The Method Statement covers a majority of the day-to-day details of carrying out work for the above project.
However, if the site conditions change then the type of work and materials to be used should be reviewed. If the
site-specific risks are different to those included in this Statement, a supplement to the Method Statement should
be added.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 1/471
CHANGE CONTROL
All changes to this document must be listed and recorded in the following table. Authority for amendment or
alteration of this document is to be obtained from the Project/Site Manager/Contracts Manager.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 2/471
METHOD STATEMENT
This Method Statement provides information assuming Credibuild Ltd is conducting works at 188 Shoreditch High
Street, London, E1 6HU, 188 Shoreditch High Street, London, London, E1 6HU
Change of use of land to rear of 188 Shoreditch High Street from residential (2 x studio) to office (B1); erection of
two storey extension and
deck to rear of existing extension in order to provide 83sqm office (B1) space; reconfiguration of retail unit in order
to provide additional 8sqm A1
space; reconfiguration of front residential unit to provide an additional bedroom; refurbishment of existing building
including facade repairs and
reconfiguration of internal floorplan at basement, ground and first floorlevel. Refurbishment of existing Grade II
listed frontage building, removal of
non-original rear infill to create light and stairwell and extension of existing 2-storey rear building with change of use
of rear building from C3
dwelling to B1 office. New Roof's throughout, re-wire of listed building and decorations.
PLEASE NOTE: OUR PROPOSED WORKS WILL NOT AFFECT THE VIADUCT OR IMPACT ON THE
RAILWAY
Demolition
Slab/ Concrete
Structural works
Brickwork
Internal Fitout
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 3/471
3.0 SUPERVISION, CONTROLS AND MONITORING
All employees and self-employed labour will comply with the requirements of the Health and Safety at Work etc. Act
1974 and all other relevant Health and Safety Regulations, our own Safety Policy, Risk Assessments and Method
Statement, together with any specific site rules and requirements from the Safety Policy and Construction Phase
Plan.
All work by Sub-Contractors will be directly controlled by the Foreman, who will ensure that the safe means of
working is complied with, as given in the Method Statement. The Supervisor is expected to liaise with the clients'
Site Manager for any overlapping issues with the client or other Sub- Contractors.
All work will be undertaken to comply with the specific requirements of the following legislation, approved codes of
practice and / or guidance:
All operatives will be required to comply with the requirements of any site induction training given by the client.
Only trained operators will use cartridge-operated tools, if required, they will also be responsible for safe storage of
equipment and cartridges.
Power tools will be checked at regular intervals and a visual inspection will be carried out before use. All power
tools will operative on a voltage of 110 volts or lower.
Only trained operatives will be allowed to erect and inspect any temporary work Towers.
5.0 OCCUPATIONAL HEALTH ASSESSMENTS
RISK ASSESSMENTS for work associated with Credibuild Ltd are included in Appendix 2 of this Method
Statement.
COSHH ASSESSMENTS for materials that are to be used on this contract are included in Appendix 3.
MANUAL HANDLING where possible, all loads in excess of 25kg will be handled by mechanical means.
WELFARE will ensure all welfare facilities will be used as provided by the client.
All employees and Sub-Contractors will be made aware during site induction of any risks their work can impose on
others in the vicinity. Work will only be undertaken in such a way as to minimise these risks or when adequate
protection is in place.
Every effort will be made to keep noise, dust and waste levels to a minimum and to ensure that they do not cause a
hazard or become a nuisance to others. Working areas will be tidied regularly and waste removed to skips.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 4/471
8.0 PERSONAL PROTECTIVE EQUIPMENT (PPE), FIRST AID & EMERGENCY PROCEDURES
PPE. All employees and Sub-Contractors will wear protective footwear, high visibility jackets and safety
helmets when there is a risk of head injury. Where it is not possible to wear a helmet then bump caps will be
used instead. Other PPE such as gloves, eye protection, hearing protection, respiratory protection and
protective clothing will be provided and be used as required.
All operatives will be made aware of First Aid and emergency procedures on their first arrival on site at the
Site Induction. The client will provide this information.
Should any work be of a non-standard nature either in regard to the materials to be used or the type of activity to
be carried out then an Appendix to this Method Statement will be added. This will include necessary Risk and/or
COSHH Assessments and changes to the Method Statement to ensure that the work is safely carried out in
accordance with the Construction Phase Plan and any site rules.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 5/471
11.0 MATERIALS USED
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 6/471
Visqueen Vapour Checktrade name:Visqueen Vapour BarrierVisqueen High Performance Vapour
BarrierVisqu
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 7/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Controlled Access
Site signage will be erected on the outside of the existing shop front with site contact numbers for site manager
There will be a signing in and out register so all operatives will be known to site and any one time
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 8/471
Don not leave chemicals out, these should be stored in the cupboards provided or container. Only use the correct
product for the task.
PPE
Hard hat, vest, safety footwear and gloves as standard. All other PPE to be task specific as a when required.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 9/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Task Description
This method statement describes the work process for the erection of Aluminium tower scaffolding including:
1) Site establishment.
3) Preparation.
5) Inspection.
Start of works
1) Report to site office and inform site manager of arrival, collect permit to work.
5) Cordon off work area if required to do so, this is especially important in areas where members of the
public or other contractors have access.
6) Ensure the area to be worked and exit points are clear of obstruction and that safe access and egress is
maintained.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 10/471
7) Do not leave tools and equipment unattended at any time.
2) Ensure you have the appropriate instruction manual for the type of scaffold used
3) Ensure that all towers have edge protection around the working platform that extends a minimum 950mm
and has intermediate rails so that the unprotected gap does not exceed 470mm.
5) All tower scaffold will be erected in accordance with the HSE information sheet Tower Scaffolds what
you need to do and the manufacturers instructions.
6) Ensure you are working to a method Recommended by the Prefabricated Access Suppliers' and
Manufacturers' Association (PASMA) as detailed below.
4) Clip horizontal bracing frame to bottom of one frame and rest on the floor.
8) Fit outrigger legs to each corner and secure with the pad firmly on the floor, this will ensure stability whilst
erecting the rest of the tower.
11) Fit the temporary guard rails to the level above ensuring that no one enters an unguarded platform.
12) Once the guard rails are in place ascend to the platform and fit the permanent bracings and next level
platform.
4) Clip horizontal bracing frame to bottom of one frame and rest on the floor.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 11/471
5) Clip horizontal brace to other base frame to set width.
8) Fit outrigger legs to each corner and secure with the pad firmly on the floor, this will ensure stability whilst
erecting the rest of the tower.
9) Fit the first level platform complete with trapdoor from below.
11) Working through the trap door fit the required guard rails and bracings to the next level.
1) To dismantle a tower using the advance guard rail method, the operator starts from the top and
reinstates the advance guard rail unit before removing the permanent guard rails and toe boards and descending to
the lower level.
2) The advance guard rail units are then relocated to the level below and the process is repeated, with
collective fall prevention measures being maintained throughout.
1) To dismantle a tower using the 3T method, after removing the toe boards, the operator disengages the
guard rail hooks furthest from the trap.
2) Guard rail components are then removed with the operator positioned through the trap before
descending to the lower level, from where the upper platform and end frames are removed.
The requirement for inspection is different for small towers under 2m, and for towers of 2m and above.
A pre-use check should be made if any part of the tower has to be removed to enable the tower to be moved past
an obstruction.
The inspection report should be completed by the competent person before the end of the working period and a
copy should be provided to the person it was carried out for within 24 hours.
The report should be kept at the site where the inspection took place until the work is completed. Thereafter it
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 12/471
should be stored for 3 months.
Where this equipment is being hired the hirer must ask to see the last report and see a certificate confirming the
integrity of the equipment. The hirer must be competent in erecting such equipment, if not they must either receive
the training to do so, or have the tower erected by someone who does have the necessary competence.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 13/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Task Description
This method statement describes the work process for the refurbishment of bathrooms including:
1) Protection
2) Stripping out
1) It is the responsibility of the principal contractor to advise tenants of works to be carried out, Credibuild Ltd staff
will liaise with the principal contractor and tenants on a daily basis to ensure safe operation.
2 )All areas of floor and furniture will be protected with adequate dust sheets and/or plastic sheeting.
Stripping Out
2) Be aware that asbestos could be present in properties build before 2000, take all necessary precautions.
3) Inform tenant and other occupants of work commencing and cordon off work area if practical to do so. Particular
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 14/471
attention should be paid to property where children are present; children and adults must be kept away from the
work area at all times and protected from dangers of power tools and substances.
4) Ensure the area to be dismantled and exit points are clear of obstruction and that safe access and egress is
maintained.
7) Test any electrical circuit before commencing work and ensure it is dead.
8) Check any electrical or hand tools for damage or faults, faulty or damaged tools must be removed from service
immediately.
9) Carefully remove existing bathroom sanitary ware and ancillary equipment and remove to designated waste
area. Large and/or heavy items will be tandem lifted; do not lift beyond your capabilities.
11) Remove existing floor covering, tiled floors will be broken up by hammer chisel
15) Ensure cooking and washing facilities are operational at end of each shift
Making Good
Adjust and reposition water supply pipes and waste pipes to accept new sanitary ware Credibuild Ltd staff will
ensure sufficient ventilation for working with solder and flux.
Carry out any necessary work to ensure plumbing falls in line with current water and building regulations.
A fire extinguisher to be close at hand during all hot work and inspection to all soldered areas to take place at end
of shift.
Make good the walls by re-plaster and skim in preparation for decoration.
Plaster mixing is to be carried out in a suitably ventilated area, refer to COSHH assessment sheets for safe use
information
Damaged floors may require concrete skim to make good, please refer to the cement safety fact sheet before using
cement based products.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 15/471
Decorating & Flooring
2) When working from stepladders the company working at height procedure must be followed.
3) Tiling will be carried out by qualified tillers using proprietary tile adhesive and grout, see COSHH assessment
sheets for safety information
4) Lay vinyl flooring onto prepared floor as per contract requirements; refer to COSHH Sheet for safe use of flooring
glue.
1) Ensure all plugs, handles taps and other ancillaries are correctly fitted to sanitary ware.
2) Test for correct operation including flushing of toilet and emptying of water through plugs and overflows.
3) Visually inspect pipe work and joints for leaks and damage.
1) The property will be cleaned prior to handover; cleaners will follow all safety procedures described in this
document.
2) NICEIC Gas Safe tests will be carried out on all installations prior to handover, the contract manager is
responsible for delivering the certificates to the principal contractor, a copy to be held on file at Credibuild Ltd
4) Handover to client
Care of equipment
1.All items must be thoroughly cleaned in either water or the relevant solvent at the end of each shift
2.Items such as brushes and rollers should be air dried and stored
3. Wash buckets, wipe inside and out and store upside down
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 16/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
First Aid
It is the responsibility of the company to ensure adequate First Aid provision for its staff. Adequate means provision
of a trained first aider, suitable first aid equipment and/or the provision of an appointed person at the minimum.
A trained First Aider will be a suitable person who has attended an HSE approved course of at least three days
duration. An Appointed Person is a person provided by the employer to take charge of the situation (e.g. to call an
ambulance) if a serious injury/illness occurs in the absence of a First Aider. The Appointed Person can render
emergency First Aid if trained to do so. All staff when inducted will be made aware of the location of the First Aid kit.
Manual Handling
All staff and contractors have been instructed on the potential dangers of manual handling, and have received
manual handling training. Equipment provided to reduce manual handling must be used where provided. Staff and
contractors will not lift items of tools or equipment that are beyond their capabilities. Heavy or awkward items will be
split into smaller
units where possible or dual lifted where this is not possible. It is the responsibility of the site foreman/employer to
identify and control manual handling activities as they occur on site on a day to day basis.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 17/471
Material Handling
All materials required for site will be unloaded to a designated unloading and storage area which will be away from
the work area as far as is practicable. This area will be kept tidy to minimise trip hazards. Materials as and when
required will be collected from the storage area and transfered to the work area. All staff will take care when
handling materials and will use mechanical aids wherever possible. When stacking materials particular care must
be taken to ensure that the stack is secure and that the product does not get damaged.
PPE will be provided as a last form of protection against a hazard. Staff will use the appropriate PPE for the task as
identified in the risk assessment.
All site workers will wear Safety boots, Hi Visibility Vests, Hard Hats and protective clothing at all times, other items
of PPE such as eye protection, hearing protection and gloves are available to be worn as and when necessary and
as determined by the risk assessment.
A risk assessment will be carried out for all tasks which will be discussed with members of staff and the sub
contractors, any queries or concerns will be raised with the contract manager who will ensure it is dealt with. Staff
and sub contractors will be inducted onto site in order to understand the hazards present on site and the tasks that
are to take place. Staff will also be advised of other site activities that could impact on their work and be made
aware of any liaison that needs to take place between different trades. Staff will follow all site rules and safety
procedures.
The task will be carried out by qualified, experienced, staff receive ongoing training, and hold suitable
qualifications. Apprentices are under constant supervision by experienced members of staff.
Any sub contractors appointed by us have been assessed for their ability and suitability to carry out the tasks
allocated to them.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 18/471
Welfare
The principle contractor is responsible for providing adequate washing, toilet, drying and refreshment facilities for
staff and sub-contractors, staff and contractors are responsible for ensuring that such welfare facilities are
maintained in a clean and wholesome manner (it may be necessary occasionally for us to identify suitable local
amenities).
The site foreman will ensure that Aluminium Tower Scaffolds are erected correctly in accordance with
recommendations provided by PASMA by a competent person. Aluminium tower scaffolds must be used on flat
level ground and the stabiliser riggers must be fully deployed and secured prior to working from the tower. Any
adverse weather conditions must be taken into account and it will be the responsibility of the site foreman or senior
person to evaluate the situation prior to work starting and throughout the task.
If the tower is less than 2 mtr in height it will be inspected on erection, after any event that might affect it's stability
and at suitable intervals dependant on frequency and condition of use.
Where the tower is above 2 mtrs in height it will be inspected after assembly in any position, after any event liable
to have affected its stability; and at intervals not exceeding seven days.
Where towers are to be used in public places: - erect barriers at ground level to prevent people from walking into
the tower or work area, minimise the storage of materials and equipment on the working platform, remove or board
over access ladders to prevent unauthorised access if it is to remain in position unattended.
Brickwork
Bricklaying the bonding together of bricks with wet mortar to form a wall.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 19/471
Expansion joint cladding from a Scissor Lift
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 20/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Pointing
7. Clean brickwork using soft brush and wet using brush or spray
9. Apply mortar mix with trowel ensuring it is worked in to the full depth
12. Move platform to new work area and restart process as required
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 21/471
Cleaning Brick Using Pressure Washer
7. Access the working area via ladder and pull equipment up with rope
8. Working in small areas approx 3-4m2, apply the solution to the stone/brick wall
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 22/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
2. Remove all paint spots and plaster spill from surfaces using a hand scraper Remove all scuff marks from
walls/paintwork.
3. Wipe down all walls to remove dust using a feather duster working from top to bottom (take extra care when
working from step ladders).
4. Sweep all floors (other than carpeted areas) ensuring that all dust is kept at ground level and regularly cleared
away.
5. Sweep the landings and stairs from top to bottom, paying particular attention to edges and corners.
6. Pick up spoil and place into refuse sack and remove to the disposal point.
8. Vacuum all floor areas taking extra care on stairs, paying particular attention to corners.
10. Ensure all light fittings are dusted down and cleaned (take extra care when working from step ladders).
11. Wipe down, dry and polish all skirting boards, ledges and surfaces.
12. Thoroughly clean all fixture and fittings, removing all paint spots.
13. Wipe down, dry and polish all wardrobes and cupboards, inside and outside.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 23/471
Damp Wiping
2. Using a damp cloth, wrung almost dry, wipe the surface from top to bottom using smooth fluent strokes.
3. Rinse the cloth regularly in clean water and recharge the cleaning solution as required.
4. Mop floor areas using cleaning solution in a bucket as per manufacturer's instructions.
5. Apply the solution to the floor using figure of eight strokes with each pass overlapping.
8. When wringing out the mop stand in front of the wringer and press down firmly.
10. Wipe skirting board by hand with a colour coded cloth to remove splashes.
12. Use the minimum amount of liquid (especially on open stairways) and leave the floor as dry as possible and
place warning signs until the area is dry.
2. Remove all paint spots,(within reason), from metal fixtures and windows.
3. Wipe down all doors, window sills and skirting boards to remove dust using a feather duster working from top to
bottom.
4. Polish all doors, window sills and skirting boards. Apply polish sparingly, taking care not to apply polish to
adjacent surfaces. When using aerosol polish, apply to the duster to prevent overspray onto floor areas to prevent
creating slippery conditions.
6. Clean the inside of the windows using a well wrung out leather or scrim, start at the sides and top of the frame
followed by a zigzag pattern over all the window.
7. Wipe the sides and top of the frame using the leather.
8. Wipe the blade of the squeegee with an absorbent cloth after each pass.
9. Finish with a straight vertical stroke down each edge of the pane.
10. Clean small window panes by applying cleaning solution with an applicator to the top row of panes.
11. Squeegee across the upper part of the windows working down to the bottom of the glass. Make a second pass
with the squeegee to remove the remaining solution.
12. Wipe down using Diamond cleaning solution, to make windows smear free.
Prior to leaving the property, remove all cleaning materials and equipment and carry out an inspection to ensure
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 24/471
that the work has been carried out satisfactorily.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 25/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Task Description
This method statement describes the work process for the use of a cement mixer
1) Site establishment.
3) Preparation.
Start of works
1) Report to site office and inform site manager of arrival, collect permit to work.
5) Cordon off work area if required to do so, this is especially important in areas where members of the
public or other contractors have access.
6) Ensure the area to be worked and exit points are clear of obstruction and that safe access and egress is
maintained.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 26/471
7) Do not leave tools and equipment unattended at any time.
Operation of mixer
1) Put on your personal protective equipment gloves, eye protection, RPE, ensure no loose clothing or
jewellery is worn
2) Ensure you have the appropriate instruction manual for the type of mixer in use
3) Prepare mixer for operation as per manufacturer's instructions. Ensure if 110V there are no trailing leads
posing trip hazards.
5) Switch on machine and ensure correct running, switch of machine to confirm operation of off switch
(other checks may be required dependent on of manufacturer).
6) Switch on machine and fill as per manufacturer instruction. Ensure no loose clothing of jewellery is worn.
7) Ensure that PPE is worn as per COSHH assessment at all times, those entering works area are to wear
ear protection.
Shut down.
3) Machine may require time to cool prior to moving due to hot working parts.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 27/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
5. Check the supply is dead by electrical test meter before connecting to supply
6. Ensure system is locked off and keys to padlock are kept with engineer
10. Before re-energizing the system all non live testing will be carried out
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 28/471
13. Tidy work area and remove all debris to designated waste area
3. Liaise with the principle contractor and other contractors to ensure safe operation
5. Cordon off work area if practical to do so, otherwise deploy banksman to keep work area clear of staff and other
contractors
6. Ensure the area to be worked and exit points are clear of obstruction and that safe access and egress is
maintained
7. Erect tower scaffold in area of work, ensure riggers are deployed and scaffold is stable before climbing, Internal
steps only to be used
8. Attach condensing/evaporator unit fixing brackets in final fixing position either by drilling wall or fixing clamps to
roof trusses with threaded rod
11. Set up lifting pulleys/chain blocks in strong point in the roof above centreline of final fixing position
12. Sling condensing/evaporator unit safely, ensuring balance at the centre of gravity and that the unit can not slip
14. Hold unit in place with lifting tackle whist bolting to fixing brackets
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 29/471
1. Liaise with other contractors and facilities manager to isolate water supplies where necessary
4. Obtain the appropriate hot work permit from the facilities manager
5. Ensure the correct type of fire extinguisher is on hand during hot work
12. Chlorinate the system if required and check for successful completion
13. Maintain fire watch for 2 to 4 hours where hot work has been carried out
1. NICEIC tests will be carried out on all installations prior to handover, the contract manager is responsible for
delivering the certificates to the principle contractor, a copy to be held on file.
5. Handover to client
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 30/471
1. Liaise with other contractors and facilities manager to isolate water supplies
5. Ensure waste pipes and other plastic pipe work are connected correctly
6. Where plastic pipe is connected with solvents, staff will follow all safe use instructions
7. Where solder work has to be carried out, prepare pipe work for solder joints
8. Obtain the appropriate hot work permit from the facilities manager
9. Ensure the correct type of fire extinguisher is on hand during hot work
15. Carry out further checks for water tightness and quality of finish
16. Chlorinate the system if required and check for successful completion
19. Pack tools an equipment and leave area clean and tidy
20. Maintain fire watch for 2 to 4 hours where hot work has been carried out
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 31/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Don not leave chemicals out, these should be stored in the cupboards provided or container. Only use the correct
product for the task.
Area to be left clear of rubbish and a clear access / egress route maintained at all times. Damp down areas
requiring sweeping.
Use class M hoover where possible. Ensure good manual handling techniques. Waste will not be stockpiled in
locations.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 32/471
Heras Fence Erection
1. Position fencing bases along the proposed fence line using a spacing gauge (a piece of timber cut to suit will
suffice)
2. The panels are supported by inserting the side posts into the holes cast in the center of the base. Each base is
cast with at least 4 post support positions for flexibility of use and hand hold positions in each end of the base.
5. With the entire panel in position, security clamps should then be placed approximately 650mm from the top of
the panel, across the adjoining side posts- a 20mm box type spanner is required to secure the clamp with the
central nut and bolt.
The fencing will ensure our compound is secured and is denoted on site-up plan. Panels will be erected whilst there
are no children about by team lift and cones and tape used as necessary. Site signage & gates will be team lifted
also and denote "contractors at work"
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 33/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
ii) The site will be surveyed to ascertain any safety or operational implications to turning off the power to the
existing installation.
iii) All operatives to be made aware of general First Aid arrangements, which will be provided by the Main
Contractor.
iv) Specific emergency arrangements in the event of a serious accident will be the responsibility of the Site
Supervisor or nominated person.
v) Method Statement / Risk Assessment checklist to be read and signed by the Site Supervisor/operative at
site, showing they fully understand the content.
Check equipment is suitable for the job. Ladders and steps to be erected on solid ground, the work area to be kept
clean and tidy and free from debris. Supervisor to brief operatives on correct system of work, talks to take place
periodically to remind operatives the need to work safely at height.
ii) Standard PPE equipment, hard hats, safety footwear, gloves, high visibility vests to be worn. Eye protection
must be worn at all times.
iv) Site Supervisor to advise other Contractors at site that works are to take place, in order that they can inform
any non-English speaking operatives they employ to be made aware of the works being carried out and what steps
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 34/471
they need to take to avoid any accidents/incidents
sequence of works
i) At a pre-arranged time the power to the distribution board will be isolated at the main switch or isolator.
ii) If possible the isolator will be locked off and warning signs will be put in place.
iii) The front cover will be removed from the distribution board and the busbars verified as �dead.
iv) If the distribution board contains MCBs, these will all be turned off.
v) If the distribution board contains fuses, all fuse carriers will be removed.
vi) New supply cabling serving site temporary supplies will be terminated into distribution board.
vii) New RCBO protective devices will be installed within available spare ways of distribution board.
xi) If the distribution board contained circuits that are to be retained the relevant MCB/fuse carriers will be
turned on/replaced.
xii) Distribution board will be turned on and any retained circuits will be checked for correct operation.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 35/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Blockwork
The area of excavations will first be checked for live services using cat scanners and plans where possible. Any
existing services will be protected or moved as required. The holes are hand dug by two men using pick and
shovel; the excavations will be 1.2metres wide maximum by the appropriate depth for each property. To prevent
the potential for subsidence or collapse a distance of approx 1.2 metres is left in situ and another section of 1.2
metres dug out, the intermediate sections are not dug out until the concrete in the original excavations has been
set for 48 hours.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 36/471
Flat Roofing
2. Tenants have been warned and barriers erected to prevent unauthorised access
6. Unclip and remove existing guttering and fall pipe and take to waste area
8. Clean down and inspect the decking under the felt for soundness and signs of damage
15. Remove all waste and Inspect the site, ensure the site is left in a clean and tidy condition
Foundations (Excavation)
1.
4. The trench will be backfilled with 40mm type 1 road stone in 150mm layers to within 100mm of surface
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 37/471
5. 20mm binder course 60mm layer
6. 10/45 surface course 40mm layerThe area of excavations will first be checked for live services using cat
scanners and plans where possible
5. Excavate the ground by hand/Mini Excavator or JCB (Follow safe operating procedures)
6. Any spoil produced by the process will be removed via wheelbarrow onto flatbed tipper trucks
7. Shuttering will be fixed to the front face of the excavations and braced with batons to prevent collapse
8. Additional Hydraulic ram braces may be required if excavation exceeds 1metre in depth
9. No persons shall enter an excavation deeper than 1 metre, without appropriate trench support being installed
11. The concrete will be delivered premixed from a recognised supplier via cement mixer or boom truck, and
poured against the face of the excavation
12. The concrete must be a minimum strength of 30 N/m2, once poured the concrete will be levelled with the use of
a vibrating poker; the site foreman is responsible for ensuring the correct distribution of the concrete into the
shuttering and that the 20mm reinforcing rod is kept in position
13. Sample cubes for concrete strength testing will be taken by as a minimum from every other concrete delivery.
3x 100mm square blocks will be cast per test and stored under test conditions. The cubes will be tested as per the
works specification and to BSEN 12390 part 1, 2, and 3. The results will be recorded and cross referenced to the
properties for which the concrete was used, and full details passed to Clients at the conclusion of works. Any test
failures will be reported to Clients immediately
4. The trench will be backfilled with 40mm type 1 road stone in 150mm layers to within 100mm of surface
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 38/471
Mixing cement for brick work.
PPE
Hard hat, vest, safety footwear and gloves as standard. All other PPE to be task specific as a when required.
Screed (new)
1. Screed to be pumped into required area(s) by aid of a screed pump and wheeled to local area if required
2. Drive Timber Plugs into the vertical brick/blockwork 150mm from bottom and top and central in between
3. Fit door casing/window frame and level and plumb frames to suit
4. Fix to timber plugs or drill and fix through brick/blockwork with propriety brick fixings where no timber plugs exist
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 39/471
5. Lift units into position pack and fix accordingly
6/ Have rescue procedure in place and ensure all employees are aware of emergency procedures.
71 Emergency contact d
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 40/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
The brick or concrete cutting or drilling works will be carried out in a phased process, this will be undertaken in
conjunction with the Principal Contractors and Company Works Program.
Manual handling, lifting / moving procedures will be undertaken by trained staff. All equipment used for cutting and
drilling will be offloaded as single units weighing 20kg per unit.
During cutting and drilling operations that require into building structures ( brick or concrete ) disposable FFP3 dust
mask to be worn at all times.
Works will be carried out on a wall by wall, ceiling by ceiling, riser by riser etc: basis within rooms, corridors and
service areas until all are complete.
Work areas will remain clear of clutter during all installation operations and restrictions / barriers will be put in place
to prevent unauthorised entry to works areas by non- company staff, but will ensure that passage along / across
the area is maintained for access and egress.
Any restrictions or specific site rules will be applied throughout the installation and Company staff will be notified of
those restrictions / site rules at induction. They will further read and obtain information if necessary of daily site risk
notifications (access and read site notice board) or by communication with site management staff.
The works will be carried out in a phased program in accordance with Principal Contractors and Company Program
of Works. Where the works undertakings are at variance to the Principal Contractor Program of Works, these will
be discussed and agreed with the Principal Contractor prior to works being carried out.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 41/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
The plaster board cutting or drilling works will be carried out in a phased process, this will be undertaken in
conjunction with the Principal Contractors and Company Works Program.
Manual handling, lifting / moving procedures will be undertaken by trained staff. All equipment used for cutting and
drilling will be offloaded as single units weighing 20kg per unit.
During cutting and drilling operations that require into building structures (plaster boards) disposable FFP3 dust
mask to be worn at all times.
Works will be carried out on a wall by wall, ceiling by ceiling, riser by riser etc: basis within rooms, corridors and
service areas until all are complete.
Work areas will remain clear of clutter during all installation operations and restrictions / barriers will be put in place
to prevent unauthorised entry to works areas by non- company staff, but will ensure that passage along / across
the area is maintained for access and egress.
Any restrictions or specific site rules will be applied throughout the installation and Company staff will be notified of
those restrictions / site rules at induction. They will further read and obtain information if necessary of daily site risk
notifications (access and read site notice board) or by communication with site management staff.
The works will be carried out in a phased program in accordance with Principal Contractors and Company Program
of Works. Where the works undertakings are at variance to the Principal Contractor Program of Works, these will
be discussed and agreed with the Principal Contractor prior to works being carried out.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 42/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
The works include all finishes associated with the detailed specification provided by
4. SCOPE OF WORKS
The cutting or drilling of brick or concrete walls and ceiling within the building to Provide for the carrying, holding
or fixing of installed electrical cables or components for building accommodations.
Working progressively through each detailed area, walls, ceilings, and service areas
The brick or concrete cutting and drilling will provide for final finishes for carrying electrical wiring and components
installed to building interior walls, ceilings, risers and plant room or service spaces of the building.
The works will conform to the requirements detailed in the works specification issued the Principal Contractor for
the project.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 43/471
5. PERMITS TO WORK
Cannock Building Services Ltd will ensure that when working on site all Permits to Work and authorizations to work,
where relevant and defined by the Principal Contractor site rules, are obtained, and any specific requirements or
restrictions complied with.
All Permits to Work or authorizations to work shall be obtained from the Site Project Office, this shall be from a Site
Manager or his representative.
All works will be assessed for Permit to Work needs and this will be undertaken by Company Site Manager and /or
Company Health and Safety Advisor.
6. MANUAL HANDLING
All loads of works materials will be broken down into single units and carried to works location by manual handling
means. All required materials will be delivered to works location prior to works commencement and stored
appropriately ready for use within working areas.
Equipment for cutting or drilling will not be above 25kg in weight and will be handled by one member of staff.
Only low voltage (110 volts) tools will be used as necessary, and all 110 volt tools will be connected to a
suitable/site provided step down transformer.
Portable electrical equipment will be checked on a regular basis, including daily inspection prior to use and a
maintenance records kept.
All portable tools if used will be PAT tested prior to use on site and inspections/reports carried out every 3 months
thereafter.
When power tools are in use and cabling extends across walkways or open walk areas, the cabling will be routed in
a manner where it crosses walkways or open walk areas it will be marked and covered and/or if possible to be
hung above head height by use of cable hooks. Communication of cabling locations will be made to site staff and
include the use and sighting of adequate signage.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 44/471
8. INDUCTION COURSE/SITE RULES
All staff to site, will attend an Induction Course (Tool box talk) and Safe Start meetings prior to working on site
(given by Company), this will support Principal Contractor Induction and adhere/inform of, all local site rules as
instructed/notified to them by Principal Contractor.
9. PROTECTIVE CLOTHING
Staff will wear appropriate Personnel Protective Equipment and work wear whilst working onsite.
· Safety Helmets
CBS Ltd staff will be responsible for the safe and proper disposal of waste arising from activities under their
management and for ensuring that disposal is carried out in accordance with legislation relevant to the waste
category involved. Site based skips provided by Principal Contractor will be utilized to dispose of all waste
materials.
Adherence of Principal Contractor Site Waste Management Plan will be carried out.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 45/471
All COSHH assessments will be carried out prior to use of any substances on site. Assessments will be
communicated to staff and copies of the assessment along with data sheets will be provided to site staff. (See
separate assessments). A COSHH Assessment for silica will be carried out as the dust produced from works
undertakings will produce dust which may contain silica from building materials.
The site project manager or his representative will be invited to inspect all completed work and working areas
before being asked to Sign Work Acceptance Form.
Working at heights will be undertaken in the carrying out of these works. All works will be carried out by use of a
temporary platform taking the form of a commercial hop up, podium steps and tower scaffold where necessary.
Tower scaffolds will be scaf tagged and inspected daily by certified member of staff.
All tower scaffold areas will be barriered off with safety notices fixed to barriers.
Step ladders/ladders will not be used as a norm and will only be sanctioned after a full risk assessment has been
carried out.
The brick or concrete cutting or drilling works will be carried out in a phased process, this
will be undertaken in conjunction with the Principal Contractors and Company Works Program.
Manual handling, lifting/moving procedures will be undertaken by trained staff. All equipment used for cutting and
drilling will be offloaded as single units weighing 20kg
per unit.
During cutting and drilling operations that require into building structures (brick or concrete) disposable FFP3 dust
mask to be worn at all times.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 46/471
Works will be carried out on a wall by wall, ceiling by ceiling, riser by riser etc., basis within rooms, corridors, and
service areas until all are complete.
