Professional Documents
Culture Documents
CABLE-STAYED BRIDGES
GROUP:-JASSIMAR SINGH,,AARSH MALHOTRA,RAJAT VERMA
Contents
▣ TECHNOLOGY ▣ CASE STUDIES ▣ STORY BOARD
1. Tensile Structures 1. Cable stayed bridge over the 1. Pylon
2. Types River Labe at Nymburk
2. Orthotropic Deck
3. Cable Structures 2. The Basohli Cable
3. Access Ramps and Stairs
4. Types Bridge,India
4.
5. Cable Stayed Bridges 3. Munich Olympic Stadium,
Parapet
Germany 5. Members and Connections
6. Components 6. Bearing and Expansion joints
7. Load Bearing Mechanism
8. Types of Cables ▣ FAILURES
9. Design 1. Morandi Bridge Collapse
10. Construction Process 2. New Haengju Bridge
11. System specifics and Materials Collapse
12. Advantages and Disadvantages
13. Cables
14. Pylon
15. Deck
16. Anchorage in Cables 2
Tensile Structures
The term tensile structures describes the category of buildings in which the load bearing capacity
is achieved through tension stress in the majority of the components, such as cables, technical
fabrics or foils.
It can also be defined as a structure where the exterior shell is a fabric material spread over a
framework. The fabric is maintained in tension in all directions to provide stability.
The only exception is represented by rigid boundaries and structural members which are
generally subjected to compression and bending.
3
Types of Tensile Structures
4
Foot Over Bridges
5
Steel Truss Bridges
Basic steel truss bridges are an extremely versatile bridge form which provides an economical
solution for spans over 20m and in their basic form can span up to around 80m with
longer lengths available as multi-span options.
The main types of the basic steel truss bridges are Vierendeel, Warren and Pratt truss.
6
Steel beam bridges
A beam and slab, or composite bridge is one where a reinforced concrete deck slab sits on top of
steel I-beams, and acts compositely with them in bending. There are two principal forms of this
beam and slab construction; multi-girder construction and ladder deck construction.
The prime structural element of a footbridge is to use a pair of girders (fabricated or rolled
sections), braced together for stability and acting as beams in bending, with a non-participating
walkway surface on top. Bridge deck might for example be formed by timbers placed transversely
across the top of the beams. Precast slabs might also be used, without a shear connection to the
steel and therefore not participating in structural action.
Cross section of a multi-girder highway bridge Cross section of a ladder deck bridge
7
Box girder bridges
Box girders comprise two webs that are joined top and bottom by
a common flange creating a closed cell that offers very good
torsional stiffness, which may be required on highly curved bridges.
In beam and slab bridges, box girders are an alternative to plate
girders at the upper end of the span range, where they offer a
lower steel weight, although this has to be balanced against
increased fabrication costs. The top flange acts as the floor of the
bridge, and there are usually short cantilevers either side of the
box. This form has the benefits of good torsional stiffness, which
can simplify support arrangements and clean surfaces which
minimize maintenance.
8
Arch bridges
The arch springs from the foundations and exerts horizontal thrusts on them. The arch elements
act primarily in compression. The deck may either be supported on struts, resting on arch below,
or it may be suspended on hangers from the arch above.
A tied-arch or "bow string" arch is a particular development of the arch form. The horizontal
thrusts from the arching action are resisted by tension members between the arch springings.
Effectively the deck acts as a tension tie, and is supported by hangers from the arch above. This
form is suited to the soft soils of riverbanks, where the ground cannot withstand the large
horizontal thrusts from arching action.
10
Types of Cable Structures
Suspension Bridge Cable-stayed Bridge
• Suspension bridges is normally limited to two towers. • Cable-stayed bridges lies in the fact that it can be built with any number
11
CABLE-STAYED BRIDGES
12
COMPONENTS
All cable-stayed bridges the structural system can be divided in to main components as follows:
▪ The stiffening girder (or truss) with the bridge deck
▪ The cable system supporting the stiffening girder
▪ The towers (or pylons) supporting the cable system
▪ The anchor blocks (or the anchor piers) supporting the cable system vertically or horizontally.
