Professional Documents
Culture Documents
DEP 80.00.10.11-Gen.
February 2017
DEM1
All rights reserved. No part of this document may be reproduced, stored in a retrieval system, published or transmitted, in any form or by any means, without the
prior written permission of the copyright owner or Shell Global Solutions International BV.
DEP 80.00.10.11-Gen.
February 2016
Page 2
PREFACE
DEP (Design and Engineering Practice) publications reflect the views, at the time of publication, of Shell Global Solutions
International B.V. (Shell GSI) and, in some cases, of other Shell Companies.
These views are based on the experience acquired during involvement with the design, construction, operation and
maintenance of processing units and facilities. Where deemed appropriate DEPs are based on, or reference international,
regional, national and industry standards.
The objective is to set the standard for good design and engineering practice to be applied by Shell companies in oil and
gas production, oil refining, gas handling, gasification, chemical processing, or any other such facility, and thereby to help
achieve maximum technical and economic benefit from standardization.
The information set forth in these publications is provided to Shell companies for their consideration and decision to
implement. This is of particular importance where DEPs may not cover every requirement or diversity of condition at each
locality. The system of DEPs is expected to be sufficiently flexible to allow individual Operating Units to adapt the
information set forth in DEPs to their own environment and requirements.
When Contractors or Manufacturers/Suppliers use DEPs, they shall be solely responsible for such use, including the
quality of their work and the attainment of the required design and engineering standards. In particular, for those
requirements not specifically covered, the Principal will typically expect them to follow those design and engineering
practices that will achieve at least the same level of integrity as reflected in the DEPs. If in doubt, the Contractor or
Manufacturer/Supplier shall, without detracting from his own responsibility, consult the Principal.
The right to obtain and to use DEPs is restricted, and is typically granted by Shell GSI (and in some cases by other Shell
Companies) under a Service Agreement or a License Agreement. This right is granted primarily to Shell companies and
other companies receiving technical advice and services from Shell GSI or another Shell Company. Consequently, three
categories of users of DEPs can be distinguished:
1) Operating Units having a Service Agreement with Shell GSI or another Shell Company. The use of DEPs by
these Operating Units is subject in all respects to the terms and conditions of the relevant Service Agreement.
2) Other parties who are authorised to use DEPs subject to appropriate contractual arrangements (whether as part
of a Service Agreement or otherwise).
3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2)
which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said
users comply with the relevant standards.
Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI disclaims
any liability of whatsoever nature for any damage (including injury or death) suffered by any company or person
whomsoever as a result of or in connection with the use, application or implementation of any DEP, combination of DEPs
or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI or other Shell Company. The
benefit of this disclaimer shall inure in all respects to Shell GSI and/or any Shell Company, or companies affiliated to these
companies, that may issue DEPs or advise or require the use of DEPs.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall
not, without the prior written consent of Shell GSI, be disclosed by users to any company or person whomsoever and the
DEPs shall be used exclusively for the purpose for which they have been provided to the user. They shall be returned
after use, including any copies which shall only be made by users with the express prior written consent of Shell GSI. The
copyright of DEPs vests in Shell Group of companies. Users shall arrange for DEPs to be held in safe custody and Shell
GSI may at any time require information satisfactory to them in order to ascertain how users implement this requirement.
All administrative queries should be directed to the DEP Administrator in Shell GSI.
DEP 80.00.10.11-Gen.
February 2016
Page 3
TABLE OF CONTENTS
1. INTRODUCTION....................................................................................................... 5
1.1 SCOPE...................................................................................................................... 5
1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS..........5
1.3 DEFINITIONS............................................................................................................ 6
1.4 CROSS-REFERENCES.......................................................................................... 10
1.5 SUMMARY OF MAIN CHANGES............................................................................10
1.6 COMMENTS ON THIS DEP....................................................................................11
1.7 DUAL UNITS........................................................................................................... 11
1.8 NON NORMATIVE TEXT (COMMENTARY)...........................................................11
2. LAYOUT STRATEGY............................................................................................. 12
3. GENERAL LAYOUT REQUIREMENTS..................................................................12
3.1 INTRODUCTION..................................................................................................... 12
3.2 HSSE....................................................................................................................... 13
3.3 CONSTRUCTABILITY.............................................................................................15
3.4 OPERABILITY AND MAINTAINABILITY.................................................................15
4. SITE MASTER PLAN..............................................................................................16
4.1 INTRODUCTION..................................................................................................... 16
4.2 MINIMUM SEPARATION DISTANCES AND SITING REQUIREMENTS................17
4.3 LNG TRAINS........................................................................................................... 23
4.4 UTILITIES................................................................................................................ 23
4.5 FIXED IGNITION SOURCES...................................................................................24
4.6 FLARES AND VENT STACKS................................................................................24
4.7 COOLING WATER TOWERS..................................................................................25
4.8 ELECTRICAL/INSTRUMENT CABLING.................................................................26
4.9 PIPING.................................................................................................................... 26
4.10 Loading facilities...................................................................................................... 27
4.11 NON-REFRIGERATED ATMOSPHERIC/Low Pressure Liquid Storage.................30
4.12 Pressurised LPG storage.........................................................................................32
4.13 Refrigerated LNG/LPG Storage...............................................................................37
4.14 BUILDINGS............................................................................................................. 38
4.15 LOGISTIC AREAS................................................................................................... 41
4.16 SITE SPECIFIC PARAMETERS..............................................................................41
5. PLOT PLAN............................................................................................................ 44
5.1 INTRODUCTION..................................................................................................... 44
5.2 SAFETY................................................................................................................... 44
5.3 CONSTRUCTION.................................................................................................... 45
5.4 COST....................................................................................................................... 46
5.5 ENGINEERING........................................................................................................ 46
5.6 OPERATION............................................................................................................ 47
5.7 MAINTENANCE....................................................................................................... 47
5.8 PLANT BUILDINGS.................................................................................................48
5.9 STRUCTURES........................................................................................................ 48
5.10 PLATFORMS/LADDERS/STAIRS...........................................................................48
5.11 PIPE RACKS........................................................................................................... 48
5.12 RELIEF/FLARE/BLOW-DOWN LINES....................................................................48
5.13 BATTERY LIMITS.................................................................................................... 49
5.14 SPECIAL UNITS...................................................................................................... 49
5.15 PACKAGE UNITS.................................................................................................... 49
DEP 80.00.10.11-Gen.