Work areas will remain clear of clutter during all installation operations and restrictions/ barriers will be put in place
to prevent un-authorized entry to works areas by non- company staff, but will ensure that passage along/across the
area is maintained for access and egress.
Any restrictions or specific site rules will be applied throughout the installation and Company staff will be notified of
those restrictions/site rules at induction. They will further read and obtain information if necessary of daily site risk
notifications (access and read site notice board) or by communication with site management staff.
The works will be carried out in a phased program in accordance with Principal Contractors and Company Program
of Works. Where the works undertakings are at variance to the Principal Contractor Program of Works, these will
be discussed and agreed with the Principal Contractor prior to works being carried out.
REFERENCE SHOULD BE MADE TO PROGRAM OF WORKS AND DRAWINGS FOR INSTALLATION AT ALL
TIMES.
The Site Manager for the works will hold appropriate certification (SMSTS).
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 47/471
The following equipment will be used on site for installation works:
· Hand tools
· Podium Steps
· Tower scaffold
· Barriers
· Safety Signs
No materials will be brought to site that will not be used within the allotted time period of application
communicated to site management.
The Company will implement the site Emergency Plan as detailed by Hinton Build & Design.
No works must/or will be carried out that has not been risk assessed and if works whilst being carried out produce a
risk that has not been assessed, all works must stop and notification given to Company Site Manager who will
implement the appropriate action.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 48/471
METHOD
STATEMENT
Activity : Deliveries
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Task/Operation:
Pre-arranged/timed deliveries to site. Contact made with the supplier to arrange a suitable time for delivery to take
place.
Drivers instructed of the traffic/public road way system and any parking restrictions and/or local schools etc in the
vicinity. The area if on a public road way will be suitably signed warning members of the public of the process being
carried out. There will be a trained banks man in attendance throughout the process.
Drivers met at the site entrance by the gate man where instructions will be provided to the lay down area.
Driver to park in the designated area and banked on site by a trained banks man.
The driver will be informed that no jumping out of the cab of the vehicle is allowed/the driver will be informed that no
jumping from the bed of the lorry will be allowed.
Should the delivery company be providing a "Mofitt" type fork lift the area around the vehicle will be barriered off
and signs displayed warning site operatives/members of the public of the process being carried out. (drivers of
Mofitt fork lifts will be required to provide the necessary training certification for such together with proof of thorough
inspection paperwork.
A banks man will be on hand at all times to supervise the unloading and stacking procedure.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 49/471
Trained (manual handling) persons will be requested to unload the vehicle and ensure that the delivery has been
stored in the lay down area or close to the area of work.
PPE Required:
Safety Boots/shoes
Gloves
Safety helmet
Hi-Vis Tabard.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 50/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Strip out
2. Inform all relevant parties and other occupants of work commencing and cordon off work area if practical to do
so. Particular attention should be paid to property where children are present; children and adults must be kept
away from the work area at all times and protected from dangers of power tools and substances
3. Ensure the area to be dismantled and exit points are clear of obstruction and that safe access and egress is
maintained
6. Test any electrical circuit before commencing work and ensure it is dead
7. Check any electrical or hand tools for damage or faults, faulty or damaged tools must be removed from service
immediately
8. Carefully remove existing coverings and ancillary equipment and remove to designated waste area. Large and/or
heavy items will be tandem lifted; do not lift beyond your capabilities
10. Remove existing floor covering, tiled floors will be broken up by hammer chisel
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 51/471
11. Remove all debris to designated waste disposal area
14. Ensure cooking and washing facilities are operational at end of each shift
1. All areas will be cleaned prior to handover; all waste and debris will be removed to the designated waste area
3. Handover to client
3/ Cordon off area to be worked in and notify persons within buildings of activities being carried out.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 52/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
2. Use this dimension to mark the ceiling and floor, allowing an additional 10mm for the thickness of the adhesive
and 12.5mm for the thickness of the plasterboard (dependent on board thickness).
3. Mark the walls with a chalk line at 900mm or 1200mm centres (distance apart), depending on plasterboard width.
4. Cut the Gyproc plasterboard 15mm short of the floor to ceiling height.
6. Using a trowel, apply a continuous band around the perimeter of the wall, ceiling edge, and around any services
or openings to provide greater airtightness
7. Apply Gyproc Dri-Wall Adhesive in dabs 50mm to 75mm wide and approximately 250mm long (trowel length), in
three vertical rows to receive the first board.
8. Ensure that dabs near a board joint are approximately 25mm from the edge of the board.
9. Apply another continuous band of Gyproc Dri-Wall Adhesive along the floor edge at skirting level.
11. Plasterboard off-cuts should be used as packing strips to rest the bottom edge of the board against.
12. Tap the board back firmly using a straight edge until the board is aligned with the chalk marks on the floor.
13. Gently lift the board using a footlifter until the board is tight against
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 53/471
15. Insert additional packing strips to wedge the board in place, and then remove the footlifter
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 54/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
1. All areas will be cleaned prior to handover; all waste and debris will be removed to the designated waste area
3. Handover to client
Confined Spaces
Confined Spaces can be any space of an enclosed nature where there is a risk of death or serious injury from
hazardous substances or dangerous conditions (eg lack of oxygen) in an enclosed drain or sewer Preparation of
emergency arrangements
Emergency arrangements will need to cover the necessary equipment, training and practice drills.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 55/471
Provision of rescue harnesses
Lifelines attached to harnesses should run back to a point outside the confined space.
Communications
An adequate communications system will be used to communicate between people inside and outside the confined
space and to summon help in an emergency.
Position someone outside to keep watch and to communicate with anyone inside, raise the alarm quickly in an
emergency, and take charge of the rescue procedures
Permit-to-work
A permit-to-work ensures a formal check is undertaken to make sure all the elements of a safe system of work are
in place before people are allowed to enter or work in the confined space. It is also a means of communication
between site management, supervisors, and those carrying out the hazardous work.
Strip Out
2. Starting at top of wall use pick and hammers to demolish coverings in small chunks for easy removal, taking care
to avoid flying debris.
4. Work down the wall, ensuring all wasted is removed from the working area as quickly as possible to keep escape
routes clear and minimise risk of trips and falls and minimise dust
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 56/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Preparation
1) Refer to site safety rules for information on signing in and starting work
3) Sub contract staff will be inducted onto sites by the main contractor; all members of staff are obliged to follow
the main contractor rules and regulations whilst on site.
4) The sub contractors site foreman will ensure that all safety measures are followed, by his staff, the site
foreman will set up and manage work patterns, equipment storage, control of visitors and protection of clients and
members of the public
5) All materials and equipment will be delivered to site by suppliers and kept in designated storage areas.
6) The site foreman will ensure staff are competent to complete the job safely and that apprentices are properly
supervised.
7) Physically check all equipment for signs of undue wear or damage, particularly plugs and cables
3) Liaise with the principal contractor and other contractors to ensure safe operation.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 57/471
4) Cordon off work area if practical to do so.
7) Ensure system is locked off and keys to padlock are kept with engineer
10)Remove fittings etc from site to designated waste or handover to client as contract dictates
Installations
3) Fix galvanised tray around perimeter of kitchen to new fuse board location
4) Wire armoured cable in all necessary outlets according to drawing BW406S_A (17/Aug/2007)
5) Wiring is tied to tray at high level and run down walls into associated boxes.
6) Wire in earth CPC to 5 separate positions for bonding stainless steel equipment
7) Install new sub main in from existing 800 Amp bus bar using a 200 Amp tap off.
8) Run 120mm 4 core cable along ladder rack into suspended ceiling through to new fuse board position.
13) Check all connections and cabling for security and integrity
14) Before re-energizing the system all non live testing will be carried out and test results written down on
Electrical Installation Certificates to conform to BS:7671
16) Tidy work area and remove all debris to designated waste area
Lighting Installations
1) Check with principal contractor/site foreman and liaise with other contractors before switching off lighting
2) Lock off lighting circuit, key to be kept with the electrical foreman
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 58/471
4) Prove the circuit is dead via test meter
5) Reposition lights according to new arrangement and alter existing switching arrangement where
necessary
1) NICEIC tests will be carried out on all installations prior to handover, the contract manager is responsible
for delivering the certificates to the principal contractor, a copy to be held on file at Credibuild Ltd
3) Handover to client
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 59/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Preparation
1. Refer to site safety rules for information on signing in and starting work
3. Sub contract staff will be inducted onto sites by the main contractor; all members of staff are obliged to follow
the main contractor rules and regulations whilst on site.
4. The sub contractors site foreman will ensure that all safety measures are followed, by his staff, the site
foreman will set up and manage work patterns, equipment storage, control of visitors and protection of clients and
members of the public
5. All materials and equipment will be delivered to site by suppliers and kept in designated storage areas.
6. The site foreman will ensure staff are competent to complete the job safely and that apprentices are properly
supervised.
7. Physically check all equipment for signs of undue wear or damage, particularly plugs and cables
1. All Staff and employees will observe the main contractor site rules for access and egress from the work
site
2. Staff and employees will attend any safety induction course provided by the main contractor prior to
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 60/471
starting work
3. Staff and Employees will be carrying out the relatively low risk operation of data cable termination for
which they will require access to all areas of the building; it will be the responsibility of the site foreman to liaise with
the main contractor, regarding the safe access and work in areas where other contractors will be working
4. For the mains voltage cables isolation and lock off procedures will be followed and all cables tested to
ensure they are not live before being worked on
5. The site foreman will also ensure other contractors are aware of the presence of staff in any area.
6. All staff are experienced and have been trained in the use of any tools which they are required to use,
where young and/or inexperienced workers are employed, it will be the responsibility of the site foreman to ensure
that these workers are supervised at all times
7. Staff are aware of the high numbers of injuries due to slips trips and falls and they will ensure that trailing
cables, tools or debris do not cause a trip hazard to themselves and other contractors
8. Staff and employees will pay particular attention to good housekeeping and ensure that the site is left
clean and tidy at the end of each shift
9. Report to site office and inform site manager of arrival, collect permit to work
10. Take tools and equipment to work area and store inside building
13. Ensure the area to be worked and exit points are clear of obstruction and that safe access and egress is
maintained
14. Check any electrical or hand tools for damage or faults, faulty or damaged tools must be removed from
service immediately
16. Floor has already been removed ready for fixings to be placed for the conduit
18. Pass cables through floors, walls etc ensuring cables remain neat and hidden where possible
19. Fix cables with tie wraps or proprietary fixings as required by contract
21. 2nd Fix Terminate cable to termination points and spurs as required
23. Once work is completed check wiring and re-energise the system as required for further testing
25. Liaise with client engineer to sign off satisfactory completion of task
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 61/471
Test and Handover
NICEIC tests will be carried out on all installations prior to handover, the contract manager is responsible for
delivering the certificates to the principal contractor, a copy to be held on file at Credibuild Ltd
Handover to client
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 62/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Preparation
1) Refer to site safety rules for information on signing in and starting work
3) Sub contract staff will be inducted onto sites by the main contractor; all members of staff are obliged to follow
the main contractor rules and regulations whilst on site.
4) The sub contractors site foreman will ensure that all safety measures are followed, by his staff, the site
foreman will set up and manage work patterns, equipment storage, control of visitors and protection of clients and
members of the public
5) All materials and equipment will be delivered to site by suppliers and kept in designated storage areas.
6) The site foreman will ensure staff are competent to complete the job safely and that apprentices are properly
supervised.
7) Physically check all equipment for signs of undue wear or damage, particularly plugs and cables
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 63/471
3) Liaise with the principal contractor and other contractors to ensure safe operation.
7) Ensure system is locked off and keys to padlock are kept with engineer
10)Remove fittings etc from site to designated waste or handover to client as contract dictates
Installations
7) Before re-energizing the system of all non live testing will be carried out and test results written down on
Electrical Installation Certificates to conform to BS:7671
9) Tidy work area and remove all debris to designated waste area
10)
Lighting Installations
1) Check with principal contractor/site foreman and liaise with other contractors before switching off lighting
2) Lock off lighting circuit, key to be kept with the electrical foreman
5) Reposition lights according to new arrangement and alter existing switching arrangement where
necessary
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 64/471
1) NICEIC tests will be carried out on all installations prior to handover, the contract manager is responsible
for delivering the certificates to the principal contractor, a copy to be held on file at Credibuild Ltd
3) Handover to client
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 65/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
The electrical testing works will be carried out in a phased process, this will be undertaken in conjunction with the
Principal Contractors and Company Works Program.
A defined and barried zone will be set up within the works area on each floor of the works and all installation works
will be undertaken within that area.
Works will be carried out on a component by component etc: basis within rooms, corridors and service areas until
all are complete on each floor level.
Work areas will remain clear of clutter during all installation operations and restrictions / barriers will be put in place
to prevent unauthorised entry to works areas by non- company staff, but will ensure that passage along / across
the area is maintained for access and egress.
Any restrictions or specific site rules will be applied throughout the installation and Company staff will be notified of
those restrictions / site rules at induction. They will further read and obtain information if necessary of daily site risk
notifications (access and read site notice board) or by communication with site management staff.
The works will be carried out in a phased program in accordance with Principal Contractors and Company Program
of Works. Where the works undertakings are at variance to the Principal Contractor Program of Works, these will
be discussed and agreed with the Principal Contractor prior to works being carried out.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 66/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
5. Check the supply is dead by electrical test meter before connecting to supply
6. Ensure system is locked off and keys to padlock are kept with engineer
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 67/471
9. Check all connections and cabling for security and integrity
10. Before re-energizing the system all non live testing will be carried out and test results written down on Electrical
13. Tidy work area and remove all debris to designated waste area
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 68/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Lighting Installation
1. Lighting will be manually carried/ handle using safe manual handling practises
3. All trusses and stands etc; will be marked with the SWL all chains and slings will carry current safety inspection
certification.
4. All equipment will be checked prior to rigging any damaged or faulty equipment will be removed from service
5. Lights will be hung onto truss using clamps and safety chains (truss will be at ground level)
6. Lights will be plugged in to generators and tested, faults will be rectified before installation
7. Truss will then be hoisted up to relevant height using chain blocks by competent persons
9. Check all cables are secure and Will not cause trip hazards
11. All systems must be rechecked after any unintentional movements or after an adverse weather event.
2. Turn off supply to Emergency Lights using MCB or Test switch if fitted
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 69/471
3. Walk around site checking that charging lights are now off and that main light is now alight (working via internal
battery)
4. Repair or replace lights as required. In the case of duration tests the lights may need to stay alight for up to 3
hours, any lights that fail within this time require attention
5. Reinstate supply to Emergency Lights after given time. Function Test Only Immediately after Test / Repairs, 1
Hour Duration Test, after 1 Hour, 3 Hour Duration Test after 3 Hours
Lighting Installation
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 70/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Start of works
5) Materials will be brought to site via lorry and checked against specification
6) Staff will break down equipment and organise into manageable loads
7) Large and/or heavy items will be assessed prior to lifting and if necessary carried by two persons
8) Materials to be transported to the storage area and stored as per manufacturers requirements
2) Ensure the area to be worked and exit points are clear of obstruction and that safe access and egress is
maintained.
3) Mark out partition positions as per construction drawing and cut timber to suit
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 71/471
6) Build timber frame and fix top timbers to ceiling
8) Ensure other trades i.e. electricians have completed work where open access to the partitions are
required
9) Measure and cut to size plasterboard to fit to partition timber posts on one side
10) When sawing or sanding plasterboards, use local exhaust system to control dust or wear a half face mask
to EN149 Class FFP 3s if dust cannot be controlled.
11) Ensure that boards are securely fixed with no steps between adjacent boards.
13) Drive home any protruding screw heads using a hand screwdriver prior to spotting and jointing
14) Install mineral fibre insulation prior to fitting plasterboard to other side
16) Hold up plasterboards to ceilings, depending on size this may be a 2 man job
To achieve a smooth continuous crack-resistant surface, use of tapered edge plasterboard and Joint Tape is widely
regarded as best practice
3) Trowel apply 1 coat of jointing compound to bulk fill and allow to dry
4) Apply 1 coat of jointing compound to secondary fill and take up any shrinkage
6) &n
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 72/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
The area of excavations will first be checked for live services using cat scanners and plans where possible. Any
existing services will be protected or moved as required. The holes are hand dug by two men using pick and
shovel; the excavations will be 1.2metres wide maximum by the appropriate depth for each property. To prevent
the potential for subsidence or collapse a distance of approx 1.2 metres is left in situ and another section of 1.2
metres dug out, the intermediate sections are not dug out until the concrete in the original excavations has been
set for 48 hours.
1. Care will be taken at all time when quick hitch is used to change over buckets, correct procedure will be followed
and a final push test will be carried out to ensure bucket is connected correctly
3. Ensuring the appropriate bucket is in use, ballast will be pulled to the agreed depth
4. Surplus ballast will be deposited along the sides of the area as directed
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 73/471
5. Areas that require deeper excavation surplus material to be removed to agreed storage area by means of a
dumper
6. Ballast will be graded until the ground is compacted and to the correct contour
Excavations
Prior to commencement of work The method of support selected needs to take account of the work to be done and
allow for adequate working space. The options for the method of support may also be limited by ground conditions
or the presence of services crossing the trench line. Support will also be required when plant for excavating or
depositing backfill will cause a surcharge on the excavation side.
Whatever the support method selected, an essential part of the method statement is a defined safe method of
work. No person should ever enter an unsupported excavation to install or remove supports. The use of proprietary
support systems which can be installed safely from existing ground level may help in this situation. Smoke head will
be isollated during work time and isollation removed when works area left unattended.
Hand digging
All trench works within 1.5m of the Ouse house plnt room are to be hand dug to expose any existing drainage or
cables.
Do not store excavated spoil or other materials or park plant and vehicles close to sides of excavations. The extra
loading from spoil, vehicles etc can make thre sides of excavations more likely to collapse. Loose materilas may fall
from spoil heaps etc into the excavation. A scaffold board used as a toe board and fixed along the outside of the
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 74/471
trench will provide extra protection against loose material falling. Hard hats will protect those working in the
excavation from falling material
Prevent people from falling by guarding excavations. Edges of more excavations more than 2m deep should be
protected with substantial barriers. Where necessary, use (painted or marked) baulks or barriers to keep vehicles
away from from excavated edges.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 75/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
1. Put on PPE
3. Collect permit to work (Work will only be carried out by competent persons).
4. Where possible work should be carried out with out isolating existing circuit and equipment.
5. If current system is wired direct to the fire service confirm the client has notified the Services of any
change or that you are working on the systems.
6. Arrange for additional fire watches if circuit are to be isolated and site is live.
7. Isolate electrical circuit to existing fire alarm at circuit protective device, remove and keep fuse and place
warning sign
8. Route the new cable run as per plans from the existing or new alarm units to the location of the new/
existing control point units.
9. This may involve working within voids or trunking that could be used to conceal the new cable.
10. Where ladder are used to reach the area to be worked the ladder will be footed by 2nd operative. Three
points of contact to be maintained.
11. Run the cable along the route as per plans to the length that is required for the new sounder and cut
cable from the reel as required
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 76/471
12. Repeat as required for the new detectors.
13. Take measurements of the lengths of trunking required and cut to those lengths. If applicable
14. Remove the top cover of the trunking and peel tape off of the self-adhesive side. Place it level on the
wall/ceiling. If applicable
17. At the end of the cable runs, the sounder and detector bases will be drilled into and then screwed into the
wall or ceiling joist.
18. The new units will then be wired up to the new system and fitted to their bases.
20. Waste and unwanted items will be removed from site and tools and equipment safely stored.
21. Contact site representative to cancel permit to work and demonstrate systems.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 77/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
1. The Fire Marshall is principally concerned with the maintenance of all the sites fire points and associated
fire exit signage
2. He will check each fire point on a daily basis and sign each fire point register to prove he has undertaken
this task
3. He will be looking for secure tags to each extinguisher
4. Checking for expiry dates to each extinguisher
5. Checking the logistics drawing on each fire point and looking for any site alterations, with respect to on-
going site works and fire emergency routes are as per the drawing. If there are any alterations to the
logistics drawing, the fire marshall will advise the Logistics Manager who will update the Logistics Plan
6. Checking all access/egress routes are clear of all obstructions. If he finds an access/egress route is
blocked he will inform the logistics manager who will identify who has blocked the route and get the
obstruction removed
7. Checking the fire point is freely accessible and free from obstructions
8. Looking for signs of tampering to the extinguishers
9. Look and place fire exit directional signage about site
10. Keep all signage clean and securely fixed
11. Ensuring the means of raising an alarm the air horn, is both present and operable.
12. Looking for sources of ignition, to include heaters, lighting, naked flames, electrical equipment, smokers
materials (cigarettes, matches etc), and anything else that can get very hot or cause sparks
13. Sources of fuel to include wood, paper, plastic, rubber or foam, loose packaging materials, waste rubbish
14. Keep sources of ignition and flammable substances apart
15. Avoid accidental fires; make sure heaters cannot be knocked over
16. Ensure good housekeeping at all times; avoid build-up of rubbish that could burn
17. Keep fire exits and escape routes clearly marked and unobstructed at all times
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 78/471
Deliveries and distribution
The fire marshal is not concerned with deliveries to site, however he will liaise with the Company Name
Management as and when supplies are needed.
Sequence of works
After the site induction the Company Name Fire Marshal will be escorted about site by an Company Name
supervisor and shown the exact location of all fire points and signage. The Fire Marshal will be shown;
trailing leads
trip hazards
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 79/471
- The fire point check sheet is on the fire point and has been checked previously
- The appropriate CO2 and Foam extinguisher indicaters are on the fire point
- No materials have been stacked in front of the fire point inhibiting access
He will also be looking for development site wide of the signage and alterations as the site routes alter.
The altering of site access/egress routes is likely to be a frequent occourance, weekly meetings with the logistics
team will advise in dvance of the proposed alterations. The fire marshal, with the assistance of the logistics
supervisor, will prepare new logistics drawings and appropriate signage, so when an alteration occurs, this
modification can be undertaken seamlessly.
· Radio
· Signage
· Cable ties
· Fire points
· Fire extinguishers
· Staple Gun
General
· The noise and vibration levels for thiese operations are not deemed as a risk to the operatives or the general
public.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 80/471
Health and safety responsibilities
HSE Manager
(NEBOSH Construction Certificate, NEBOSH Fire Safety and Risk Management Certificate, CSCS & NVQ level 5
Occupational Health and Safety
The health and safety manager has the overall responsibility for H&S matters within the company on a day-to-day
basis. They are responsible for preparing the site H&S plan and issuing it to the relevant personnel within the
business. They are also responsible for issuing the required risk assessments and COSHH assessments to the
Contracts manager.
Contracts Manager
The contracts manger is responsible for ensuring policies and procedures are adopted and adhered to by
operatives. Undertakes bi-weekly health and safety inspection tour and produces reports. They also liaise with the
Logistics Manager and site operatives.
Logistics Manager
The logistic manger is responsible for day to day health and safety matters on site, adoption of policies and
procedures by all operatives and liaising with the project management team. Undertakes weekly health and safety
inspection tour and produces reports for the contracts manager.
Site Operatives
(CSCS Cards)
The site operatives are responsible for taking reasonable care for themselves and all those working around them
who may be affected by their acts or omissions. Will follow the H&S instructions of Company Name where
directed
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 81/471
Company Name are confident that we have sufficient Operatives and Supervision dedicated to this task and all the
operative will have the relevant project/trade experience to safely and efficiently carry out the above mentioned
tasks.
All materials are not to be stored in access routes, Traffic Marshall to ensure Fire Exit are clear at all times.
Manual handling
Where possible all manual handling will be kept to a minimum, however moving and placing fire extinguishers will
be undertaken using a flat bed trolley. The extinguishers will be loadIed in their packaging for ease of
transportation.
Sources of ignition
The fire marshall whilst on patrols will look for flammable materials, sources of ignition and their appropriate
storage. He will advise the logistics manager of his daily findings.
Incorrect PPE
The correct PPE such as hard hats, HIVIZ, safety boots, Gloves 4343 must be worn all the times and when dealing
with hazardous materials
RA-002
Manual Handling
RA-002
Signage
RA-003
Personal protective equipment will be worn / used at all times. Task related PPE will be required and given by the
Company Name Site Manager as indicated on the Task Safety Plan.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 82/471
The minimum requirement for this project is:-
Emergency Procedures:
A first aid box is kept in the Company Name site office and Derwent office for minor accidents. In the event of a
serious injury the emergency services will be contacted (999) by the Logistics Manager or one of the Logistics team
members. Derwent Management is to be informed immediately of any accident or near miss.
If the fire marshall needs to activate the fire alarm he will radio the Company Name logistics manager and advise
him of this action prior to activating the alarm, to advise of the location and severity of fire. After consultation with
the logistics manager the marshall will activate the alarm.
If the fire marshall is informed to evacuate the site, he will assist in escorting staff from site (if there is no risk to
himself. Directing site personel to the emergency routes, exit and muster point, presently located by the main
entrance security cabin.
The fire marshall will relay the exact position of the fire, nature of the fire and of any potential excelerants within the
immediate vicinity to the Company Name / Derwent manager, so this information can be given to the emergency
services. The fire marshall will then make his way to the muster point.
After the emergency has passed and Derwent management have given the all clear to re-enter site, the fire
marshal will liaise with the mace and the logistics team and repopulate site.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 83/471
4. ACCESS & EGRESS
Pedestrian access for this element of the works is through the Derwent pedestrian entrance off Mallow Street. The
operatives will be asked to sign in and produce their site access card. They will then be permitted to enter the
project demise and follow the pedestrian walkway to the site welfare. From the site welfare they will gain follow the
pedestrian walkways to the work face.
All deliveries shall be programmed in advance, so that the Company Name logistics team can arrange in
the correct delivery slots.
A nominated and trained Company Name Traffic Marshal will be present at all times to direct and, where
necessary, reverse each delivery vehicle into the designated drop-off point.
The Company Name Traffic Marshal will liaise with the Logistics manager to agree a set-down area for the
materials, which shall be moved to the relevant floor once the delivery has been off loaded.
The set-down area and immediate vicinity will be cleared of personnel prior to all offloading works
commencing, so as to minimise risk to others.
The process for each type of delivery shall be as follows:
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 84/471
5. LIGHTING
N/A
1. Radio
2. Signage
3. Fire points
4. Fire extinguishers
7.
Please Note: Company Name Management will monitor all the operatives PPE and if any of it is damaged or not fit
for purpose it will be replaced and recorded.
Competence
Company Name traffic marshals all have undertaken the "take control" CITB recognised course.
Additionally traffic marshals employed at 1 Old Street Yard, White Collar Factory have a proven company
history working safely and competently on many Company Name sites.
All Company Name operatives will have CSCS cards and copies of their cards will be issued to Derwent
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 85/471
during their site induction and copies of the above mentioned cards will be kept in our site file.
The Company Name Site Manager will give the operatives a "Toolbox Talk" on the produced Method
Statement, COSHH and Risk Assessments for the relevant task required of them prior to any works
commencing.
Operatives will also be given a weekly generic toolbox talk on relevant tasks. After all toolbox talks the
operatives will sign a briefing register.
Material / Substance
COSHH data sheets for CO2 and Foam fire extinguishers are attached
YES
9. WASTE MANAGEMENT
The fire marshall is not overly concerned with waste management with this task, however any waste his tasks
generate will be placed into the 660litre wheelie bins on and about site.
Any COSHH waste generated by his tasks will be segregated from the general waste and will be placed into the
correct bins/skips
Please Note: Company Name will be responsible for the removal of facilietes and our own waste only.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 86/471
10. SPECIAL CONTROL MEASURES
ALL operatives undertaking works activities shall be briefed as to the content of method statements pertaining to
their work by the site supervisor. All operatives attending briefings shall sign the Method Statement Briefing
Register to confirm their understanding and acceptance. The Method Statement Briefing Register shall be attached
to the relative Method Statement and placed within the Method Statement file kept within the site office.
On and about the fire marshals patrols, if he notices any hit works being undertaken which he believes are likely to
have the potential to cause a fire, he will speak with the persons undertaking the hot works and advise them of his
concerns, he will additionally discuss with his logistics supervisor.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 87/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Preparation
1. Refer to site safety rules for information on signing in and starting work
3. Sub contract staff will be inducted onto sites by the main contractor; all members of staff are obliged to follow
the main contractor rules and regulations whilst on site.
4. The sub contractors site foreman will ensure that all safety measures are followed, by his staff, the site
foreman will set up and manage work patterns, equipment storage, control of visitors and protection of clients and
members of the public.
5. All materials and equipment will be delivered to site by suppliers and kept in designated storage areas.
6 The site foreman will ensure staff are competent to complete the job safely and that apprentices are properly
supervised.
7. Physically check all equipment for signs of undue wear or damage, particularly plugs and cables
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 88/471
Electrical First Fix
4. Isolate supply and use torches and temporary lighting for light while power is out
7. Review site plan and establish new location of main board and ancillary sockets and lighting
8. Mark out socket and light fitting position on walls and floor joists
10. Run wiring through from locations, ensure all wires are marked up as to their intended use at both board and
socket ends
12. Pack tools an equipment and leave area clean and tidy
13. Report to staff that work is complete, hand over to second fix
NICEIC tests will be carried out on all installations prior to handover, the contract manager is responsible for
delivering the certificates to the principal contractor, a copy to be held on file at Credibuild Ltd
Handover to client
Cable containment is an important part ofinstalling a networks infrastructure. The purpose of containment can
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 89/471
befourfold: to support the cables en route, to make subsequent management ofcables easier, to provide isolation of
power and data cabling and also to makethe installation aesthetically pleasing. Typically, products such as
cabletrays, cable ladders, and cable baskets are used to support a cable throughoutthe cabling route and trunking
is used in the final presentation.
The systems below represent some of themain forms of cable containment systems available; however, the list is
notexhaustive and new products are appearing on the market all the time.
CableTray is normally available in a range of light,medium and heavy duty gauges. It is usually galvanised,
although specialfinishes such as powder coating are sometimes used.
WireBasket is a variant of cable tray. It consistsof a basket structure which, although not as structurally strong as
cable tray,is lighter and easier to install. It is commonly used for support of lightcabling such as data and telephone
wiring.
Conduit comes as lengths of robust tube, available in both PVC and Steel.PVC conduit is available in light and
heavy duty grades. Steel conduit isavailable in a galvanised finish or stainless steel.
Miniand Maxi Trunking has a rectangular form and isavailable in various sizes manufactured from PVC and is
suitable for datacabling, fibre cabling or power. Mini style is available in non-adhesive andself-adhesive variants,
Maxi style is a larger and available as non-adhesiveonly.
FloorTrunking specially adapted for installationwithin floor voids, or screeds floor trunking commonly has two or
morecompartments enabling segregation and hence is used for 240V services as wellas data and
telecommunication systems. It is often fitted with custom floorboxes.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 90/471
FloorBoxes commonly installed in conjunction withfloor trunking systems, recessed floor boxes can be installed into
a cavityfloor or screeded floor. They comprise one or more compartments and accessoryboxes which can be used
to terminate many different services at one box.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 91/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Painting Ceiling from Tower Scaffold and walls to "cut in at the top"
Plumbing work
1. Liaise with other contractors and facilities manager to isolate water supplies
5. Ensure waste pipes and other plastic pipe work are connected correctly
6. Where plastic pipe is connected with solvents, staff will follow all safe use instructions
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 92/471
7. Where solder work has to be carried out, prepare pipe work for solder joints
8. Obtain the appropriate hot work permit from the facilities manager
9. Ensure the correct type of fire extinguisher is on hand during hot work
15. Carry out further checks for water tightness and quality of finish
16. Chlorinate the system if required and check for successful completion
19. Pack tools an equipment and leave area clean and tidy
20. Maintain fire watch for 2 to 4 hours where hot work has been carried out
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 93/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Cordon off area to be worked in and notify persons within buildings of activities being carried out. Ensure all PPE is
in place and of good quality.
First Aid
It is the responsibility of the company to ensure adequate First Aid provision for its staff. Adequate means provision
of a trained first aider, suitable first aid equipment and/or the provision of an appointed person at the minimum.
A trained First Aider will be a suitable person who has attended an HSE approved course of at least three days
duration. An Appointed Person is a person provided by the employer to take charge of the situation (e.g. to call an
ambulance) if a serious injury/illness occurs in the absence of a First Aider. The Appointed Person can render
emergency First Aid if trained to do so. All staff when inducted will be made aware of the location of the First Aid kit.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 94/471
Manual Handling
All staff and contractors have been instructed on the potential dangers of manual handling, and have received
manual handling training. Equipment provided to reduce manual handling must be used where provided. Staff and
contractors will not lift items of tools or equipment that are beyond their capabilities. Heavy or awkward items will be
split into smaller
units where possible or dual lifted where this is not possible. It is the responsibility of the site foreman/employer to
identify and control manual handling activities as they occur on site on a day to day basis.
