Date: 19/08/2020 (Wednesday)

Weather: Am-Raining (8:00am to 1:00 pm)


Pm-Cloudy

Work Progress Report (Nanga Makut to Nanga Engkuah)

-Repairing Access Road to Site.


- Repairing Pipe for Base Camp.

Man Power
-Project Manager-1
-Project Engineer-1
-QAQC Manager-1
-Site Supervisor-2
-Safety Officer-1
-Safety Supervisor-1
-Surveyor-1
-Chainman-4
-Carpenter-4
-Operator-2
-Security Guard-2
-General Worker-15
-Lab Technician-1
-Cook-1
Total 36

Machinery / Equipment
-Excavator-1
-Bulldozer-1