13
LOAD BEARING MECHANISM
In the cable-stayed bridge, the towers are the primary load-bearing structures which transmit
the bridge loads to the ground.
A cantilever approach is often used to support the bridge deck near the towers, but lengths
further from them are supported by cables running directly to the towers.
This has the disadvantage, compared to the suspension bridge, that the cables pull to the sides
as opposed to directly up, requiring the bridge deck to be stronger to resist the resulting
horizontal compression loads, but has the advantage of not requiring firm anchorages to resist
the horizontal pull of the main cables of the suspension bridge.
By design all static horizontal forces of the cable-stayed bridge are balanced so that the
supporting towers do not tend to tilt or slide, needing only to resist horizontal forces from the
live loads.
The high tensile strength of steel, combined with the efficiency of simple tension, makes a
steel cable the ideal structural element to span large distances.
Cables are flexible because of their large lateral dimensions in relation to their lengths.
As uneven stresses true to bending are prevented by flexibility the tensile load is evenly
divided among the cable strands.
14
Two types of cable-stayed bridges
Fan design
The cables all connect to or pass over the top of the towers. The fan design is structurally superior with
minimum moment applied to the towers but for practical reasons the modified fan is preferred especially where
many cables are necessary
In the modified fan arrangement, the cables terminate near to the top of the tower but are spaced from each other
sufficiently to allow better termination, improved environmental protection, and good access to individual cables for
maintenance.
15
DESIGN
There are four major
classes of rigging on cable-
stayed bridges: mono,
harp, fan, and star.
16
DESIGN
1. The mono design uses a single cable from its towers and
is one of the lesser-used examples of the class. 2. In the harp or parallel design, the cables are nearly parallel so that
the height of their attachment to the tower is proportional to the
distance from the tower to their mounting on the deck.
3. In the fan design, the cables all connect to or pass over the top of
the towers. The fan design is structurally superior with a minimum
moment applied to the towers, but, for practical reasons, the
modified fan (also called the semi-fan) is preferred, especially 4. In the star design, another relatively rare design, the cables are
where many cables are necessary. In the modified fan spaced apart on the tower, like the harp design, but connect to
arrangement, the cables terminate near the top of the tower but one point or a number of closely spaced points on the deck.
are spaced from each other sufficiently to allow better termination,
improved environmental protection, and good access to individual
cables for maintenance.
17
CONSTRUCTION PROCESS
18
STEPS OF
CONSTRUCTION
19
STEPS OF CONSTRUCTION OF THE FOUNDATION
1. First the piled pylon foundations 2. A sealed coffer dam is built using 3. A temporary bridge, or jetty, is 4. Materials within the dam are
are installed, using a board piling rig sheet piles, installed using a constructed for transportation and excavated
working from a barge vibrating hammer to required depth excavation activities
5. A concrete slab is cast in the 6. A pile cap is placed in dry 7. The various segments of the 8. The lower segments of the pylon
home of the coffer dam and is conditions, supporting the piles, bridge are then fabricated and leg are installed form a crane at the
anchored to the board piles, and the along with a tower crane used for transported to the site for jetty
water is pumped out construction construction
20
SYSTEM SPECIFICS AND MATERIALS
The primary construction materials used in cable-stayed bridges are
21
Advantages Disadvantages
•
•
Still inferior to suspension bridges for super-
The cable-stayed deck is in compression, pulled towards long spans
the towers, and has to be stiff at all stages of construction • Requires checking deformations at all
and use.
•
conditions
A great advantage of the cable-stayed bridge is that it is • Requires experience in both design and
essentially made of cantilevers, and can be constructed by construction
building out from the towers.
• Cable-stayed bridges possess higher stiffness and display
smaller deflections when compared with suspension
bridges.
• Construction time is less for cable stayed bridges.