A risk assessment will be carried out for all tasks which will be discussed with members of staff and the sub
contractors, any queries or concerns will be raised with the contract manager who will ensure it is dealt with. Staff
and sub contractors will be inducted onto site in order to understand the hazards present on site and the tasks that
are to take place. Staff will also be advised of other site activities that could impact on their work and be made
aware of any liaison that needs to take place between different trades. Staff will follow all site rules and safety
procedures.
All tools and equipment will be visually inspected on a regular basis, defective or damaged equipment will be
removed from service. Electrical tools will be 110V or battery operated where possible. Sub contractors will not be
allowed to bring on to site any damaged or defective tools, the site foreman is responsible for ensuring that all tools
and equipment allowed on the site are fit for purpose. Any portable electrical equipment taken on to site must be
PAT tested every 3 months when used on construction sites, 6 monthly for heavy use activities and annually for
other activities. A risk assessment will determine if inspection periods need to be varied.
Welfare
The principle contractor is responsible for providing adequate washing, toilet, drying and refreshment facilities for
staff and sub-contractors, staff and contractors are responsible for ensuring that such welfare facilities are
maintained in a clean and wholesome manner (it may be necessary occasionally for us to identify suitable local
amenities).
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 95/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Client responsibilities:
Method:
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 96/471
Load materials to your work area using manual handling guidelines
If working at height you must comply with the guidelines outlined in this document
Install all necessary DPM and insulation as per agreed specification
Cement slurry pre-cast concrete bases.
Pump screed to place of work to a mix of at least 1 shovel of cement to 4 shovels of sharp sand with
manufacturers recommended amount of fibres.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 97/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
1. Allemployees, contractors and visitors to the site will use the designated parkingareas.
2. Allemployees, contractors and visitors will attend the site induction whichincludes this method / risk
assessment.
3. Allemployees, contractors and visitors will register their presence within thedaily site register.
All persons will comply with site rules in the wearingof personal protective equipment.
1. Allsite rules and conditions must be strictly adhered to and any person failing todo so will be subject to P&B
Walsh Decorators Ltd disciplinary action andmay be removed from site.
2. P&BWalsh Decorators Ltd Site Manager / Foreman will ensure that all working areasand means of access /
egress are clear and free from obstruction; on discoveryof any obstruction caused by other trades he will ensure
the area is made safeimmediately.
A stepladder may be used to gain access to high levelwork to the top surfaces and will only be used for short
duration and lightduties i.e. mastic / sealant around window. All work from off ladders will be carriedout from inside
of the building.
1. Beforework commences the site supervisor will check that the area is suitable andsafe for work to commence.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 98/471
2. All furniture / fittings within the work area are to be protectedplus signs displayed warning building users of the
danger and prohibitingaccess to unauthorised personnel.
4. Debrisarising from works to be disposed in bins near place of work and disposed ofimmediately on completion
of works
5. Whenhandling glass the use of PPE is required including eye and foot protection,strong industrial gloves with
wrist protection.
6. SiteSupervisor to ensure that storage facilities are adequate and are maintained tothe required standard.
7. Allcuts to kitchen units are done locally on firm flat surface. All cuttingdevices are to be fitted with vacuum air
bags to minimise dust.
8. Oncebase units are fixed, work tops can be installed. Lifting the work top into position (minimumtwo operative
using correct lifting techniques) the surface will then besecured into position.
9. Onceall surfaces are plumb, exposed joints are filled with silicone sealant. (seeCOSHH assessment).
10. When complete or at the end of a workingday, clean all debris from surrounding area, ensuring that the area is
cleanand tidy before leaving site.
2. Topstep of stepladder must not be used unless designed for that purpose.
3. Laddermust be checked to ensure correct length, type and condition before use.
5. Ladderwork is restricted to that which can be carried out using one hand only, andstepladder work to that
which can be carried out ensuring the stability of thestepladder.
8. Laddersmay only be footed as a sole precaution against movement if less that 3m high.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 99/471
9. Useof ladders will be monitored regularly, to ensure that operatives are notover-reaching or using two hands to
work.
1. Allmaterials will be below the recommended guidance for manual handling liftingweight of 25kg.
2. Allpallets of materials will be transported around site by the mobile plant underthe control of the principal
contractor and positioned as close as possible tothe workface.
Where the movement requires short distances operatorswill use barrows or where this risk is minimal passage of
materials betweennumbers of operatives.
q Operativesare to have received training in Manual Handling and Working at Height (use ofstepladders).
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 100/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Banking In Vehicles
No vehicles will be allowed to park in the Club carparks, they must be either directed to the office compound or the
service road around the grass roundabout.
Area to be left clear of rubbish and a clear access / egress route maintained at all times. Damp down areas
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 101/471
requiring sweeping.
Use class M hoover where possible. Ensure good manual handling techniques. Waste will not be stockpiled in
locations.
Don not leave chemicals out, these should be stored in the cupboards provided or container. Only use the correct
product for the task.
General Cleaning
Cleaning
1. Position fencing bases along the proposed fence line using a spacing gauge (a piece of timber cut to suit will
suffice)
2. The panels are supported by inserting the side posts into the holes cast in the center of the base. Each base is
cast with at least 4 post support positions for flexibility of use and hand hold positions in each end of the base.
5. With the entire panel in position, security clamps should then be placed approximately 650mm from the top of
the panel, across the adjoining side posts- a 20mm box type spanner is required to secure the clamp with the
central nut and bolt.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 102/471
The fencing will ensure our compound is secured and is denoted on site-up plan. Panels will be erected whilst there
are no children about by team lift and cones and tape used as necessary. Site signage & gates will be team lifted
also and denote "contractors at work"
PPE
Hard hat, vest, safety footwear and gloves as standard. All other PPE to be task specific as a when required.
Strip out
2. Inform all relevant parties and other occupants of work commencing and cordon off work area if practical to do
so. Particular attention should be paid to property where children are present; children and adults must be kept
away from the work area at all times and protected from dangers of power tools and substances
3. Ensure the area to be dismantled and exit points are clear of obstruction and that safe access and egress is
maintained
6. Test any electrical circuit before commencing work and ensure it is dead
7. Check any electrical or hand tools for damage or faults, faulty or damaged tools must be removed from service
immediately
8. Carefully remove existing coverings and ancillary equipment and remove to designated waste area. Large and/or
heavy items will be tandem lifted; do not lift beyond your capabilities
10. Remove existing floor covering, tiled floors will be broken up by hammer chisel
14. Ensure cooking and washing facilities are operational at end of each shift
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 103/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Preparation
1) Report to site office and inform site manager of arrival, collect permit to work where required.
6) Ensure the area to be worked on and the exit points are clear of obstruction and that safe access and
egress is maintained.
7) Check any electrical or hand tools for damage or faults, faulty or damaged tools must be removed from
service immediately.
9) Ensure the work area is left safe at end of each shift and when unattended.
Maintenance/repair work
1) Liaise with other contractors and facilities manager to isolate water supplies.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 104/471
4) When chasing out the walls firstly use the cable/pipe finder to locate any electric cables or pipe work.
7) On plaster walls chase out using a Kango power chisel or hand bolster.
8) If necessary remove any skirting boards by driving the bolster chisel behind the board and carefully levering it
away from the wall (gloves should always be worn)
9) If necessary to take up any floorboards these should first be checked with the cable/pipe finder to ensure the
area below the board is clear.
10)Set the circular saw to 18mm depth and along the length of the board on both sides through the tennon (on
some floors it may be necessary to reset the saw to a depth of 22mm and take a second cut
11)Using the bolster chisel lever up the board, remove all nails.
12)When taking up carpet and lifting floorboards attention will be paid to the trip hazard created, do not leave open
floorboards and upturned carpets any longer than is necessary, sufficient warning signs must be posted where
there is a risk of other contractors entering the site.
14)Ensure waste pipes and other plastic pipe work are connected correctly.
15)Where plastic pipe is connected with solvents, staff will follow all safe use instructions.
16)Where solder work has to be carried out, prepare pipe work for solder joints.
17)Obtain the appropriate hot work permit from the facilities manager.
18)Ensure the correct type of fire extinguisher is on hand during hot work.
24)Carry out further checks for water tightness and quality of finish.
28)Pack tools and equipment and leave area clean and tidy.
29)Maintain fire watch for 30 minutes where hot work has been carried out.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 105/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Task Description This method statement describes the work process for the supply of labour and materials to
construct a pitched roof to residential property including:
1. Site Establishment
2. Site manager to conduct induction of staff, to include all safety talks and actions and restrictions as agreed
with owners of adjacent properties
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 106/471
5. Large and/or heavy items will be assessed prior to lifting and if necessary carried by two persons
6. Equipment and materials are ordered as and when required for construction
2. Scaffold will be erected from the ground and tied into the brick work or secured through available window
openings
3. Scaffold will be erected to up to eaves level and the handrail will extend a minimum of 1 metre above
4. All kick boards etc will be supplied to prevent falling of tools and material
6. Scaffolding contractors will return to the property to carry out any alterations or extension as required when
the job progresses
7. The scaffolding contractor will hand over a completion certificate prior to allowing access to the scaffold
8. The site foreman will be responsible for inspecting the scaffold on a daily basis and ensuring its continued
adequacy
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 107/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Preparation
7) Liaise with the principal contractor and other contractors to ensure safe operation
9) Ensure the area to be worked and exit points are clear of obstruction
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 108/471
13) Prepare area to be excavated by clearing slabs, debris etc
2) Carry out CAT scans of ground to check and locate live services
4) Bring heavy machinery onto site following safety procedures listed above
6) Dig out ground as per contract drawings to required size and depth
7) Where live services have been located machines must not dig within 0.5 meters
8) Hand dig around live services where necessary using spade and shovel
9) Live services will be encased in concrete and capped off by the local authority
10) You must ensure contaminated water does not get onto the skin or enter the body.
11) Ensure that deep excavations are cordoned off with secure barriers
12) All excavations must be left safe at the end of each shift
N.B. where operatives must enter the trenches to work you must follow the Standard Operating Procedure for
shoring and protecting trenches
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 109/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Start of works
1) Report to site office and inform site manager of arrival, collect permit to work
6) Ensure the area to be worked and exit points are clear of obstruction and that safe access and egress is
maintained.
7) Check any electrical or hand tools for damage or faults, faulty or damaged tools must be removed from
service immediately.
Fit new gutter support brackets by drilling and screwing into the facia ensuring correct flow direction
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 110/471
Clip the guttering into position and secure. Outlets to be fitted as site dictates
Fit the downpipe(s) and secure. Swan necks and bends to be fitted as site dictates
All work should be carried out from the scaffolding or access platform
4. Clean area
7. Handover to client
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 111/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
FLOOR JOISTS
2. Collect lengths of wood from storage area and take to cutting area
7. Lay temporary platform for use as work area or lay weather protective safedeck boards as per drawings
8. Lift the first floor joists into position using the telescopic handler if available, if Not ensure good manuall handling
techniques are observed
10. Lay first floor temporary platform for use as work area or lay weather protective safedeck boards as per
drawings
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 112/471
STAIRCASE
4. Fix though strings into the wall to secure stairs using supplied fixing screws
5. Fix under third tread from bottom using small stud frame to give support
4. Temporary wedge the frame in place in preparation for fixing and check for plumb
5. Drill the fixing holes and screw fix with raw plugs or frame fixings
6. Cut the interior sill to size and fix with propriety fixings
STUD WALLS
1. Mark out the position of the internal walls as per the site plan
5. Nail fix the Sole Plate ensuring they are plumb with the Ceiling Plate
6. Mark out the position of the Studs on both the Ceiling Plate & Sole Plate
8. Skew nail each stud both top and bottom and check for vertical with the spirit level
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 113/471
9. Mark out the position for the horizontal noggins as per site plan
14. Remove all waste and dispose of as per local authority guidelines
Panels
Panels will be erected whilst there are no children about by team lift and cones and tape used as necessary. Site
signage
2. Dry test the door in the casing and mark where trimming is needed
4. Wedge the door in place and mark out the hinges and lock position
5. Chop out and fit the hinges to the frame either by hand or router
7. Hang the door and check for plumb and correct clearance
8. Drill & chop out the door before fitting the lock
10. Mark out the frame and fit the striking plate
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 114/471
FITTING THE ARCHITRAVE
4. Fix the architrave to the door frame using the nail gun
4. Fix to the wall by nail gun / screw & plug or instant grip adhesive as required
1. Measure / cut and fix the newel posts ensuring each is upright
2. Measure the run of the base/hand rail and cut to size with the chop saw
5. Measure the angle of the balusters and mark out the position on the base rail and handrail
6. Cut the balusters to size and fix to the base rail and hand rail
KITCHEN UNITS
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 115/471
2. Mark out the floor with the position of the units and equipment
5. Fix the units in place with the appropriate fixings, ensure units are levelled up correctly
9. Mark out the wall for the position of the wall units
10. Mark a plumb line at the correct height for the underside of the units
11. Drill and subsequently fix the adjustable brackets to the wall
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 116/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Work will be carried out using our normal Hot Works procedure (including Hot Work Permit to be issued by
theSupervisor) filled in by the site operative.
The site will be examined and checked by the operatives for any obvious fire risks.
Any fire hazards will be removed or protected by the operatives and suitable fire extinguishers will be kept
next to the heat source.
A minimum one hour fire watch will be kept after cessation of the hot works and adjacent areas to which
sparks and heat might spread and areas on the other side of walls, partitions, etc will be inspected during
the hour.
A hot works permit will be signed by the operative in charge of the Hot works after a minimum of one hour.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 117/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
The distribution boards and panels installation works will be carried out in a phased process, this will be
undertaken in conjunction with the Principal Contractors and Company Works Program.
Materials will be delivered to site by delivery vehicle which will unload materials at the location. The material will be
offloaded to commercial wheeled trollies for onward movement to works locations.
Manual handling, lifting / moving procedures will be undertaken by trained staff. All materials will be offloaded as
single units weighing 25kg per cable drum unit.
A defined and barried zone will be set up within the works area on each floor of the works and all installation works
will be undertaken within that area.
During installation operations that require any drilling into building structure disposable FFP3 dust mask to be worn
at all times.
Works will be carried out on walls within rooms, corridors and service areas on all floor levels of the building.
Work areas will remain clear of clutter during all installation operations and restrictions / barriers will be put in place
to prevent unauthorised entry to works areas by non- company staff, but will ensure that passage along / across
the area is maintained for access and egress.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 118/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
The second fixing installation works will be carried out in a phased process, this will be undertaken in conjunction
with the Principal Contractors and Company Works Program.
Materials (electrical outlets and distribution boards) will be delivered to site by delivery vehicle which will unload
materials at the site. The material will be offloaded to commercial wheeled trollies for onward movement to works
locations.
Manual handling, lifting / moving procedures will be undertaken by trained staff. All materials will be offloaded as
single units weighing 25kg per cable drum unit.
A defined and barried zone will be set up within the works area on each floor of the works and all installation works
will be undertaken within that area.
During wiring installation operations that require any drilling into building structure disposable FFP3 dust mask to
be worn at all times.
Works will be carried out on a wall by wall, ceiling by ceiling, riser by riser etc: basis within rooms, corridors and
service areas until all are complete on each floor level.
Work areas will remain clear of clutter during all installation operations and restrictions / barriers will be put in place
to prevent unauthorised entry to works areas by non- company staff, but will ensure that passage along / across
the area is maintained for access and egress.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 119/471
Any restrictions or specific site rules will be applied throughout the installation and Company staff will be notified of
those restrictions / site rules at induction. They will further read and obtain information if necessary of daily site risk
notifications (access and read site notice board) or by communication with site management staff.
The works will be carried out in a phased program in accordance with Principal Contractors and Company Program
of Works. Where the works undertakings are at variance to the Principal Contractor Program of Works, these will
be discussed and agreed with the Principal Contractor prior to works being carried out.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 120/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
3. DESCRIPTION OF WORKS
Installation of Electrical Wiring to internal areas to the building within and on all floors, risers, and plant room areas
throughout the building.
The works include all finishes associated with the detailed specification provided by the Principal Contractors for
the project.
4. SCOPE OF WORKS
Installation of all electrical domestic wiring installations within and throughout the building to provide for
consumer circuits for building accommodations.
Working progressively through each detailed area, which includes all domestic Premises
apartments, service risers and plant rooms, including areas identified on drawings supplied by the Principal
Contractors.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 121/471
The domestic electrical circuits work will provide for final installation works (second fitting electricals) for carrying
electrical power to installed components to building interior wall, ceilings, risers and plant room or service spaces of
the building.
The works will conform to the requirements detailed in the works specification issued to the Principal Contractor for
the project.
5. PERMITS TO WORK
Cannock Building Services Ltd will ensure that when working on site all Permits to Work and authorizations to work,
where relevant and defined by the Principal Contractor site rules, are obtained, and any specific requirements or
restrictions complied with.
All Permits to Work or authorizations to work shall be obtained from the Site Project Office, this shall be from a Site
Manager or his representative.
All works will be assessed for Permit to Work needs and this will be undertaken by Company Site Manager and/or
Company Health and Safety Advisor.
6. MANUAL HANDLING
All loads of works materials will be broken down into single units and carried to works location by manual handling
means. All required materials will be delivered to works location prior to works commencement and stored
appropriately ready for use within working areas.
Each role of electrical cable will not be above 25kg in weight and will be handled by one member of staff or two
members of staff during installation of long lengths (in excess of five meters).
Only low voltage (110 volts) tools will be used as necessary, and all 110 volt tools will be connected to a
suitable/site provided step down transformer.
Portable electrical equipment will be checked on a regular basis, including daily inspection prior to use and a
maintenance records kept.
All portable tools if used will be PAT tested prior to use on site and inspections/reports carried out every 3 months
thereafter.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 122/471
When power tools are in use and cabling extends across walkways or open walk areas, the cabling will be routed in
a manner where it crosses walkways or open walk areas it will be marked and covered and/or if possible to be
hung above head height by use of cable hooks. Communication of cabling locations will be made to site staff and
include the use and sighting of adequate signage.
All staff to site, will attend an Induction Course (Tool box talk) and Safe Start meetings prior to working on site
(given by Company), this will support Principal Contractor Induction and adhere/inform of, all local site rules as
instructed/notified to them by Principal Contractor.
9. PROTECTIVE CLOTHING
Staff will wear appropriate Personnel Protective Equipment and work wear whilst working onsite.
· Safety Helmets
Cannock Building Services Ltd staff will be responsible for the safe and proper disposal of waste arising from
activities under their management and for ensuring that disposal is carried out in accordance with legislation
relevant to the waste category involved. Site based skips provided by Principal Contractor will be utilized to dispose
of all waste materials.
Adherence of Principal Contractor Site Waste Management Plan will be carried out.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 123/471
11. COSHH DETAILS
All COSHH assessments will be carried out prior to use of any substances on site.
Assessments will be communicated to staff and copies of the assessment along with data sheets will be provided
to site staff. (See separate assessments).
The site project manager or his representative will be invited to inspect all completed work and working areas
before being asked to Sign Work Acceptance Form.
Working at heights will be undertaken in the carrying out of these works. All works will be carried out by use of a
temporary platform taking the form of a commercial hop up or podium steps where necessary.
Step ladders/ladders will not be used as a norm and will only be sanctioned after a full risk assessment has been
carried out.
The domestic wiring installation works will be carried out in a phased process, this will be undertaken in conjunction
with the Principal Contractors and Company Works Program.
Materials (electrical cable drums) will be delivered to site by delivery vehicle which will unload materials at building
underground carpark entrance. The material will be offloaded to commercial wheeled trollies for onward movement
to works locations.
Manual handling, lifting/moving procedures will be undertaken by trained staff. All materials will be offloaded as
single units weighing 25kg per cable drum unit.
A defined and berried domestic cable installation zone will be set up within the works area on each floor of the
works and all installation works will be undertaken within that area.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 124/471
During wiring installation operations that require any drilling into building structure disposable FFP3 dust mask to
be worn at all times.
Works will be carried out on a wall by wall, ceiling by ceiling, riser by riser etc. basis within rooms, corridors, and
service areas until all are complete on each floor level.
Work areas will remain clear of clutter during all installation operations and restrictions/barriers will be put in place
to prevent un-authorized entry to works areas by non- company staff, but will ensure that passage along/across the
area is maintained for access and egress.
Any restrictions or specific site rules will be applied throughout the installation and Company staff will be notified of
those restrictions/site rules at induction. They will further read and obtain information if necessary of daily site risk
notifications (access and read site notice board) or by communication with site management staff.
The works will be carried out in a phased program in accordance with Principal Contractors and Company Program
of Works. Where the works undertakings are at variance to the Principal Contractor Program of Works, these will
be discussed and agreed with the Principal Contractor prior to works being carried out.
REFERENCE SHOULD BE MADE TO PROGRAM OF WORKS AND DRAWINGS FOR INSTALLATION AT ALL
TIMES.
The Site Manager for the works will hold appropriate certification (SMSTS).
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 125/471
· Hand tools
· Podium Steps
No materials will be brought to site that will not be used within the allotted time period of application communicated
to site management.
The Company will implement the site Emergency Plan as detailed by xxxxxxxxxxxxxxx.
No works must/or will be carried out that has not been risk assessed and if works whilst being carried out produce a
risk that has not been assessed, all works must stop and notification given to Company Site Manager who will
implement the appropriate action.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 126/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Inform tenant and other occupants of work commencing and cordon off work area if practical to do so. Particular
attention should be paid to property where children are present; children and adults must be kept away from the
work area at all times and protected from the dangers of power tools and substances.
· Place Warning signs at the extremes of the work area prior to the work commencing.
· Physically check the condition of all equipment before and after use.
Stripping Out
2) Check for the presence of asbestos, if present instigate control measures and waste disposal
arrangements.
3) Ensure the area to be worked and exit points are clear of obstruction and that safe access and egress is
maintained.
4) Check any electrical or hand tools for damage or faults, faulty or damaged tools must be removed from
service immediately.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 127/471
6) Purge gas pipes where necessary.
7) Carefully dismantle all gas, appliances, and ancillary equipment and remove to designated waste area.
Large and/or heavy items will be tandem lifted; do not lift beyond your capabilities.
10) Cat scan the walls to locate hidden services, ensure all services are isolated, mark out positions of new
services and chase out walls.
4) Carry out gas integrity test on any gas supplies once appliances have been fitted.
5) Turn on services and check all appliances for safety and correct operation.
4) Where plastic pipe is connected with solvents, staff will follow all safe use instructions.
5) Where solder work has to be carried out, prepare pipe work for solder joints.
6) Obtain the appropriate hot work permit from the facilities manager.
7) Ensure the correct type of fire extinguisher is on hand during hot work.
13)Carry out further checks for gas tightness and quality of finish.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 128/471
15)Request facilities manager to inspect works.
17)Pack tools & equipment and leave area clean and tidy.
18)Maintain fire watch for 2 - 4 hours where hot work has been carried out.
4) Sweep floor area and ensure all debris is removed from site.
6) Handover to client.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 129/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 130/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
ii) Positions of equipment will be inspected to identify any specific access requirements.
iii) Company Site Supervisor will monitor operations, the services of an external consultant may be utilised
where necessary.
iv) All live retained services will be identified and labelled to prevent accidental contact. All operatives to be
made aware of general First Aid arrangements, which will be provided by the Main Contractor.
v) Specific emergency arrangements in the event of a serious accident will be the responsibility of the Site
Supervisor or nominated person.
vi) Method Statement / Risk Assessment checklist to be read and signed by the Site Supervisor/operative at
site, showing they fully understand the content.
Check plant equipment is suitable for the job. Step ladders/Podium erected correctly and are suitable for the job.
Step ladders and podiums to be erected on solid ground, the work area to be kept clean and tidy and free from
debris. Use of towers, once erected, ensure that safety tags are present, no boards missing, double guardrails
present, and toe boards present. Supervisor to brief operatives on correct system of work, talks to take place
periodically to remind operatives the need to work safely at height. Signs and barriers to be used to warn that
operatives are working overhead.
ii) Standard PPE equipment, hard hats, safety footwear, gloves, high visibility vests to be worn. Safety
glasses, goggles and dust masks to be worn when drilling or cutting. Eye protection must be worn at all times.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 131/471
iv) Site Supervisor to advise other Contractors at site that works are to take place, in order that they can inform
any non-English speaking operatives they employ to be made aware of the works being carried out and what steps
they need to take to avoid any accidents/incidents.
sequence of works
ii) Power supplies to control panels and interface units will be installed in accordance with a separate
Method Statement.
iii) Wall mounted equipment such as sounders, interface units and control panels will be securely fixed to
the building fabric using suitable fixings. The associated cables will be terminated into the equipment using suitable
glands. The cables will not be connected to the control panel at this point.
iv) Ceiling mounted devices will be mounted using a suitable back box. The base of the device will be fixed
to the backbox through the ceiling/ceiling tile using at least two fixing screws. The alarm cables will pass through a
hole in the ceiling/ceiling tile and will be connected to the base unit in accordance with the manufacturers
instructions. If the ceiling tile is of the metal type suitable protection will be provided where the cables pass through.
v) When all the detector bases, sounders, interface units, ancillary equipment and control panels are fitted
and the site is clean and free from the dust, the complete fire alarm system will be tested and commissioned in
accordance with B.S. 5839 part 1. by a recognised system commissioner.
vi) During commissioning all detector heads will be fitted and all detection and alarm circuits, interface
devices and control panels will be verified as operating correctly.
vii) If the system is addressable each device will be given a unique address.
viii) If required a full demonstration of the system will be given to the building occupier or designated
representative.
ix) All commissioning and record documentation will be included in the Operation and Maintenance Manuals.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 132/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Installation of Second Fixing Electrical Installations to internal areas to the building within and on all floors, risers,
and plant room areas throughout the building.
The works include all finishes associated with the detailed specification provided by
4. SCOPE OF WORKS
Installation of all electrical second fixings installations within and throughout the
building to provide for consumer circuit outlets or distribution boards for building
accommodations
Working progressively through each detailed area, which includes all domestic premises apartments,
service risers and plant rooms, including areas identified on drawings supplied by Principal Contractors.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 133/471
The domestic electrical second fixing works will provide for final installation finish to works (electrical outlets and
distribution boards) for carrying electrical connections and power outlets of installed components to building interior
wall, ceilings, risers and plant room or service spaces of the building.
The works will conform to the requirements detailed in the works specification issued to the Principal Contractor for
the project.
5. PERMITS TO WORK
Cannock Building Services Ltd will ensure that when working on site all Permits to Work and authorizations to work,
where relevant and defined by the Principal Contractor site rules, are obtained, and any specific requirements or
restrictions complied with.
All Permits to Work or authorizations to work shall be obtained from the Site Project Office, this shall be from a Site
Manager or his representative.
All works will be assessed for Permit to Work needs and this will be undertaken by Company Site Manager and/or
Company Health and Safety Advisor.
6. MANUAL HANDLING
All loads of works materials will be broken down into single units and carried to works location by manual handling
means. All required materials will be delivered to works location prior to works commencement and stored
appropriately ready for use within working areas.
Each role of electrical cable will not be above 25kg in weight and will be handled by one member of staff or two
members of staff during installation of long lengths (in excess of five meters).
Only low voltage (110 volts) tools will be used as necessary, and all 110 volt tools will be connected to a
suitable/site provided step down transformer.
Portable electrical equipment will be checked on a regular basis, including daily inspection prior to use and a
maintenance records kept.
All portable tools if used will be PAT tested prior to use on site and inspections / reports carried out every 3 months
thereafter.
When power tools are in use and cabling extends across walkways or open walk areas, the cabling will be routed in
a manner where it crosses walkways or open walk areas it will be marked and covered and/or if possible to be
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 134/471
hung above head height by use of cable hooks. Communication of cabling locations will be made to site staff and
include the use and sighting of adequate signage.
All staff to site, will attend an Induction Course (Tool box talk) and Safe Start meetings prior to working on site
(given by Company), this will support Principal Contractor Induction and adhere/inform of, all local site rules as
instructed/notified to them by Principal Contractor.
9. PROTECTIVE CLOTHING
Staff will wear appropriate Personnel Protective Equipment and work wear whilst working onsite.
· Safety Helmets
CBS Ltd staff will be responsible for the safe and proper disposal of waste arising from activities under their
management and for ensuring that disposal is carried out in accordance with legislation relevant to the waste
category involved. Site based skips provided by Principal Contractor will be utilized to dispose of all waste
materials.
Adherence of Principal Contractor Site Waste Management Plan will be carried out.
All COSHH assessments will be carried out prior to use of any substances on site.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 135/471
Assessments will be communicated to staff and copies of the assessment along with data sheets will be provided
to site staff. (See separate assessments).
The site project manager or his representative will be invited to inspect all completed work and working areas
before being asked to Sign Work Acceptance Form.
Working at heights will be undertaken in the carrying out of these works. All works will be carried out by use of a
temporary platform taking the form of a commercial hop up or podium steps where necessary.
Step ladders/ladders will not be used as a norm and will only be sanctioned after a full risk assessment has been
carried out.
The second fixing installation works will be carried out in a phased process, this will be undertaken in conjunction
with the Principal Contractors and Company Works Program.
Materials (electrical outlets and distribution boards) will be delivered to site by delivery vehicle which will unload
materials at building underground carpark entrance. The material will be offloaded to commercial wheeled trollies
for onward movement to works locations.
All materials will be offloaded as single units weighing 25kg per cable drum unit.
A defined and barried zone will be set up within the works area on each floor of the works and all installation works
will be undertaken within that area.
During wiring installation operations that require any drilling into building structure disposable FFP3 dust mask to
be worn at all times.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 136/471
Works will be carried out on a wall by wall, ceiling by ceiling, riser by riser etc, basis within rooms, corridors, and
service areas until all are complete on each floor level.
Work areas will remain clear of clutter during all installation operations and restrictions/barriers will be put in place
to prevent un-authorized entry to works areas by non- company staff, but will ensure that passage along/across the
area is maintained for access and egress.
Any restrictions or specific site rules will be applied throughout the installation and Company staff will be notified of
those restrictions / site rules at induction. They will further read and obtain information if necessary of daily site risk
notifications (access and read site notice board) or by communication with site management staff.
The works will be carried out in a phased program in accordance with Principal Contractors and Company Program
of Works. Where the works undertakings are at variance to the principal Contractor Program of Works, these will be
discussed and agreed with the Principal Contractor prior to works being carried out.
REFERENCE SHOULD BE MADE TO PROGRAM OF WORKS AND DRAWINGS FOR INSTALLATION AT ALL
TIMES
The Site Manager for the works will hold appropriate certification (SMSTS).
· Hand tools
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 137/471
· Podium Steps
No materials will be brought to site that will not be used within the allotted time period of application communicated
to site management.
The Company will implement the site Emergency Plan as detailed by Hinton Design & Build.
No works must/or will be carried out that has not been risk assessed and if works whilst being carried out produce a
risk that has not been assessed, all works must stop and notification given to Company Site Manager who will
implement the appropriate action.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 138/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
ii) Conduit routes will be inspected to identify any specific access requirements.
iii) Company site supervisor will monitor operations, the services of an external consultant may be utilised
where necessary.
iv) All live retained services will be identified and labelled to prevent accidental contact.
v) All operatives to be made aware of general First Aid arrangements, which will be provided by the Main
Contractor.
vi) Specific emergency arrangements in the event of a serious accident will be the responsibility of the Site
Supervisor or nominated person
vii) Method Statement/Risk Assessment checklist to be read and signed by the Site supervisor/operative at site,
showing they fully understand the content.
i) Check equipment is suitable for the job. Step ladders and podiums to be erected on solid ground, the work
area to be kept clean and tidy and free from debris. Supervisor to brief operatives on correct system of work, talks
to take place periodically to remind operatives the need to work safely at height.
ii) Standard PPE equipment, hard hats, safety footwear, gloves, high visibility vests to be worn. *Safety
glasses, goggles and dust masks must worn when drilling and cutting.* Eye protection to be worn at all times.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 139/471
iii) Operatives to be fully briefed on job to be carried out by Site Supervisor.
iv) Site Supervisor to advise other Contractors at site that works are to take place, in order that they can inform
any non-English speaking operatives they employ to be made aware of the works being carried out and what steps
they need to take to avoid any accidents/incidents.
sequence of works
i) Conduit will have been installed in accordance with Method Statement MS11.
ii) Cable size/type and circuits will be as determined by the designated electrical designer and as indicated on
the installation documentation.
iii) Conduit installation will be complete and inspected to ensure it is mechanically sound, dry and free from
grease etc., prior to installation of cables.
iv) The working area will be kept as clear as possible to avoid damage to cables as they are pulled into the
conduit.
v) Drums of cables will be suitably supported to allow them to run off the drums smoothly.
vi) Where possible, all cables to be installed in a conduit will be pulled in at the same time to avoid over pulling.
viii) Care will be taken during the installation of the cables to avoid twists and damage to the cables.
ix) If the cables are not to be terminated immediately following installation they will be left neatly coiled.
x) Cables will be tested in accordance with B.S. 7671 17th Edition IEE Wiring Regulations prior to connection.
xi) New circuits will be connected to the distribution board in accordance with Method Statement MS05.
xiii) When all accessories are fitted and it is safe to do so the circuits will be energised.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 140/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Installation of window frames to first and second floors at the front of the building and first floor at the rear of the
building
Introduction
Prior to any works being carried out all operatives will receive the usual toolbox talk and site
inductions.
