EQUIPMENT MAINTENANCE SCHEDULE

EQUIPMENT TYPE
EQUIPMENT CODE
LOCATION PRACTICAL WORK AREA/WAF
Schedule for the Month of March
MANPOWER Daily Every Weekly Every Monthly Remarks
ACTIVITIES
Other 15th
Day Day
1. Check panel board, and Electrician Activity is
circuit breakers’ electrical Trainer X done before
connections, cables and and after
outlets using the
 Clean and kept dry equipment
 Parts are well-
secured/attached
 Properly labeled
2. Check Mig gun (nozzle, Trainees Activity is
contact tip, diffuser) and Trainer X done before
ground cable: using the
 Clean and kept dry equipment
 Parts are well-
secured/ attached
 Inspect for damages
and replace parts if
necessary
3. Check adjustment lever’s Trainees Activity is
if functional Trainer X done before
(amperages/speed); if using the
not, calibrate equipment
4. Check Gas cylinder outfit Trainees Activity is
for any abnormality Trainer X done before
 Gate valve using the
 Co2 regulator equipment
 Gas hose Fittings
 Fittings

5. Check/Clean wire feeder Trainees


(rollers, wire speed/spool Trainer X
adjustment); remove used
oil, dust; keep dry.
6. Run the equipment for 5 Check
minutes and observe for X warranty
unusual noise or and after
abnormal operation; if service
repair is necessary, send assistance
to technician. from dealer