• Cable stayed bridges require less cables.
• Much greater stiffness than the suspension bridge, so that
deformations of the deck under live loads are reduced.
• For a symmetrical bridge (i.e., spans on either side of the
tower are the same), the horizontal forces balance and
large ground anchorages are not required.
22
Cables
▪ A cable is composed of one or more structural ropes, structural strands, locked coil strands or parallel wire strands.
A strand is an assembly of wires formed helically around centre wire in one or more symmetrical layers.
▪ A strand can be used either as an individual load-carrying member, where radius or curvature is not a major
requirement, or as a component in the manufacture of the structural rope.
▪ A rope is composed of a plurality of strands helically laid around a core. In contrast to the strand, a rope provides
increased curvature capability and is used where curvature of the cable becomes an important consideration.
▪ Cables are made of high-strength steel, usually encased in a plastic or steel covering that is filled with grout, a fine-
grained form of concrete, for protection against corrosion
23
Types of Cables
24
SHAPE OF PYLON
• A-type
• H-type
• Y-type
25
TYPES OF DECK
Twin I Girder Box girder
Orthotropic girder
Truss girder
26
ANCHORAGE IN CABLES
In concrete
27
ANCHORAGE IN CABLES
In steel
28
Cable stayed bridge
over the River Labe at
Nymburk
CASE STUDY
INTRODUCTION
Location: north-east of Nymburk in the Czech Republic
Span: main span of 132m together with a very shallow
structural depth
Open for use: May 2007
Company: Pontex Consulting Engineers Ltd.
the bridge carries the I/38 road over the River Labe as part of a
by-pass scheme built to alleviate traffic congestion from the
historical centre of the city. Due to the span and a shallow
structural depth, a so-called "extradosed“ main bridge
structure with low pylons was developed, representing a
transition between the traditional cable-stayed bridge and a
bridge with external prestressing tendons.
30
BUILDING DESIGN
•The complete bridge crossing has a continuous superstructure 530m long with expansion joints located only at the abutments.
•The main concrete bridge superstructure consists of a 132m span over the River Labe and two adjacent 41m spans that are directly
connected to the approach spans.
•The concrete deck sections of the main span are of a symmetrical double-girder shape of variable depth and width, and are supported
by sets of 3 parallel grouped stays anchored to the 16m high pylons.
•The middle section of the main span was designed as a relatively lightweight composite steel-concrete drop-in structure. This 52m span
comprises two main steel box girders that are tied by steel I section cross beams at 3.0m centres. The thickness of the lower and upper
flanges and webs of the main steel girders vary in accordance with the magnitude of the internal forces.
•After being delivered to site by barges the box girders were lifted into place and welded to 700mm long steel members that were cast
into the concrete structure and tied to it using longitudinal prestressing anchors fixed to the end plates.
•Shear studs tie a 245mm thick reinforced concrete slab to the steel girder structures.
31
32
Pylons
• The 16m high, heavily reinforced concrete pylons are topped with hollow
steel plated box chambers for anchoring the cable stays.
• The anchor plates are one of the most highly stressed parts of the
structure and were fabricated from 150mm thick steel plate.
• Welded into the front face of each anchor plate are six, 377mm diameter,
16mm thick steel tubes through which the stays were passed and then 1: Embedded steelwork ready to receive steel girders, fig 2: steel plated pylon box assembly
anchored.
• The bottom flange of the chamber is formed from 50mm thick steel plate
with stiffeners to provide a uniform distribution of the forces to the
concrete section.
• The side walls of the box are of 40mm thick plate with 50mm thick vertical
stiffeners at the anchor plate locations.
• Steel studs, welded uniformly to the sides and top of the box chamber,
bond the steel box to the self-compacting concrete that was subsequently
applied. A 600mm square manhole cover in the top of the pylon provides
maintenance access.
