This document provides a cost estimate for road construction project totaling 9.608 km. It lists 21 line items of civil works with their unit rates and quantities. The total estimated cost is Rs. 503.1 crores or Rs. 52.363 crores per km. The cost estimate includes the base civil works, GST, additional centages for contingencies, supervision, and maintenance, and preconstruction costs for utility shifting and land acquisition.
This document provides a cost estimate for road construction project totaling 9.608 km. It lists 21 line items of civil works with their unit rates and quantities. The total estimated cost is Rs. 503.1 crores or Rs. 52.363 crores per km. The cost estimate includes the base civil works, GST, additional centages for contingencies, supervision, and maintenance, and preconstruction costs for utility shifting and land acquisition.
This document provides a cost estimate for road construction project totaling 9.608 km. It lists 21 line items of civil works with their unit rates and quantities. The total estimated cost is Rs. 503.1 crores or Rs. 52.363 crores per km. The cost estimate includes the base civil works, GST, additional centages for contingencies, supervision, and maintenance, and preconstruction costs for utility shifting and land acquisition.
Bill Cost Item of works and Sub-Heads Unit Quantity No (Rs. lakhs) 1 SITE CLEARANCE AND DISMANTLING Km 9.608 23.33 L 2 EARTH WORK Km 9.608 7518.99 L 3 SLOPE PROTECTION WORK Km 9.608 138.88 L 4 SOIL STABILIZATION WORK Km 9.608 619.24 L 5 BASE & SUB-BASE COURSES (340 mm) Km 9.608 5448.84 L 6 BITUMINOUS COURSES (130 mm) Km 9.608 3611.36 L 7 CULVERTS (34 Nos.) Nos. 34 4637.61 L 8 DRAINAGE & MEDIAN SEPARATOR WORKS a) RCC Covered Drain Mtr. 527 90.76 L b) CC Kerb channel and Chute Drain Mtr. 2588 50.24 L c) CC open Drain at toe connecting chute Mtr. 2588 61.57 L drain d) Median Mtr. 9170 259.57 L TRAFFIC SIGNS, MARKINGS AND OTHER 9 Km 9.608 486.51 L ROAD APPURTENANCES MAJOR BRIDGE ( 3 Nos, 4x40m,4x40m and 10 Mtr. 380 7241.51 L 2x30 m 11 TRUCK LAYBY Nos. 1 72.22 L 12 MAJOR JUNCTION ROAD Nos. 2 324.47 L 13 MINOR JUNCTION ROAD Nos. 18 996.28 L 14 FOOTPATH Mtr. 3510 416.4 L 15 PROTECTION WORK (STONE PITCHING) RM 2370 746.84 L 16 TOE WALL RM 6651 1683.23 L 17 RETAINING WALL RM 1360 1800.43 L 18 SLIP ROAD RM 1145 175.341 L 19 V.U.P. Nos. 1 169.72 L 20 S.V.U.P. Nos. 3 390.88 L TREE TRANSPLANTATION, CUTING & 21 Nos. PLANTATION Cutting of Trees Nos. 397 3.2 L Compensatory Plantation of Trees Nos. 3970 69.99 L Transplantation of Trees Nos. 99 5.32 L A. TOTAL OF CIVIL WORKS (A)= 37042.73 L Add GST @18% of (A) 6667.69 L Construction cost+GST 43710.42 L Bill Cost Item of works and Sub-Heads Unit Quantity No (Rs. lakhs) B. Total Civil cost+GST 43710.42 L C. ADDITIONAL CENTAGES : a Contingency Charges@ 1.0% of (A) 370.43 L b Agency Charges@ 3% of (A) 1111.28 L c Supervision Charges@ 3% of (A) 1111.28 L d Excalation Charges@ 5% for 2.0 years of (A) 1852.14 L e Maintenance Charges @ 2.5% on (B) 1092.76 L TOTAL COST OF CENTAGES (C)= (a+b+c+d+e) 5537.89 L D. Total Cost including, GST and Centages (B+C) 49248.31 L E. Preconstruction Cost Electric utility shifting (APDCL) 69.22 L Electric utility shifting (AEGCL) 621.783 L Other utility shifting (Irrigation and PHE) 65.26 L Additional LA for Asharikandi 305.705 L Total Cost of Preconstruction Cost (E) = 1061.968 L Total Project Cost ( D + E ) = 50310.28 L SAY IN CRORES 503.1 Cr. COST PER KM OF PROJECT (in Rs. Crores) : 52.363 Cr.