February 2016
Page 4
1. INTRODUCTION
1.1 SCOPE
This DEP specifies requirements and gives recommendations for layout of onshore facilities
and specifically covers the following deliverables:
a. Site master plans
b. Plot plans
c. Mechanical general arrangement drawings
This DEP is applicable both for new sites (greenfield projects) as well as for revamps or
expansions of existing sites (brownfield projects).This DEP is applicable to commonly
applied facilities and explicitly excludes Movable Modular Liquefaction Systems (MMLSs)
and Modular Liquefaction Units (MLUs) for LNG. This DEP is applicable to artificial islands
where the Principal has defined them to be onshore facilities.This DEP contains mandatory
requirements to mitigate process safety risks in accordance with Design Engineering
Manual (DEM) 1 – Application of Technical Standards.This DEP is a revision of the same
number dated February 2016; see (1.5) regarding the changes.
1.3 DEFINITIONS
1.3.1 General definitions
The Contractor is the party that carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a project or operation of a
facility. The Principal may undertake all or part of the duties of the Contractor.
The Manufacturer/Supplier is the party that manufactures or supplies equipment and
services to perform the duties specified by the Contractor.
The Principal is the party that initiates the project and ultimately pays for it. The Principal
may also include an agent or consultant authorised to act for, and on behalf of, the
Principal.
The word shall indicates a requirement.
The capitalised term SHALL [PS] indicates a process safety requirement.
The word should indicates a recommendation.
The word may indicates a permitted option.
Term Definition
Facility Process and utility plants, tanks, buildings, marine structures, pipe racks
and roads located within a site boundary.
Flammable The term flammable is used to cover both flammable and combustible
fluids which are classified as Class I,II or III(a) in DEP 80.00.10.10-Gen.
(DEP 80.00.10.13-Gen.).
Layout One or more of the following deliverables: site master plan, plot plans
and mechanical general arrangement drawings.
Minimum Separation distances aim to ensure that the risk of escalation from a fire
Separation and/or explosion event(s) on an adjacent area are tolerable, for most
Distances common processes.
These distances allow for safe SIMOPs during normal operations,
construction and maintenance activities. The required protection
measures for the construction workforce have to be assessed on a
case-by-case basis
DEP 80.00.10.11-Gen.
February 2016
Page 7
Term Definition
Occupied Building that personnel occupy while doing a major part of their work,
building such as control rooms, laboratories, office buildings, maintenance work
areas, outside operator buildings, etc.; or a building with a primary
purpose that necessitates people to occupy it, such as field labs, lunch
rooms, locker facilities used to change clothes, showers, restrooms or
toilets (lightweight plastic porta-toilets are excluded from this definition),
etc.
Other buildings that have a primary purpose to house or store
equipment or materials are considered an “occupied building” if an
individual spends on average 10 hours or more a week inside the
building, 10 or more people are in the building at any given time, or a
group spends an average of 200 hours or more a week inside the
building.
Observation shelters provided for weather protection for the marine,
road, or rail loading operator may, in consultation with the Principal’s
relevant Technical Authority, be excluded from the definition of an
occupied building. By nature, such buildings are small and require a
large amount of window area to satisfy operational safety requirements
with the loading operations.
For the purpose of this DEP, the requirements for occupied buildings
also apply to those buildings containing safety critical equipment
Plot Plan Overall spatial arrangement of one or more unit(s) and related general
facilities within a plot boundary, showing the arrangement of equipment
within units.
Property The location of the site fence line or area of control based on risk and
boundary radiation criteria as defined in this DEP.
Restricted A road which cannot be accessed without a permit and which has either
plant road physical barriers or signs posted.
Risk Contour Iso-risk line on the map to indicate Location of the specific risk value.
Safety Critical Any equipment, structure, or system (including software logic) acting as
Equipment a barrier to prevent or mitigate the uncontrolled release of a hazardous
(SCE) substance or release of energy leading to a worst case credible
scenario with RAM red, yellow 5A or yellow 5B Risk.
In the context of this DEP the requirements only apply to the Safety
Critical Equipment that enables controlled process shutdown or
potentially controls further incident escalation in the event of an incident.
DEP 80.00.10.11-Gen.
February 2016
Page 8
Term Definition
Site Master Overall spatial arrangement of all process and utility plants, tankage
Plan areas, buildings and connecting infrastructure (e.g., roads, pipe racks).
The site master plan shows the individual plant boundaries within the
overall site boundary.
1.3.3 Abbreviations
Term Definition
KO Knock-Out
Term Definition
STSC Short Term Survivability Criteria at short term exposure (e.g., 5 minutes)
that may be received with a negligible statistical probability of fatality
and without impairment of individual ability to escape.
1.4 CROSS-REFERENCES
Where cross-references to other parts of this DEP are made, the referenced section or
clause number is shown in brackets ( ). Other documents referenced by this DEP are listed
in (7).
Section/Clause Change
2 A site master plan also for the construction phase
3.2 Removed SHALL [PS] on Segregation, rewrote sub-sections on
Toxics and on Safety critical equipment
3.3 Moved to Section 4.2 and clarified for Brownfield
4 New Figure 4.1
4.2 Amended tables and notes
4.5 Modified title and wording of SHALL [PS]
4.9 Modified to change to recommendations
4.10.2 Removed section on LPG bulk transfer via road or rail
4.11 Removed radiation criteria
4.12 Modified separation valued C, E and F and removed
requirements for radiation
4.14 Modified Flowchart for building design and various distances in
the sub-sections
4.16 Modified various distances in sub-sections
5.2. Simplified requirement for drains
5.11 Revised recommendations to requirements
6.3 Deleted requirement to assess critical interventions
6.4 Simplified requirements
6.6 Simplification of various sub-sections and revision of SHALL [PS]
DEP 80.00.10.11-Gen.
February 2016
Page 11
Feedback that has been registered in the DEP Feedback System by using one of the above
options will be reviewed by the DEP Custodian for potential improvements to the DEP.
2. LAYOUT STRATEGY
This DEP defines the requirements at the different stages of layout development in a
project from the site master plan (4), into more defined plot plans (5) and finally the
detailed mechanical general arrangements drawings (6).
General requirements are explained in (3) and further expanded in later sections as
greater design definition is achieved.
1. A layout strategy shall be developed, documented in the Layout Dossier and
implemented.
The layout strategy aims to achieve the following:
Safety and environmental risk levels for surrounding facilities and
communities are tolerable and as low as reasonably practicable (ALARP)
Safety risk levels for “on site” workforce are tolerable and ALARP
Minimum cost by utilizing compact layouts with minimum hydrocarbon
inventory and minimum required separation distances
Minimum lost production resulting from damage to facilities in the event of
fire and/or explosion.