33
Cross beams and rocking struts
34
THE BASOHLI CABLE STAYED
BRIDGE,
INDIA
CASE STUDY
INTRODUCTION
36
SPAN CONFIGURATION
The span layout is symmetric (121m – 350m -121m), with pylons positioned at the top of the river banks (Figure 3). Two
inclined cable planes splay outwards from each pylon in a semi-fan configuration, connecting to the superstructure at 14-
meter spacing in the main span and 10.3 meters in the side spans. Near the abutments, three sets of intermediate piers
spaced at just over 20 meters form a secondary support system. the bridge accommodates two lanes of traffic as well as
two footpaths.
37
PYLON DETAILS
• Several different pylon configurations were evaluated during the bridge’s development,
including an A-frame and an inverted Y-shape, amongst others. However, the modified
diamond configuration offered several advantages (Figure 4).
• With large seismic demands, it was considered prudent to reduce the transverse
stiffness of the pylons while providing ductility so that energy could be effectively
dissipated during a seismic event.
• An inverted Y-shaped pylon behaves similarly to a truss with large axial tension and
compressions in the lower pylon legs under transverse seismic loading. With
predominately axial demands, the inability to achieve adequate ductility or energy
absorption into the pylon was deemed unacceptable.
• By reversing the inclination of the legs at deck level and bringing them together at the
base, thereby forming a modified diamond shape, the seismic behavior is changed from
predominately axial demands to flexural which can be utilized for ductility and energy
absorption.
• In addition, bringing the lower legs together reduces the footprint of the foundations.
• Each pylon was designed with a constant width of 5 meters for the full height.
Additionally, the 48 cables at each pylon are anchored within the top 33 meters by
utilizing steel anchor boxes which act compositely with the concrete walls. Pylon Geometry
38
SUPERSTRUCTURE DETAILS
• After pylon construction has proceeded beyond the first few sets of cable
anchorages and the side spans are complete, erection of the main span can
commence in a progressive cantilever fashion using prefabricated steel
elements.
• Using the progressive cantilever method with a previously completed side
span has a significant advantage of adding stability to the system to resist
wind buffeting loads during cantilevering. As such, supplemental tie-downs
or counter weighting is not required.
• With two different superstructure systems in use, two different stay
anchorages had to be designed. In the side spans, the stay cables extend
through the concrete edge girders and are anchored on the bottom soffit in
concrete blisters.
• Conversely, in the mainspan, the stay cables are anchored above deck using
a steel anchorage assembly that is welded directly to the web of the steel
edge girders, providing a direct load path for the axial cable loads into the Mainspan Cable Anchorage
longitudinal girder system (Figure).
40
MUNICH OLYMPIC STADIUM,
GERMANY
LONG SPAN STRUCTURE CASE STUDY
INTRODUCTION
42
FUNCTIONAL REQUIEREMENTS
43
ROOF
• The roof grid over the main stadium is formed by nine saddle-shaped
nets of 25mm steel cables spaced in a 762mm square grid.
• The total length of steel cable in the complex exceeds 408km and
tension loads in the cable net are as much as 5000 tons.
44
ROOF
• Originally the foundation design was intended to consist of prestressed anchors. Local code officials however insisted on
more conservative piers to provide stability. In some cases, these piers are as much as 18m deep and 6m wide.
• These enormous foundations were required to resist the tremendous tensile stresses in the cable network and the live
loads imposed by winds across and under the open structures.
Structural elements used Steel cable and mast Connection of two masts
45
ENVELOPE
Bronze-tinted acrylic plastic panels & Polyester fabric coated with PVC
•
installed above the cable wires.
Connections between the panels had to allow for thermal expansion
and structural movement of up to 1m deflection under heavy wind
•
loads.
The acrylic panels were attached to the supporting net at the
•
intersection points of the cables.
However, because of the irregularity of the net, the panels
•
sometimes overlapped the cable grid at varying angles.
Apart from offering enough colour contrast for improved
photography, the bronze tinting also helped reduce heat gains and
glare without casting shadows as a canvas canopy would have. Bronze tinted plastic panels
46
LIMITATIONS
▣ HVAC:
The fabric that is used as the roofing system of tensile structures usually have a very low R-value, making it very difficult to
maintain a certain temperature. This causes the heating and cooling loads to be enormous, and is an inefficient structure.