All plant will have the necessary test certificates and all personnel involved in the task will be suitably trained in the
safe operation, where required.
Is to install replacement window frames to the first and second floor at the front of the building and the first floor of
the rear of the building.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 141/471
3. Control measures
The Site Manager will also be ensuring that all carrying routes are clear of all other trades, materials etc, and free
from trip hazards.
4. Duration of Activity
The work activity will take place at 87 Arlington Road on the first and second floor of the building.
6. Access systems
Method of Work
The area of work and the route for carrying the windows to their location shall be free from stored materials and any
trip hazards removed. The windows will be carried to their location via the existing internal staircase; care must be
exercised in carrying the pre-glazed window panels.
These pre-glazed panels are of a Georgian design and consist of several small panes of glass.
Before any personnel begin the installation task they will be given a TBT on Manual Handling and Working on
Scaffolding. All personnel will also read this Method Statement prior to any work beginning.
The window frames will be passed out of the existing window opening and fixed to the building from the outside via
the scaffolding, the pre-glazed panels will be installed from the inside of the building.
All waste material shall be placed in bags and carried down the internal staircase and removed outside into a skip
provided for waste.
The area both inside the building and the scaffold shall be left in a clean and tidy state.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 142/471
The forklift truck will have all necessary test certificates and the operator will be suitably trained (copies will be
available for inspection).
8. Supervision
9. Special conditions
a) Work on the scaffold will only take place providing it has a current safety certificate or hand
Over certificate.
b) Care must be taken when handling the pre-glazed panels. (These frames are made up of several
Small panes of glass, if one is broken the risk of the whole panel breaking is reduced).
c) The work area is to be free from other trade contractors and no works are to be permitted
overhead.
Extreme care will be exercised when working on the scaffold to prevent any tools or materials from
falling
11. Resources
Hand tools
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 143/471
At present there are no temporary works required.
13. PPE
Standard site protective equipment applies (hard hat, boots, hi-vis vest)
File
Signed
D. Meakin
This method statement will be explained to the actual works persons carrying out the works, this by the immediate
works supervisor, before any work is commenced. Records to show this has taken place should be retained.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 144/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Selecting the right underlay and damp-proof membrane (DPM) for the type of flooring and room setting.
Lay a DPM.
Laying the packs of planks, leave the unopened packs of planks lying horizontally on the floor in the room where
they are to be laid for at least 48 hours so it can acclimatise to the rooms temperature. Planks not to be stored in
direct sunlight.
Works will start to lay the planks. Planks should be laid lengthways, parallel to the longest side of the room and
towards the main incoming source of light if possible. Use spacers to create expansion gaps between the floor and
the wall or skirting.
Start the row by placing the plank with tongue facing the wall. Continue with the first row, using the tongue and
groove to interlock planks, making sure the row is straight and parallel with the wall. If you are laying laminate
flooring in a kitchen or bathroom you will need to apply wood adhesive to all end and side tongue and groove joints.
Turn it face down and lay it next to the previous plank, tongue to tongue, using spacers to maintain the expansion
gap with the wall.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 145/471
Use a square to mark a line across it in line with the end of the previous plank.
Cut and position it to complete the first row. Continue to lay planks a row at a time, making sure that joints between
planks in adjacent rows are staggered.
When laying the last row, lay a plank over the previous row. Place a third plank on top with the tongue against the
spacer and use the edge of the plank to mark a line on the plank beneath, cut along the plank and use a hammer
and pull bar to make sure it is tightly in place.
When all the flooring is laid, remove the spacers. The matching threshold strips will be fitted.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 146/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Inform tenant and other occupants of work commencing and cordon off work area if practical to do so. Particular
attention should be paid to property where children are present; children and adults must be kept away from the
work area at all times and protected from substances such as paint and paint stripper.
· Place Warning signs at the extremes of the work area prior to the work commencing.
· Physically check the condition of all equipment before and after use
Stripping Wallpaper
2) Ensure the area to be stripped and exit points are clear of obstruction and that safe access and egress is
maintained.
3) Carefully wet down wallpaper with warm soapy water and allow to soak through
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 147/471
8) Ensure area is left safe at end of each shift
9) Ensure cooking and bathroom facilities are operational at end of each shift
Applying Wallpaper
3) Mix sufficient paste for area to be covered, refer to Safety Sheet for paper paste
6) When working from stepladders the company working at height procedure must be followed.
7) DO NOT REMOVE any light switches or sockets, cut and shape the paper around switches and sockets.
8) Remove all waste and debris from site to designated area, site will be left clean and tidy at the end of
each shift
4) If using chemical stripping agents such as Nitromors, you must read and understand the safety data
sheet for the product you are using
5) Electric hot air stripping tools will be PAT tested on an annual basis and checked for defects on a daily
basis, damaged or defective tools will be removed from service immediately
6) Electric hot air strippers can get extremely hot and therefore create a fire risk, ensure a suitable fire
extinguisher is at hand during hot work.
7) N.B. Chemical cleaners and work tools such as hot air strippers will not be left unattended in residential
properties, this is especially important where children are present
8) Make sure any extension leads are kept tidy and do not cause a trip hazard
2) Cover floor area and any furniture etc with dust sheets to prevent paint splashes
4) When working from stepladders the company working at height procedure must be followed.
6) Ensure surface is clean, dry and free from dirt, grease, and oil
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 148/471
7) Do not leave paints open and unattended at any time
8) Apply undercoat and allow to dry, do not apply too much and watch for runs etc.
9) Check undercoat for correct adhesion to surface and wipe down if necessary
2) Cover floor area and any furniture etc with dust sheets to prevent paint splashes
3) Clean down surface to be painted using proprietary cleaner as per instructions above
4) Ensure surface is clean, dry and free from dirt, grease, and oil
5) When working from stepladders the company working at height procedure must be followed.
7) Apply emulsion paint with brush or roller and allow to dry, do not apply too much and watch for runs etc
1) The kitchen and bathroom will be cleaned prior to handover; all waste and debris will be removed to the
designated waste area.
3) Handover to client
Care of equipment
1) All items must be thoroughly cleaned in either water or the relevant solvent at the end of each shift
2)
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 149/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
This document is submitted to cover so far as is reasonably practicable, the health, safety and welfare of our
employees and others who may be affected by the erection, adaption, or dismantling process of the Internal
birdcage.
ENVIRONMENTAL IMPACTS
The site itself is accessed by a public highway the main access for materials is through the Main Site
Entrance gate. From here the vehicles will access the plant using side access road avoiding crossing the
Weighbridge.
The scaffold Working areas are within the plant it is, therefore, an Absolute Requirement that any working
plant either immediately above or below the working operatives is taken out of operation, this particularly
applies to the operation of open Conveyor belt systems.
The working area is self-contained and poses no risk to the public all others will be excluded whilst the
scaffold is being installed.
The site carries a possible risk of diseases such as Weils and others, therefore, gloves to be worn always
and regular washing of hands and other exposed areas as frequently as possible but particularly prior to
eating food.
RESPONSIBLITLIES
The Customer
The customer shall be responsible for the following and in addition to any clauses indicated in our quotation
and any drawings calculations submitted.
Provision of suitable and sufficient artificial lighting for carrying out the scaffold works.
Obtain all necessary permissions, permits, notices etc.
Ensure that all health and safety and welfare amenities are available including first aid activities.
Ensure that a site client representative attends the site always to discuss or liaise in the event of difficulties
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 150/471
that may be encountered in carrying out the scaffold works.
Supply and place all necessary warning lights, notices, fenders hoarding etc.
Ensure that all foundations are capable of safely withstanding all the imposed loads from our scaffold and
supply and placement of any necessary spreaders or back propping.
Supply sufficient quantities of protective fencing to form enclosures and barriers to segregate work zones
during erection or dismantling periods.
Weekly signature of the appropriate site inspection report.
110 v power supply as appropriate.
The customer will provide as necessary all specific safety induction to all employees.
Ensure that suitable anchorage/scaffolding tie locations are made available for the restraint of the scaffold
and fully maintained during the period of contract hire.
The customer will provide a copy of the appropriate construction phase plan for inclusion within our contract
safety file.
Will keep a copy of or keep ready access to the appropriate method statement whilst carrying out the work.
Ensure that all work is carried out in accordance with the method statement submitted, including any
subsequent revisions.
Identify any change or alteration which may be required and submit for review.
Liaise and coordinate with the site management to monitor and review in all aspects towards health and
safety and welfare requirements which affect the scaffolding works in particular.
GENERAL SAFETY/TRAINING
Training Statement
All operatives shall be CISRS/CITB registered or equivalent and approved cardholders appropriate to their
status.
In addition, all operatives shall be fully briefed on their specific site responsibilities and made aware of all
current client contractual obligations under health, safety and welfare issues generally. REF: NASC SG
4.05
Safety Harness
Prior to the commencement of any erection, adaption or dismantling activities, the following procedures
must be adhered to.
All scaffolding operatives, however, employed will be issued with and instructed and trained for the sole use
of full body safety harness and shock absorber lanyards.
Harnesses shall be worn always whilst engaging in scaffolding activities and attached to a suitable node
point of the scaffolding frame in line with guidance NOTE: NASC SG 4.05.
General Safety
All Giraffe Scaffolding operatives shall, whilst on site, conform to the customer's specific safety induction
and strictly operate under the guidance of all other safety requirements set by our Principal Contractor site
management.
Our operatives shall be provided with and always wear steel toe capped boots and safety harnesses whilst
erecting, altering or dismantling scaffold, as well as safety helmets (when required).
Suitable rescue procedures involving fall arrest shall be set up by arrangement and agreement with
client/principal contractor.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 151/471
Erection Tolerances
Standards vertical to within plus/minus 20mm in 2.0m ( subject to a total deviation of 50mm ) Bay lengths &
width plus/minus 200mm on the designated lengths level to within plus/minus 20mm in 2.0m ( subject to a
maximum deviation of 50mm ).
Lift height plus/minus 150mm on the designated height.
Nodes less than equal to 150mm on the designated height.
METHOD
Before work on the scaffold, all Giraffe Scaffolding operatives involved in the task will be briefed on this
document and sign to accept.
This is the standard that Giraffe Scaffolding set for work that falls under the TG20:13 criteria for all
scaffolding projects.
The operatives will then be given a task briefing on the scaffold being erected. This will be a 2-way
conversation between the Giraffe Scaffolding Supervisor and the scaffolders involved in the erection of the
scaffold.
The briefing will take place on site at the work area. Proof of the briefing will be sent to PC. A hard copy will
be kept in the Giraffe Scaffolding site file.
The scaffold that has been requested requires a design and will be erected in strict compliance with that
design (large internal birdcage) as well as best practice from the TG20:13.
The scaffold material will be transported to the project on a Giraffe Scaffolding scaffold lorries.
Giraffe Scaffolding operatives will access the back of the lorry via a secured ladder and the bed will have a
handrail that will run around the 3 sides for maximum safety.
The lorry will sit in the designated loading area and the scaffold material will be removed from the trailer
manually and transported to the work areas and erected.
The Giraffe Scaffolding vehicle will be maneuvered onto the site through the site entrance by Giraffe
Scaffolding trained traffic marshals and will exit site in the same manner.
Should the situation arise whereby emergency services need to access the road then the vehicle will be
moved out of the way immediately.
The driver will stay on site with the lorry always.
This process will be repeated daily.
The lorry will be marshaled out by Giraffe Scaffolding scaffolders wearing Hi-Vis vests and PPE.
The lorry will comply with the site speed limit when entering or exit the site.
An exclusion zone will be set up around the areas of work.
This will be erected, controlled and monitored by the PC.
The scaffold independent will be erected in strict compliance with the guidelines set out in TG20:13. The
use of hop up brackets or step up brackets will be used to erect an advanced guardrail where applicable.
Scaffolders will be clipped onto to the scaffold always when standing on the hop up brackets. Scaffolders
will always clip on above their heads to a securely fixed point. This will ensure that Giraffe Scaffolding
scaffolders will be working behind the safety of a single handrail always when erecting or dismantling
scaffold on site and that the harnesses are being used correctly.
All power tools on the site will be PAT tested and certification of the in date tools are in the Giraffe
Scaffolding site file. Giraffe Scaffolding use a cold cut reciprocator saw for cutting scaffold tubes and
boards. All scaffold tubes will be secured to a fixed tube low to the floor when cutting so that the off cut falls
directly into a scaffold sack from only a few inches away. If the tube being cut is longer, then a second
scaffolder will hold the off cut as it separates from the cut steel.
There will always be a safe route for access to and from the work area. A ladder access will be erected as
the independent progress to enable safe access to the scaffold at all times. All ladders will be secured
adequately always with ladder ties. All scaffold tubes and fittings that have the potential to cause harm will
be fitted with safety caps. All ladder accesses will have a swing gate or ladder hatch attached to the
entrance/exit of the ladder on all working lifts.
All scaffold operatives will be fully compliant with the site rules PPE policy always.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 152/471
The scaffolds will be erected with safety as the primary concern at all times. Giraffe Scaffolding operatives
erecting or dismantling the scaffolds will work on a safe platform with adequate fall prevention. Scaffolders
must be standing on a minimum of 3 scaffold boards and be behind a single guardrail unless the area is too
small and 3 scaffold boards do not fit. If the situation may arise where a safe working platform cannot be
erected scaffolders will be clipped on to ensure maximum safety or erect as many boards as possible
depending on the space in which the scaffold is being erected. Giraffe Scaffolding operatives will stop work
and report to their supervisor if the working environment changes from when the daily task briefing was
carried out or where their safety may be put at risk from situations being carried out on site by other trades.
All fittings used in the erections of the scaffolds conform to BSEN-74 regulations.
The top lift of the scaffold independent will be fully guard railed and toe boarded.
There will always be a safe means of access to and from the scaffold during the erection or dismantle. This
will be via a ladder secured to the scaffold with ladder ties.
All ladders used in any scaffold will protrude 1m past the scaffold boards as stated in SG4:15. Where a
ladder cannot fit due to space, an alternative fixed rail will be installed to accommodate where the ladder
would have been.
Giraffe Scaffolding scaffolders have had in-house manual handling training and are aware of the correct
means of picking up or placing down scaffold components.
Operatives are advised to only pick up weights that they are comfortable with or to share the load if need
be.
When passing scaffold components to pairs of hands will always be on the tube at the point of interchange.
No tubes/boards or scaffold fittings are to be dropped or thrown to or from the scaffold at any time. Where
necessary a secure pulley system will be fixed to the scaffold to hoist material up. This will be set up within
our exclusion zone.
The scaffold will be handed over to PC and a hand over sheet will be signed by both Giraffe Scaffolding and
PC and copies will be filed by each party for their records.
On completion of any scaffold, it will be inspected and scafftagged to show that it is in good working order
and compliant with PC requirements. The scaffold will then be inspected as a minimum every 7 days
thereafter, this will be the PC responsibility to organise.
Special control measures will be taken whilst working at height and site segregation will be:
Safety fall arrest harnesses to be used in strict compliance with the SG4;15
Single/Double lanyards
Work to the guidelines set out in TG20:13 and this accepted RAMS
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 153/471
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 154/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Plant to be Utilised
MethodStatement;
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 155/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Manual Handling Tool Box Talk will be carried out before works commence
Operatives will inspect the access route to make sure all walkways and paths are clear
Steel to be carried from the pavement to the courtyard. Operatives are to lift what they are comfortable handling
Operatives are to spread out along the length of the steel to spread the weight
Steel to be carried up the stairs to the 1st floor with the operatives spread along the length of the steel
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 156/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Method Statement
Operatives should familiarise themselves with the fire evacuation plan which can be found in the site file.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 157/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Start of works
1. Report to site office and inform site manager of arrival, collect permit to work and schedule of works
5. Ensure that floor boarding is in place at levels above the ground floor and that stairwells have fall protection in
place.
7. Ensure the area to be worked and exit points are clear of obstruction and that safe access and egress is
maintained.
8. Check any electrical or hand tools for damage or faults, faulty or damaged tools must be removed from service
immediately.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 158/471
3. Make sure area and wall that glass is to me mounted is clear of any obstructions and surface is smooth
4. Place plastic packers on the floor/work top under where the glass will be mounded so that when lifting into place
the glass will not make contact with it
5. Apply Mirror glue of adhesive to back of glass and manually lift into position on to the plastic packers already in
place
6. Firmly press the glass un to the wall, manoeuvre plug sockets through cut outs in glass if necessary until the
glass is flush with the wall/surface behind
7. Check Glass is level and silicone around the edges if in a wet room environment
9. Remove all waste and debris from site to designated area, site will be left clean and tidy at the end of each shift
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 159/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
The work area to be surveyed to plan the work including any requirements to avoid working at height where
practicable. Where painting at height is unavoidable then a suitable method of access is to be used and discussed
with site manager. All tools and equipment to be brought to site and stored in a secure place.
All removable fixtures, furniture and fittings to be removed from the room before work starts. Dust sheets to be
placed to protect fixtures and fittings that cannot be removed.
Painters tape (not masking tape) to be used to attach plastic drops to the floor and woodwork, and drops to be
covered with newspapers.
Painter's tape to be used to protect door and window frames and mouldings etc. Small plastic bags to be used to
cover door knobs.
All cracks and holes to be filled using paste filler applied with a putty knife and to be sanded down after the filler
paste is dry.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 160/471
Corners and edges of walls and ceilings to be cut-in using an angled 2" trim brush applying paint in a series of
short strokes away from the edges where walls or ceiling and wall meet.
Walls to be painted using a roller and tray. Paint to be applied in a vertical motion working horizontally across a
room from side to side.
On completion of the work all brushes and rollers to be washed and put away. Dust sheets and painters tape to be
removed and taken away.
The site is to be cleared of all equipment and left clean and tidy
Brickwork
Bricklaying the bonding together of bricks with wet mortar to form a wall.
1. All items must be thoroughly cleaned in either water or the relevant solvent at the end of each working day
2. Items such as brushes and rollers should be air dried and stored
3. Wash buckets, wipe inside and out and store upside down
4. All items should be stored out of reach of tenants and children. Ideally removed from site each working day
3. Apply vinyl covering to plasterboard and smooth out from the centre to ensure no air bubbles remain
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 161/471
4. Check all applications of vinyl
2. Dry test the door in the casing and mark where trimming is needed
4. Wedge the door in place and mark out the hinges and lock position
5. Chop out and fit the hinges to the frame either by hand or router
7. Hang the door and check for plumb and correct clearance
8. Drill & chop out the door before fitting the lock
10. Mark out the frame and fit the striking plate
4. Fix the architrave to the door frame using the nail gun
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 162/471
FITTING SKIRTING BOARDS
4. Fix to the wall by nail gun / screw & plug or instant grip adhesive as required
1. Measure / cut and fix the newel posts ensuring each is upright
2. Measure the run of the base/hand rail and cut to size with the chop saw
5. Measure the angle of the balusters and mark out the position on the base rail and handrail
6. Cut the balusters to size and fix to the base rail and hand rail
KITCHEN UNITS
2. Mark out the floor with the position of the units and equipment
5. Fix the units in place with the appropriate fixings, ensure units are levelled up correctly
9. Mark out the wall for the position of the wall units
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 163/471
10. Mark a plumb line at the correct height for the underside of the units
11. Drill and subsequently fix the adjustable brackets to the wall
Tarmacing
1. Prepare area to be tarmaced, by cutting edges straight and making sure that the sub base is compacted by
means of a whacker plate or whacker foot.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 164/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
General hand tools to include hammers, wrecking bars,hand saw, 110v angle grinders
Tile guillotine
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 165/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
The works include all finishes associated with the detailed specification provided by the Principal Contractors for
the project.
4. SCOPE OF WORKS
The cutting or drilling of plaster board walls and ceiling within the building to carry, hold or fix installed
electrical cables or components for building accommodations.
Working progressively through each detailed area, walls, ceilings, and service areas identified on
drawings supplied by the Principal Contractors.
The plaster board cutting and drilling will provide for final finishes for carrying electrical wiring and components
installed to building interior walls, ceilings, risers and plant room or service spaces of the building.
The works will conform to the requirements detailed in the works specification issued to the Principal Contractor for
the project.
5. PERMITS TO WORK
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 166/471
CBS Ltd will ensure that when working on site all Permits to Work and authorizations to work, where relevant and
defined by the Principal Contractor site rules, are obtained, and any specific requirements or restrictions complied
with.
All Permits to Work or authorizations to work shall be obtained from the Site Project Office, this shall be from a Site
Manager or his representative.
All works will be assessed for Permit to Work needs and this will be undertaken by Company Site Manager and /or
Company Health and Safety Advisor.
6. MANUAL HANDLING
All loads of works materials will be broken down into single units and carried to works location by manual handling
means. All required materials will be delivered to works location prior to works commencement and stored
appropriately ready for use within working areas.
Equipment for cutting or drilling will not be above 20kg in weight and will be handled by one member of staff.
Only low voltage (110 volts) tools will be used as necessary, and all 110 volt tools will be connected to a
suitable/site provided step down transformer.
Portable electrical equipment will be checked on a regular basis, including daily inspection prior to use and a
maintenance records kept.
All portable tools if used will be PAT tested prior to use on site and inspections/reports carried out every 3 months
thereafter.
When power tools are in use and cabling extends across walkways or open walk areas, the cabling will be routed in
a manner where it crosses walkways or open walk areas it will be marked and covered and / or if possible to be
hung above head height by use of cable hooks. Communication of cabling locations will be made to site staff and
include the use and sighting of adequate signage.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 167/471
8. INDUCTION COURSE/SITE RULES
All staff to site, will attend an Induction Course (Tool box talk) and Safe Start meetings prior to working on site
(given by Company), this will support Principal Contractor Induction and adhere/inform of, all local site rules as
instructed/notified to them by Principal Contractor.
9. PROTECTIVE CLOTHING
Staff will wear appropriate Personnel Protective Equipment and work wear whilst working onsite.
· Safety Helmets
Cannock Building Services Ltd staff will be responsible for the safe and proper disposal of waste arising from
activities under their management and for ensuring that disposal is carried out in accordance with legislation
relevant to the waste category involved. Site based skips provided by Principal Contractor will be utilized to dispose
of all waste materials.
Adherence of Principal Contractor Site Waste Management Plan will be carried out.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 168/471
All COSHH assessments will be carried out prior to use of any substances on site. Assessments will be
communicated to staff and copies of the assessment along with data sheets will be provided to site staff. (See
separate assessments).
A COSHH Assessment for silica will be carried out as the dust produced from works undertakings will produce dust
which may contain silica from building materials.
The site project manager or his representative will be invited to inspect all completed work and working areas
before being asked to Sign Work Acceptance Form.
Working at heights will be undertaken in the carrying out of these works. All works will be carried out by use of a
temporary platform taking the form of a commercial hop up, podium steps and tower scaffold where necessary.
Tower scaffolds will be scaf tagged and inspected daily by certified member of staff.
All tower scaffold areas will be barriered off with safety notices fixed to barriers.
Step ladders/ladders will not be used as a norm and will only be sanctioned after a full risk assessment has been
carried out.
The plaster board cutting or drilling works will be carried out in a phased process, this will be undertaken in
conjunction with the Principal Contractors and Company Works Program.
All equipment used for cutting and drilling will be offloaded as single units weighing 20kg
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 169/471
per unit.
During cutting and drilling operations that require into building structures (plaster boards) disposable FFP3 dust
mask to be worn at all times.
Works will be carried out on a wall by wall, ceiling by ceiling, riser by riser etc., basis within rooms, corridors, and
service areas until all are complete.
Work areas will remain clear of clutter during all installation operations and restrictions/ barriers will be put in place
to prevent un-authorized entry to works areas by non- company staff, but will ensure that passage along/across the
area is maintained for access and egress.
Any restrictions or specific site rules will be applied throughout the installation and Company staff will be notified of
those restrictions/site rules at induction. They will further read and obtain information if necessary of daily site risk
notifications (access and read site notice board) or by communication with site management staff.
The works will be carried out in a phased program in accordance with Principal Contractors and Company Program
of Works. Where the works undertakings are at variance to the Principal Contractor Program of Works, these will
be discussed and agreed with the Principal Contractor prior to works being carried out.
REFERENCE SHOULD BE MADE TO PROGRAM OF WORKS AND DRAWINGS FOR INSTALLATION AT ALL
TIMES.
The Site Manager for the works will hold appropriate certification (SMSTS).
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 170/471
· Hand tools
· Podium Steps
· Tower scaffold
· Barriers
· Safety Signs
No materials will be brought to site that will not be used within the allotted time period of application communicated
to site management.
The Company will implement the site Emergency Plan as detailed by Hinton Design & Build.
No works must/or will be carried out that has not been risk assessed and if works whilst being carried out produce a
risk that has not been assessed, all works must stop and notification given to Company Site Manager who will
implement the appropriate action.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 171/471
METHOD
STATEMENT
Activity : Plastering
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
1. Agree location for storage and mixing of materials with site management
2. Ensure that mixing areas are covered and floors are adequately protected prior to commencement of
plastering.
3. Check that water butts are suitably positioned and ensure that they do not overflow.
5. Ensure the surface is free from efflorescence, dirt, paint, grease, mould oil or dirt prior to the application of
material.
6. Ensure that all angle and stop beads are free from any defects and fix securely and true to line and level at
all external angles and where specified. Cut using tin snips / chop saw
7. Check that strips of expanded metal lathing are fixed across joints of dissimilar solid backgrounds where
plaster is continued without a break across the surface. Cut using tin snips / chop saw
8. Check that strips of expanded metal lathing are fixed across joints of dissimilar solid backgrounds where
walls are chased for services.
9. Ensure that materials are correctly mixed using mixer + paddle in well-ventilated areas as recommended by
the manufacturer
10. Check that each coat is applied correctly in accordance with the manufacturers recommendations with care
being taken to ensure that adequate adhesion and thickness is achieved.
11. Check that the finished surface complies with the tolerances prescribed by the relevant specification and
carry out spot checks with a straight edge at intermittent intervals.
12. Where the ceiling height is over 2.4m high but not exceeding 3m high, hop-ups or stilts would be used
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 172/471
13. Ensure that waste/debris is cleared to an agreed location at regular intervals and upon completion of the
works
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 173/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
2. Ensure the area to be worked has been clearly signed and marked out with warning tape; if necessary erect
physical barriers to prevent unauthorized access
4. Prepare the area to be plastered removing any loose material, ensure the surface to be plastered is clean
6. Collect the required materials from the storage area; ensure that you follow good manual handling techniques for
heavy material such as 25kg plaster bags
7. Ensure the RCD is in the socket before connecting any electrical device
9. Mix hand trowel led gypsum by hand or mechanical paddle using a clean container, ensure all material in a batch
is mixed thoroughly
10. Ensure that dust is kept to a minimum during mixing and that mixing is carried out in a well ventilated area
11. Apply the plaster to the designated areas as per work instructions
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 174/471
12. If working from step ladders follow the working at height procedure
13. Apply any finish coats following the procedures defined above
14. Keep the work area clean and tidy at all times, remove rubbish and debris as it accumulates
Plastering - Spraying
2. Ensure the area to be worked has been clearly signed and marked out with warning tape; if necessary erect
physical barriers to prevent unauthorized access
4. Unload the PFT G5 machine: ensure that you follow good manual handling techniques for heavy machinery
5. Prepare the area to be plastered removing any loose material, ensure the surface to be plastered is clean
6. Collect the required materials from the storage area; ensure that you follow good manual handling techniques for
heavy material such as 25kg plaster bags
7. Ensure the RCD is in the socket before connecting any electrical device
10. Ensure that dust is kept to a minimum during mixing and that mixing is carried out in a well ventilated area
13. Apply the plaster to the designated areas as per work instructions from top to bottom
14. If working from step ladders follow the working at height procedure
15. Keep the work area clean and tidy at all times; remove rubbish and debris as it accumulates
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 175/471
2. Fit the appropriate specified beads to the plasterboard
3. Mix hand trowel led gypsum by hand or mechanical paddle using a clean container, ensure all material in a batch
is mixed thoroughly
4. Ensure suitable ventilation during mixing, use local exhaust system to control dust or wear a half face mask to
9. Do not attempt to use any mix after initial set, and do not attempt to re-temper, discard all such mix immediately
10. Do not attempt to plaster where extremes of temperature or moisture will affect the finish
11. Make good any damage after completion of second fix and carpentry work
12. Remove all debris to designated area, leave area clean and tidy
3. Mix hand trowelled gypsum by hand or mechanical paddle using a clean container, ensure all material in a batch
is mixed thoroughly
4. Ensure that dust is kept to a minimum during mixing and that mixing is carried out in a well ventilated area
7. Do not attempt to use any mix after initial set, and do not attempt to re-temper, discard all such mix immediately
8. Do not attempt to plaster where extremes of temperature or moisture will affect the finish
9. Remove all debris to designated area, leave area clean and tidy
Tiling
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 176/471
1. Cover floor area and any furniture/fittings to prevent damage to goods
3. N.B. Chemical cleaners and work tools such as hot air strippers will not be left unattended in residential
properties, this is especially important where children are present
5. Ensure wall is clean dry and free from dust and contaminants
7. Ensure correct adhesive for type of tiles being applied, if necessary consult tile supplier
8. When doing full walls, shower enclosures etc hang a plumb line and mark to ensure good level of finished tiles
9. Mix sufficient adhesive to cover desired application area and apply to wall using flat side of trowel
10. Comb the adhesive to a uniform depth using the notched side of trowel
11. Fit spacers or wedges to top of sinks, shower trays etc to allow 3mm
15. Tiles will be cut where necessary using proprietary cutting tools. Notched, curved or quarter round cuts will be
done with a wet saw
17. Remove all waste and debris from site to designated area, site will be left clean and tidy at the end of each shift
19. Ensure floor area and any fittings are covered to prevent damage
21. Mix sufficient grout to cover required area, refer to manufacturers instructions
24. Allow grout to set for 20 minutes then wipe residue of with damp sponge cleaned regularly
25. Minimal clean-up water should be used to ensure proper grout curing and maintain colour uniformity
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 177/471
METHOD
STATEMENT
Activity : Plumbing
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Plumbing work
1. Liaise with other contractors and facilities manager to isolate water supplies
5. Ensure waste pipes and other plastic pipe work are connected correctly
6. Where plastic pipe is connected with solvents, staff will follow all safe use instructions
7. Where solder work has to be carried out, prepare pipe work for solder joints
8. Obtain the appropriate hot work permit from the facilities manager
9. Ensure the correct type of fire extinguisher is on hand during hot work
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 178/471
13. Check all joints
15. Carry out further checks for water tightness and quality of finish
16. Chlorinate the system if required and check for successful completion
19. Pack tools an equipment and leave area clean and tidy
20. Maintain fire watch for 2 to 4 hours where hot work has been carried out
1. Liaise with other contractors and facilities manager to isolate water supplies
5. Ensure waste pipes and other plastic pipe work are connected correctly
6. Where plastic pipe is connected with solvents, staff will follow all safe use instructions
7. Where solder work has to be carried out, prepare pipe work for solder joints
8. Obtain the appropriate hot work permit from the facilities manager
9. Ensure the correct type of fire extinguisher is on hand during hot work
15. Carry out further checks for water tightness and quality of finish
16. Chlorinate the system if required and check for successful completion
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 179/471
17. Request facilities manager to inspect works
19. Pack tools an equipment and leave area clean and tidy
20. Maintain fire watch for 2 to 4 hours where hot work has been carried out
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 180/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
1. All work is to be carried out under the direct supervision of competent operatives.
3. Form work and meshing to be positioned by mechanical means as far as practicable. The correct manual
handling techniques will be utilised by operatives at all times.
4. Where mesh requires cutting this will be done by bolt croppers where possible. Where disc cutters are used an
appropriate risk assessment must be conducted and available on site.
5. Concrete will be discharged directly into the form from ready mix truck through a concrete pump. A trained
banksman will aid in the positioning of the vehicle.
