Professional Documents
Culture Documents
Caroline White BP
Agenda
• Context
• UK Decommissioning legal regime
• Topsides cleaning
• Quantification of waste
• Waste management strategy
• How we did
• Lessons learned
North West Hutton – key facts
• BPEO assessment was carried out to identify best option for removal of liquid
and NORM wastes
• Clear set of criteria established for cleanliness:
- All surfaces clean from hazardous quantities – hydrocarbons, process chemicals, sediments,
metal scales etc.
- All free liquid removed in confined spaces
- All hazardous confined spaces removed
through achievement of specific
atmospheric conditions e.g. hydrocarbons in
air <1% Lower Explosive Limit,
- No visible sign of NORM with no instrument
reading >2X background
Quantification of ‘waste’
• Where residual waste was identified as a coating these data were used to
estimate quantities for a range of coating thicknesses (1mm and 5mm)
throughout pipework lengths, vessels and systems
Worst and best case estimates
Estimated quantities of residual hydrocarbons and NORM scale, based on different assumptions of
thickness of residue:
Estimated
Waste type Weight
(t)
Steel 28,500
Marine Growth 436
Residual hydrocarbon 20
sludge
Production chemicals 0.6
Drilling chemicals 9
NORM Scale 5
Diesel oil 0.1
Heating medium 0.5
Hydraulic oil 0.04
Lube oil 1
Seal oil 1
PCBs 0.034
Mercury 0.00034
Asbestos 5
Decommissioning waste – onshore capability?
Reviewed:
12
• The handling capacity of the facility (size
14
and weight of modules)
13
7
• Docking capacity (size, weight, depth)
16
• Optimisation of the waste hierarchy
18
• Licences and consents held by facility,
17
25 relevant to decommissioning activities
Waste management planning
• Waste management strategy developed to ensure alignment between
BP, decommissioning contractor and onshore dismantlement and
disposal contractor. This provided:
• Document was shared with the regulator to ensure they had full
understanding of the materials being transferred
Waste Management Process Overview
Location (e.g. skip number) of waste Onshore Dismantling Yard Project Waste Management
once removed from module and stored Plan
in Dismantling Yard awaiting reuse /
recovery / disposal
Final Disposal Actual weight of each waste Weighbridge data of all material leaving Dismantling
Point consignment leaving site for re-use / Yard
Third Party recycling / disposal