However, the availability of fabrics that are efficient at maintaining favourable conditions has greatly increased in recent
times, enabling the widening of the range of environments in which this system can be used. Furthermore, new materials
can provide not just insulation, but UV protection and can be fireproof for safety aspects.
▣ STRUCTURE:
The main limitation of this system is the inability to support any kid of large compressive load. The fabric used as the
roofing is in tension, and will not have enough compressive strength to support another floor above. In fact, it is unable to
support snow in some cases. Three dimensional tension structure also cannot be used on large vertical spans because of
their lack of ability to support large horizontal loads such as wind. The fabric or sheets act like a sail, and a small tear
caused by loadings can lead to bigger damages. An even more severe failure would be the breaking of the cables in
tension breaking under a large load. Due to this reason, this structure is often shaped to ensure that rain and snow will
slide off the structure.
47
STRUCTURAL ANALYSIS
48
CONSTRUCTION PROCESS
49
JOINERY DETAILS
51
JOINERY DETAILS
Overlapping
joints/Fixing joints
Foundation
52
JOINERY DETAILS
Overlapping
joints/Fixing joints
53
Morandi Bridge Collapse
FAILURE
About the Bridge
55
56
▣ Comparing the above shown Morandi M5 system to the modern practice, it is striking how tight the strands were located
inside the duct. In modern practice, the void section is around 50% larger than in the Morandi case. Moreover, the injecting
material available today is far more fluid than those available in the 1960s. It could thus be concluded that the ducts used in
the case of the Morandi bridge were essentially impossible to be injected and the same was proven based on descriptions
and photos reproduced in the report of the Commission of the Ministry of Infrastructure and Transportation. So, the
behavior of the strands was quite different from the one that was expected in terms of corrosion protection, effects of
fatigue, structural stiffness, and localized sectional response.
▣ In the case of bonded tendons, concrete contributed to resisting tension to an extent and even when cracked, tension
stiffening would contribute to reduced cable elongation. However, when the tendon isn’t bonded, concrete will not assist in
resisting tensile force and the stiffness would be due to the tendons alone.
▣ Similarly, if the tendons are bonded, a fracture of one of the tendons will cause a visible crack, without significantly affecting
the overall compression in stay concrete. On the contrary, if the tendons are unbonded, the progressive reduction of steel
will lead to a reduction in post-tensioning force, not necessarily causing cracks, but a global elongation & loss of compression
in stay concrete.
57
The Morandi Pre-compression
System for cable-stays
Morandi had developed and patented a pre-compression system that was specifically used in this bridge. In all cases, the
strands were coupled in groups of four and the ducts were supposed to be grouted with the usual injection of cement
mortar.
Fig. Details of the end part of a 16 ½ inch strands post-tensioning cable according to the Morandi System,
re-drawn (Units: mm)
58
The Morandi Pre-compression
System for cable-stays
▣ Comparing the above shown Morandi M5 system to the modern practice, it is striking how tight the strands were
located inside the duct. In modern practice, the void section is around 50% larger than in the Morandi case.
Moreover, the injecting material available today is far more fluid than those available in the 1960s. It could thus be
concluded that the ducts used in the case of the Morandi bridge were essentially impossible to be injected and the
same was proven based on descriptions and photos reproduced in the report of the Commission of the Ministry of
Infrastructure and Transportation. So, the behavior of the strands was quite different from the one that was
expected in terms of corrosion protection, effects of fatigue, structural stiffness, and localized sectional response.
▣ In the case of bonded tendons, concrete contributed to resisting tension to an extent and even when cracked,
tension stiffening would contribute to reduced cable elongation. However, when the tendon isn’t bonded, concrete
will not assist in resisting tensile force and the stiffness would be due to the tendons alone.