2. Depending on the relevant stage of the Opportunity Realisation Process (ORP) one or
more of the following deliverables shall be included:
a. Site master plan for the operational phase and for the construction phase
b. Plot plans
c. Mechanical general arrangement drawings
3. The layout strategy, the site master plan, the plot plans and mechanical general
equipment arrangement drawings shall incorporate and address the requirements of
the Project Health, Safety, Security and Environment (HSSE) plan.
4. Allowance for the defined future phases by the project, taking unhindered access
during construction and sufficient separation distances considering Simultaneous
Operations (SIMOPS), shall be taken into account.
3.1 INTRODUCTION
The layout requirements, defined in this DEP, are applicable to all project phases and
deliverables.
Additional requirements or exceptions for site master plans, plot plans or mechanical
general arrangement drawings are specified in the relevant chapters.
DEP 80.00.10.11-Gen.
February 2016
Page 13
3.2 HSSE
3.2.1 General
This DEP is based on the assumption that the measures described in
DEP 80.47.10.30-Gen. are implemented.
3.2.2 Segregation inside the property boundary
1. The required segregation between all new, or between new and existing process and
utility plants, tankage areas, buildings and supporting/connecting infrastructure shall
be obtained either by providing:
a. adequate separation distance
b. a physical barrier (being a mitigation measure which reduces the likelihood of
escalation between two units).
2. The barrier shall not increase the escalation risk associated with any increased
confinement or obstruction of access.
3. The effectiveness of a barrier shall be demonstrated.
4. Adequate separation shall be provided by applying the minimum separation distances
as defined within this DEP, including Table 4.1 and (4.3) to (4.16).
Defined minimum separation distances aim to ensure that the risk of escalation
from a fire and/or explosion event(s) on an adjacent area are tolerable, for most
common processes. The project hazard and effects management processes
confirm this later in the project.
The separation distances have in general been arrived at through consequence
modelling of relevant failure scenarios (e.g., tank top fire, or loss of containment via
a 25 mm (1 inch) hole in a pressurized system), giving distances to blast
overpressures and radiation levels.
These distances include allowance for safe SIMOPS during normal operations,
construction and maintenance.
5. Increased separation, above the minimum distances specified, shall be provided to the
extent required to allow for sufficient access and working space to support
construction and maintenance activities.
6. Reduced minimum separation distances or physical barriers shall only be used when
sufficient segregation is demonstrated to be ALARP by using appropriate
consequence modelling or risk assessment.
a. The methodology and criteria to be used for the modelling or assessment, and
the results, shall be subject to the approval of Principal’s designated Technical
Authority.
7. For plant, equipment, units, tankage, buildings and connecting/supporting
infrastructure not included in Table 4.1 and (4.3) to (4.16), it SHALL [PS] be
demonstrated that the risk of escalation from a fire and/or explosion event(s) on an
adjacent area is ALARP.
The above approach typically applies for scenarios such as:
Products with particular reactive hazards, low ignition energy, high
flammable range or high heat of combustion (e.g., Ethylene Oxide, Ethylene),
Non-typical storage pressures or leakage scenarios.
8. ALARP demonstration shall be executed in accordance with Principal’s ALARP guide.
9. If a risk assessment is applied, it shall be used in conjunction with the project risk
tolerability criteria.
DEP 80.00.10.11-Gen.
February 2016
Page 14
3.3 CONSTRUCTABILITY
1. Requirements as defined in the project or facility construction strategy (including pre-
commissioning and initial start-up) shall be included in all layout activities to include
optimal provisions for:
a. Human factors engineering to address accessibility (3.4.3),
b. Suitable (in terms of obstructions, slope, and bearing capacity) access for
construction equipment (including cranes, heavy equipment and transporters),
c. Minimum workspace envelope (including turning radii) for construction equipment
(including cranes, heavy equipment and transporters),
d. Areas for laydown, storage and temporary facilities (e.g., office, camps, welfare),
e. Material (off) loading facilities,
f. Safe SIMOPs,
g. Traffic and pedestrian management,
h. Security and exclusion requirements,
i. Desired construction strategy (stick built/modular), sequence and schedule.
2. During expansions of an existing site, the construction area should have a separate
entrance, gatehouse and fence to keep free access for construction personnel and
delivery of construction materials clear of the existing operating facilities.
3. A clear distinction shall be established by physical barriers between operating areas
and construction areas for both security of operating facilities and to ensure control of
hazards, e.g., vehicle traffic through the operating facility.
4.1 INTRODUCTION
The site master plan of a facility gives the overall spatial arrangement of all process and
utility plants, tankage areas, buildings and connecting infrastructure (e.g., roads, pipe
racks).
The site master plan shows the individual plot boundaries within the overall site
boundary.
The site master plan indicates relevant surrounding local geographic features (e.g.,
rivers, coastline, slopes).
DEP 80.00.10.11-Gen.
February 2016
Page 17
Figure 4.1B Minimum separation distances (USC) for process plants (brownfield)
Figure 4.1C Minimum separation distances (SI) for process plants (greenfield)
DEP 80.00.10.11-Gen.
February 2016
Page 19
Figure 4.1D Minimum separation distances (USC) for process plants (greenfield)
DEP 80.00.10.11-Gen.