6. Operatives working on the vicinity of the wet concrete will wear wellington boots, trousers, long sleeves, gloves
and eye protection.
7. Vibrating pokers, screed beams and powerfloats are only to be used by trained persons, appropriate ear
protection is to be worn by those operating the equipment and in the immediate area.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 181/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Start of works
1) Report to site office and inform site manager of arrival, or in occupied properties Inform tenant and other
occupants of work commencing.
2) Cordon off work area if practical to do so. Particular attention should be paid to property where children
are present; children and adults must be kept away from the work area at all times and protected from dangers of
power tools and substances.
4) Ensure the area to be prepared and exit points are clear of obstruction and that safe access and egress
is maintained.
5) Check any electrical or hand tools for damage or faults, faulty or damaged tools must be removed from
service immediately.
6) Place tools and equipment in safe storage near the work area
7) Large and/or heavy items will be tandem lifted; do not lift beyond your capabilities.
2) The sub floor must be sound, dry, free from cracks, clean and free from materials that would impair adhesion.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 182/471
3) Remove existing floor covering if necessary
4) Sweep and vacuum the floor and ensure it is free from dust and loose debris
6) Test the sub floor with a hygrometer and ensure a relative humidity reading of no more than 75%
8) Mix the self levelling cement compound in a bucket in the ratio of 6 litres per 25kg bag
10)Pour onto primed surface and distribute evenly with a smoothing trowel or screeding rake
1) Wooden Floors must be structurally sound, level, smooth, dry and clean.
2) Worn or uneven floorboards should either be replaced or levelled by sanding, planning or by patch filling
3) The floor will then be covered with flooring grade plywood or hardboard.
4) Sheets should be positioned, joints staggered and fixed with the staple gun at 100mm - 150mm centres.
1) Check carpet for colour, quantity, and batch and roll sizes against your order before cutting.
4) Spread Styccobond F3 or other approved adhesive with the recommended 'V' notched trowel (2.4mm x
4.75mm). The coverage rate should be 12-15m 2/5 litres.
5) Carpet must be 100% adhered to the sub floor ' no spot gluing.
7) Place the carpet and press from the centre outwards to exclude air and ensure overall contact with the
adhesive.
1) Check carpet for colour, quantity, batch and roll sizes against your order before cutting
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 183/471
2) Fit Gripper around perimeter of each room, fit door bars where required
1) Check flooring packs for colour quantity and batch numbers against order
10) Clip flooring together and knock into place with an angle block to ensure good jointing
12) Fit quadrant beading around edge of room and skirting boards
1) Check tiles for colour, quantity and batch numbers against order
5)
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 184/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
1 Soft strip the building of carpets, other floor finishes and any furniture.
4 Form openings in timber stud partitions, by cutting and removing the timbers and plasterboard. And remove to
skips provided.
5 Form opening in non-loadbearing brick walls by propping any wall to remain, remove a section to install a lintel,
then carefully remove the rest of the wall.
6 Form opening in load bearing walls or removal of loadbearing walls by assessing the extent of what the wall is
supporting.
Mortar in the steel beam and temporary prop whilst the mortar cures.
Cut down the wall using a disc cutter with water suppression to prevent dust.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 185/471
Make good to all surfaces.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 186/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
1. Existing roof covering will be stripped by hand. Slate sand tiles will be stacked
and lowered by hoist or via rubbish chute.
2. Skip to be situated within secure compound.
3. Battens will stripped and de-nailed ensuring operatives fall protection at all
times.
4. Battens will be bundled up, de-nailed and lowered to ground via hoist.
5. Existing felt will be bagged and placed within the rubbish chute or bagged and
lowered via hoist.
6. Roof timbers will be inspected and any defects reported to CA for further
instruction.
7. New felt will be fixed to rafters with specified nails.
8. Roof will be fly battened to ensure roof remains water tight ahead of installation
of tiling battens.
9. New treated timber battens will be fixed to rafter sin accordance with
manufacturers recommendations.
10. New slates or tiles will be raised to roof level via hoist.
11. Slates or tiles will be loaded out onto roof battens in preparation for fixing.
12. Slates or tiles will be laid as manufacturers recommendations. Slates or tiles will
be fixed by nailing at required courses.
13. Mortar will be mixed at ground floor level and raised to roof level via hoist
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 187/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
2. The site foreman will ensure a handover certificate is received from the contractor prior to allowing access to
the scaffold.
3. During the works access to the scaffold will be via ladder which will be tied off at the top, ladders will be
removed or boarded off at the end of each shift to prevent unauthorised access.
4. Inspections shall be carried out before the scaffold is put into use for the first time and also after any event that
has affected stability or at a period not exceeding 7 days.
5. Reports of inspections shall be given to the responsible person who will keep reports on site for the duration of
the contract and for 3 months after the end of the contract.
6. No one shall be allowed access to the scaffold if the inspection finds any faults.
7. The delivery vehicle will be parked as close as practicable to minimise the distance needed to carry the
scaffold poles.
8. The site will be inspected to ensure that the ground is capable of taking the weight of the scaffold, and that
there are no voids
9. Any access points will be noted and kept clear where practically possible.
10. Dependant on the type of scaffold being erected it will be tied into the building at prescribed intervals.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 188/471
12. Access ladders will be blocked off when the scaffold is incomplete or not ready for use.
14. The scaffold will be signed off and a certificate issued when the scaffold is ready for use.
15. A weekly inspection by competent person will be made to ensure the security of the scaffold.
16. Dismantling will start from the upper levels and scaffold poles will be passed down manually to the level below.
17. All connection pieces will be passed (not thrown) and collected in buckets or other suitable receptacles.
18. All poles will be loaded and secured on the lorry for removal from site.
19. Scaffolds erected / dismantled as per NASC guidance TG20:13 and in accordance with the requirements of BS
EN 12811-1.
20. All scaffolding operatives wear and use personal fall arrest equipment (harnesses, etc) at all times in
accordance with NASC guidance SG4:15.Personal fall protection equipment complies with BS EN 361 (full body
harnesses), BS EN 354 (lanyards), BS EN 362 (connectors), BS EN 355 (Energy absorbers).
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 189/471
METHOD
STATEMENT
Activity : Scaffolding
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Task/Operation:
Provide independent access scaffold to enable safeaccess to undertake works in accordance with the specification.
Method Statement
Specialist subcontractors will be employed to erect the Scaffolding and will provide their own detailed Risk
Assessments and Method statements
Warning signs and barriers will be used to segregate the work area.
Materials to form the independent scaffold will be lifted by hand or by manual hoist.
Once the access scaffold is formed handrails will be installed at roof level to provide safe edge protection
for the intended roof works.
The scaffold will be fully enclosed in mesh or sheeting to contain debris and water.
All standards at ground floor level shall be sleeved with hi vis foam.
Fully trained, experienced operatives will undertake these works.
Hand-over certificate to be issued upon completion.
Environmental Issues (give details)
Ensuring the area of activity is adequately segregated from members of the public.
Identification of Control Measures following Risk Assessment
Erect barriers/warning signs at ground level
Only NASC accredited scaffold operatives to undertake works
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 190/471
Correct lifting techniques to be used
Appropriate PPE such as hard hats, safety footwear and fall arrest harnesses will be worn
Emergency Procedures
In the event of incident the emergency services shall be contacted details in the H&S plan.
All works shall cease and the area will be cordoned off if the area represents a risk to health and safety.
Scaffolds erected / dismantled as per NASC guidance TG20:13 and in accordance with the requirements of
BS EN 12811-1.
All scaffolding operatives wear and use personal fall arrest equipment (harnesses, etc) at all times in
accordance with NASC guidance SG4:15.Personal fall protection equipment complies with BS EN 361 (full
body harnesses), BS EN 354 (lanyards), BS EN 362 (connectors), BS EN 355 (Energy absorbers).
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 191/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Start of works
1) Report to site office and inform site manager of arrival, or in occupied properties Inform tenant and other
occupants of work commencing.
2) Cordon off work area if practical to do so. Particular attention should be paid to property where children
are present; children and adults must be kept away from the work area at all times and protected from dangers of
power tools and substances.
4) Ensure the area to be prepared and exit points are clear of obstruction and that safe access and egress
is maintained.
5) Check any electrical or hand tools for damage or faults, faulty or damaged tools must be removed from
service immediately.
6) Place tools and equipment in safe storage near the work area
7) Large and/or heavy items will be tandem lifted; do not lift beyond your capabilities.
2) The sub floor must be sound, dry, free from cracks, clean and free from materials that would impair adhesion.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 192/471
3) Remove existing floor covering if necessary
4) Sweep and vacuum the floor and ensure it is free from dust and loose debris
6) Test the sub floor with a hygrometer and ensure a relative humidity reading of no more than 75%
8) Mix the cement screeding compound in a bucket in the ratio of 6 litres per 25kg bag
10)Pour onto primed surface and distribute evenly with a smoothing trowel or screeding rake
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 193/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Cordon off area to be worked in and notify persons within buildings of activities being carried out. Ensure all PPE is
in place and of good quality.
Controlled Access
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 194/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 195/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
b. Deliveryof Goods
c. Welfarefacilities
d. WasteManagement
e. TrafficManagement
f. AccessControl
g. FireManagement
h. LogisticsOperatives
i. FirstAid Provision
j. WelfareServices / Management
k. HoistOperators
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 196/471
l. Provisionand maintenance of fire extinguishers and associated Equipment
p. PersonnelProtective Equipment
3. Access Control
Before any works commence all operatives will receive a siteinduction and issued with a security pass.
The CompanyName Logistics Manager will then give all operatives an Company Name Company(site specific)
Induction, for which they will sign Company Name Induction register.
The Logistics Manager will issue any PPE that is prescribedor that is required for the Logistics work, (goggles,
gloves, ear defenders,masks etc.).
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 197/471
Once completed, all operatives will be given a toolbox talkon relevant method statements and all associated risk
assessments andapplicable COSHH and manual handling assessments. The toolbox talk will not begiven as read,
but will highlight the major safety requirements of the methodstatement and the required safe systems of work.
The operatives will then be informed of the specific riskshighlighted through the assessments carried out and how
we require theoperatives to actively participate in implementing the assessed controlmeasures. The Logistics
Manager will then ask all operatives if they understandwhat has been told to them and if they want to ask any
questions about themethod statement and risks assessed.
When finished, all operatives will then sign the toolboxtalk register to confirm their understanding of the method
statement and riskassessments and to prove that the talk has actually taken place.
The Logistics Manager will then issue a copy of this methodstatement and risk assessments as a term of reference
for them. A copy of thiswill also be placed in the work area for any person to view or refer to.
The first activity will be for the Logistics Manager tosurvey the required working area(s) to ensure that there are no
major hazardsthat will affect the Logistics operatives. The Logistics Manager will belooking for slip, trip & fall
hazards, he will also be ensuring that thereis safe access and egress to the place of work and that there is no
interfacethat would compromise Alandale or any other third party.
If there are any interface problems or specific risk thenthis will be brought to the attention of those concerned
before work commences.Once satisfied, the Logistics Manager will allow the Logistics operatives worksto
commence.
Where the works may cause hazards to a third party the workarea(s) will be segregated to ensure that no
unauthorised persons can enter thearea. This will be achieved by means of physical barriers in the form of
eitherscaffolding or pedestrian barriers. Strategically placed signage will be placedto warn all others of our
presence and our work intentions. The entire areawill then be checked by the Logistics Manager to ensure the
integrity of thebarriers and to ensure that it is sufficient to protect and warn all thirdparties and provide
CompanyName with adequate working boundaries for the operations.
Logistics Operatives
The mainduties of the Logistics operatives will be keeping the site clean and tidy atall times. They will ensure that
no materials or rubbish is stored or stackedin fire exits or escape corridors. The operatives will also remove all
fullwheelie bins to the collection point.
A Toolbox talk will be provided on Manual handling, correctusage of bins and the risks involved with loading out
and transporting waste inwheelie bins. Operatives will be instructed to be constantly aware ofprotruding objects and
to visually inspect the bins on a regular basis,reporting any damage to the Logistics Manager for immediate
replacement orrepair. The bins will be regularly monitored for types of waste, fullness andsafety loadings.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 198/471
Operatives will be informed by the Logistics Manager which areasare unauthorised at particular times during the
course of the project.
Welfare Operatives
Welfare operativeswill be provided to carry out the cleaning and maintenance of all toilets,urinals and sinks and to
keep the cubicles fully stocked with toilet tissue andwash areas with soap and hand towels. Whererequired
COSHH Assessments will be carried out for all relevant cleaningmaterials used and the necessary PPE will be
issued. Toolbox talks will becarried out weekly and recorded accordingly.
COSHH cleaningagents will be stored in a lockable container when not being used which is tobe secured at all
times.
Hoist Drivers
Onlyqualified Hoist Operators are to operate the hoists. Copies of relevantcertificates are to be held in the Logistics
Office. Prior to operation allHoist Operatives are to receive instructions on the method of operation andrelevant risk
assessments.
Ahoist-lifting plan (including emergency procedures), will be drafted,communicated to the hoist operators and
displayed within the hoist.
Hoistdriver are to carryout daily inspections of hoists and report any faults to theLogistics Manager. Should any
faults found of a serious nature, the hoist willcease operation until the fault has been rectified by the hoist
installers.
All hoistoperators will receive a site inducted and be fully aware of site fireprocedures. They are required to wear
PPE at all times.
At no timewill the hoist be left unattended during working hours, i.e. 8 am 6 pm.Monday to Friday and 8 am 1.30pm
Saturday. When the hoist is not required,power will be isolated and the hoist padlocked shut.
Fire Marshall
The FireMarshall will be fully trained (a copy of his certificate will be held on sitein the site health and safety file).
Prior to commencing their duties they areto attend a site inducted and be issued with and wear the relevant PPE at
alltimes.
They willbe responsible for carrying out daily checks on all fire points and fire /evacuation signage together with any
other tasks as specified by the LogisticsManager
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 199/471
They areto check the fire points for general condition / expiry dates / signs oftampering or abuse, ensuring that the
appropriate signage is in place (fireplan / fire action / types of extinguisher / assembly points etc.) and that
anywarning media is visible and working correctly (bell / klaxon / break glassactivators) and will report to the
Logistics Manager if any damage orreplacements are required.
They arealso to ensure all escape routes and fire exit doors are kept clear at alltimes.
They areto be fully aware of the site fire plan and will assist in the practiseevacuations and fire alarm tests.
The firemarshall will also issue and monitor all permits to work, ensuring that thecorrect procedures are followed
and signed off when complete. Any offenders areto be notified to the Logistics Manager.
Traffic Management
TheLogistics team will provide fully trained traffic management operatives for thepurpose of traffic control and
management during deliveries.
As thesite is situated in a very busy area, good traffic control is vital. This is where a strict delivery bookingregime
must be implemented.
All tradecontractors shall adhere to a booking in system for deliveries that willrequire notification 48 hours in
advance.
On arrivalthey will report to Security who in turn will inform the appropriate contractorwho will in turn provide
operatives to unload the delivery.
There willbe no provision for waiting vehicles; therefore any deliveries that arriveunannounced will be turned away.
Anypackaging or ties relating to deliveries must be the sole responsibility of thecontractor involved.
As thesecurity guards are the first point of contact for deliveries to site weintend to train the guards as traffic
management operatives as this willbenefit the efficiency of the throughput of deliveries and will ensure that
thetraffic management is implemented safely.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 200/471
TwoBanksmen will be required for the manoeuvring of vehicles into and out of site this is to assist in the reversing
in of the vehicles and the introduction ofthe vehicle back into the busy traffic.
Aspreviously mentioned at no time are banksmen to become enclosed or trappedwhen reversing vehicles an
escape point must always be available and thiswill be surveyed and implemented by the Logistics Manager who
will constantlymonitor the working procedures of the banksmen.
A riskassessment will be carried out for this operation which will take into accountall generic, specific residual and
environmental hazards associated with thistask.
Waste Management
A wheeliebin method will be used for removing waste from site. There will be binsallocated to each floor in pre-
designated locations; bins will be moved fromdifferent floors within the building by means of the hoist.
All binswhen full will be transferred to a pre-designated removal area for collectionby the Approved Waste
Contractor.
During theemptying process, a suitably trained (by induction / toolbox talk) operativewill assist the driver to firmly
locate the bins to the lifting mechanism ofthe compactor the bin must be properly located into place on the
liftingdevice prior to lifting.
Bins willbe pushed to the rear of the compactor unit no bins are to be located nearthe compactor during its
manoeuvring emptying of bins will not be permitteduntil the compactor has completely stopped and the driver has
secured thevehicle.
Once thebin is ready to be lifted all persons (including the driver) must keep clearof the lift (to the side) until the bin
is emptied and placed back on theground..
Riskassessments on Manual Handling and the Movement of Bins have been carried out andthe results
communicated kept on site in the safety file.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 201/471
Allcurrent test certificates for the lifting mechanism will be gained from theWaste Management Company by the
Logistics Manager this will also includeservicing records for the compactor and for the general road-worthiness of
thecompactor.
Trafficcones and bunting tape will be placed as required around the vehicle during theloading operations.
Uponcompletion of the loading and the subsequent departure of the compactor, thetraffic cones and bunting will be
removed and the general area around theoperation will be completely cleared of any residual spoil or rubbish, and
willbe maintained in a satisfactory condition.
Since thesite is located in a very busy and densely populated area, particular care mustbe given to the
management and control of the general public ensuring theirsafety as a priority at all times.
Stringentsteps will be taken to minimise disruption to the general public (bothpedestrians and motorists).
The Site Logistics Managers will be responsible for the Management and Safety of the following Persons /
Procedures / Tasks:
1. Logistics Operatives
5. Fire Marshalling
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 202/471
All of the above management will play an active role in the supervision and management of the Health and Safety
on site.
The following Key Work activities have been identified as requiring Risk Assessments to be carried out :
The key risks to operatives health and safety have been identified as follows:
a. Manual handling
A register containing relevant risk assessments which contain details of the key safety control measures and
precautions to be implemented to control the health and safety risks will be located in the site office.
The company is committed to providing a safe place of work and a safe means of access and egress within all
parts of the workplace. Safe access and egress includes movement in and out of the workplace, and safe access
within the workplace. The Site Manager / Supervisor is responsible for implementing this policy
To ensure adequate illumination during the refurbishment programme the existing lighting will be utilised and
additional 110V lighting will be provided as required in work areas.
A register of plant and equipment will be kept in the site office. It Is envisaged that only small hand tools will be
used and these will all be PAT tested prior to being brought to site.
Where required statutory test/examination certificates will be available on site, together with copies of relevant
training/competence certificates for plant and equipment operators.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 203/471
Tool box talks will be given to operators of hand tools prior to commencement of works to ensure their correct use
and that operators are aware of the safety implications.
A project specific training register which identifies operations / activities requiring specific training certification for
work personnel will be kept on site.
No hazardous materials or substances have been identified at this time and therefore it is anticipated that a register
will not be required.
Should any hazardous materials or substances be identified the necessary COSHH assessments will be carried out
and a register completed which will be available in the site office.
The register will contain the key measures and precautions to be implemented to control the risk to health.
During the store refurbishment the Logistics team will keep the workplace clean and tidy, and ensure the
segregation of Plaster Board and COSHH waste. All waste will be logged using the SmartWaste system.
Special Waste:
A special waste bin will be provided in the loading bay area this bin will be individually identified as a special waste
bin and will be fitted with a lockable lid.
This bin will be removed as a separate item and will be disposed of to a licensed / registered waste disposal site.
As previously mentioned the duty of care provisions will be adhered to and the relevant consignment notes will be
gained for the disposal of all special waste.
The Logistics Manager will constantly monitor work activities for safety, and compliance with the Method
Statement /Risk Assessments.
A first aid box will be kept in the Logistics Office for minor accidents. In the event of a serious injury the emergency
services will be contacted by either a member of security or the Logistics team who will provide assistance where
necessary, The key for the first aid room will be kept in security along with a register containing contact names and
numbers for all First Aiders on site.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 204/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
2) Site manager to conduct induction of staff, to include all safety talks and actions and restrictions as agreed
with owners of adjacent properties
5) Large and/or heavy items will be assessed prior to lifting and if necessary carried by two persons
6) Equipment and materials are ordered as and when required for construction
2) Scaffold will be erected from the ground and tied into the brick work or secured through available window
openings
3) Scaffold will be erected to up to eaves level and the handrail will extend a minimum of 1 metre above
4) All kick boards etc will be supplied to prevent falling of tools and material
6) Scaffolding contractors will return to the property to carry out any alterations or extension as required
when the job progresses
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 205/471
7) The scaffolding contractor will hand over a completion certificate prior to allowing access to the scaffold
8) The site foreman will be responsible for inspecting the scaffold on a daily basis and ensuring its
continued adequacy
1) Ensure adequate fall protection has been provided i.e. safety nets
3) Install 100mm Celotex XR3000 or other suitable Insulation between rafters ensuring a 50mm ventilation
gap
4) Fit a further 40mm Celotex XR3000 or other suitable insulation across face
6) Working from the bottom up fix breathable membrane underlay across the rafters and temp nail in
position
7) Fix by nailing 50mm x 25mm treated timber battens across the rafters over the top of the breathable
membrane
8) Ensure knots are removed from the timber battens and battens are joined on the centre line of the rafters
9) Roll out the next length ensuring the correct amount of lap 100mm for pitches of 35° or steeper,
150mm for 15° to 34° and 225mm for 12.5° - 14° and temp nail in position
10) Fix timber battens as above and work up the roof to the ridge on both sides
13) Work up the roof at 45 ° angle ensuring safe access at all times
15) Fit ridge tiles to roof ridge and bed on cement mortar mix
16) Install Velux escape windows as per manufacturers instructions where required
5) It is not anticipated that there will be any damage however if any occurs it will be repaired immediately by
the roofing contractor
6) Clear all tools and equipment from the site leaving clean and tidy
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 206/471
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 207/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Objectives:
The objective of this task is to strip out and remove the existing internal fabrications.
Existing Environment:
Then from the entrance of the site, the operatives will require a Safe Route" to the staircase that lead to the third
floor welfare facilities (depending of where the current welfare facilities are - these will be moved around site to
suitable locations to suit scope of works.
This safe route will consist of a demarcated clean route", and will be created as a priority, with the intention of
stripping out the required surrounding fabrication, as soon as possible, but with the minimal disruption to the main
access egress to the site and without causing any hazards to the operatives using the route, therefore the strip out
works in these areas will be controlled and isolated where required.
The reason for this is because TWA will be taking occupancy of the third floor, and due to security reasons, will be
restricted access.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 208/471
Because of this restriction, and the need to be able to gain access to the welfare facilities within the TWA area (to
gain the required PPE) there will be the requirement for this safe route.
Once the required PPE is gained, All operatives will then return to the second floor work area.
Because the building is occupied and will remain so, there is the constant hazard of interfaces between ourselves
and the staff within the building.
This possible interface will be constantly monitored by Company Name Management, and if not sufficiently
controlled within this method statement, then an addendum will be drafted to supplement this method statement.
The initial foreseeable interfaces, are to the preliminary strip out works, where 50% of the second floor will remain
occupied, whilst we are carrying out the strip out to the remaining 50% of the floor.
This will be controlled by the placement of temporary pedestrian barriers and warning signage.
Company Name Management will also draft a memo to the remaining staff to inform them of our works, intentions
and the procedure in the event of an emergency which will basically mean that in the event of a fire, that the staff
will be permitted to enter the site area to gain escape if no other means of escape is available - only.
This will also work in the alternative that is to say that the site operatives would be able to escape through the live
area if the means of escape is blocked / unreachable.
Another possible interface area will be the lifts, which will be the common means of access, but will be of a minimal
basis as this will be for access means only.
Other interfaces will involve the use of the goods lift this will be on a good will basis and Company Name
Management will ensure the tenants have priority of the use of the goods lift.
Company Name will only use the lift when absolutely necessary, and will wait until the lift is no longer required / not
in use before utilising we will also ensure the safety of any third parties, during the use of the goods lift, this will be
implemented, with the use of a dedicated banksman.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 209/471
His duties will be to constantly monitor the construction activities, and to ensure the protection and integrity of the
general public / staff at all times.
Supervision:
The supervision that will be present for this task will be:
Name - Supervisor
All of the above Management will play an active role in the supervision and management of the Health and Safety
on site.
Sequence Of Works :
1. Before any works commence all operatives will receive a site induction from Mace from which each
operative will be registered.
1.1 The Company Name Site Manager will then after this induction, give all operatives a Company Name
specific Induction, afterwhich they will sign Company Name Induction register to confirm their understanding of the
given induction.
1.2 After signing the induction register, all persons will be given an Company Name Induction helmet
sticker, which states the operatives name, specific ACL Job No, date of induction and the Site Managers
signature, they will then place the label to the helmet to show all concerned parties that they have been
inducted.
1.3 The site manager will, as he is issuing the labels, will check that all persons are wearing site prescribed
Personal Protective Equipment, if they are not then they will be issued with the appropriate equipment.
no person will be permitted into the site confines without the site prescribed PPE.
1.4 The site manager will then issue any PPE that is required over and above the prescribed, that
is required for the strip out work, (goggles, gloves, ear defenders Etc.).
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 210/471
1.5 Once completed all operatives will be given a toolbox talk on this method statement and all
associated risk assessments and applicable COSHH and manual handling assessments,
1.6 The toolbox talk will not be given as read, but will highlight the major safety requirements of
this method statement and the required safe systems of work created, the purpose of this is to ensure that the
operatives receive the most valuable and important safety
1.7 The operatives will then be informed of the specific risks highlighted through the
assessments carried out and how we require the operatives to actively participate in implementing the
assessed control measures.
1.8 The site manager will then ask all operatives if they understand what has been told to them and if they
want to ask any questions about the method statement and risks assessed.
1.9 When finished, all operatives will then sign the toolbox talk register to confirm their understanding of
the method statement and risk assessments and to prove that the talk has actually taken place.
1.10 The site manager will then issue to all operatives a copy of this method statement and risk
assessments as a term of reference for them.
1.11 A copy of this will also be placed in the work area for any person to view or refer to.
2.1 The first activity will be for the site manager to survey the required area(s) to ensure that there are no major
hazards that will affect the commencement of the works.
2.2 The site manager will be looking for slip, trip & fall hazards, he will also be ensuring that there are no
hazardous materials and checking that all existing services are isolated, this will be accomplished through receiving
a copy of the minor works isolation certificate from Mace (through the electrical contractor) he will also be ensuring
that there is safe access and egress to the place of work and that there is no interface that would compromise
Company Name or any other third party.
2.3 If there were any interface problems or specific risk then this will be brought to the attention of Mace
before works begin.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 211/471
Once satisfied, the site manager will allow works to commence.
3.1 The next activity will be to encapsulate the work area to ensure that no unauthorised persons can enter
the area.
3.2 This will be achieved by means of physical barriers in the form of pedestrian barriers and warning
signage.
3.3 We will then use strategically placed prominent signage, to warn all others of our presence and our works /
intentions, and as previously mentioned, a memo will be drafted and circulated to the remaining staff of the level.
3.4 This will be implemented at every accessible entry to the work site.
3.5 The entire area will then be checked by the site manager to ensure the integrity of the barriers and to
ensure that it is sufficient to protect and warn all third parties and provide Company Name with adequate
working boundaries to for the operation.
3.6.1 Prior to commencement of any works Mace will copy all relevant certification as regards to mechanical /
electrical isolation for the works area or if Hazardous materials are identified I.E (asbestos etc) again Mace will
issue relevant certification stating what and where any hazardous materials are located or that all known hazardous
have been removed / made safe prior to ACL commencement on site.
3.6.2 Once ACL have all the current certification, works will start. Due to the sensitive nature of some of the
works, the exact sequencing of the works is not known, and will be carried out on a day to day basis.
3.6.3 Because of this, the supervisor, Company Name Manager and Mace Management, will agree all areas of
works, prior to commencement.
3.6.4 The strip out work for this project requires the following items to be removed:
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 212/471
Drylined demountable partitioning
All redundant services 1st and 2nd fix electrics / mechanical items / Sanitaryware
Glazed Units:
These will be carefully removed as a whole unit, and will require two persons for each unit being removed.
Operatives will ensure that the entire area is clear of persons / obstructions, prior to commencement, and will have
a holding area ready prior to removal.
As soon as works begin operatives will wear gloves, goggles, and will be fully clothed (long sleeves etc.) as a
precautionary measure.
The units are held in frames, and are removed by unclipping the retaining bead from the frame.
One operative will remove the beads, whilst the other holds the unit in its position to prevent the unit falling out.
Once the beads are removed, both operatives will take the weight of the unit, (which is of an moderate weight /
size), and lower the unit to the ground taking care at all times.
During this operation, the supervisor will be monitoring the works ensuring that the area remains clear and free of
third parties at all times.
Once lowered to the ground, the unit will be positioned in a safe place ready for later disposal.
Drylining:
The supervisor is to ensure that all services are isolated prior to removal of the partitions.
As previously mentioned, the majority of the drylining is demountable, and will therefore be removed
sectionally and unscrewed as opposed to breaking out.
Operatives will wear gloves, goggles and if necessary masks during the removal works this will be monitored by the
supervisor & ACL manager.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 213/471
The board will be stacked in reasonable sizes, in a safe area for later disposal.
Once the skins of the partition have been removed, the remaining frame / track will be removed.
This will be carried out by cold methods as much as possible eg. By unscrewing or with the use of a pair of snips /
hacksaw.
When a unit has been dismantled, the arisings will be disposed of to the skip area.
Redundant Services:
(once confirmed as isolated) the remaining services, containment, wireways and associated
These will be erected by a competent person and inspected by Company Name manager, who will ensure that a
Company Name mobile tower scafftag is used.
This acts as a checklist for the erector and is signed by both the erector and the user has both parties have
responsibilities for the tower and its use.
All persons will be aware of the remote possibility of the discovery of hazardous material during these works, and
will stop immedietely if suspicion is raised by a insulkation material.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 214/471
Trunking / ducting / mechanical items will be removed sectionally and lowered to the ground carefully.
Basic PPE for this task will be gloves / goggles / hard hat / boots etc.
Where grinding is used to remove items, the area will be cleared of any combustible materials / operative will wear
goggles / mask and will have a banksman present to act as a fire watch, and to protect third parties.
Goggles / gloves (impervious) / masks (where necessary) / Hard hats and steel toecap boots will be worn at all
times.
Very good personal hygiene will be required at all times and this must be given to the operatives as a toolbox talk.
All PPE must be disposed off each day and replaced with new.
Joinery:
All timber removal will be done by operatives using nail bars to lever doors / architraves / timber skirtings, box outs,
etc.
Gloves / goggles hard hat and boots will be worn at all times.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 215/471
All timber will be de-nailed as necessary and no protruding screws / nails will be left by the operatives.
Timber will be removed progressively, to prevent a build up of combustible materials on site, and will never be left
on site overnight.
All doors / heavy items will be removed / disposed of by two operatives at all times.
Finishes:
All wallpaper will be removed by stripping of the walls, this will be bagged immediately, and again constantly
removed from site, as a combustible material,
Wall / floor Tiles will be removed using a hammer and bolster goggles and gloves must be worn at all times during
this operation, as well as the normal site PPE.
And all work areas must be isolated to prevent unauthorised access into the areas.
Ceiling tiles will be removed using a mobile tower - to the controls previously mentioned.
Operatives will wear masks and goggles during these works due to the dusty nature of the operation.
Operatives will also ensure that hard hats remain worn during this operation, due to the possibility of items being
above the ceiling tiles.
Where towers cannot be used, stepladders will be introduced, this will be a last resort, and operatives will be given
a toolbox talk on the safe use of stepladders, and this will be recorded on to a register, and the use of the ladders
monitored.
This will include correct ascent / descent full extension of the ladders one hand holding to the ladder at all times
correct footing - not overstretching or working above the top fourth rung of the ladder etc.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 216/471
All tile debris will be loaded into bags and relocated in another room adjacent to the work area, until sufficient is
ready to be taken to the skip area.
Operatives will place debris into bags / wheel barrows by hand or using shovels, all operatives will
wear gloves to prevent injury to hands whilst disposing of debris, goggles and masks will also be
Once the tiles have been removed, the remaining grids will dismantled by hand where possible and the main
perimeter grid, levered form the perimeter wall and again disposed of.
3.9 All electrical equipment will be visually inspected by the user, and will be tested and certificated prior to its
use on site, (along with leads).
Any equipment which is found to be not functioning correctly will be replaced immediately.
Operatives not involved with the works shall be informed not to enter the works area, operatives
clearing the debris shall not enter into or under the works until advised by the supervisor that it is
clear that works over head has ceased and it is safe to do so.
