Professional Documents
Culture Documents
The Existing Structure The key determining factors during the ‘optioneering’
Bridge 2/11~2/12 was originally built circa 1890 and stage were:
comprised of mass brick abutments and a central pier that • Minimise the prefabricated deck weight
supported a deck of riveted hogged-backed wrought iron • Minimising the crane pad footing load
Design and Reconstruction of Bridge 2/11~2/12
between Clapham Junction and Waterloo Stations
• Provision of sufficient tolerance during erection overall weight and avoided the potential maintenance
• Maintaining existing construction depth and issues associated with the cross girder and main girder
headroom clearances connections. Welding procedures were developed with
the steelwork fabricator, with particular attention made to
• Working within the limitations of the rail- welding access restrictions, distortion and general
mounted crane capabilities buildability issues.
• Construction sequence and planning
The use of ‘modern’ rail cranes to lift in bridge deck units
• Working within the possession limitations for is relatively new to the industry. They are predominantly
the rail-locked site employed for lifting in and out sleepers and switches and
Half-through, girder type construction was decided upon at crossings as part of permanent way improvements; such
an early stage, as being the most practicable solution when elements weigh considerably less than the decks
considering the existing track arrangement and the fact that proposed for this bridge replacement scheme. Prior to
this type of arrangement typically provides a light form of embarking on the design, the full capabilities of the
construction. The weight limitations immediately ruled out KIROW crane were interrogated - this being the only
the use of concrete or steel composite floors. The form of reasonable way that the new decks could be satisfactorily
deck construction thus adopted was to provide an all steel installed in the time available.
modified ‘Z’ type arrangement.
The available construction depth (top of rail to deck soffit) Detailed Design
was approximately 1000mm and the minimum headroom to
the railway lines below was 4200mm. The preliminary deck design was taken forward with little
further change, other than to optimise plate sizes in order
to minimise the weight of each deck unit.
It was proposed to utilise the KIROW cranes for both the
demolition and installation of the new works. Excluding
demolition, there were a total of 44 crane lifts. These
comprised ten deck units, eighteen cill units, ten ballast
wall units, four robust kerbs and two walkway hand rail
assemblies. Minimising the weight of the individual units
and reducing the number of crane movements and set-ups
was considered to be key to the success of the scheme.
The deck spans varied slightly due to the tapering nature
of the existing abutments and central pier. This resulted
in a range of deck weights between 32 and 36 tonnes.
The calculated (predicted) weights were confirmed during
Figure 3: Cross section of deck a trial erection undertaken prior to the possession.
The bridge skew is of the order of 40° which worked to
The standard ‘Z’ type deck is normally designed with either the crane’s advantage as it meant that three bridge decks
an all-steel ‘T’ ribbed floor, or a floor of concrete-encased could be placed from a single set-up (by placing one in
steel beams. These floors include machined end plates that front and two to the side working back with the skew).
are bolted to the web of the main girder. To minimise deck With each set-up requiring the crane to track back to the
weight and on-site operations, the practicality of utilising nearest set of crossovers to change line, the reduction in
only welded deck connections (as opposed to bolted number of set-ups saved a significant amount of valuable
connections) was discussed with Network Rail and the possession time.
steelwork fabricator. These discussions resulted in an
innovative solution that involved fabricating the bottom Careful planning of the crane movements and the flat-bed
flange of the main girders and cross-girders from a single wagons that delivered the deck units to site was required,
16m x 3m x 40mm thick rolled plate. This was achieved by to ensure that sufficient time and space were available to
cutting out rectangular panels from the 40mm thick rolled remove the existing deck, raise the new deck units, and
plate. This not only permitted a structurally efficient section locate them in their correct and final positions.
and improved fatigue classifications, but also reduced the