February 2016
Page 20
Non-refrigerated
atmospheric/low pressure [60
H [(i)] [(i)] [(i)] [75] [(i)] [(i)] [(i)]
flammable or combustible liquid ]
storage tanks (j)
Oily Water Interceptors [15 [15 [15
I [15] [15] [15] [15] [15] NA
(CPI/API) ] ] ]
Road/Railcar loading station for [60 [60 [60
J [(f)] [(f)] [(f)] [(f)] [(f)] [(f)] NA
LPG ] ] ]
Road/Railcar loading station [30 [30 [30
K [(f)] [(f)] [(f)] [(f)] [(f)] [(f)] [(f)] NA
except LPG ] ] ]
[60/1 [60/ [60/ [60/ [60/ [60/ [60/ [60/
[10 [10 [10
Elevated Flare L 00 100 100 100 100 100 100 100 NA
0] 0] 0]
(a)] (a)] (a)] (a)] (a)] (a)] (a)] (a)]
[50/ [60/1
[60 [60 [60
Transfer Pumps in tank farms M [30] [30] 25 [30] [15] [15] [(f)] [(f)] 00 NA
] ] ]
(c)] (a)]
[60/1
[15 [15 [15 [7.5 [7.5
Main Pipeway N [15] [15] [15] [15] [(f)] [(f)] 00 NA NA
] ] ] ] ]
(a)]
[60/1
Not
Unrestricted plant road O 3 3 3 3 [(k)] [(k)] 3 [(k)] [(k)] [(k)] [(k)] 00 [(k)] NA
ep
(a)]
[60/1
Restricted plant road P 3 3 3 3 (l) (l) 3 (l) (l) (l) (l) 00 (l) (l) NA NA
(a)]
[150/
[(m) [(m) [(m) [(m) [15
Property Boundary Q 10 10 10 30 30 [(f)] [(f)] 250 [(m)] 3 3 NA
] ] ] ] ]
(b)]
[(6 [(6 [(6
[60/1
0)] 0)] 0)] [(g) [(g) [(g)
Pressurized LPG Storage R [(g)] [50] [(g)] [(g)] [(g)] [(o)] [(g)] [(g)] 00 [60] [(m)] [(g)]
[(n) [(n) [(n) ] ] ]
(a)]
] ] ]
[60/1
[10 [10 [10 [30 [30 [15
Refrigerated Storage (d) S [80] [45] [80] [45] [45] [60] [(f)] [(f)] 00 [30] [(m)] [(g)] [45]
0] 0] 0] ] ] ]
(a)]
A B C D E F G H I J K L M N O P Q R S
Occupied Buildings (e)
Non –blast resistant
products
Utilities Area not handling flammable
Cooling Towers
flammable products
Process Plants/Utility Areas handling
Elevated Flare
Main Pipeway
Property Boundary
A B C D E F G H I J K L M N O P Q R S
Occupied Buildings (e)
Non –blast resistant
Cooling Towers
flammable products
Process Plants/Utility Areas handling
Elevated Flare
Main Pipeway
Property Boundary
4.4 UTILITIES
4.4.1 General
1. For layout purposes, utility units handling flammable materials shall be treated as a
hydrocarbon processing plant.
2. Site shared utilities (such as central cooling towers and units producing steam, water
and power) shall be located in positions where they will not be put out of action by an
explosion, fire (from outside the utility area) or flood.
3. In locating the steam and water producing plant, the effects of the prevailing wind on
the stack emission should be taken into account.
4. The steam, water and electricity supply mains to the major consumers should not be
uneconomically lengthy.
a. These services may be on the periphery, but close to the largest users.
b. Consideration should be given to a ring main system.
c. Allowance should be made for future expansion.
5. Large water producing plants should be located in a separate building (if climatologic
conditions require) or a separate area, to permit access for chemicals required for
regeneration, locating water storage and effluent drainage systems.
6. The location of the power generation facility shall take into account the area
classification requirements.
DEP 80.00.10.11-Gen.
February 2016
Page 24
7. For noise reasons, power generators should be located at an acceptable distance from
the office buildings and/or include noise attenuating buildings or enclosures as defined
in DEP 31.10.00.31-Gen.
4.4.2 Primary water treatment facilities
1. Oily Water Interceptors (CPI/API) that are part of primary water treatment facilities are
considered to be hydrocarbon containing equipment and the distance to a fixed source
of ignition SHALL [PS] be as per (4.5, Item 1).
2. See DEP 34.14.20.31-Gen. for the design and layout of drainage and primary
treatment facilities.
4.4.3 Air separation units
1. For further guidance on design issues for and location of air separation units, refer to
DEP 30.05.10.30-Gen.
4.4.4 Distribution of utility services
1. Steam and water mains, electricity and telephone cables etc., shall not run through
plant areas.
4.9 PIPING
4.9.1 General
1. Consult with piping engineers to define the dimensions and locations of piping in
accordance with DEP 31.38.01.11-Gen.
2. The length of piping shall be kept to a minimum to minimise cost and to minimise
process inventory.
4.9.2 Piping at ground level
1. Piping should be at ground/grade level unless one of the following apply:
a. it is not possible for process/operational reasons;
b. it obstructs emergency access
c. it obstructs access for operations and maintenance.
2. Open pipe trenches should not be used in places where there is a risk of:
a. flammable vapours or liquids (e.g., naphtha) collecting;
b. flooding.
4.9.3 Overhead piping
1. Pipe-racks/bridges and supports should be of the simplest form with minimum cross
bracing or in-filling of steel-work to give the maximum freedom of pipe routings, while
meeting (5.2.3) and (5.2.5).
DEP 80.00.10.11-Gen.
February 2016
Page 27
Figure 4.2.B Minimum separation distances (USC) for bulk vehicle loading
7. Determination of Class I, II or III shall be based on closed cup flash points, as per
DEP 80.00.10.10-Gen. or DEP 80.00.10.13- Gen., as applicable.
8. Storage arrangements within bunded areas may be provided with intermediate kerbs
(normally not higher than 0.6 m (2 ft)) to improve containment in case of fire and to
divide the tankage into groups of a convenient size.
a. Layout and supporting design considerations shall be submitted to the Principal’s
relevant Technical Authority for approval.
9. Tank farms SHALL [PS] be designed such that in case of spillage the liquid cannot
flow into process units or to any source of ignition.
10. For firefighting reasons, there shall be no more than two rows of tanks between
access roads.
a. The use of more than two rows of tanks between access roads (e.g., for other
tank sizes, product properties, tank types, fire safety measures and available
fixed and mobile firefighting capabilities) shall be validated by a fire safety
assessment and is subject to acceptance by the Principal’s designated Technical
Authority.
11. Access to the tank farm area SHALL [PS] be provided from two opposite sides with the
access roads linked in such a way that access is always possible should any road be
cut off.
12. Pipe racks and tracks containing process, utility, flare piping that are not connected to
the tanks shall not be routed through the bund.
13. When stored liquids are incompatible such that they can produce a hazardous
substance when they react, the tanks shall be segregated and not located in the same
bund.
14. Tank farms shall be placed on one side or not more than two sides of the process
plant area.
This arrangement allows that adequate safety precautions can be taken and it gives
the possibility to expand either the tank farm area or process plant area at any time
in the future.
DEP 80.00.10.11-Gen.
February 2016
Page 32
15. Tanks shall be grouped and bunded so that the contents of the tanks in one bund will
require one type of firefighting method only.
16. Tanks for the storage of the same materials shall be located in one group within a
bund area, subject to the prescribed limitations of the bunded area.
17. The distance from a process area to the tank farm may need to be limited because of
process reasons (e.g., polymerisation of chemicals in the line connecting the process
area and tank farm). Intermediate tanks should be located in an area close to the
unit(s) providing the materials to those tanks.
18. For tanks grouped together, consideration should be given to a common walkway with
not less than two means of escape landing outside of any containment or berms,
dependent upon the number of tanks served.