ACL shall display signage at the relevant entrance points to the works area informing all operatives
Debris will be loaded into wheel barrows by operatives using shovels,this will then be disposed of
as previously described.
Any raised flooring will be lifted and stacked onto wheeled trolley operatives will then pull the trolley to
Removal of the flooring will commence from the far end of the room, retaining the trolley on the raised floor area at
all times until complete.
The supporting stools will be removed by an operative using a sledge hammer, these will be placed
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 217/471
4.0 IT WILL BE POLICY OF Company Name TO ENSURE THAT UNDER NO CIRCUMSTANCES ARE ANY
PERSONS TO WORK OR BE POSITIONED DIRECTLY UNDER ANY DEMOLITION OPERATIONS.
ANY PERSON DISREGARDING THIS SIMPLE DUTY WILL BE REMOVED FROM SITE BY
Grinding operations - a 110v angle grinder will be used for all grinding / cutting operations
which will be tested and certificated and all blade changes, carried out by a trained abrasive wheel
mounter.
An hot works permit will be gained for each operation from Mace Management and at least two
extinguishers of the correct type for the works (water / Co2) will be present with a nominated person
Oxy / acetylene, if required for larger removal works. the following controls will be implemented, all cylinders will be
in good condition and all connections / regulators / flash back
arrestors / hoses / appliances will be in good condition and visually inspected for integrity.
A extinguisher will be positioned at the cylinders at all times and the equipment will be used by a
Manual Handling:
A large majority of the works involve Manual Handling and Company Name will be aware of this.
To minimise the hazard concerning Kinetic Lifting, Company Name Management will adopt the following
procedures.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 218/471
Mechanical Means will be used wherever practicable
Any lifting will be assessed in compliance with the Manual Handling Operations Regulations 1992
Plant:
All Company Name plant is checked prior to it arriving on site to ensure that 'Test Dates' are current and that
equipment has been tested and certified as safe prior to issue to the site.
Company Name Plant Manager(a qualified Portable Appliance Tester) carries out a full visual inspection of
the equipment, which is followed by a thorough test of the equipments earth bonding, insulation
resistance and continuity, this is carried out using a calibrated Proprietary Portable Appliance Tester. Any Plant
that is Procured through a plant hire company will be specifically requested to supply upon
The details of all plant will be entered into the site plant register.
Throughout the entirety of the project all plant shall be selected by Company Name Site Management who have
the upmost experience and considered very competent to select all plant required. If a specialist task arises
Company Name shall take professional advice from a reputable manufacturer or supplier.
All hired plant will not be accepted without an upto date P.A.T. certificate
All plant will be maintained and kept in good working condition, this will be achieved by one of
Company Name qualified Portable Appliance Testers regularly visiting site (at the site managements
All plant issued by Company Name Construction Ltd will have as a minimum these requirements and
registered in the site register. When not it use, all plant will be safely stored
in a lockable container.
All plant test certificates will be held in the site Health and Safety File (plant register section), the Site
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 219/471
Safety co-ordinator shall be responsible for the checking of plant certificates (before use) and the
All guidelines and practises as above will be stringently followed by Company Name Construction Manager,
all plant will be constantly supervised and replaced/repaired as necessary and the relevant statutory
4.2 Any Dust will be periodically dampened with water to keep levels to a minimum.
4.3 Noise will be monitored by the management and if necessary the noise levels will be taken and an
assessment will be carried out, and the appropriate controls put into place.
4.4 Good personal hygiene will be essential (especially during the sanitaryware removal) and operatives will be
required to wash thoroughly after each shift, gloves must be worn when handling debris and care must be taken to
avoid sharp objects, dirt, debris Etc.
4.5 The site management will inspect the intended work area before works begin and ensure that any
walls / structures etc. are safe to remove and that all safety procedures are in place and all third
4.2 Any Dust will be periodically dampened with water to keep levels to a minimum.
4.3 Noise will be monitored by the management and if necessary the noise levels will be taken and
an assessment will be carried out, and the appropriate controls put into place.
4.4 Good personal hygiene will be essential (especially during the sanitaryware removal) and operatives will be
required to wash thoroughly after each shift, gloves must be worn when handling debris and care must be taken to
avoid sharp objects, dirt, debris Etc.
4.5 The site management will inspect the intended work area before works begin and ensure that any
walls / structures etc. are safe to remove and that all safety procedures are in place and all third
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 220/471
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 221/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
1) Site foreman will ensure site is safe to commence work, Tenants have been warned and barriers
erected to prevent unauthorised access where necessary
2) On main contractor sites, staff will report to site office and receive permits to work etc
5) Site foreman will inspect the gas torch and cylinders and ensure proper connection to gauges and
pipes.
8) Lead will be lifted to work area following good manual handling procedures
10) Lead sheeting will be worked and dressed into position using a combination of Oxy-Propane heating
torch and dressing tools
12) All hot work precautions will be taken including; fire watchman, fire extinguishers to hand etc. Where
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 222/471
hot work is carried out near existing structures, care will be taken to protect from heat damage by the use of heat
shields etc
5) It is not anticipated that there will be any damage however if any occurs it will be repaired immediately by
the roofing contractor
6) Clear all tools and equipment from the site leaving clean and tidy
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 223/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
1. Put on the correct PPE safety boots, hi-vis, hard hat and gloves, ensure intensity and direction of lighting is
suitable to enable a satisfactory finish. Task lighting to be used where required, safety lighting to be installed by
MC.
2. Operative will ensure that all boards are securely fixed with no steps between adjacent boards.
3. Ensure boards have no protruding screws or broken paper as this can create an uneven finish. Contact the DPM
site manager in the event of this occurring. Do not continue with works until surfaces are fit for purpose
5. Fix the appropriate specified beads to the plasterboard using a Stanley staple gun. Contact DPM site manager
should any of the plasterboard be protruding. Do not continue with beading until these have been rectified.
6. Scrim tape must be applied to vertical plasterboard butt joints and paper tape applied to internal corners. All
beads also to receive fibre scrim tape
7. 2 applications of jointing compound and 1 finish coat will be applied to all joints, screw holes and
internal/external corners to a uniformed thickness.
8. Each coat will be given a suitable time to dry before the next one is applied, feathering each out beyond the
previous application.
10. All surfaces to be sanded to a smooth finish. The use of sanding machines must be utilised where possible to
reduce dust pollution, when sanding clean up at each stage before moving on to the next area. FFP3 dust masks
must be worn for this operation.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 224/471
Note:
Ø This area is to be kept neat and tidy at all times and waste removed to agreed location. Jointing compounds
should be placed into the general waste bins and metal beads into the mixed metal bins.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 225/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
1.1 Before any works commence all operatives will receive a site induction from Company Name Management
and the Site Manager will then ensure all operatives sign the Induction register.
1.2 After signing the induction register, all persons will be given an Company Name Induction helmet sticker,
which states the operatives name, specific Job No, date of induction and the Site Managers signature. They will
then place the label to the helmet to show all concerned parties that they have been inducted.
1.3 The site manager will, as he is issuing the labels, will check that all persons are wearing site prescribed
Personal Protective Equipment, if they are not then they will be issued with the appropriate equipment (either
Company Name or their employer).
No person will be permitted into the site confines without the site prescribed PPE.
1.4 The site manager will then issue any PPE that is required over and above the prescribed, i.e. that required
for the demolition work, (goggles, gloves, ear defenders etc.).
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 226/471
1.5 Once completed all operatives will be given a toolbox talk on this method statement and all associated risk
assessments and applicable COSHH and manual handling assessments.
1.6 The toolbox talk will not be given as read, but will highlight the major safety requirements of the method
statement and the required safe systems of work created.
1.7 The operatives will then be informed of the specific risks highlighted through the assessments carried out
and how we require the operatives to actively participate in implementing the assessed control measures.
1.8 When finished, all operatives will then sign the toolbox talk register to confirm their understanding of the
method statement and risk assessments and to prove that the talk has actually taken place.
1.9 The site manager will then issue to the foreman / ganger a copy of this method statement and risk
assessments as a term of reference for them.
2.1 The first activity will be for the site manager to survey the required area(s) to ensure that there are no major
hazards that will affect the commencement of the works.
2.2 The site manager will be looking for slip, trip & fall hazards, he will also be ensuring that there is safe
access and egress to the place of work and that there are no interface problems that would compromise Company
Name or any other third party.
2.3 Once satisfied, the site manager will allow works to commence.
3.1 The next activity will be to encapsulate the first work area to ensure that no unauthorised persons can enter
the area.
3.2 This will be achieved using either pedestrian barriers or Heras Panels.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 227/471
3.3 We will then use strategically placed prominent signage, to warn all others of our presence and our
works / intentions.
3.5 The entire area will then be checked by the site manager to ensure integrity of the barriers. Also to ensure it
is sufficient to protect/warn third parties and provide Company Name with adequate working boundaries to for the
operation.
4.1 The temporary accommodation will consist of high security portacabins for offices drying / rest and canteen
facilities there will also be 1 No toilet pod which will be segregated to accommodate office staff and site personnel.
Drying facilities will be fully benched out with adequate heating dry out wet clothing.
4.2 Each urinal will be fitted with a cistern to provide adequate flushing and sanitation. Each sink will be of
adequate size to allow the washing of the hands, face and forearms, hot and cold water will be provided to each
sink, the hot water will be of a sufficient temperature as not to cause discomfort but hot enough to allow suitable
washing.
4.3 Hand towels, paper towels or automatic hand drier(s) will be provided at all times and these will be checked
and replenished. The canteen will be fitted out and will be adequately heated and lit at all times. The canteen will
be supplied with a microwave oven and Berko boiler for the preparation of hot food and drinks.
4.4 Adequate ventilation / extraction will also be provided in the canteen for the cooking facilities. Suitable fire
fighting media will also be provided to all facilities (as per the safety plan), this will be fire blankets, powder and Co2
extinguishers, all staff will be trained in the correct type of appliance and in the usage of the extinguishers.
4.5 All cabins will be delivered to site by a flat bed lorry with and integral Hiab system. The driver of the lorry
will be trained and experienced in the use of the Hiab and will be responsible for the slinging of the cabins.
4.6 A banksman will be required to guide the lorry onto the site and to its first off -loading position (the driver &
banksman will take note of the site rules and speed limits & will wear site prescribed P.P.E).
4.7 The area surrounding the intended point of the setting down of the cabin will be either compacted and
sleepers positioned or the area will be sufficiently hard standing and will not require sleepers.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 228/471
4.8 No persons will be permitted into the unloading area at any time and a banksman will be used to ensure
that the operation is carried out safety.
4.9 The S.W.L of the chains / slings and of the Hiab will be noted and the weight of the cabin will correspond to
that of the lifting equipment.
4.10 The cabin will be raised from the back of the lorry sufficiently to allow the cabin to "slew" away from the lorry
without obstruction, during this operation persons will be not permitted within the area of the cabin or lorry.
4.11 Once the cabin has been slewed to its final position, a banksman will be introduced to the area to guide the
cabin to its sleepers, (if applicable). At no time will the banksman be allowed under or near the edge of the cabin.
4.12 Once the cabin has been lowered an operative will unchain the cabin; this will be done from a ladder at all
times and will be footed by another person to prevent slippage. Once unchained the lorry will leave site and the
same operation will be carried out for all other required cabins.
4.13 All services to the facilities will be preplanned and will be protected throughout the route of the cables to
their destination, this will be as possible by means of burying the cable at a sufficient depth to prevent damage and
by using armoured cable for all installations
4.14 All offices and welfare facilities will have Residual Current Devices ( R.C.D's) and each distribution board
with each cabin will be fitted with Miniature circuit Breakers ( M.C.B's) These installations will be commissioned
before first use by a N.I C. E.I.C approved contractor, for which a certificate of adequacy will be issued to the site
Management and then regularly tested as dictated by the environment of the project.
4.15 For this project the installations to the cabins will be tested at least every 3 months or when there is any
change to the configuration or condition of the installation. An adequate supply will be required suitable to power
the canteen appliances, this will be achieved from the existing supply.
4.16 All appliances to the offices and welfare will be regularly inspected and tested, all portable appliances will
be tested between every 6 & 12 months ( dependant on the environment of the equipment). Water supplies to the
welfare facilities will be taken from the existing supplies to the site, this supply is potable and wholesome, therefore
suitable for drinking purposes, and (A drinking water point will be designated and appropriately signed as such).
4.17 Drainage for the facilities will be run to the sanitation tank sited beneath the toilet block, which will be
pumped out periodically. Communications requirements will be gained from the relevant statutory company ( BT),
B.T. will carry out all works and requirements will be directed from our site management.
4.18 There is no requirement for any gas services as all appliances are electrical.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 229/471
5.0 Access, Egress, Deliveries and Debris Removal:
5.1 All access/egress will be via the ramped service road off Campden Hill Road to the Company Name site
compound. This road will have a 5 mph speed restriction in operation with speed restriction signs erected
accordingly.
5.2 On entrance to the area operatives will make themselves known to Company Name management.
5.3 Materials and debris will be carried in and out via the ramped service road and deposited in a covered
skip.
· In the event of a fire, or any other type of emergency the following procedures must be followed:
· Inform the site manager immediately, of the situation and then leave building to your assembly point (TBC)
· All persons are to leave the site by the quickest means possible.
· When the work area is clear the site manager or nominated fire warden will take the floors fire warden sign
from the lobby area and hand it to the fire Marshall at the street level exit.
· Make your way to TBC group together in an orderly fashion and DO NOT LEAVE until you have been
accounted for by the site manager/fire warden
· If you discover any left packages or other items, DO NOT TOUCH IT, and inform the site manager.
· Ensure that the site doors are always closed and secured when leaving site, do not allow unauthorised
persons onto site.
· If you see someone on site who you do not recognise or suspect if you have the confidence, then approach
and challenge, if not then inform the site manager.
· Ensure that all plant / equipment is isolated when not in use and is unplugged especially when finishing work
each day.
· Lock all plant away or take away from site do not leave unsecured on site.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 230/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Testing of Electrical Installations to internal areas to the building within and on all floors, risers, and plant room
areas throughout the building.
The works include all finishes associated with the detailed specification provided by the Principal
Contractors for the project.
4. SCOPE OF WORKS
Testing of all electrical fixings and installations within and throughout the building to provide for consumer circuit
electrical supplies for building accommodations.
Working progressively through each detailed area, which includes all domestic premises apartments, service risers
and plant rooms, including areas identified on
The electrical testing works will provide for final installation finish to works and for confirmation of electrical
connections, power outlets and installed components to building interior as being safe and passing all regulatory
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 231/471
tests required.
The works will conform to the requirements detailed in the works specification issued to the Principal Contractor for
the project.
5. PERMITS TO WORK
Cannock Building Services Ltd will ensure that when working on site all Permits to Work and authorizations to work,
where relevant and defined by the Principal Contractor site rules, are obtained, and any specific requirements or
restrictions complied with.
All Permits to Work or authorizations to work shall be obtained from the Site Project Office, this shall be from a Site
Manager or his representative.
All works will be assessed for Permit to Work needs and this will be undertaken by Company Site Manager and/or
Company Health and Safety Advisor.
6. MANUAL HANDLING
All loads of works materials will be broken down into single units and carried to works location by manual handling
means. All required materials will be delivered to works location prior to works commencement and stored
appropriately ready for use within working areas.
Each role of electrical cable will not be above 25kg in weight and will be handled by one member of staff or two
members of staff during installation of long lengths (in excess of five meters).
Only low voltage (110 volts) tools will be used as necessary, and all 110 volt tools will be connected to a
suitable/site provided step down transformer.
Portable electrical equipment will be checked on a regular basis, including daily inspection prior to use and a
maintenance records kept.
All portable tools if used will be PAT tested prior to use on site and inspections/reports carried out every 3 months
thereafter.
When power tools are in use and cabling extends across walkways or open walk areas, the cabling will be routed in
a manner where it crosses walkways or open walk areas it will be marked and covered and/or if possible to be
hung above head height by use of cable books. Communication of cabling locations will be made to site staff and
include the use and sighting of adequate signage.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 232/471
8. INDUCTION COURSE/SITE RULES
All staff to site, will attend an Induction Course (Tool box talk) and Safe Start meetings prior to working on site
(given by Company), this will support Principal Contractor Induction and adhere/inform of, all local site rules as
instructed/notified to them by Principal Contractor.
9. PROTECTIVE CLOTHING
Staff will wear appropriate Personnel Protective Equipment and work wear whilst working onsite.
· Safety Helmets
Cannock Building Services Ltd staff will be responsible for the safe and proper disposal of waste arising from
activities under their management and for ensuring that disposal is carried out in accordance with legislation
relevant to the waste category involved. Site based skips provided by Principal Contractor will be utilized to dispose
of all waste materials.
Adherence of Principal Contractor Site Waste Management Plan will be carried out.
All COSHH assessments will be carried out prior to use of any substances on site. Assessments will be
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 233/471
communicated to staff and copies of the assessment along with data sheets will be provided to site staff. (See
separate assessments).
The site project manager or his representative will be invited to inspect all completed
work and working areas before being asked to Sign Work Acceptance Form.
Working at heights will be undertaken in the carrying out of these works. All works will be carried out by use of a
temporary platform taking the form of a commercial hop up or podium steps where necessary.
Step ladders/ladders will not be used as a norm and will only be sanctioned after a full risk assessment has been
carried out.
The electrical testing works will be carried out in a phased process, this will be undertaken in conjunction with the
Principal Contractors and Company Works Program.
A defined and barried zone will be set up within the works area on each floor of the works and all installation works
will be undertaken within that area.
Works will be carried out on a component by component etc., basis within rooms, corridors and service areas
until all are complete on each floor level.
Work areas will remain clear of clutter during all installation operations and restrictions/barriers will be put in place
to prevent un-authorized entry to works areas by non- company staff, but will ensure that passage along/across the
area is maintained for access and egress.
Any restrictions or specific site rules will be applied throughout the installation and Company staff will be notified of
those restrictions/site rules at induction. They will further read and obtain information if necessary of daily site risk
notifications (access and read site notice board) or by communication with site management staff.
The works will be carried out in a phased program in accordance with Principal Contractors and Company Program
of Works. Where the works undertakings are at variance to the Principal Contractor Program of Works, these will
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 234/471
be discussed and agreed with the Principal Contractor prior to works being carried out.
REFERENCE SHOULD BE MADE TO PROGRAM OF WORKS AND DRAWINGS FOR INSTALLATION AT ALL
TIMES.
The Site Manager for the works will hold appropriate certification (SMSTS).
· Hand tools
· Podium Steps
No materials will be brought to site that will not be used within the allotted time period of application communicated
to site management.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 235/471
The Company will not be providing a site First Aider.
The Company will implement the site Emergency Plan as detailed by Hinton Design & Build.
No works must/or will be carried out that has not been risk assessed and if works whilst being carried out produce a
risk that has not been assessed, all works must stop and notification given to Company Site Manager who will
implement the appropriate action.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 236/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
All staff will report to the site foreman for induction on arrival at the site. The site manager will inform staff of any
hazards that are present on site. Staff will inform the site manager of the work to be carried out and how it could
affect other trades working on the site.
Where necessary notices will be posted advising of any hazards present during the works.
Where contractor activities cross, the senior person must liaise with the other trades to ensure safe operation.
First Aid
It is the responsibility of the company to ensure adequate First Aid provision for its staff. Adequate means provision
of a trained first aider, suitable first aid equipment and/or the provision of an appointed person at the minimum.
A trained First Aider will be a suitable person who has attended an HSE approved course of at least three days
duration. An Appointed Person is a person provided by the employer to take charge of the situation (e.g. to call an
ambulance) if a serious injury/illness occurs in the absence of a First Aider. The Appointed Person can render
emergency First Aid if trained to do so. All staff when inducted will be made aware of the location of the First Aid kit.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 237/471
Manual Handling
All staff and contractors have been instructed on the potential dangers of manual handling, and have received
manual handling training. Equipment provided to reduce manual handling must be used where provided. Staff and
contractors will not lift items of tools or equipment that are beyond their capabilities. Heavy or awkward items will be
split into smaller
units where possible or dual lifted where this is not possible. It is the responsibility of the site foreman/employer to
identify and control manual handling activities as they occur on site on a day to day basis.
Material Handling
All materials required for site will be unloaded to a designated unloading and storage area which will be away from
the work area as far as is practicable. This area will be kept tidy to minimise trip hazards. Materials as and when
required will be collected from the storage area and transfered to the work area. All staff will take care when
handling materials and will use mechanical aids wherever possible. When stacking materials particular care must
be taken to ensure that the stack is secure and that the product does not get damaged.
PPE will be provided as a last form of protection against a hazard. Staff will use the appropriate PPE for the task as
identified in the risk assessment.
All site workers will wear Safety boots, Hi Visibility Vests, Hard Hats and protective clothing at all times, other items
of PPE such as eye protection, hearing protection and gloves are available to be worn as and when necessary and
as determined by the risk assessment.
A risk assessment will be carried out for all tasks which will be discussed with members of staff and the sub
contractors, any queries or concerns will be raised with the contract manager who will ensure it is dealt with. Staff
and sub contractors will be inducted onto site in order to understand the hazards present on site and the tasks that
are to take place. Staff will also be advised of other site activities that could impact on their work and be made
aware of any liaison that needs to take place between different trades. Staff will follow all site rules and safety
procedures.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 238/471
Staff and Training
The task will be carried out by staff, all staff are qualified, experienced, receive ongoing training, and hold suitable
qualifications. Apprentices are under constant supervision by experienced members of staff.
Any sub contractors appointed by us have been assessed for their ability and suitability to carry out the tasks
allocated to them.
All tools and equipment will be visually inspected on a regular basis, defective or damaged equipment will be
removed from service. Electrical tools will be 110V or battery operated where possible. Sub contractors will not be
allowed to bring on to site any damaged or defective tools, the site foreman is responsible for ensuring that all tools
and equipment allowed on the site are fit for purpose. Any portable electrical equipment taken on to site must be
PAT tested every 3 months when used on construction sites, 6 monthly for heavy use activities and annually for
other activities. A risk assessment will determine if inspection periods need to be varied.
Welfare
The principle contractor is responsible for providing adequate washing, toilet, drying and refreshment facilities for
staff and sub-contractors, staff and contractors are responsible for ensuring that such welfare facilities are
maintained in a clean and wholesome manner (it may be necessary occasionally for us to identify suitable local
amenities).
Painting Ceiling from Tower Scaffold and walls to "cut in at the top"
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 239/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
2) Correct PPE is to be worn at all times, including safety glasses and appropriate gloves, hearing
protection and overalls.
3) Ensure location of fire extinguishers is known, and that they are close to hand
4) Ensure all staff in the area are aware of your actions and will not come into contact with the work.
Cutting
3) Securely fix the material into position using the clamps provided
4) Visually check the guards and set within the correct tolerance
7) Cut through the work at a slow rate by keeping a firm grip on the handle
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 240/471
10)Remove swarf from the machine using the brush provided Housekeeping is an important part of working in a
factory environment. It is everyone's responsibility to ensure they keep all working areas clean and tidy at all times.
All debris is to be removed from the floor and working areas as soon as possible and working areas to be swept
after work. The leaving of dirty rags, metal off cuts, wire, boxes or packaging and any other material, which should
be disposed of, will not be tolerated. Poor housekeeping is a major cause of slips trips and falls and can cause
serious injury.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 241/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Preparation
2) Correct PPE is to be worn at all times, including Safety Glasses and appropriate gloves and overalls
3) Ensure location of fire extinguishers is known, and that they are close to hand
4) Ensure all staff in the area are aware of your actions and will not come into contact with the work.
Cutting
3) Securely fix the material into position using the clamps provided.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 242/471
6) Press green button to start the machine.
10) Remove material from clamps taking care as material may be hot
11) Remove swarf from the machine using the brush provided
Housekeeping
Housekeeping is an important part of working in a factory environment. It is everyones responsibility to ensure they
keep all working areas clean and tidy at all times. All debris is to be removed from the floor and working areas as
soon as possible all working areas are to be swept after work.
The leaving of dirty rags, metal off cuts, wire, boxes or packaging and any other material, which should be disposed
of, will not be tolerated. Poor housekeeping is a major cause of slips trips and falls and can cause serious injury.
Blade replacement
1) Turn the power supply off at the main incoming to the machine
6) Ensure the new blade teeth are facing the correct direction and position on guides
9) On start up stand clear of the machine and let it run for 30 seconds before using under load
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 243/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Before grinding
1) The material to be ground is to be positioned appropriately, please consult the correct method statement
and risk assessment for the movement of large items.
3) Correct PPE is to be worn at all times, including burning masks and appropriate gloves and overalls.
4) Ensure location of fire extinguishers is known, and that they are close to hand.
5) Appoint a fire watcher if appropriate, all staff are to be vigilant with regard to fires at all times.
6) Put screens in place and warn other staff of your intention to grind.
7) Ensure all staff in the area are aware of your actions and will not come into contact with the work.
Grinding
1) Check grinder and wiring for damage. All damaged equipment to be reported for repair or replacement
and should not be used under any circumstances.
2) Put on PPE.
3) Plug in grinder and turn on power supply, but not the grinder.
4) Secure all larger material which may become unstable during the grind.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 244/471
5) Position yourself comfortably ready for the grind. Grinding can cause serious injury. Great care is to be
taken not to get any part of your body in contact with the grinding wheel.
7) Once grinder is up to speed grind material as required. Aim flashes away from your body, and away from
other people.
8) Turn off grinder and wait for it to stop before placing on a secure table, do not cause yourself a trip
hazard.
9) Repeat as necessary.
11) Turn off grinder at the plug and remove plug. Return grinder to its storage place.
1) Waste is to be removed from the working area as quickly as possible to the appropriate skip. Care is to
be taken about the amount of waste lifted. It is your responsibility to clean the area once you have completed your
work.
2) All manual handling advice given in the risk assessment to be followed at all times
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 245/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
iv) Company Site Supervisor will monitor operations, the services of an external consultant may be utilised
where necessary.
v) Compile all necessary record documentation on the area undergoing survey, including relevant record
drawings, circuit charts and test certificates etc.
vi) All live retained services will be identified and recorded to prevent accidental contact.
vii) All operatives to be made aware of general First Aid arrangements, which will be provided by the Main
Contractor.
viii) Specific emergency arrangements in the event of a serious accident will be the responsibility of the Site
Supervisor or nominated person.
ix) Method Statement / Risk Assessment checklist to be read and signed by the Site Supervisor/operative at
site, showing they fully understand the content.
ii) Ladders/Podiums have been erected correctly and are suitable for the task/works. Ladders, steps and
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 246/471
podiums to be erected on solid ground, the work area to be kept clean and tidy and free from debris.
iii) Standard PPE equipment, hard hats, safety footwear, gloves, high visibility vests to be worn. Eye
protection must be worn at all times.
v) Site supervisor to advise other Contractors at site that works are to take place, in order that they can
inform any non-English speaking operatives they employ to be made aware of the works being carried out and
what steps they need to take to avoid any accidents/incidents
sequence of works
Gain access to tenants electrical risers to verify accuracy of circuit charts, number of spare ways available and
future cable access routes into the distribution boards.
ii) Sample test readings will be taken at the distribution boards to verify accuracy of test certification.
iii) A visual inspection of under floor busbars, to determine quantity, location and arrangement is in
accordance with record documentation.
A visual inspection of all accessories with covers on and 20% sample with covers off.
v) Sample test readings will be taken on busbars and small power outlets to verify accuracy of test
certification.
vi) A visual inspection of high-level modular wiring and distribution hubs, to determine quantity, location
and arrangement is in accordance with record documentation.
vii) A visual inspection of lighting control equipment including PIRs and LCMs, to determine quantity, location
and arrangement are in accordance with record documentation.
viii) Quantities, location and arrangement of light fittings and emergency light fittings will be surveyed to
confirm accuracy with record drawings.
x) Every emergency light will be visually inspected to verify that the LED charging light is visible and is lit.
xi) If applicable, it will be ensured that all lamps in maintained emergency light units are on.
xii) At designated times, following sufficient warning, mains failure will be simulated by means of key
operated test switches and a check that the relevant emergency fluorescent lamp is illuminated and
remains so for 3 minutes.
xiii) Emergency lighting levels will be checked to ensure compliance with B.S. 5266 1988.
xiv) Following restoration of the mains supply a visual check will be made to ensure that the red LED
charging light is lit.
xv) The fire alarm system and voice annunciation system will be visually surveyed to verify quantities and
location of equipment inspected.
xvi) LED displays on fire alarm and voice annunciation panels are to be visually inspected to determine
presence of any inherent faults.
xvii) Main contractor to request print out from fire alarm and voice annunciation panels to verify the system
is fully operational and free from defects.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 247/471
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 248/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
1. All items must be thoroughly cleaned in either water or the relevant solvent at the end of each shift
2. Items such as brushes and rollers should be air dried and stored
3. Wash buckets, wipe inside and out and store upside down
The work area to be surveyed to plan the work including any requirements to avoid working at height.
Where painting at height is unavoidable then a suitable method of access is to be used in this instance Tower
Scaffold
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 249/471
All tools and equipment to be brought to site and stored in a secure place.
All removable fixtures, furniture and fittings to be removed from the room before work starts. Dust sheets to be
placed to protect fixtures and fittings that cannot be removed.
Painters tape (not masking tape) to be used to attach plastic drops to the floor and woodwork, and drops to be
covered with newspapers.
Painter's tape to be used to protect door and window frames and mouldings etc. Electric power points etc to be
covered using painters tape. Small plastic bags to be used to cover door knobs.
All cracks and holes to be filled using paste filler applied with a putty knife and to be sanded down after the filler
paste is dry.
All ceilings to be washed down using the sponge mop using warm water and sugar soap/detergent and left to dry.
Walls and mouldings to be cleaned using a hand sponge or cloth.
Newly plastered walls to be treated with a primer coat and left to dry.
Corners and edges of walls and ceilings to be cut-in using an angled 2" trim brush applying paint in a series of
short strokes away from the edges where walls or ceiling and wall meet.
Where possible working at height to be avoided. When painting ceilings a roller and tray are to be used with an
extension pole and paint to be applied in one direction only.
Walls to be painted using a roller and tray. Paint to be applied in a vertical motion working horizontally across a
room from side to side.
On completion of the work all brushes and rollers to be washed and put away. Dust sheets and painters tape to be
removed and taken away.
The site is to be cleared of all equipment and left clean and tidy
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 250/471
Expansion joint cladding from a Scissor Lift
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 251/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Waste skips
Method Statement
Small waste and the like will be placed inside rubble bags and taken to the waste skips.
Rubbish is to be cleared regularly so it does not build up and create any obstructions.
All access and egress routes are to be kept clear of rubbish at all times.
Environmental Issues (give details)
Damp down waste to prevent dust
Identification of Control Measures following Risk Assessment
Vehicles delivering and removing skips are to only drive and park in arranged locations.
Operatives moving rubbish and loading skips are to be trained in manual handling.
Emergency Procedures
Work suspended during adverse weather conditions.
Operatives should familiarise themselves with the fire evacuation plan which can be found in the site file.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 252/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
The positioning of the skip is the responsibility of the customer who must have due regard for the health and safety
of all those likely to be affected.
When loading Compactor skips raise the bin on the lift chains sufficient to clear the ground and move to a location
where the skip can be loaded safely. N.B. ENSURES SUFFICIENT HEAD ROOM BEFORE LIFTING.
Regularly check chains and lifting equipment for signs of wear & tear.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 253/471
Any damage etc; must be reported to the supervisor. The driver has the authority to stop the load if at any time you
deem it as unsuitable for transportation or note any defects contrary to the road regulation
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 254/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Objectives
The objective of this task is to clean Company Name office and welfare facilities at White Collar Factory.
Working Hours
Within normal site working hours: Monday Friday 08:00 18:00 hrs, Saturday 08:00 13:00. Out of hours worked will
be advised by Derwent London and activity will be covered under a specific M/S and R/A applicable to the works
being under taken.
Supervision
· First Aid
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 255/471
· Name - Company Name
Labour
1 x Welfare Cleaners.
Before any works commence all operatives will receive a site induction from Derwent, Company Name
operative must bring a valid CSCS Card in order to attend Derwent Site Safety Induction. The respective
Manager will then ensure all operatives sign the project induction registers.
Company Name operative must bring a valid CSCS Card in order to work on site, Company Name
Manager to check card competence prior commence the works.
Before any works commence the Company Name Manager will check that all persons are issued with and
wearing site prescribed P.P.E.
NO PERSON WILL PERMITTED TO WORK WITHOUT THE PRESCRIBED P.P.E
The relevant Company Name Manager will then issue any P.P.E. that is required over and above the
prescribed, (hat, sole and toe protectors, gloves, hi viz vest & eye protection), that is required for the works
in compliance with any method statement above this issue.
