Powermec

I&C Da

S.N Date Shift Area Location Equipment

1 1/Jun/23 Day CHP CC-1A All Instruments

2 1/Jun/23 Day CHP TT-1 Dust Collector

3 1/Jun/23 Day CHP TT-1 Dust Supression

4 1/Jun/23 Day CHP Stacker Hooter

5 1/Jun/23 Day AHP ESP Feed valve

6 1/Jun/23 Day AHP ESP Feed valve


Powermech Project Ltd.
I&C Daily Report

Work Type KKS Description

PM PM of CC-1A Instruments cleaning and checking work completed

PM of TT-1A Dust Collector Instruments cleaning and checking work


PM
completed
PM of TT-1A Dust Supression Instruments cleaning and checking
PM work completed
Stacker LT hooter getting on while isolating LT feeder checking work
CM
under progress

CM Unit 2 ESP 6 th field 1s vessel feedvalve limit checking work under


progress
Unit 2 ESP 6 th field 6th vessel feedvalve limit checking work under
CM progress
Manpower: Pavendan,
Swapnil, Anwar, Shahid Remarks
Raju,
Night:- Sunil

2
Powermec
I&C Da

S.N Date Shift Area Location Equipment

1 2/Jun/23 Day CHP CC-0B All Instruments

2 2/Jun/23 Day CHP TT-1 Dust Collector

3 2/Jun/23 Day CHP Stacker Hooter

4 2/Jun/23 Day CHP Stacker DCS

5 2/Jun/23 Day AHP Jetty All Instruments


Powermech Project Ltd.
I&C Daily Report

Work Type KKS Description

PM PM of CC-0B Instruments cleaning and checking work completed

PM of TT-1B Dust Collector Instruments cleaning and checking work


PM
completed
Stacker LT hooter getting on while isolating LT feeder checked found
CM fuse broken in VFD panel, Fuse replaced and now ok
Stacker with 9A interlock checked, DCS logic checked, Due to 4B ZSS
CM interloack stacker was tripping, After starting the sequence, trial
taken
PM of Jety fire pump MDLS Instrument checking and cleaning work
PM completed
Manpower: Pavendan,
Swapnil, Anwar, Shahid Remarks
Raju,
Night:- Sunil

2
Powermec
I&C Da

S.N Date Shift Area Location Equipment

1 3/Jun/23 Day CHP CC-3A All Instruments

2 3/Jun/23 Day CHP TT-3 Dust Collector

3 3/Jun/23 Day CHP TT-3 Dust SUPPRESSION

4 3/Jun/23 Day AHP U1 ESP Air Intake

5 3/Jun/23 Day U1 ESP Air Assist

6 3/Jun/23 Day CHP Jetty Fire Instruments


Powermech Project Ltd.
I&C Daily Report

Work Type KKS Description

PM PM of CC-3A Instruments cleaning and checking work completed

PM of TT-3 Dust Collector-A Instruments cleaning and checking work


PM
completed
PM of TT-3 Dust Suppression Instruments cleaning and checking
PM work completed
U1 Esp Air intake open feedback not showing on DCS limit switch
CM
adjustment work completed

CM U1 Esp air assist valve opeated slowly overhauling work of actuator


completed
PM of JETY Fire PMP instruments MDLS cleaning and checking work
PM completed
Manpower: Pavendan,
Swapnil, Anwar, Shahid Remarks
Raju,
Night:- Sunil

2
Powermec
I&C Da

S.N Date Shift Area Location Equipment

1 4/Jun/23 Day CHP CC-7A/B,6A/B & 0A/B Metal detectors

2 4/Jun/23 Day CHP CC-7A/B & 0A/B Belt weigher

3 4/Jun/23 Day CHP Bunker 2 Dust Collector

4 4/Jun/23 Day AHP Unit 3 ESP Blower


Powermech Project Ltd.
I&C Daily Report

Work Type KKS Description

PM PM of CC-7A/B, 6A/B & 0A/B Metal detectors Instruments cleaning


and checking work completed
PM of TT-3 Dust Collector-A Instruments cleaning and checking work
PM
completed
Dust collector 2A bunker Purging not working, Checking work under
CM progress
PM of Unit 3 Blower Instruments cleaning and checking work
PM
completed
Manpower: Pavendan,
Anwar, Shakthi, Sunil, Remarks
Murugan
Night:-Shahid

2
Powermec
I&C Da

S.N Date Shift Area Location Equipment

1 5/Jun/23 Day CHP CC-2A All Instruments

2 5/Jun/23 Day CHP TT-2 Dust Collector

3 5/Jun/23 Day CHP Bunker 2 Dust Collector

4 5/Jun/23 Day CHP CC-9A CBS

5 5/Jun/23 Day AHP Uniit 3 ESP


Powermech Project Ltd.
I&C Daily Report

Work Type KKS Description

PM PM of CC-2A Instruments cleaning and checking work completed

PM of TT-2 Dust Collector-A Instruments cleaning and checking work


PM
completed
Dust collector 2A bunker Purging not working, Checking work under
CM progress
9A to 4B Chute block switch Acted, Switch cleaned and power supply
CM
resetted

CM Unit 3 Field 1 1st vesel vent valve, limit checked after MMD work
Manpower: Pavendan,
Anwar, Shakthi, Sunil, Remarks
Murugan
Night:-Shahid

2
Powermec
I&C Da

S.N Date Shift Area Location Equipment

1 6/Jun/23 Day CHP Stacker Reclimer All Instruments

2 6/Jun/23 Day CHP Stacker Reclimer PLC

3 6/Jun/23 Day CHP TT-5 DFDS

4 6/Jun/23 Day CHP Unit 3 ESP

5 6/Jun/23 Day AHP Unit 3 ESP

6 6/Jun/23 Day AHP Unit 3 ESP


Powermech Project Ltd.
I&C Daily Report

Work Type KKS Description

PM PM of Stacker- Reclimer Instruments cleaning and checking work


completed
PM of Stacker- Reclimer PLC and RIO panels cleaning and checking
PM
work completed

TT-5 DFDS Air Compressor outlet air pressure Not Increasing,


CM checking and overhauling work completed , now in healthy condition

Unit 3 ESP 6th field 8th vessel vent valve operation checked,
CM operation ok but open limit indication continously coming, to be
checked

CM Unit 3 SCR 4th vessel vent valve operation checked, operation ok

Unit 3 ECO 4th vessel feed valve operation checked, operation ok,
CM But open limit continously coming, to be checked
Manpower: Pavendan,
Anwar, Shakthi, Sunil, Remarks
Murugan
Night:-Shahid