19. Pumps, valve manifolds and transfer piping shall be installed outside of bund walls or
impounding basins to minimise the amount of piping, valves and flanges in the bund
area.
Figure 4.4.A Minimum separation distances (meters) for pressurised LPG vessels
Individual
vessel A (1) B C D (2) E F G (3) H I J K (3) L N (2) O P S
capacity
≤2.5 m3 (D1+D2)/4 10 50 1.5Dr 15 15 7.5 15 5 5 15 10 Dr (8)
1 3
3 (8)
2.5<m ≤5 (D1+D2)/4 10 50 1.5Dr 15 15 7.5 15 5 5 15 10 Dr 1 3
5<m3≤10 (D1+D2)/4 10 50 1.5Dr 15 15 7.5 15 5 5 15 10 Dr (8)
1 3
10<m3≤50 (D1+D2)/4 10 50 1.5Dr 15 15 7.5 15 5 5 15 10 Dr (8)
1 3
50<m3≤95 (D1+D2)/4 10 50 1.5Dr 15 15 7.5 15 5 5 15 10 Dr (8)
1 3
3 (8)
95<m ≤135 (D1+D2)/4 10 50 1.5Dr 15 15 7.5 15 5 5 15 10 Dr 1 3
3 (8)
135<m ≤265 (D1+D2)/4 15 50 1.5Dr 25 22.5 7.5 22.5 15 5 15 22.5 Dr 1 3
3 (8)
265<m ≤500 (D1+D2)/4 15 50 1.5Dr 25 30 7.5 30 15 5 15 30 Dr 1 3
3 (8)
>500 m (D1+D2)/4 15 50 1.5Dr 25 30 7.5 30 15 5 15 30 Dr 1 3
DEP 80.00.10.11-Gen.
February 2016
Page 34
Figure 4.4.B Minimum separation distances (feet) for pressurised LPG vessels
Individual
K N
vessel A (12) B C D (2) E F G (3) H I J (3) L (2) O P S
capacity
≤90 ft3 (D1+D2)/4 33 165 1.5Dr 50 50 25 50 16 16 50 33 Dr (8)
3.25 10
(8)
3
90<ft ≤180 (D1+D2)/4 33 165 1.5Dr 50 50 25 50 16 16 50 33 Dr 3.25 10
3 (8)
180<ft ≤350 (D1+D2)/4 33 165 1.5Dr 50 50 25 50 16 16 50 33 Dr 3.25 10
(8)
3
350<ft ≤1750 (D1+D2)/4 33 165 1.5Dr 50 50 25 50 16 16 50 33 Dr 3.25 10
DEP 80.00.10.11-Gen.
February 2016
Page 35
(8)
1750<ft3≤3350 (D1+D2)/4 33 165 1.5Dr 50 50 25 50 16 16 50 33 Dr 3.25 10
3 (8)
3350<ft ≤4770 (D1+D2)/4 33 165 1.5Dr 50 50 25 50 16 16 50 33 Dr 3.25 10
(8)
3
4770<ft ≤9350 (D1+D2)/4 50 165 1.5Dr 82 75 25 75 50 16 50 75 Dr 3.25 10
3 (8)
9350<ft ≤17,650 (D1+D2)/4 50 165 1.5Dr 82 100 25 100 50 16 50 100 Dr 3.25 10
(8)
>17,6500 ft 3
(D1+D2)/4 50 165 1.5Dr 82 100 25 100 50 16 50 100 Dr 3.25 10
4.14 BUILDINGS
4.14.1 General
1. The location of buildings for a new or existing facility may be determined either by
following the prescriptive distance within this DEP or using calculated Building Risk
values.
a. Where used, the Building Risk values should be calculated by completing a
Facility Siting study.
2. Where a Facility Siting study is completed, the following shall be met:
a. The assessment shall be completed using the Shell Shepherd software or a
model approved by the Principals’ designated Technical Authority.
b. The generic building construction type used to generate the building risk contour
shall be chosen to best represent the proposed building construction type.
3. Figure 4.6 SHALL [PS] be used to determine the design requirements of all new
buildings except for occupied portable buildings including Blast Resistant Modules, for
which refer to (4.14.3).
4. In calculations, construction villages shall be considered to have a 24 hr per day
occupation.
5. Buildings should be located upwind or cross wind of the prevailing wind direction of
any plant capable of venting fumes to the atmosphere.
6. On-site buildings shall have no more than two stories if they meet one of the following:
a. within 500 m (1640 ft) of process units;
b. within 200 m (660 ft) of storage tanks.
7. Temporary and permanent buildings shall be located outside bund walls used for
product containment.
8. The potential risks arising from neighbouring facilities (outside of the site boundary)
shall be considered when siting all buildings.
DEP 80.00.10.11-Gen.
February 2016
Page 39
YES NO
YES NO NO
8. Workshop/warehouse, etc., should be located together and within easy access of the
process units.
9. Off-loading to the workshop/warehouse buildings should not interfere with other traffic.
The workshop may need adjacent external space for activities such as outside
fabrication, scrap yard, storage and lay down area.
4.14.5 Plant buildings
4.14.5.1 General
1. The requirements in (4.14.1) and (4.14.2) shall apply for plant buildings containing
safety critical equipment (e.g., unit electrical substations/field auxiliary rooms/analyser
houses) and for plant buildings considered to be occupied.
2. See (4.5) for the siting of unit electrical substations and field auxiliary rooms relative to
potential hydrocarbon leak sources
3. Unit electrical substations should be located near the centre of the load they are
required to supply. Reference is made to DEP 33.64.10.10-Gen. and
DEP 33.64.20.10-Gen., as applicable.
4.14.5.2 Analyser houses
1. An analyser house may not be considered a potential hydrocarbon leak source where
sufficient measures are in place, in accordance with DEP 32.31.50.10-Gen. and
DEP 32.31.50.13-Gen., to:
a. bring the hydrocarbon content in the analyser house to below the lower explosive
limit (LEL) level, and
b. allow emergency shutdown in case of hydrocarbon content reaching LEL level.
2. Where analyser houses are a potential hydrocarbon leak source, see (4.5) regarding
the minimum distance to fixed ignition sources.
3. There shall be enough space between the analyser building and surrounding
equipment to allow maintenance access for both the analyser building as well as for
the surrounding equipment.
4.16.2 Bathymetry
1. The location of the jetty, material off-loading (MOF) and/or Roll-Off Roll-On (Ro-Ro)
facility should be decided such that the length of the required causeway is minimised.
2. The bathymetry of the water-body, the required exclusion zones, the draught of ships,
the possible area to be dredged and the tide and currents shall be considered.
