Main Activities

1 Depot Site Work

1.1 water leak test inspection for Oily Drum pit NA-21-V-02,06

1.2 Compaction test for surge relief pumps NA-06-P-01,02 A/B

1.3 Compaction test for soil around TK-07,V-05

1.4 Rebar work for relief Tank-2

1.5 Start with rebar work for pie supports

1.6

1.7

1.8

1.9

1.10

1.11

0
Remarks
1.1 water leak test inspection for Oily Drum pit NA-21-V-02,06 1.2 Compaction test for surge relief pump

1.3 Compaction test for soil around TK-07,V-05


1.5 Start with rebar work for pie supports
1.2 Compaction test for surge relief pumps NA-06-P-01,02 A/B

1.4 Rebar work for relief Tank-2