B2 (Single Floor) Ramp E 100% 100% 100% 100% 100% 60% 75% 50% 0% 0% 0% 0% 0% 0%
B3 (Two Floor)-
office Complex 100% 100% 100% 100% 100% 80% 0% 95% 90% 90% 25% 0% 25% 0% 50%
B2 (Single Floor)-
Generator /Driver 100% 100% 100% 100% 100% 90% 0% 95% 80% 80% 25% 0% 10% 0% 60%
B1 (Two Floor)-
Police Building 100% 100% 100% 100% 100% 45% 0% 70% 0% 0% 25% 0% 0% 0% 60%
FLOOR READY COLUMN ( All BRICK/ BLOCK PLASTERING / PLASTERING / FLOOR FINISHES PAINTING ELECTRICAL ELECTRICAL PLUMBING /
Buildings Ramp (SGT/Filling) FOUNDATION Floor) TIE BEAM SLAB ROOF FRAME ROOF COVERING WORK INTERNAL EXTERNAL ( TILING or ( INTERNAL AND WIRING FIXTURES FIXTURES
OTHERS) EXTERNAL))
B5 (Three Floor) 100% 100% 100% 100% 100% 65% 80% 60% 55% 20% 0% 30% 0% 25%
B2 (Single Floor) 100% 100% 100% 100% 0% 95% 100% 100% 100% 40% 20% 10% 0% 0%
###