Once completed, all operatives will then be briefed on his/her method of works/method statement and all
associated risk assessments and applicable COSHH and manual handling assessments as required.
Information will then be presented highlighting the major safety requirements of the method statement and
the required safe systems of work to be practiced.
The operatives will then be informed of the specific risks highlighted through the assessment carried out
and how we require the operatives to actively participate in implementing the assessed controlled
measures.
The Company Name Manager will then ask all operatives if they fully understand what has been presented
to them and if they would like to ask questions about the method statement and the associated risks.
When finished, all operatives will then sign the method statement briefing register to confirm their
understanding of the method statement and safe working practice.
A copy of this will also be placed in the work area for any person to view or refer to. Once the works begin.
The first activity will be for the Company Name Manager to survey the required areas to ensure there are
no major hazards that will affect commencement of the works.
The Site Manager will be looking for slip, trip and fall hazards. He will also be ensuring that there is safe
access and egress to the place of work and there are no interface problems that would compromise
Company Name or any other third party.
Once satisfied, the Company Name Manager will allow work to commence.
Emergency procedures as explained in site induction must be adhered to, as will any emergency
procedures regarding the use of substances (these can be found on the individual COSHH Assessments)
· All Company Name personnel will attend the Derwent site induction to receive instruction on the general
requirements for works on site. This method statement will be delivered verbally by the Company Name Manager
prior to the site induction. On completion, all operatives are to demonstrate understanding of their duties by verbal
testing and then sign the register.
· All Company Name personnel will wear personal protective equipment in line with site requirements and such
additional equipment as identified by risk assessment review carried out by the Company Name site manager.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 256/471
· All Company Name personnel to have site access via designated site pedestrian walk wall, also, to assembly
and maintain pedestrians walk ways, when required.
· Risk assessments have been produced for each of these and are attached to this statement. Personnel will
now be briefed on each of the assessments and be questioned to confirm understanding of the controls placed.
· Operatives must ensure that all emergency routes are kept clear.
· Cleaner will be issued with the relevant COSHH assessments for all cleaning materials issued.
· Cleaner will use any cleaning material as directed by the manufactures instructions and the relevant COSHH
assessment.
· All electrical appliances must be inspected before use and faulty equipment reported to the supervisor and
taken out of use until either repaired or replaced.
· When moping floor surfaces wet floor warning notices must be displayed.
· Rubber gloves and safety glasses to be worn at all times while cleaning.
· Only approved access equipment must be used for any high level works or long reach equipment must be
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 257/471
used.
The Company Name Site Logistics Manager will monitor and ensure compliance during the works.
This person will give Derwent a signed copy of a Method Statement / Risk Assessment Briefing Register.
Document Review - Who will update Method Statement if there are any deviations/changes required during the
works?
Name
Updated Method Statements are to be resubmitted to Derwent for review before work can re-start. Document to be
reviewed when necessary due to work circumstances.
PPE Requirements
Hi-Vis vests, Safety footwear with steel toe mid-sole protection, Gloves as required by COSHH and Eye protection
as required by COSHH.
Tool Requirements
Disposal of Waste
Waste is to be disposed of through the site waste streams. Ensure empty COSHH containers clear-up materials
are disposed of in line with the relevant COSHH Assessments. Any spillage found, must be reported for Company
Name Site Manager, he will instruct Company Name operatives how to deal with it.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 258/471
Noise
Noise will be monitored by the management and if necessary the noise levels will be taken and an assessment will
be carried out, and the appropriate controls put into place.
A copy of this method statement will be kept within the site confines for all operatives to refer to if needed.
All areas will be cleared on a daily basis and left in a safe and suitable manner when unattended, all finished areas
will be left in a clean condition to the satisfaction of Derwent London.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 259/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
3. Place Warning signs at the extremes of the work area prior to the work commencing.
4. If possible work from ground level rather than use access equipment.
5. Access equipment should be erected, checked, and dismantled by a competent person only.
6. Check access equipment carefully before use and when moving from one area to another.
7. Ladders and mobile access equipment must be securely anchored before starting work.
8. Do not climb onto window ledges without safety harness securely anchored.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 260/471
13. Do not use powder, paste, or abrasive cleaners.
14. Treat painted or stained glass or two way mirrors according to manufacturers instructions.
1. Use a well wrung leather or scrim and start at the sides and top of frame, followed by a zigzag pattern down the
frame
2. Wipe the sides and top of the frame using a well wrung leather or scrim, followed by using a squeegee. When
using a squeegee, make a vertical stroke from top to bottom at one side of pane, then using a zigzag stroke across
the pane horizontally keeping the blade at 45degrees to the direction of travel. Move the blade horizontally in a
zigzag pattern never lifting the blade off the pane. Finally finish with a straight vertical stroke down each edge of
pane. Wipe blade with absorbent cloth after each operation.
Extension pole
3. Use extension pole with leather on it to dry top edge. Wipe bottom edge of pane with leather or scrim.
4. Clean small pane windows by applying cleaning solution with an applicator to top row of panes. Then squeegee
across upper part of the windows, tilting handle slightly to push water towards bottom of glass. Make a second pass
with squeegee to remove remaining solution. With scrim wipe dry lower moulding, then proceed to next row of
panes and repeat.
1. Park van in a suitable position as close as is reasonably practicable to the work area.
2. Assemble all of the equipment to be used and check each item for safety.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 261/471
7. Select a suitable pole for the height of window to be cleaned
10. Begin the cleaning process from the highest point sweeping the brush from left to right until each window is
clean.
11. Ensure all framework and sills are washed during the clean
12. When all first clean is complete spray each glass pane with pure water, working top to bottom, ensuring the
brush is not in contact with the glass.
17. Return all equipment, materials, and warning signs to the van and store safely and securely.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 262/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
2. Dry test the door in the casing and mark where trimming is needed
4. Wedge the door in place and mark out the hinges and lock position
5. Chop out and fit the hinges to the frame either by hand or router
7. Hang the door and check for plumb and correct clearance
8. Drill & chop out the door before fitting the lock
10. Mark out the frame and fit the striking plate
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 263/471
11. Test the door for correct operation
4. Fix the architrave to the door frame using the nail gun
4. Fix to the wall by nail gun / screw & plug or instant grip adhesive as required
1. Measure / cut and fix the newel posts ensuring each is upright
2. Measure the run of the base/hand rail and cut to size with the chop saw
5. Measure the angle of the balusters and mark out the position on the base rail and handrail
6. Cut the balusters to size and fix to the base rail and hand rail
KITCHEN UNITS
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 264/471
1. Check all units for sign of damage
2. Mark out the floor with the position of the units and equipment
5. Fix the units in place with the appropriate fixings, ensure units are levelled up correctly
9. Mark out the wall for the position of the wall units
10. Mark a plumb line at the correct height for the underside of the units
11. Drill and subsequently fix the adjustable brackets to the wall
FLOOR JOISTS
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 265/471
2. Collect lengths of wood from storage area and take to cutting area
7. Lay temporary platform for use as work area or lay weather protective safedeck boards as per drawings
8. Lift the first floor joists into position using the telescopic handler if available, if Not ensure good manuall handling
techniques are observed
10. Lay first floor temporary platform for use as work area or lay weather protective safedeck boards as per
drawings
STAIRCASE
4. Fix though strings into the wall to secure stairs using supplied fixing screws
5. Fix under third tread from bottom using small stud frame to give support
4. Temporary wedge the frame in place in preparation for fixing and check for plumb
5. Drill the fixing holes and screw fix with raw plugs or frame fixings
6. Cut the interior sill to size and fix with propriety fixings
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 266/471
STUD WALLS
1. Mark out the position of the internal walls as per the site plan
5. Nail fix the Sole Plate ensuring they are plumb with the Ceiling Plate
6. Mark out the position of the Studs on both the Ceiling Plate & Sole Plate
8. Skew nail each stud both top and bottom and check for vertical with the spirit level
9. Mark out the position for the horizontal noggins as per site plan
14. Remove all waste and dispose of as per local authority guidelines
5. Check the supply is dead by electrical test meter before connecting to supply
6. Ensure system is locked off and keys to padlock are kept with engineer
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 267/471
10. Before re-energizing the system all non live testing will be carried out
13. Tidy work area and remove all debris to designated waste area
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 268/471
METHOD
STATEMENT
The information and data provided herein shall not be duplicated, disclosed or disseminated by the recipient in
whole or in part for any purpose whatsoever without the prior written permission from Credibuild Ltd
Plant to be Utilised
Scaffolding
Method Statement
Work at height will not begin until the required scaffolding has been erected, including temporary edge
protection where necessary.
Where materials are stored on the roof they will be carefully stacked and stored in a manner that will not
cause any risk of the materials falling from the roof or presenting a trip hazard.
When transporting items to and from the roof, load sizes are t be kept to a manageable level in order to
avoid risk of injury or items falling from height. Correct technique is to be observed in cases of manual
handling and any hoist or rubbish chute is to be used in a safe, appropriate manner.
Only fully trained and experienced operatives are to carry out work at height.
All efforts must be taken in order to ensure that nothing falls from height, including materials, tools and
plant. Items stored on the roof are to be neatly and carefully stacked in a safe manner, no items are to be
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 269/471
placed on edges such as parapet walls.
Working platform to be fully boarded and adequately sheeted or netted. Entrances to buildings protected
by nets or fans. Exclusion zones to be created and monitored where necessary
All Contractors instructed to clear up their waste materials within a reasonable time of it being created and
before it becomes a hazard.
Emergency Procedures
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 270/471
COSHH ASSESSMENT
Trade Name : Dulux Trade Diamond Eggshell Class : General painting purposes of interior walls & ceilings.
Manufacture :Dulux Trade Paints Ltd Phone : 01753 550000
Desc : General painting purposes of interior walls & ceilings. Format : Liquid
Constituents
Other Constituents Propylene Glycol Workplace Exposure Limits WEL Propylene Glycol 150 LTEL 8hr TWA ppm
470 LTEL 8hr TWA mg m3
Effect :
Action :
Protective Clothing :
Safety boots Gloves Overalls
First Aid :
Emergency and First Aid Action Skin Contact Wash sin with soap and water Do not use a solvent Eye contact
Irrigate with plenty of clean tepid water or eyebath Inhalation Remove casualty from exposure ensuring one s own
safety whilst doing so Consult a doctor Ingestion Wash out mouth with water Do not induce vomiting Transfer to
hospital as soon as possible
Disposal :
Disposal operations DO NOT EMPTY INTO DRAINS OR WATERCOURSES The user s attention is drawn to the
possible existence of regional or national regulations regarding disposal Some local authorities have special
facilities for disposal or disposing of waste paint
Fire :
Fire Fighting Requirements Extinguishing media Recommended - alcohol resistant foam CO2 powders Not to be
used - waterjet Recommendations Fire will produce dense black smoke Exposure to decomposition products may
cause a health hazard Fire fighters should wear self-contained breathing apparatus Closed containers exposed to
fire should be cooled with water Do not allow run-off from fire-fighting to enter drains or water-courses
Spillages :
Spillages Ventilate area Spills may be collected with absorbent materials Place collected material in an
impervious container Spilled material is extremely slippery Dike and contain spill Use absorbent to pick up excess
residue Keep salvageable material and rinse water out of sewers and water courses Small spills - use absorbent
to pick up residue and dispose of properly
Storage :
Storage Handling Transport Store in a cool dry well ventilated place away from sources of heat ignition and direct
sunlight No smoking Prevent unauthorised access Containers which are opened should be properly resealed and
kept upright to prevent leakage Do not use or store any paint container by hanging on a hook
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 271/471
COSHH ASSESSMENT
Trade Name :Dulux Trade Diamond Eggshell Class : General painting purposes of interior walls & ceilings.
Manufacture :Dulux Trade Paints Ltd Phone : 01753 550000
Desc : General painting purposes of interior walls & Format : Liquid
ceilings.
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 272/471
COSHH ASSESSMENT
Trade Name : FAIRY Manual Washing Up Liquid Class : Washing and cleaning products (including solvent based
products)
Manufacture :Procter & Gamble Ltd Phone : 0191 279 2000
Desc : Washing and cleaning products (including solvent based Format : Liquid
products)
Constituents
Sodium Lauryl Sulphate CAS No 1231880-35-5 REACH-no 01-2119582870-31 10 - 20 Xn R22 Xi R41 Xi R38 Acute Tox 4 Oral H302 Skin Irrit 2 H315 Eye Dam 1 H318
Aquatic Chronic 3 H412 Sodium C12-14 Pareth-3 Sulfate CAS No 68891-38-3 EC no Polymer 5 - 10 Xi R41 Xi R38 Skin Irrit 2 H315 Eye Dam 1 H318 Aquatic Chronic 3 H412
Lauramine Oxide CAS No 308062-28-4 EC no 931-292-6 REACH-no 01-2119490061-47 5 - 10 Xn R22 Xi R41 Xi R38 N R50 Acute Tox 4 Oral H302 Skin Irrit 2 H315 Eye
Dam 1 H318 Aquatic Acute 1 H400 Aquatic Chronic 2 H411 Sodium C12-14 Alkyl Sulfate CAS No 85586-07-8 EC no 287-809-4 REACH-no 01-2119489463-28 1 - 5 Xn R22 Xi
R41 Xi R38 Acute Tox 4 Oral H302 Skin Irrit 2 H315 Eye Dam 1 H318 Aquatic Chronic 3 H412
Effect :
Acute toxicity Not classified P G Professional FAIRY Manual Washing Up Liquid LD50 oral calculated 2000 mg kg Lauramine Oxide 308062-28-4 LD50 oral rat 1064 mg kg
OECD 401 LD50 dermal rat 2000 mg kg OECD 402 ATE CLP oral 1064 mg kg bodyweight Sodium C12-14 Alkyl Sulfate 85586-07-8 LD50 oral rat 2000 mg kg EC 440 2008 B
1 bis LD50 dermal rabbit 500 mg kg ATE CLP oral 2000 mg kg bodyweight Sodium C12-14 Pareth-3 Sulfate 68891-38-3 LD50 oral rat 4100 mg kg LD50 dermal rat 2001 mg
kg ATE CLP oral 4100 mg kg bodyweight ATE CLP dermal 2001 mg kg bodyweight Sodium Lauryl Sulphate 1231880-35-5 LD50 oral rat 1063 mg kg OECD 401 LD50 dermal
rabbit 500 mg kg bodyweight OECD 402 ATE CLP oral 1063 mg kg bodyweight Skin corrosion irritation Not classified pH 9 Serious eye damage irritation Causes serious eye
irritation pH 9 Respiratory or skin sensitisation Not classified Germ cell mutagenicity Not classified Carcinogenicity Not classified Reproductive toxicity Not classified Specific
target organ toxicity single exposure Not classified Specific target organ toxicity repeated exposure Not classified Aspiration hazard Not classified Potential Adverse human
health effects and symptoms Acute Toxicity based upon available data of the substances classification criteria are not met Carcinogenicity based upon available data of the
substances classification criteria are not met Corrosivity based upon available data of the substances classification criteria are not met Irritation severly irritant to eyes
Mutagenicity based upon available data of the substances classification criteria are not met Repeated Dose Toxicity based upon available data of the substances classification
criteria are not met Sensitization based upon available data of the substances classification criteria are not met Toxicity for Reproduction based upon available data of the
substances classification criteria are not met Other information Likely routes of exposure skin and eye Information on Effects
Action :
No dangerous reactions known Stable under normal conditions Not required for normal conditions of use
Protective Clothing :
Personal protective equipment Protective personal equipment only required in case of professional use or for large packs not for household packs For consumer use please
follow recommendation as indicated on the label of the product Hand protection Not applicable Eye protection Wear eye face protection Skin and body protection Not
applicable Respiratory protection Not applicable
First Aid :
First-aid measures after inhalation IF INHALED remove victim to fresh air and keep at rest in a position comfortable for breathing Call a POISON CENTER or doctor physician
if you feel unwell First-aid measures after skin contact IF ON SKIN Wash with plenty of soap and water Take off contaminated clothing and wash before reuse If skin irritation
occurs Get medical advice attention Discontinue use of product First-aid measures after eye contact IF IN EYES Rinse cautiously with water for several minutes Remove
contact lenses if present and easy to do Continue rinsing Immediately call a POISON CENTER or doctor physician First-aid measures after ingestion IF SWALLOWED rinse
mouth Do NOT induce vomiting Immediately call a POISON CENTER or doctor physician Symptoms injuries after inhalation Coughing sneezing Symptoms injuries after skin
contact Redness Swelling dryness Itching Symptoms injuries after eye contact Severe pain Redness Swelling Blurred vision Symptoms injuries after ingestion Oral mucosal or
gastro-intestinal irritation Nausea Vomiting Excessive secretion Diarrhea
Disposal :
Regional legislation waste Disposal must be done according to official regulationsDisposal recommendations The waste codes waste designations below are in accordance
with EWC Waste must be delivered to an approved waste disposal company The waste is to be kept separate from other types of waste until its disposal Do not throw waste
product into the sewer Where possible recycling is preferred to disposal or incineration For handling waste Empty uncleaned packaging need the same disposal considerations
as filled packaging EURAL Waste code product 20 01 29 - detergents containing dangerous substances 15 01 10 - packaging containing residues of or contaminated by
dangerous substances
Fire :
Suitable extinguishing media Dry chemical powder alcohol-resistant foam carbon dioxide CO2 Fire hazard No fire hazard Non combustible Explosion hazard Product is not
explosive Reactivity No dangerous reactions known Firefighting instructions No specific firefighting instructions required Protection during firefighting In case of inadequate
ventilation wear respiratory protection
Spillages :
Protective equipment Wear suitable gloves and eye face protection Protective equipment Wear suitable gloves and eye face protection For containment Scoop absorbed
substance into closing containers Methods for cleaning up Small quantities of liquid spill take up in non-combustible absorbent material and shovel into container for disposal
Large spills contain released substance pump into suitable containers This material and its container must be disposed of in a safe way and as per local legislation
Storage :
Precautions for safe handling Avoid contact with eyes Use personal protective equipment as required Do not eat drink or smoke when using this product Do not handle until all
safety precautions have been read and understood Storage conditions Store in original container Incompatible materials Not applicable Prohibitions on mixed storage Not
applicable Storage area Store in a cool area Store in a dry area
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 273/471
COSHH ASSESSMENT
Trade Name : FAIRY Manual Washing Up Liquid Class : Washing and cleaning products (including solvent based
products)
Manufacture :Procter
& Gamble Ltd Phone : 0191 279 2000
Desc : Washing and cleaning products (including solvent Format : Liquid
based products)
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 274/471
COSHH ASSESSMENT
Constituents
FORMIC ACID 200-579-1 64-18-6 1 C R35 LIMONENE 205-341-0 138-86-3 1 R10 R43 Xi R38 N R50 53 SODIUM HYDROXIDE 215-185-5 1310-73-2
1 C R35
Effect :
INHALATION Vapour may irritate respiratory system or lungs INGESTION May cause discomfort if swallowed SKIN CONTACT Irritating to skin May
cause sensitisation by skin contact EYE CONTACT Irritating to eyes MEDICAL CONSIDERATIONS Skin disorders and allergies
Action :
STABILITY Stable under normal temperature conditions CONDITIONS TO AVOID Avoid contact with strong oxidisers HAZARDOUS
DECOMPOSITION PRODUCTS Fire or high temperatures create Carbon monoxide CO Carbon dioxide CO2
Protective Clothing :
ENGINEERING MEASURES Well-ventilated area HAND PROTECTION Protective gloves must be used if there is a risk of direct contact or splash Use
protective gloves made of Nitrile EYE PROTECTION Wear splash-proof eye goggles to prevent any possibility of eye contact OTHER PROTECTION
Wear appropriate clothing to prevent any possibility of liquid contact and repeated or prolonged vapour contact Provide eyewash station HYGIENE
MEASURES DO NOT SMOKE IN WORK AREA Wash at the end of each work shift and before eating smoking and using the toilet Wash promptly if
skin becomes wet or contaminated Promptly remove any clothing that becomes contaminated When using do not eat drink or smoke
First Aid :
INHALATION Remove victim immediately from source of exposure Move the exposed person to fresh air at once Get medical attention if any discomfort
continues INGESTION DO NOT induce vomiting Get medical attention immediately SKIN CONTACT Promptly flush contaminated skin with water
Promptly remove clothing if soaked through and flush the skin with water Get medical attention if irritation persists after washing EYE CONTACT Rinse
the eye with water immediately Continue to rinse for at least 15 minutes and get medical attention
Disposal :
DISPOSAL METHODS Dispose of waste and residues in accordance with local authority requirements WASTE CLASS Classified as Special Waste Not
permitted for landfill in liquid state
Fire :
EXTINGUISHING MEDIA Use fire-extinguishing media appropriate for surrounding materials SPECIAL FIRE FIGHTING PROCEDURES Keep run-off
water out of sewers and water sources Dike for water control If risk of water pollution occurs notify appropriate authorities SPECIFIC HAZARDS Fire
creates Carbon monoxide CO Carbon dioxide CO2
Spillages :
SPILL CLEAN UP METHODS Wear necessary protective equipment Stop leak if possible without risk DO NOT touch spilled material Runoff or release
to sewer waterway or ground is forbidden Absorb in vermiculite dry sand or earth and place into containers Flush area with plenty of water Do not let
washing down water contaminate ponds or waterways
Storage :
USAGE PRECAUTIONS Avoid spilling skin and eye contact Provide good ventilation Persons susceptible for allergic reactions should not handle this
product STORAGE PRECAUTIONS Store in tightly closed original container in a dry cool and well-ventilated place Keep in original container
STORAGE CLASS Chemical storage
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 275/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 276/471
COSHH ASSESSMENT
Constituents
Composition Comments No classified ingredients or those having occupational exposure limits present above the
levels of disclosure
Effect :
Health Warnings Serious long-term effects are not known to be related to this type of product Particles in the eyes
may cause irritation and smarting May cause discomfort if swallowed
Action :
10 1 Reactivity No specific reactivity hazards associated with this product 10 2 Chemical stability Stable under
normal temperature conditions 10 3 Possibility of hazardous reactions Not available Hazardous Polymerisation
Unknown 10 4 Conditions to avoid Avoid excessive heat for prolonged periods of time 10 5 Incompatible materials
Materials To Avoid No incompatible groups noted
Protective Clothing :
Hand protection Use suitable protective gloves if risk of skin contact Use thin cotton gloves inside the rubber
gloves if allergy risk Eye protection If risk of splashing wear safety goggles or face shield Other Protection Wear
suitable protective clothing as protection against splashing or contamination Hygiene measures Wash promptly if
skin becomes wet or contaminated Promptly remove any clothing that becomes contaminated When using do not
eat drink or smoke Wash hands at the end of each work shift and before eating smoking and using the toilet Use
appropriate skin cream to prevent drying of skin DO NOT SMOKE IN WORK AREA
First Aid :
General information General first aid rest warmth and fresh air Inhalation Move the exposed person to fresh air at
once Get medical attention if any discomfort continues Ingestion DO NOT induce vomiting Get medical attention
immediately Skin contact Remove affected person from source of contamination Rinse the skin immediately with
lots of water Get medical attention if irritation persists after washing Eye contact Rinse the eye with water
immediately Continue to rinse for at least 15 minutes and get medical attention
Disposal :
General information When handling waste consideration should be made to the safety precautions applying to
handling of the product 13 1 Waste treatment methods Dispose of waste and residues in accordance with local
authority requirements Recover and reclaim or recycle if practical
Fire :
Extinguishing media This product is not flammable Use fire-extinguishing media appropriate for surrounding
materials 5 2 Special hazards arising from the substance or mixture Specific hazards Fire or high temperatures
create Toxic gases vapours fumes of Carbon dioxide CO2 Carbon monoxide CO 5 3 Advice for firefighters
Protective equipment for fire-fighters Use protective equipment appropriate for surrounding materials
Spillages :
Do not discharge into drains water courses or onto the ground 6 3 Methods and material for containment and
cleaning up Stop leak if possible without risk Do not contaminate water sources or sewer Pick up with vacuum or
absorbent solid store in closed container for disposal Avoid generation and spreading of dust Avoid contact with
skin or inhalation of spillage dust or vapour Wear necessary protective equipment Containers with collected
spillage must be properly labelled with correct contents and hazard symbol
Storage :
Do not handle broken packages without protective equipment Use mechanical ventilation in case of handling
which causes formation of dust Avoid spilling skin and eye contact Store in tightly closed original container in a
dry cool and well-ventilated place Keep in original container
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 277/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 278/471
COSHH ASSESSMENT
Trade Name : 4 TRADE MORTAR & CONCRETE WATERPROOFER Class : Waterproofing Liquid
Manufacture :Bostik Ltd Phone : 01533 510015
Desc : Waterproofing Liquid Format : Liquid
Constituents
LIMONENE 1 CAS-No 138-86-3 EC No 205-341-0 Classification EC 1272 2008 Flam Liq 3 - H226 Skin Irrit 2 - H315 Skin Sens 1 - H317 Aquatic Acute
1 - H400 Aquatic Chronic 1 - H410 Classification 67 548 EEC R10 R43 Xi R38 N R50 53 SODIUM HYDROXIDE 1-5 CAS-No 1310-73-2 EC No
215-185-5 Registration Number 01-2119457892-27 Classification EC 1272 2008 Classification 67 548 EEC Skin Corr 1A - H314 C R35
Effect :
Inhalation Vapour may irritate respiratory system or lungs Ingestion May cause discomfort if swallowed Skin contact Irritating to skin May cause
sensitisation by skin contact Eye contact Irritating to eyes Medical Considerations Skin disorders and allergies
Action :
Stable under normal temperature conditions 10 3 Possibility of hazardous reactions Not available 10 4 Conditions to avoid Avoid contact with strong
oxidisers 10 5 Incompatible materials 10 6 Hazardous decomposition products Fire or high temperatures create Carbon monoxide CO Carbon dioxide
CO2
Protective Clothing :
Engineering measures Well-ventilated area Hand protection Protective gloves must be used if there is a risk of direct contact or splash Use protective
gloves made of Nitrile Eye protection Wear splash-proof eye goggles to prevent any possibility of eye contact Other Protection Wear appropriate
clothing to prevent any possibility of liquid contact and repeated or prolonged vapour contact Provide eyewash station Hygiene measures DO NOT
SMOKE IN WORK AREA Wash hands at the end of each work shift and before eating smoking and using the toilet Wash promptly if skin becomes wet
or contaminated Promptly remove any clothing that becomes contaminated When using do not eat drink or smoke
First Aid :
Inhalation Remove victim immediately from source of exposure Move the exposed person to fresh air at once Get medical attention if any discomfort
continues Ingestion DO NOT induce vomiting Get medical attention immediately Skin contact Promptly flush contaminated skin with water Promptly
remove clothing if soaked through and flush the skin with water Get medical attention if irritation persists after washing Eye contact Rinse the eye with
water immediately Continue to rinse for at least 15 minutes and get medical attention
Disposal :
Dispose of waste and residues in accordance with local authority requirements Waste Class Classified as Special Waste Not permitted for landfill in
liquid state
Fire :
Extinguishing media Use fire-extinguishing media appropriate for surrounding materials Specific hazards Fire creates Carbon monoxide CO Carbon
dioxide CO2 5 3 Advice for firefighters Special Fire Fighting Procedures Keep run-off water out of sewers and water sources Dike for water control If risk
of water pollution occurs notify appropriate authorities
Spillages :
Wear necessary protective equipment Stop leak if possible without risk DO NOT touch spilled material Runoff or release to sewer waterway or ground is
forbidden Absorb in vermiculite dry sand or earth and place into containers Flush area with plenty of water Do not let washing down water contaminate
ponds or waterways
Storage :
Avoid spilling skin and eye contact Provide good ventilation Persons susceptible to allergic reactions should not handle this product 7 2 Conditions for
safe storage including any incompatibilities Store in tightly closed original container in a dry cool and well-ventilated place Keep in original container
Storage Class Chemical storage
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 279/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 280/471
COSHH ASSESSMENT
Constituents
Toluene 50 p p m 8hr T W A Caustic Potash No given standard
Effect :
Irritant in contact with eyes and skin
Action :
Avoid contact with skin and eyes Avoid breathing fumes Ensure adequate ventilation
Protective Clothing :
Suitable respiratory equipment should be worn if solvent vapour is above the O E L Wear impervious gloves
First Aid :
Inhalation If inhaled remove to fresh air and rest Skin Wash from skin with a recognised hand cleaner and then
with soap and water Ingestion Do not induce vomiting Eyes Irrigate eyes with copious amounts of clean fresh
water for at least 15 mins Seek medical advice Ingestion If ingested seek medical advice
Disposal :
Dispose of in accordance with Local Authority Regulations
Fire :
Use foam dry powder or C02 extinguishers
Spillages :
Contain spillages and soak up with sand or earth
Storage :
Protect from frost Store under cover
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 281/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 282/471
COSHH ASSESSMENT
Trade Name : 5L SUPER PINE DISINFECTANT QAP30 GREEN Class : Detergent. Disinfectant. Washing and cleaning.
Manufacture :Coventry Chemicals Limited Phone : 02476 639739
Desc : Detergent. Disinfectant. Washing and cleaning. Format : Liquid
Constituents
NA
Effect :
General information This product has low toxicity Inhalation No specific health hazards known Ingestion May cause irritation Symptoms following
overexposure may include the following Stomach pain Nausea vomiting Diarrhoea Skin contact Skin irritation should not occur when used as
recommended Repeated exposure may cause skin dryness or cracking Eye contact May cause temporary eye irritation
Action :
Reactivity There are no known reactivity hazards associated with this product Stability Stable at normal ambient temperatures Possibility of hazardous
reactions Not applicable
Protective Clothing :
Appropriate engineering controls Provide adequate ventilation Eye face protection No specific eye protection required during normal use Hand
protection For prolonged or repeated skin contact use suitable protective gloves Other skin and body protection Use barrier creams to prevent skin
contact Wear appropriate clothing to prevent repeated or prolonged skin contact Hygiene measures When using do not eat drink or smoke Good
personal hygiene procedures should be implemented Wash hands and any other contaminated areas of the body with soap and water before leaving
the work site Use appropriate skin cream to prevent drying of skin Respiratory protection Respiratory protection not required Environmental exposure
controls Avoid release to the environment Users should be aware of environmental considerations and their duties under the environmental protection
act Further information may be found on Government websites www dti gov uk access index htm and www envirowise gov uk
First Aid :
Inhalation Move affected person to fresh air at once Rinse nose and mouth with water Get medical attention if any discomfort continues Ingestion Never
give anything by mouth to an unconscious person Do not induce vomiting Rinse mouth thoroughly with water Get medical attention if any discomfort
continues Skin contact Rinse immediately with plenty of water Remove contaminated clothing Get medical attention if irritation persists after washing
Eye contact Rinse immediately with plenty of water Remove any contact lenses and open eyelids wide apart Continue to rinse for at least 15 minutes
Get medical attention if irritation persists after washing Show this Safety Data Sheet to the medical personnel
Disposal :
General information Do not discharge into drains or watercourses or onto the ground Disposal methods Dispose of waste to licensed waste disposal site
in accordance with the requirements of the local Waste Disposal Authority Packaging is recyclable Wash out containers with water before disposal
Fire :
Suitable extinguishing media The product is not flammable Use fire-extinguishing media suitable for the surrounding fire Foam carbon dioxide or dry
powder Hazardous combustion products Oxides of carbon Thermal decomposition or combustion may liberate carbon oxides and other toxic gases or
vapours Protective actions during firefighting Control run-off water by containing and keeping it out of sewers and watercourses Special protective
equipment for firefighters Wear positive-pressure self-contained breathing apparatus SCBA and appropriate protective clothing
Spillages :
In case of spills beware of slippery floors and surfaces Do not discharge into drains or watercourses or onto the ground
Storage :
Usage precautions Provide adequate ventilation Avoid contact with skin and eyes Advice on general occupational hygiene No specific hygiene
procedures recommended but good personal hygiene practices should always be observed when working with chemical products Wash at the end of
each work shift and before eating smoking and using the toilet
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 283/471
COSHH ASSESSMENT
Trade Name : 5L SUPER PINE DISINFECTANT QAP30 Class : Detergent. Disinfectant. Washing and cleaning.
