You are on page 1of 2

This Summary for construction Cost for NRC

Amount
Sl. No. Particular's of work
(Rs. in lacs)
1 Length (M) 16.96
Width (M) 12.39
Plinth Area of building (SQM) 210.13
2 Building works 3902114.10
a Add 10 % for Internal water Supply 390211.41

b Add 3.75 % for external electric connection 146329.28

c Add 12.5 % for Internal Electrification 487764.26

d Add 1.25 % for civil external service connection 48776.43

e Add 4 % for Power plug and wiring 156084.56

f Add 0.5% for Central callbell system 39021.14


g Add 0.25% for Lightining conductor 9755.29

h ADD 0.25 % for telephone conduit system 9755.29

i ADD 1 % for third party quality assurance 39021.14

Levelling with avg 0.3 m cutting& filiing with 5 to 8


j 14709.10
kmcarted earth on plot area as and where required.

k Septic tank for 50 user capacity 170000.00

3 Total Construction cost 5413542.00


a Add 1 % contingency 54135.42
b Total(1+2) 5467677.42
c Add 12 % GST 656121.29
d Add 1 % Labour cess 54676.77
e Add 0.5% of construction cost for soil test 27067.71
Add 1.5% of construction cost structural drawing,
f design, working drawings for layout, electrical and 81203.13
plumbing fittings.

g ADD 18 % GST on 5 and 6 19488.75


Total(b+c+d+e+f+g) 6306235.07
Says 63.06 Lacs

)Sukhdev prasad( )Udai Narayan(


Junior Engineer )Amit Singh( Executive Engineer
C.D.-P.W.D., Sonebhadra Assistant Engineer C.D. P.W.D. Sonbhadra
C.D.-P.W.D. Sonbhadra