▣ Similarly, if the tendons are bonded, a fracture of one of the tendons will cause a visible crack, without significantly
affecting the overall compression in stay concrete. On the contrary, if the tendons are unbonded, the progressive
reduction of steel will lead to a reduction in post-tensioning force, not necessarily causing cracks, but a global
elongation & loss of compression in stay concrete.
59
The Collapse
▣ In the early 1990s during the inspection, it was noted that the stays of the 3 balanced system were suffering from
wide spread general deterioration and several instance of concentrated degradation. Maintenance work was carried
out on pier 11 and 10 over the years after this. Reports between 2011-2015 stated that there was a loss in post-
tensioning such that few of the strands were free to move. However, no major intervention was scheduled for pier 9
and reports stated that stays were in better condition due to limited corrosion. On 14 th August 2018, Pier 9
collapsed during a storm.
▣ The position of the debris seems to indicate that the southwest side of the stay should have been released first.
With this as the trigger, elastic analysis was performed for the structure with construction stages, but without the
time-dependent effects. From that, it was concluded that a stay removal will induce a bending moment in the plane
of the deck and torque that will be above the capacity of the structure.
▣ Judging that structure from the knowledge we have today, we can say that it had several issues like lack of
redundancy in the structure, improper time-dependent behavior consideration, and lack of insight that made
inspecting and maintaining the stays very inconvenient. No doubt though, the structure was a masterpiece for the
time that it was made in and structurally sound based on the knowledge of the time.
60
Lesson
▣ Morandi bridge was designed to carry the loads acting on it even today by quite a safe margin. However, it still
collapsed majorly owing to a lack of maintenance/intervention at the right time. No doubt, it's easier said than done
for that time. However, with such advancement in technology, real-time monitoring of any structure could be
implemented if required. Relatively priceless sensors could be installed on the structure to send data to systems that
can detect any minor deterioration with high accuracy.
▣ Being specific about the Morandi bridge, its collapse helped researchers in developing a satellite-based identification
of at-risk structures. That study showed that the Morandi bridge showed signs of warping in the months prior to its
collapse. With such systems and techniques available, early signs of collapse or deformation can be obtained.
▣ Globally, many landmark structures are quickly approaching the end of their life cycle. From 2000 itself, at least 125
bridges have collapsed. This showed that immediate action needs to be taken in the field of structural health
monitoring, especially for infrastructure projects.
61
New Haengju
Bridge Collapse
FAILURE
About the Bridge
63
Sequence
▣ The PC connected box girders were installed by the extrusion method (Incremental Launching Method). Each block
was constructed in 20m lengths in the production yards installed near the abutment of both sides, and were pushed
out while being connected one after another. It was planned to complete the section of 800m south from the
northern abutment and the section of 660m north from the southern abutment by the extrusion method.
▣ Since the span of the superstructure (the bridge girder part) was 60m, 2 temporary pillars (temporary piers) were
installed in each of the 2 rather long spans at the cable-stayed bridge section which were 100m and 120m long, and,
in the each primary spans near the production yards on both sides and in the span where the bridge girders from
both sides meet, temporary pillars were installed.
▣ One of the features of the wire of the PC cable-stayed bridge over the 3 spans was that it was not typical flexible
steel cable, and that rigid PC members were used in it.
▣ It was planned to install plain concrete at appropriate timing into the central part (20m long) of the central span
within the 3 ones under the cable-stayed bridge for the counterweight to suppress the negative cross sectional
power, which is caused owing to the length (120m) of the central span which is longer than the side ones of 100m
length. It is said that this plain concrete for the counterweight installed just before the accident acted as an
unexpected load on the temporary pillars which were placed at the center span.
64
Sequence
▣ By the day of the collapse accident, the caisson
foundations, the pallet pile foundations, the abutments,
the bridge piers, 2 main towers of the cable-stayed bridge
and the PC connected box girder part had been all
completed except for the facilities for military purposes.