4.16.3 Meteorology
1. The prevailing wind directions shall be considered when establishing spatial
arrangements and orientation of the facilities.
2. Analysis shall include circumstances where the wind does not always blow in the
prevailing wind direction or is strongly affected by seasonal or other factors.
3. The site master plan shall be designed such that flooding of sensitive areas is avoided.
4.16.4 Geotechnical conditions and seismicity
1. The siting of plant, tankage areas, buildings and connecting infrastructure shall
consider the local geotechnical conditions to arrive at the most optimal foundation
solution and to reduce the potential risks from geo-hazards and earthquake events in
seismically active regions.
4.16.5 Environment
1. Visual impact, impact to wildlife and impact to local communities shall be addressed.
High elevation equipment and stacks may cause an aerial hazard and might be
limited to a maximum height.
2. Plants producing gaseous effluents, dust and other pollutants, or noise, should not be
located upwind of residential or similar property.
3. Liquid effluent shall not be able to flow to plants on adjacent property and vice versa.
4. Solid effluents storage should be remote from adjacent property.
5. Storm water shall be directed to the appropriate drain.
6. Outside stores of drums or unwanted or scrap equipment should not be visible from
any location outside the fence.
7. Rail spurs should be placed so that noise of shunting to persons onsite as well as the
public is minimized.
4.16.6 Site boundary and access
4.16.6.1 Roads and parking areas
1. The edge of restricted and unrestricted plant roads shall be located at least 3.0 m
(10 ft) from equipment handling hydrocarbons.
2. For unrestricted plant roads, additional requirements are given in (4.5).
3. The site shall:
a. have a peripheral road connected at a minimum of two points with the public road
system.
b. be arranged such that a major fire can be approached from two directions.
4. In laying out the road system, the expected handling and traffic requirements during
construction, operation, (shutdown) maintenance, emergency and decommissioning of
the facilities shall be analysed. Future traffic requirements shall be taken into account.
5. Access roads shall be designed to be kept open during facility maintenance
campaigns to allow passage of fire trucks or other equipment in case of an
emergency.
DEP 80.00.10.11-Gen.
February 2016
Page 43
6. See DEP 34.13.20.31-Gen., Section 2 for the extent, type, width, radii, and gradients
of roads.
7. Corner radii should suit the turning circle of the largest vehicle and any special loads.
8. Railway crossings, crossroads, road junctions, dead ends, right angle bends and
ramps should be avoided.
9. A traffic circulation plan shall be made to arrange the roads such that vehicles do not
pass through process areas or violate area classifications.
a. The total number of road car kilometres on site should be minimized.
10. Clearances for passage of mobile equipment shall be based on the largest piece of
equipment anticipated.
11. The minimum elevation of the bottom of overhead obstructions outside units shall be:
a. 6.0 m (20 ft) over railways
b. 6.0 m (20 ft) over unrestricted plant roads
In some situations the lower side of the pipe supports or the supporting steel
dictates the minimum elevation of overhead piping.
12. There should always be at least one route to each unit and to the expansion areas
without pipe rack crossings.
13. A plant area shall be accessible on all four sides by a road.
14. Turning areas for tankers and vehicles shall not be allowed.
15. Pedestrian pathways adjacent to roads should be included in areas of high personnel
concentration and traffic movement.
16. In the sizing of roads, room shall be allowed for adjacent drainage channels, especially
if the site is low or near surface water.
17. Adequate parking space shall be available for vehicles waiting:
a. to load and unload;
b. for the weighbridge;
c. to receive clearance to enter or leave the facility.
18. Vehicles should not have to queue on the public road to gain entrance to the facility.
19. Car and bus parks for personnel and visitors and their access roads should be in a
safe area and outside security points.
20. The parking area for night-shift employees should be under observation of the
gatekeeper.
4.16.6.2 Rail tracks
1. The rail layout should be considered early in the development of the site master plan
in conjunction with the road plan.
2. Rail tracks and rail links with a local or national system shall be laid-out in consultation
with the responsible railway authorities.
3. Rail-tracks shall be situated outside hazardous areas as defined in
DEP 80.00.10.10-Gen. or DEP 80.00.10.13-Gen., as applicable.
DEP 80.00.10.11-Gen.
February 2016
Page 44
5. PLOT PLAN
5.1 INTRODUCTION
A plot plan gives the overall spatial arrangement of the individual units and general
facilities within the available plant boundaries.
1. Due to process configuration and to minimise space requirements, air-cooled heat
exchangers should be located on top of the pipe-racks.
2. The area under a pipe rack may be used for access by forklifts/smaller vehicles.
3. Free area under a pipe rack may be utilised for underground electrical and instrument
cables if it is permitted by local regulations and practices.
5.2 SAFETY
5.2.1 General
1. The requirements in this Section apply in conjunction with (3.2.2).
2. The general philosophy should be to apply open structures, unless this is constrained
by other factors such as the nature and frequency of operators' work, climate, type of
equipment, nature of process, proximity of hazards, noise.
3. The temperature on working areas (e.g., platforms, staircases, column cage ladders)
shall not exceed the limit defined in the project HSSE Plan, taking into account heat
emission sources (e.g., hot air outlets of air-cooled heat exchangers, heater stacks).
4. Mirror image equipment/unit arrangements should be avoided. For example, refer to
the requirements in DEP 30.05.10.30-Gen.
5.2.2 Utility units
1. Utility units handling flammable products (e.g., hot oils, fuel oils, fuel gas) shall be
treated as units processing hydrocarbons and located as follows:
a. in close proximity to the serviced process units
b. away from office buildings, workshops.
c. See (4.5) regarding the minimum distance to fixed ignition sources.
2. Utility handling non-flammable products (e.g., instrument air, boiler feed water,
nitrogen) should not have process safety related requirements.
5.2.3 Escape and personnel access
1. The layout shall provide an escape route during an emergency and shall provide
personnel access during operation and maintenance. Reference is made to
DEP 34.28.00.33-Gen.
DEP 80.00.10.11-Gen.
February 2016
Page 45
5.3 CONSTRUCTION
1. The plot plan shall be designed such that adequate access is available to transport
and lift all equipment into place.
2. Reference is made to the ORP with respect to the constructability reviews to be
carried out early in the design phases.
DEP 80.00.10.11-Gen.
February 2016
Page 46
5.4 COST
1. All equipment should be at the same elevation unless there is a safety, process, space
limitation, or accessibility requirement that requires equipment to be located at varying
elevations (e.g., gravity flow from one vessel to another).
2. Positioning equipment on elevation should only be considered when dictated by
ground space limitations and/or process requirements.
