PROJECT DAILY REPORT

ROW STRINGING CABLE TOWER

Client : Sorik Merapi Geothermal Power Date : 21 November 2017


Contractor : PT. Supraco Indonesia Report No. : 01
Location : Mandailing Natal, North Sumatra Number of Days :1

Weather Condition :
A.M
- Normal
- Cloudy
- Windy
- Rainy At 01.30pm
- Hard Rain
- Other

Manpower :
Staff : Direct Manpower :
- Number of Staff = 1 Person - Number of Direct Manpower = 1 Persons

Safety :
- Work Permit - - PPE Inspection - - Safety Note :
- Safety Induction - - Safety Inspection - - We meeting and discuss first with SMGP
- Prejob Meeting - Equipment Inspection - survey for marking area stringing cable tower
- Safety Talk - - - Other -

Progress Work : (Key Actifity and Material Deliveries)


- Prepared material: barricade and sword (parang)
- Marking area for stringing cable tower from wellpad A to TA-01
- Marking area for stringing cable tower from TA-01 to TA-02
- We can't continue marking area at 01.30pm because hard rain and we will continue next day

Items Accomplised :
- Tomorrow we will continue marking area for row stringing cable tower TA-02 to TA-04

Unresolved Issue / Factor Contributing to Delay :


- We need 3 more helpers for marking right and left area stringing cable tower

Report By, Checked By, Approved By,

Irvan Apriliandi Shandy Sukmana


Drafter Project Manager PT. Sorik Merapi Geothermal Power

Page 1 of 2
PROJECT DAILY REPORT
ROW STRINGIN CABLE TOWER
Pictures/Evidances :

Marking area

Page 2 of 2