The installation of the cable for the main tower of one side
was finished and the cable for the other was temporarily
put on the surface of the bridge girder. The concrete
installation work of the joint with the bridge girder was
carried out while the required tensile force (prestress) was
not supplied to the cable.
▣ Then the collapse accident occured, and the PC connected
box girder part of about 800m length which was pushed
out for the south from the northern abutment was
completely destroyed, and the main tower of one side
broke. The temporary pillars and 10 piers were damaged
heavily or destroyed.
65
Cause
▣ The collapse originated in the center span between 2 main towers of the cable-stayed bridge, and the
collapse of the temporary pillars which were set there was supposed to be the direct cause.
▣ The connection performance of the PC connected box girders which were constructed by the extrusion
method was considerably lowered (shear slip) by the installation work of the cable and the plain concrete.
Therefore, the vertical load that acted on the temporary pillars increased considerably. As the result, the
load supporting capability of the temporary pillars was markedly weakened, and the unexpected force and
deformation acted on the PC connected box girders near the main towers and the cable, and it led to the
collapse of the main towers and the bridge girder. Since the whole PC box girder section of 800m length
was a connected digit structure, it is supposed that the big change of the load action condition by a collapse
of one place triggered the collapse of one after another place where the cross sectional power surpassed
the yield capability of the member.
▣ There might have been a failure in design and construction concerning the load supporting performance of
the temporary pillars. However, since the construction was carried out without any prior examination about
the effect of the load which arises during erection on the temporary pillars, the cable, superstructure, and
substructure, it is evident that an excessive load acted and destroyed the members.
66
Cause
67
Response
▣ The destroyed part of the bridge was removed and newly constructed.
▣ The whole part of the PC connected box girders of 102m length, 1 damaged main tower, and 12 piers were
removed. In the demolition, breakers (large rock drill), the dropping steel sphere strike method, nonvibratile
high temperature and the pressure jet method, and wires-saw method, etc. were applied. The removal of the
main tower was determined by horizontal load safety test.
▣ The remedial work was carried out by the joint enterprise of DS Co. from Germany in the substructure and DRS
Co. from USA in the superstructure under thorough design checking and construction management, and New
Haengju Bridge opened on May 19th, 1995.
68
Counter Measures
As a result of the technological study during the remedial construction, many design changes were carried out.
▣ The cable of PC member whose rigidity was big was changed into flexible steel one in order to improve the workability
and reduce the dead load.
▣ They reduced the load on the main towers by changing the cable-stayed bridge part (300m) to steel and concrete
synthetic girder from PC connected box girder, and the length constructed by the continuous extrusion method was
changed to 420m.
▣ The foundations of the removed 12 piers were changed to the circular concrete piles and their number and length was
increased. The piers were strengthened by adding partitions to inside the hollow sections. Two of the three temporary
pillars of the cable-stayed bridge part were changed to permanent structures, and the other was changed to steel from
concrete.
69
Counter Measures
The construction bureau of Korean government carried out safety checks on public works and public facilities, and special
inspections on bridges of the national roads. The necessity of instituting law, regulation and technical standards on the
construction management technology was shared in order to strengthen responsibility and authority of the design and
construction company, and in order to improve the construction supervision system. A prior qualification check system
(P.Q.) for judging the construction ability of the builders was introduced. Remedies such as prior announcement of
schedule price and basic research expenses, a multiple schedule price system, installation and extension of tender and a
contract monitoring committee were introduced and the penal regulation on prior leakage of tender information was
strengthened in order to prevent foul play in the tendering and contract of public works.
70
Lesson
71
STORY BOARD
Pylon
'A' frame pylon with twin planes of cable stays with one to each side of the bridge deck. For the required span it is only required at
one end of the span.
Severinsbrücke bridge
Faro bridge
Rib-to-Deck Joint
Anchorage points welded on to the main bridge deck Anchorage bolts for the cables Cables
Link pin and cable anchorage Bearing and jacking point Bearing and jacking point
Hunslet Moor Footbridge
Thanks!
79