINDOWS
DOORS
Ground floor
1 2100mmx910mm solid core with hard 2 sets $ 740.00 $ 1,480.00
ware
2 2100x910 interior hollow core door 3 sets $ 935.00 $ 2,805.00
with hardware
3 145x45 door frame 25.5 l/m $ 65.63 $ 1,673.57
4 4" concrete nail 5 kg $ 25.00 $ 125.00

First floor
5 2100mmx910mm solid core door with 2 sets $ 740.00 $ 1,480.00
hard ware
6 2100x910 interior hollow core door 4 sets $ 935.00 $ 3,740.00
with hardware
7 145x45 door frame 30.6 l/m $ 65.63 $ 2,008.28
4" concrete nail 6 kg $ 25.00 $ 150.00

WINDOW
Ground floor
145x45 timber as specified in:
8 Window sill 8 l/m $ 76.79 $ 614.32
9 window head 8 l/m $ 65.63 $ 525.04
10 wilndow frame 16 l/m $ 65.63 $ 1,050.08

Aluminuim louvre frame


11 8 blade aluminium lovre frame 6 pairs $ 124.50 $ 747.00
12 Ditto but to 7 blades 1 pair $ 110.20 $ 110.20
13 Ditto but 4 blades 2 pairs $ 62.20 $ 124.40
14 Louvre frame Screw 6 pks $ 32.00 $ 192.00
Louvre glass
15 30" clear louvre glass 55 pcs $ 9.90 $ 544.50
16 30" obscure louvre glass blades 8 pcs $ 9.90 $ 79.20
Security mesh
17 Aluminium security mesh 10 m² $ 60.60 $ 606.00
18 20x20 Beads 14 l/m $ 21.40 $ 299.60
19 Concrete sill bed 7.2 l/m $ -

First floor
DOOR
20 2100mmx910mm solid core door with 2 sets $ 740.00 $ 1,480.00
hard ware
21 2100x910 interior hollow core door 4 sets $ 935.00 $ 3,740.00
with hardware
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

22 145x45 door frame 28 l/m $ 65.63 $ 1,837.64

ITEM DESCRIPTION OF MATERIALS QTY UNIT RATE AMOUNT


WINDOW
145x45 timber as specified in:
23 window frame 39 l/m $ 65.63 $ 2,559.57
24 window head 16 l/m $ 65.63 $ 1,050.08
25 window sill 16 l/m $ 76.79 $ 1,228.64

Aluminuim louvre frame


26 8 blades louvre frame 13 pairs $ 124.50 $ 1,618.50
27 Ditto but to 4 blades 9 pairs $ 62.20 $ 559.80
28 Ditto but to 6 blades 4 pairs $ 93.90 $ 375.60
29 Louvre frame Screw 4 pkt $ 36.00 $ 144.00

Louvre glass
30 30" clear louvre glass blades 48 pcs $ 9.90 $ 475.20
31 30" obscure louvre glass blades 16 pcs $ 9.90 $ 158.40

Batten
32 75x20 batten 53 l/m $ 26.06 $ 1,381.18
BOQ FOR PROPOSED 2 STORY BUILDING AT XXX LOCATION

AMOUNT OF WINDOWS AND DOORS CARRIED TO SUMMARY $ 9,550.97

You might also like