3. Equipment should be located such that long pipe runs are minimised.
5.5 ENGINEERING
5.5.1 Equipment grouping
1. Equipment sharing a common need or serving a common purpose should be grouped
together.
2. Equipment grouping should be done for:
a. Equipment involving high pressure piping
b. Equipment involving similar maintenance requirements (compressors, pumps)
c. Equipment with high electrical power requirement or under the same area
classifications
d. Locating of heavy equipment on stronger surface
5.5.2 Pipe routing
1. Space for piping shall be reserved during the development of the layout.
2. Pipe routing shall be established to ensure that:
a. All special process requirements (e.g., gravity flow, self-draining, mixed phase,
critical NPSH, etc.) have been addressed
b. The cost of piping runs (e.g., large diameter, alloy, high temperature, high
pressure, etc.) has been optimised
c. Adequate space has been provided for considerations as expansion loops,
manifolding, orifice runs, utility service stations, etc.
d. Piping does not hamper inspection or servicing of equipment
e. Valves and instruments can be effectively and efficiently accessed
3. Within plant limits, piping should run aboveground.
4. Firewater lines may be buried if considered necessary for safety (mechanical
protection).
5.5.3 Instrument and electrical cable routing
1. Space for instrument and electrical cables shall be reserved during the development of
the layout.
2. When cable trays are located on pipe racks, the following shall be met:
a. Cables trays shall be on the top level to create segregation between piping and
cable trays.
b. Electrical cables shall be at one side of the pipe rack and instrument cables at the
other side to create segregation between the two
DEP 80.00.10.11-Gen.
February 2016
Page 47
5.6 OPERATION
5.6.1 Operation/monitoring considerations
1. Equipment requiring frequent attendance by operation personnel shall be identified
and the layout optimised to enable the shortest and most direct routes for operators
when on routine operator rounds.
In this context, frequent access is equipment that is expected to be checked daily
as part of the operator surveillance round.
5.6.2 Operating areas
1. The arrangement of equipment, instruments and controls (in terms of location,
orientation, spacing and clearances) shall support safe, effective and efficient human
performance on operational tasks.
2. The dimensions of the areas required for operation shall be assessed for normal and
emergency activities taking human factors constraints and local requirements into
account (3.4.3).
5.7 MAINTENANCE
5.7.1 General
1. Clearances for passage of mobile equipment shall be based on the largest piece of
equipment anticipated and local practices. Reference is made to
DEP 34.13.20.31-Gen., Section 2.3.
2. The layout should prevent the need to lift or slew over live operating (on-stream)
equipment when conducting maintenance.
a. Where deemed necessary, a risk assessment shall be conducted during the
design to confirm the residual risk is ALARP.
5.7.2 Maintenance space
5.7.2.1 General
1. The arrangement of equipment, instruments and controls (in terms of location,
orientation, spacing and clearances) shall support safe, effective and efficient human
performance of maintenance tasks (3.4.3).
2. Adequate access shall be provided to areas where maintenance has to be carried out
and to areas where equipment or material is brought in for maintenance/cleaning
purposes.
3. The dimensions of the areas required for maintenance shall be:
a. based on the largest piece of equipment that will service the area;
b. assessed for normal and emergency activities, taking human factors constraints
into account.
4. Adequate free space shall be provided for the access to equipment and to remove, lift,
and transport equipment (parts) during maintenance or replacement.
5. Use of restricted access roads into the process area should be considered depending
on the nature of the equipment to be serviced.
6. To allow maintenance access and safe escape, the area under plant pipe racks shall
not be obstructed.
a. An open space of at least 4 m (13 ft) wide over the entire length of the pipe rack,
not obstructed by manifolds, ladders, equipment, etc., and accessible from the
roads, shall be left available.
DEP 80.00.10.11-Gen.
February 2016
Page 48
5.9 STRUCTURES
1. The number of structures should be minimised by combining structures (e.g., for shell
and tube heat exchangers and for vessels).
5.10 PLATFORMS/LADDERS/STAIRS
1. Refer to DEP 34.28.00.31-Gen. and DEP 34.28.00.33-Gen. for the design of
platforms/ladders/stairs.
6.1 INTRODUCTION
The mechanical general arrangement drawings give the overall spatial arrangement of
equipment within the available unit boundaries.
6.2 SAFETY
1. The requirements in this Section apply in conjunction with (3.2.2).
2. Equipment shall be protected against major mechanical impact (e.g., fork lift truck,
crane/hoist impacts and car collision),
3. Valves that isolate the unit inventory should be located in areas where they will not be
affected by mechanical damage.
6.4 INSTRUMENTATION/ELECTRICAL
6.4.1 General
1. Instrument tubing and cable routing shall not interfere with unit accessibility for
emergencies, operation and maintenance.
2. The optimum location of instrumentation and electrical hardware (including supports)
shall be determined taking instrumentation, electrical, mechanical, engineering, and
maintenance aspects into account.
DEP 80.00.10.11-Gen.
February 2016
Page 51
6.4.2 Instrumentation
1. Instruments displays or indicators that need to be read by personnel shall be visible for
operators/maintenance personnel from grade or from platforms.
2. Instruments shall either be mounted at a height that allows access for routine
maintenance and calibration, or provided with platform access.
3. Refer to (3.4.3) and DEP 32.31.00.32-Gen., Section 2.5 for minimum accessibility
requirements for plant instruments.
6.4.3 Local control panels
1. All local control panels, instruments and valves required for controlled start-up or
emergency shutdown of the unit shall be mounted at one side of the unit and be easily
accessible/visible.
6.4.4 Electrical
1. High and/or low voltage cables shall be laid in trenches or on trays separated from
those used for instrumentation, telecom and computer/data cables.
2. Refer to DEP 33.64.10.10-Gen., Section 5 for additional requirements.
6.5 ANALYSERS
1. Space is required for the instruments, storage compartments, washbasin, portable
equipment and containers.
6.6.7.2.1 General
1. Pumps in C4 and lighter services SHALL [PS] be located to meet all of the following
a. a minimum of 3 m (10 ft) from pipe racks and major process structures;
b. accessible for fire fighting
c. in the open (on the outside of the unit);
d. in a non-congested area;
In this context, non-congested means that the area the pump is located in is
sufficiently open so that, in case of release of process material, the resulting
vapour is able to disperse.
2. Pumps in flammable services (C5 or heavier) above their minimum auto-ignition
temperature SHALL [PS] be located as follows:
a. a minimum of 3 m (10 ft) from pipe racks and major process structures;
This is to avoid escalation of a possible fire due to chimney effects.
b. accessible for firefighting.
3. Pumps in flammable services (C5 or heavier) below their minimum auto-ignition
temperature shall be located as follows unless otherwise agreed with the Principal’s
Technical Authority:
a. a minimum of 3 m (10 ft) from pipe racks and major process structures;
This is to avoid escalation of a possible fire due to chimney effects.
b. accessible for firefighting.
If there are major constraints and cost implications, it can sometimes be acceptable
to locate the pumps between pipe rack and equipment such as distillation columns
provided ALARP is achieved.
4. Only pumps handling non-flammable liquids may be located under pipe racks or
structures.
5. Pumps shall be located on ground level and above the known flood level. If there is no
NPSH reason, pumps should not be installed in a sump or pit in order to avoid gas
traps and to avoid costly civil work and drainage problems.
6. Whenever practical, pumps shall be located in a row with the concrete blocks in one
line and with the motors all facing the same direction to be able to make a straight
underground drain line.
7. All pumps shall be accessible for operation, maintenance and emergencies. (3.4.3)
8. Pumps should be located close to the equipment from which they take suction.
9. Double rows of pumps may be arranged with pumps back-to-back piped up to a
common pipe rack.
a. Piping should be arranged alongside the pump end of the assembly.
10. Groups of pumps should have their discharges and discharge valves and, if possible,
their suction valves and seal pipes lined up.
11. Adequate length shall be available to install flow measurement or control apparatus
associated with the pumps.
a. Minimum suction line straight length shall comply with DEP 31.38.01.11-Gen.,
Section 4.2.
DEP 80.00.10.11-Gen.
February 2016
Page 55
6.6.7.3 Compressors
DEP 80.00.10.11-Gen.
February 2016
Page 58
6.6.7.3.1 General
1. Compressors should be supported from grade or on a concrete table top.
2. Access, space and lay-down area shall be provided around the compressor packages
to allow efficient removal of driver, casing, pistons etc. as well as cooler equipment.
3. When two or more similar compressors are installed adjacent to each other with
connecting maintenance platforms, the decking shall be at the same elevation. Side
steps on the platform are not acceptable.
4. Compressors decks shall be large enough for safe and efficient equipment operations
and maintenance without overhanging the decked surface.
a. A minimum 1.8 m (6 ft) wide maintenance walkway shall be provided around the
compressor driver.
b. A clearance of minimum 1.8 m (6 ft) between the compressor frame side and the
first obstruction shall be provided.
5. A minimum of one maintenance drop zone near a maintenance access way shall be
provided on each compressor deck.
6. All accessible areas between the machine and/or foundation and the deck shall be
covered with grating.
7. The start/stop station shall be located near the compressor.
DEP 80.00.10.11-Gen.
February 2016
Page 59
6.6.10 Valves
6.6.10.1 General
1. For categorization and human factors engineering aspects of valves, see
DEP 31.38.01.11-Gen. and DEP 30.00.60.20-Gen.
2. The location of and access requirements for a valve shall be based on the criticality
and access frequency for operational/maintenance requirements as determined as
part of the Valve Criticality Analysis in DEP 30.00.60.20-Gen.
3. Valves used for emergency operations shall be accessible as per
DEP 30.00.60.20-Gen
6.6.10.2 Relief valves
1. Relief valves and block/bypass valves shall be accessible for inspection, and where
applicable local testing during operation as per DEP 30.00.60.20-Gen.
6.6.10.3 Control valves and block/bypass valves
1. Control valves and block/bypass valves shall be accessible for operation and
maintenance as per DEP 30.00.60.20-Gen.
6.6.11 Mixers
1. Access shall be provided to mixer mounting manholes and to mixer drive mechanisms,
as well as space to remove the whole or parts of the mixer for maintenance purposes.
6.6.12 Filters
1. Access shall be provided to basket filters and strainers to remove the filter or strainer
elements for cleaning or replacement.
6.6.13 Air intakes/exhausts
1. Air intakes/exhausts SHALL [PS] be located according to area classification.
Reference is made to DEP 80.00.10.10-Gen. and DEP 80.00.10.13-Gen., as
applicable.
6.6.14 Vacuum installations
1. The length of a barometric leg, which depends on the specific density of the liquid and
the depth of the vacuum, shall be taken into account.
6.6.15 Mechanical conveyors
1. The Manufacturer/Supplier shall be consulted on layout and operation/maintenance
aspects.
2. For multiple belt conveyors, a maintenance walkway of 600 mm (2 ft) width minimum
shall be provided along each conveyor.
6.6.16 Manholes
1. For sizes of manholes, see DEP 31.22.00.31-Gen., section 5.13, and
DEP 30.00.60.20-Gen.
2. An access platform shall be provided if the manhole centre is higher than 4 m (13 ft)
above grade. Up to 4 m (13 ft) scaffolding may be used.
6.6.17 Filling and packaging equipment
1. Adequate area shall be available close to the packaging line for buffer storage of
components with adequate access from supply routes.
2. Sufficient area shall be available for pallets and storage/handling of finished product.
3. Space shall be available for vehicles and fork lift truck access.
DEP 80.00.10.11-Gen.
February 2016
Page 62
7. REFERENCES
In this DEP, reference is made to the following publications:
NOTES: 1. Unless specifically designated by date, the latest edition of each publication shall be used,
together with any amendments/supplements/revisions thereto.
2. The DEPs and most referenced external standards are available to Shell staff on the SWW
(Shell Wide Web) at http://sww.shell.com/standards/.
SHELL STANDARDS
API RP 500)
Design of pressure relief, flare and vent systems DEP 80.45.10.10-Gen.
(amendments/supplements to API RP 520 Part II and API STD 521
Chapter 5)
Assessment and design of the fire safety of onshore installations DEP 80.47.10.30-Gen.
Shell HSSE & SP Control Framework, Design Engineering Manual DEM1
(DEM) 1 – Application of Technical Standards Design Engineering
Manual (DEM) 1 - Application of Technical Standards
Design Engineering Manual (DEM) 1 - Application of Technical
Standards
ALARP Guide, Shell Global Library, Dec 2013 SR.13.14005
Shell HSSE & SP Control Framework, Health Manual Control Health Manual
Framework - Health Manual
Control Framework - Health Manual
Shell HSSE & SP Control Framework, Design Engineering Manual DEM2
(DEM) 2 – Process Safety Basic Requirements Design Engineering
Manual (DEM) 2 – Process Safety Basic Requirements
Design Engineering Manual (DEM) 2 – Process Safety Basic
Requirements
AMERICAN STANDARDS
INDUSTRY STANDARDS