GREEN
Manufacture :Coventry Chemicals Limited Phone : 02476 639739
Desc : Detergent. Disinfectant. Washing and cleaning. Format : Liquid
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 284/471
COSHH ASSESSMENT
Trade Name : 732 Multi -Purpose Sealent - Clear Class : Silicone elastomer
Manufacture :Dow Corning Hansil Ltd Phone : 01932 351911
Desc : Silicone elastomer Format : Paste
Constituents
CAS Number Wt Component Name 4253-34-3 1 0 - 5 0 Methyltriacetoxysilane 17689-77-9 1 0 - 5 0 Ethyltriacetoxysilane The above components are hazardous as defined in
29 CFR 1910 1200
Effect :
Acute Effects Eye Direct contact may cause moderate irritation Skin May cause moderate irritation Inhalation Irritates respiratory passages very slightly Oral Low ingestion
hazard in normal use Prolonged Repeated Exposure Effects Skin No known applicable information Inhalation No known applicable information Oral No known applicable
information Signs and Symptoms of Overexposure No known applicable information Medical Conditions Aggravated by Exposure No known applicable information The above
listed potential effects of overexposure are based on actual data results of studies performed upon similar compositions component data and or expert review of the product
Please refer to Section 11 for the detailed toxicology information
Action :
Chemical Stability Stable Hazardous Polymerization Hazardous polymerization will not occur Conditions to Avoid None Materials to Avoid Water moisture or humid air can
cause hazardous vapours to form Oxidizing material can cause a reaction
Protective Clothing :
Engineering Controls - Local Ventilation Recommended General Ventilation Recommended Personal Protective Equipment for Routine Handling - Eyes Use proper protection -
safety glasses as a minimum Skin Wash at mealtime and end of shift Contaminated clothing and shoes should be removed as soon as practical and thoroughly cleaned before
reuse Chemical protective gloves are recommended Suitable Gloves Silver Shield R 4H R Inhalation No respiratory protection should be needed Suitable Respirator None
should be needed Personal Protective Equipment for Spills - Eyes Use proper protection - safety glasses as a minimum Skin Wash at mealtime and end of shift Contaminated
clothing and shoes should be removed as soon as practical and thoroughly cleaned before reuse Chemical protective gloves are recommended Inhalation Suitable Respirator
No respiratory protection should be needed Precautionary Measures Avoid eye contact Avoid skin contact Use reasonable care Comments Product evolves acetic acid HOAc
when exposed to water or humid air Provide ventilation during use to control HOAc within exposure guidelines or use respiratory protection Note These precautions are for
room temperature handling Use at elevated temperature or aerosol spray applications may require added precautions
First Aid :
Eye Immediately flush with water for 15 minutes Get medical attention Skin Remove from skin and wash thoroughly with soap and water or waterless cleanser Get medical
attention if irritation or other ill effects develop or persist Inhalation No first aid should be needed Oral No first aid should be needed Comments Treat according to person s
condition and specifics of exposure
Disposal :
RCRA Hazard Class 40 CFR 261 When a decision is made to discard this material as received is it classified as a hazardous waste No State or local laws may impose
additional regulatory requirements regarding disposal Call Dow Corning Corporate Environmental Management 989 496-6315 if additional information is required
Fire :
Flash Point Not applicable Autoignition Temperature Not determined Flammability Limits in Air Not determined Extinguishing Media Carbon dioxide CO2 Water spray Dry
chemical Foam Water can be used to cool fire exposed containers Fire Fighting Measures Self-contained breathing apparatus and protective clothing should be worn in fighting
large fires involving chemicals Determine the need to evacuate or isolate the area according to your local emergency plan Unusual Fire Hazards None Hazardous
Decomposition Products Thermal breakdown of this product during fire or very high heat conditions may evolve the following hazardous decomposition products Silicon dioxide
Carbon oxides and traces of incompletely burned carbon compounds Hydrogen Formaldehyde
Spillages :
Containment Clean up Wipe up or scrape up and contain for salvage or disposal Observe all personal protection equipment recommendations described in this document Local
state and federal laws and regulations may apply to releases and disposal of this material as well as those materials and items employed in the cleanup of releases You will
need to determine which federal state and local laws and regulations are applicable
Storage :
Use with adequate ventilation Product evolves acetic acid HOAc when exposed to water or humid air Provide ventilation during use to control HOAc within exposure guidelines
or use respiratory protection Avoid eye contact Avoid skin contact Keep container closed and store away from water or moisture
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 285/471
COSHH ASSESSMENT
Trade Name : 732 Multi -Purpose Sealent - Clear Class : Silicone elastomer
Manufacture :Dow Corning Hansil Ltd Phone : 01932 351911
Desc : Silicone elastomer Format : Paste
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 286/471
COSHH ASSESSMENT
Trade Name : 750ML SUPER WAX FREE POLISH Class : Detergent. Cleaning agent. Wax free polish.
Manufacture :Coventry Chemicals Limited Phone : 02476 639739
Desc : Detergent. Cleaning agent. Wax free polish. Format : Liquid
Constituents
ETHANOL 5-10 CAS-No 64-17-5 EC No 200-578-6 Classification 67 548 EEC F R11 Classification EC 1272 2008 Flam Liq 2 - H225 PROPAN-2-OL 2
5-5 CAS-No 67-63-0 EC No 200-661-7 Classification 67 548 EEC F R11 Xi R36 R67 Classification EC 1272 2008 Flam Liq 2 - H225 Eye Irrit 2 - H319
STOT Single 3 - H336 ALKYL ALCOHOL C9-11 ETHOXYLATES 1-2 5 CAS-No 68439-46-3 EC No 266-367-6 Classification 67 548 EEC Xn R22 Xi
R36 38 Classification EC 1272 2008 Acute Tox 4 - H302 Skin Irrit 2 - H315 Eye Irrit 2 - H319
Effect :
General information This product has low toxicity Only large volumes may have adverse impact on human health Inhalation No specific health warnings
noted Ingestion May irritate and cause stomach pain vomiting and diarrhoea Skin contact Skin irritation is not anticipated when used normally Repeated
exposure may cause skin dryness or cracking Eye contact May cause temporary eye irritation
Action :
No specific reactivity hazards associated with this product Stable under normal temperature conditions Not applicable Avoid exposure to high
temperatures or direct sunlight Materials To Avoid No specific or groups of materials are likely to react to produce a hazardous situation
Protective Clothing :
Engineering measures Provide adequate ventilation Respiratory equipment Respiratory protection not required Hand protection For prolonged or
repeated skin contact use suitable protective gloves PVC or rubber gloves are recommended Simple Design for minimal risk Eye protection Wear
approved tight fitting safety glasses where splashing is probable EN 166 Other Protection Use barrier creams to prevent skin contact Wear appropriate
clothing to prevent repeated or prolonged skin contact Hygiene measures When using do not eat drink or smoke Good personal hygiene is necessary
Wash hands and contaminated areas with water and soap before leaving the work site Use appropriate skin cream to prevent drying of skin
First Aid :
Inhalation Move the exposed person to fresh air at once Rinse nose and mouth with water Get medical attention if any discomfort continues Ingestion
NEVER MAKE AN UNCONSCIOUS PERSON VOMIT OR DRINK FLUIDS Rinse mouth thoroughly Get medical attention if any discomfort continues
Skin contact Rinse immediately with plenty of water Remove contaminated clothing Contact physician if irritation continues Eye contact Immediately
flush with plenty of water for up to 15 minutes Remove any contact lenses and open eyelids widely If irritation persists Seek medical attention and bring
along these instructions
Disposal :
General information Do not discharge into drains water courses or onto the ground Dispose of waste and residues in accordance with local authority
requirements Packaging is recyclable Wash out containers with water before disposal
Fire :
Extinguishing media This product is not flammable Use fire-extinguishing media appropriate for surrounding materials Foam carbon dioxide or dry
powder Hazardous combustion products Thermal decomposition or combustion may liberate carbon oxides and other toxic gases or vapours
Spillages :
Stop leak if possible without risk Absorb in vermiculite dry sand or earth and place into containers Flush with plenty of water to clean spillage area Do
not contaminate water sources or sewer In case of spills beware of slippery floors and surfaces
Storage :
Provide good ventilation Avoid contact with skin and eyes Wear protective clothing Good personal hygiene is necessary Wash hands and contaminated
areas with water and soap before leaving the work site Do not eat drink or smoke when using the product
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 287/471
COSHH ASSESSMENT
Trade Name : 750ML SUPER WAX FREE POLISH Class : Detergent. Cleaning agent. Wax free polish.
Manufacture :Coventry Chemicals Limited Phone : 02476 639739
Desc : Detergent. Cleaning agent. Wax free polish. Format : Liquid
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 288/471
COSHH ASSESSMENT
Trade Name : AC95 Acoustic Intumescent Sealant and Adhesive Class : Adhesive
Manufacture :Everbuild Building Products Lt Phone : 0113 240 3456
Desc : Adhesive Format : Paste
Constituents
None relevant
Effect :
Skin Contact There may be mild irritation at the site of contact Eye Contact There may be irritation and redness
Ingestion There may be irritation of the throat Inhalation No symptoms
Action :
Stable under normal conditions Conditions to avoid Heat Materials to avoid Strong oxidising agents Strong acids
Haz decomp products In combustion emits toxic fumes
Protective Clothing :
Respiratory protection Not required Hand protection Protective gloves Eye Protection Safety glasses Ensure eye
bath is to hand Skin protection Protective clothing
First Aid :
Skin Contact Wash immediately with plenty of soap and water Eye Contact Bathe the eye with running water for
15 minutes Ingestion Wast out mouth with water
Disposal :
Dispose of according to local or national regulations
Fire :
Extinguishing media Suitable extinguishing media for the surrounding fire should be used Exposure hazards In
combustion emits toxic fumes Advice for fire-fighters Wear self-contained breathing apparatus Wear protective
clothing to prevent contact with skin and eyes
Spillages :
Environmental Precautions Do not discharge into drains or rivers Clean-up procedures Wash the spillage site with
large amounts of water
Storage :
Storage conditions Store in cool well ventilated area Store in original containers between 5 and 25 degrees
Storage outside these parameters will dramatically reduce shelf life and invalidates all product warranties Suitable
packaging Must only be kept in original packaging
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 289/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 290/471
COSHH ASSESSMENT
Trade Name : ACO Drain Metal Gratings & Covers Class : Plastering
Manufacture :ACO Technologies plc Phone : 01462 816666
Desc : Drainage Format : Solid
Constituents
Steel No given standard Cast Iron No given standard Total inhaleable dust 10mg cu metre 8hr T W A
Effect :
Possible abrasion to hands and skin During cutting grinding etc may project fragments causing impact damage If
cut metal dust will be produced
Action :
Avoid contact with skin and eyes Cutting drilling etc should not be carried out in areas where sparks may cause a
fire or explosion Avoid inhalation of dust
Protective Clothing :
Wear protective gloves Wear safety glasses with eye shields or goggles Wear suitable dust mask to BS EN 149
2001 A1 2009 spec if necessary
First Aid :
Eyes Dust particles in the eyes should be removed by flushing with clean water Eyes Carefully remove small
particles from eyes Seek medical attention if irritation is felt Inhalation If Dust inhaled remove to fresh air and seek
medical advice Skin Wash from skin under running water prior to washing with soap water
Disposal :
Metals should be recovered when possible Dispose of in accordance with Local and National regulations
Fire :
Inert
Spillages :
Not applicable
Storage :
Care should be exercised in stacking product taking into account weight angle of repose stability etc
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 291/471
COSHH ASSESSMENT
Trade Name : ACO Drain Metal Gratings & Covers Class : Plastering
Manufacture :ACO Technologies plc Phone : 01462 816666
Desc : Drainage Format : Solid
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 292/471
COSHH ASSESSMENT
Trade Name : Acrylic Eggshell Class : Decorative coating for application by brush, roller or spray
Manufacture :ZOFFANY LIMITED Phone : 0844 543 4600
Desc : Decorative coating for application by brush, roller or spray Format : Viscous Liquid
Constituents
Description Mixture including the following substances presenting a health or environmental hazard within the meaning of the CHIP Regulations or
which are assigned occupational Workplace Exposure Limits Substance content CAS Number Classification EINECS EU Number Diuron 0 1
000330-54-1 Xn N R40 206-354-4 006-015-00-9 R48 22 R50 53
Effect :
Acute toxicity There is no data available on the product itself Excessive exposure may affect human health as follows Skin contact Repeated or
prolonged contact with the product may lead to removal of natural fats from the skin resulting in non-allergic contact dermatitis Eye contact Splashes in
the eyes may cause irritation Inhalation ingestion Not likely to cause any long term harm
Action :
Conditions to avoid Stable under the recommended storage and handling conditions Materials to avoid Strong acids alkalis and oxidizing agents
Hazardous decomposition In a fire hazardous decomposition products such as smoke carbon monoxide products carbon dioxide and oxides of nitrogen
may be produced
Protective Clothing :
Respiratory protection If exposure to hazardous substances identified above cannot be controlled by the provision of local exhaust ventilation and good
general extraction suitable respiratory protective equipment should be worn Skin Protection Cotton or cotton synthetic overalls or coveralls are normally
suitable Grossly contaminated clothing should be removed and the skin washed with soap and water or a proprietary skin cleaner Regular skin
inspection of users of this product is recommended Eye protection Eye protection designed to protect against liquid splashes should be worn Hand
protection When skin exposure may occur advice should be sought from glove suppliers on appropriate types and usage times for this product Barrier
creams may help to protect exposed areas of skin but are not substitutes for full physical protection They should not be applied once exposure has
occurred Hygiene measures Ensure hands are washed before eating drinking or going to the toilet Apply skin protection cream before handling
Immediately remove any contaminated clothing
First Aid :
General In all cases of doubt or when symptoms persist seek medical attention Never give anything by mouth to an unconscious person Skin contact
Remove contaminated clothing Wash skin thoroughly with soap and water or use a proprietary skin cleanser Do NOT use solvents or thinners Eye
contact Remove contact lenses Irrigate copiously with clean fresh water for at least 10 minutes holding the eyelids apart and seek medical advice
Ingestion If accidentally swallowed obtain immediate medical attention Keep at rest Do NOT induce vomiting Inhalation Remove to fresh air keep patient
warm and at rest If breathing is irregular or has stopped administer artificial respiration Give nothing by mouth If unconscious place in recovery position
and seek medical advice
Disposal :
Wastes including emptied containers are controlled wastes and should be disposed of in accordance with regulations made under The Control of
Pollution Act and The Environmental Protection Act The Hazardous Waste Regulations do not apply to this product Do not allow into drains or water
courses or dispose of where ground or surface waters may be affected
Fire :
Should a fire occur where this material is in use or stored then Suitable extinguishing media Alcohol resistant foam CO2 powder water spray mist
Unsuitable extinguishing media High volume water jet Required special protective equipment Fire will produce dense black smoke containing hazardous
products of for fire-fighters combustion Exposure to decomposition products may be a hazard to health Appropriate self-contained breathing apparatus
may be required Do not allow run-off from fire fighting to enter drains or water courses
Spillages :
Contain and collect spillages with non-combustible absorbent materials e g sand earth vermiculite diatomaceous earth and place in a suitable container
for disposal in accordance with the waste regulations If the product enters drains or sewers immediately contact the local water company in the case of
contamination of streams rivers or lakes the relevant environment agency Methods for cleaning Clean preferably with a detergent avoid the use of
solvents
Storage :
Handling Keep the container tightly closed Avoid skin and eye contact Smoking eating and drinking should be prohibited in areas of use Never use
pressure to empty the container it is not a pressure vessel Always keep in containers made of the same material as the supply container Storage
Observe the label precautions Store between 5 and 25 C in a dry well ventilated place away from sources of heat and direct sunlight Containers which
are opened should be properly resealed and kept upright to prevent leakage Store separately from strongly alkaline and strongly acidic materials
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 293/471
COSHH ASSESSMENT
Trade Name : AcrylicEggshell Class : Decorative coating for application by brush, roller or spray
Manufacture :ZOFFANY LIMITED Phone : 0844 543 4600
Desc : Decorative coating for application by brush, roller or Format : Viscous Liquid
spray
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 294/471
COSHH ASSESSMENT
Trade Name : ACRYLIC TOPCOAT HIGH GLOSS Class : Paint or paint related material. Industrial use only.
Manufacture :SHERWIN-WILLIAMS Italy S.r.l. Phone : 39 051 770511
Desc : Paint or paint related material. Industrial use only. Format : Liquid
Constituents
n-Butyl Acetate Xylene Methyl Isobutyl Ketone Identifiers Classification Regulation EC No 1272 2008 CLP Type 1 2 1 2 1 2 REACH 01-2119485493-29 EC 204-658-1 CAS
123-86-4 Index 607-025-00-1 REACH 01-2119488216-32 EC 215-535-7 CAS 1330-20-7 Index 601-022-00-9 REACH 01-2119473980-30 EC 203-550-1 CAS 108-10-1 10 - 25
14 5 9 Flam Liq 3 H226 STOT SE 3 H336 EUH066 Flam Liq 3 H226 Acute Tox 4 H312 Acute Tox 4 H332 Skin Irrit 2 H315 Eye Irrit 2 H319 STOT SE 3 H335 STOT RE 2 H373
Asp Tox 1 H304 Flam Liq 2 H225 Acute Tox 4 H332 Eye Irrit 2 H319 STOT SE 3 H335 1-Methoxy-2-Propanol Acetate Ethylbenzene Toluene Methyl Methacrylate
2-Hydroxyethyl Methacrylate UV Light Absorber Butyl Acrylate Benzotriazole Hydroxyphenyl Polymer Index 606-004-00-4 REACH 5 01-2119475794-29 EC 203-603-9 CAS
108-65-6 Index 607-195-00-7 REACH 3 01-2119489370-35 EC 202-849-4 CAS 100-41-4 Index 601-023-00-4 REACH 1 01-2119471310-51 EC 203-625-9 CAS 108-88-3
Index 601-021-00-3 REACH 1 01-2119452498-28 EC 201-297-1 CAS 80-62-6 Index 607-035-00-6 REACH 0 3 01-2119490169-29 EC 212-782-2 CAS 868-77-9 Index
607-124-00-X CAS 104810-48-2 0 3 REACH 0 3 01-2119453155-43 EC 205-480-7 CAS 141-32-2 Index 607-062-00-3 CAS 104810-47-1 0 3 EUH066 Flam Liq 3 H226 Flam
Liq 2 H225 Acute Tox 4 H332 STOT RE 2 H373 hearing organs Asp Tox 1 H304 Flam Liq 2 H225 Skin Irrit 2 H315 Repr 2 H361d Unborn child STOT SE 3 H336 STOT RE 2
H373 Asp Tox 1 H304 Flam Liq 2 H225 Skin Irrit 2 H315 Skin Sens 1 H317 STOT SE 3 H335 Skin Irrit 2 H315 Eye Irrit 2 H319 Skin Sens 1 H317 Skin Sens 1 H317 Aquatic
Chronic 2 H411 Flam Liq 3 H226 Skin Irrit 2 H315 Eye Irrit 2 H319 Skin Sens 1 H317 STOT SE 3 H335 Skin Sens 1 H317 Aquatic Chronic 2 H411
Effect :
n-Butyl Acetate Xylene Methyl Isobutyl Ketone 1-Methoxy-2-Propanol Acetate Ethylbenzene Toluene Methyl Methacrylate 2-Hydroxyethyl Methacrylate Butyl Acrylate LD50
Dermal LD50 Oral LC50 Inhalation Gas LD50 Oral LD50 Oral LD50 Dermal LD50 Oral LD50 Dermal LD50 Oral LC50 Inhalation Vapour LD50 Oral LC50 Inhalation Vapour
LD50 Dermal LD50 Oral LD50 Oral LC50 Inhalation Gas LD50 Oral Rabbit Rat Rat Rat Rat Rabbit Rat Rabbit Rat Rat Rat Rat Rabbit Rat Rat Rat Rat 17600 mg kg 10768 mg
kg 5000 ppm 4300 mg kg 2080 mg kg 5 g kg 8532 mg kg 5000 mg kg 3500 mg kg 49 g m3 636 mg kg 78000 mg m3 5 g kg 7872 mg kg 5050 mg kg 2730 ppm 900 mg kg - - 4
hours - - - - - - 4 hours - 4 hours - - - 4 hours - Dermal Inhalation gases Inhalation vapours 8141 mg kg 37004 4 ppm 136 mg l n-Butyl Acetate Xylene Methyl Isobutyl Ketone
Ethylbenzene Toluene Butyl Acrylate Eyes - Moderate irritant Skin - Moderate irritant Eyes - Mild irritant Eyes - Severe irritant Skin - Mild irritant Skin - Moderate irritant Skin -
Moderate irritant Eyes - Moderate irritant Eyes - Severe irritant Skin - Mild irritant Eyes - Severe irritant Skin - Mild irritant Eyes - Mild irritant Eyes - Mild irritant Eyes - Severe
irritant Skin - Mild irritant Skin - Mild irritant Skin - Moderate irritant Skin - Moderate irritant Eyes - Mild irritant Eyes - Mild irritant Skin - Mild irritant Skin - Mild irritant Rabbit
Rabbit Rabbit Rabbit Rat Rabbit Rabbit Rabbit Rabbit Rabbit Rabbit Rabbit Rabbit Rabbit Rabbit Pig Rabbit Rabbit Rabbit Rabbit Rabbit Rabbit Rabbit - - - - - - - - - - - - - - - - -
- - - - - - 100 milligrams 24 hours 500 milligrams 87 milligrams 24 hours 5 milligrams 8 hours 60 microliters 24 hours 500 milligrams 100 Percent 24 hours 100 microliters 40
milligrams 24 hours 500 milligrams 500 milligrams 24 hours 15 milligrams 0 5 minutes 100 milligrams 870 Micrograms 24 hours 2 milligrams 24 hours 250 microliters 435
milligrams 24 hours 20 milligrams 500 milligrams 24 hours 500 milligrams 50 milligrams 24 hours 10 milligrams 500 milligrams - - - - - - - - - - - - - - - - - - - - - - -
Action :
No specific test data related to reactivity available for this product or its ingredients Stable under recommended storage and handling conditions 10 4 Conditions to avoid 10 5
Incompatible materials 10 6 Hazardous decomposition products The product reacts slowly with water resulting in the production of carbon dioxide In closed containers pressure
build-up could result in distortion expansion and in extreme cases bursting of the container In a fire hazardous decomposition products may be produced Keep away from
oxidising agents strong alkalis strong acids amines alcohols water Uncontrolled exothermic reactions occur with amines and alcohols Under normal conditions of storage and
use hazardous decomposition products should not be produced
Protective Clothing :
Wear suitable gloves tested to EN374 Short Term Exposure less than 30 minutes Continuous use LDPE gloves 30 microns or Butyl gloves 0 7mm Long Term Exposure Spill
For prolonged or repeated handling use PE PE Laminate gloves 8 hours breakthrough time There is no one glove material or combination of materials that will give unlimited
resistance to any individual or combination of chemicals The breakthrough time must be greater than the end use time of the product The instructions and information provided
by the glove manufacturer on use storage maintenance and replacement must be followed Gloves should be replaced regularly and if there is any sign of damage to the glove
material Always ensure that gloves are free from defects and that they are stored and used correctly The performance or effectiveness of the glove may be reduced by physical
chemical damage and poor maintenance Barrier creams may help to protect the exposed areas of the skin but should not be applied once exposure has occurred The user
must check that the final choice of type of glove selected for handling this product is the most appropriate and takes into account the particular conditions of use as included in
the user s risk assessment Personnel should wear antistatic clothing made of natural fibres or of high- temperature-resistant synthetic fibres Personal protective equipment for
the body should be selected based on the task being performed and the risks involved and should be approved by a specialist before handling this product When there is a risk
of ignition from static electricity wear anti-static protective clothing For the greatest protection from static discharges clothing should include anti-static overalls boots and gloves
Refer to European Standard EN 1149 for further information on material and design requirements and test methods Appropriate footwear and any additional skin protection
measures should be selected based on the task being performed and the risks involved and should be approved by a specialist before handling this product Use a properly
fitted air-purifying or air-fed respirator complying with an approved standard if a risk assessment indicates this is necessary Respirator selection must be based on known or
anticipated exposure levels the hazards of the product and the safe working limits of the selected respirator
First Aid :
General Eye contact Inhalation In all cases of doubt or when symptoms persist seek medical attention Never give anything by mouth to an unconscious person If unconscious
place in recovery position and seek medical advice Remove contact lenses irrigate copiously with clean fresh water holding the eyelids apart for at least 10 minutes and seek
immediate medical advice Remove to fresh air Keep person warm and at rest If not breathing if breathing is irregular or if respiratory arrest occurs provide artificial respiration
or oxygen by trained personnel
Disposal :
The generation of waste should be avoided or minimised wherever possible Disposal of this product solutions and any by-products should at all times comply with the
requirements of environmental protection and waste disposal legislation and any regional local authority requirements Dispose of surplus and non- recyclable products via a
licensed waste disposal contractor Waste should not be disposed of untreated to the sewer unless fully compliant with the requirements of all authorities with jurisdiction Yes
waste isocyanates 08 05 01 Do not allow to enter drains or watercourses Residues in empty containers should be neutralised with a decontaminant Dispose of according to all
federal state and local applicable regulations If this product is mixed with other wastes the original waste product code may no longer apply and the appropriate code should be
assigned For further information contact your local waste authority The generation of waste should be avoided or minimised wherever possible Waste packaging should be
recycled Incineration or landfill should only be considered when recycling is not feasible Using information provided in this safety data sheet advice should be obtained from the
relevant waste authority on the classification of empty containers Empty containers must be scrapped or reconditioned Dispose of containers contaminated by the product in
accordance with local or national legal provisions European waste catalogue EWC 10 Special precautions This material and its container must be disposed of in a safe way
Care should be taken when handling emptied containers that have not been cleaned or rinsed out Empty containers or liners may retain some product residues Vapour from
product residues may create a highly flammable or explosive atmosphere inside the container Do not cut weld or grind used containers unless they have been cleaned
thoroughly internally Avoid dispersal of spilt material and runoff and contact with soil waterways drains and sewers
Fire :
Remove contaminated clothing and shoes Wash skin thoroughly with soap and water or use recognised skin cleanser Do NOT use solvents or thinners If swallowed seek
medical advice immediately and show the container or label Keep person warm and at rest Do NOT induce vomiting No action shall be taken involving any personal risk or
without suitable training If it is suspected that fumes are still present the rescuer should wear an appropriate mask or self-contained breathing apparatus It may be dangerous to
the person providing aid to give mouth-to-mouth resuscitation
Spillages :
Keep unnecessary and unprotected personnel from entering If specialised clothing is required to deal with the spillage take note of any information on suitable and unsuitable
materials See also the information in For non-emergency personnel Do not allow to enter drains or watercourses If the product contaminates lakes rivers or sewers inform the
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 295/471
appropriate authorities in accordance with local regulations Contain and collect spillage with non-combustible absorbent material e g sand earth vermiculite or diatomaceous
earth and place in container for disposal according to local regulations see Section 13 Place in a suitable container The contaminated area should be cleaned immediately with
a suitable decontaminant One possible flammable decontaminant comprises by volume water 45 parts ethanol or isopropyl alcohol 50 parts and concentrated d 0 880 ammonia
solution 5 parts A non-flammable alternative is sodium carbonate 5 parts and water 95 parts Add the same decontaminant to the remnants and let stand for several days until
no further reaction in an unsealed container Once this stage is reached close container and dispose of according to local regulations
Storage :
Prevent the creation of flammable or explosive concentrations of vapours in air and avoid vapour concentrations higher than the occupational exposure limits In addition the
product should only be used in areas from which all naked lights and other sources of ignition have been excluded Electrical equipment should be protected to the appropriate
standard Mixture may charge electrostatically always use earthing leads when transferring from one container to another Operators should wear antistatic footwear and
clothing and floors should be of the conducting type Care should be taken when re-opening partly-used containers Precautions should be taken to minimise exposure to
atmospheric humidity or water CO2 will be formed which in closed containers could result in pressurisation Keep away from heat sparks and flame No sparking tools should be
used Avoid contact with skin and eyes Avoid the inhalation of dust particulates spray or mist arising from the application of this mixture Avoid inhalation of dust from sanding
Eating drinking and smoking should be prohibited in areas where this material is handled stored and processed Put on appropriate personal protective equipment see Section 8
Never use pressure to empty Container is not a pressure vessel Always keep in containers made from the same material as the original one Comply with the health and safety
at work laws Do not allow to enter drains or watercourses Information on fire and explosion protection Vapours are heavier than air and may spread along floors Vapours may
form explosive mixtures with air When operators whether spraying or not have to work inside the spray booth ventilation is unlikely to be sufficient to control particulates and
solvent vapour in all cases In such circumstances they should wear a compressed air-fed respirator during the spraying process and until such time as the particulates and
solvent vapour concentration has fallen below the exposure limits
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 296/471
COSHH ASSESSMENT
Trade Name : ACRYLIC TOPCOAT HIGH GLOSS Class : Paint or paint related material. Industrial use only.
Manufacture :SHERWIN-WILLIAMS Italy S.r.l. Phone : 39 051 770511
Desc : Paint or paint related material. Industrial use only. Format : Liquid
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 297/471
COSHH ASSESSMENT
Trade Name : All purpose Tile Adhesive & Grout Class : Adhesives
Manufacture :Unibond - Copydex Phone : 01276 685345
Desc : Plastering Format : White Paste
Constituents
None Listed Not applicable
Effect :
Prolonged or repeated contact with skin can cause irritation or dermatitis Mildly irritant in contact with eyes and
skin
Action :
Avoid contact with skin and eyes
Protective Clothing :
No protective clothing required in normal use
First Aid :
Eyes Irrigate eyes with copious amounts of clean fresh water for at least 10 mins Seek medical advice Ingestion If
swallowed wash out mouth with water and give no more than a cupful to drink Skin Wash with lukewarm water
before product hardens
Disposal :
Dispose of in a safe manner
Fire :
Non-combustible
Spillages :
Pick up discarded material and place in suitable container If water courses drains are contaminated inform the
local water company or National Rivers Authority Do not allow to enter drains or water courses Do not allow to
enter drains or water courses
Storage :
Store under cover Protect from frost Keep in a secure dry well ventilated area Store at temperatures below 30
degrees C
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 298/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 299/471
COSHH ASSESSMENT
Trade Name : ALL PURPOSE WOOD FILLER Class : Filler for interior and exterior use.
Manufacture :ICI Paints AkzoNobel Phone : 44 (0) 333 222 70 7
Desc : Filler for interior and exterior use. Format : Liquid
Constituents
There are no ingredients present which within the current knowledge of the supplier and in the concentrations applicable are classified as hazardous to health or the
environment are PBTs vPvBs or Substances of equivalent concern or have been assigned a workplace exposure limit and hence require reporting in this section
Effect :
There are no data available on the mixture itself The product is not classified as hazardous according to Regulation EC 1272 2008 as amended If splashed in the eyes the
liquid may cause irritation and reversible damage This takes into account where known delayed and immediate effects and also chronic effects of components from short-term
and long-term exposure by oral inhalation and dermal routes of exposure and eye contact Contains 1 2-benzisothiazol-3 2H -one reaction mass of
5-chloro-2-methyl-4-isothiazolin-3-one EC no 247-500-7 and 2-methyl-2H-isothiazol-3-one EC no 220-239-6 3 1 May produce an allergic reaction
Action :
No specific test data related to reactivity available for this product or its ingredients Stable under recommended storage and handling conditions Under normal conditions of
storage and use hazardous reactions will not occur When exposed to high temperatures may produce hazardous decomposition products Keep away from the following
materials to prevent strong exothermic reactions oxidising agents strong alkalis strong acids Under normal conditions of storage and use hazardous decomposition products
should not be produced
Protective Clothing :
Hand protection Eye face protection Skin protection Appropriate engineering controls Wash hands forearms and face thoroughly after handling chemical products before eating
smoking and using the lavatory and at the end of the working period Appropriate techniques should be used to remove potentially contaminated clothing Wash contaminated
clothing before reusing Ensure that eyewash stations and safety showers are close to the workstation location Hygiene measures Individual protection measures There is no
one glove material or combination of materials that will give unlimited resistance to any individual or combination of chemicals The breakthrough time must be greater than the
end use time of the product The instructions and information provided by the glove manufacturer on use storage maintenance and replacement must be followed Gloves should
be replaced regularly and if there is any sign of damage to the glove material Always ensure that gloves are free from defects and that they are stored and used correctly The
performance or effectiveness of the glove may be reduced by physical chemical damage and poor maintenance Barrier creams may help to protect the exposed areas of the
skin but should not be applied once exposure has occurred Not applicable Gloves Body protection Other skin protection Appropriate footwear and any additional skin protection
measures should be selected based on the task being performed and the risks involved and should be approved by a specialist before handling this product For prolonged or
repeated contact use protective gloves Barrier creams may help to protect the exposed areas of skin they should however not be applied once exposure has occurred Skin
should be washed after contact Use chemical resistant gloves classified under Standard EN 374 Protective gloves against chemicals and micro-organisms Recommended
gloves Viton or Nitrile Breakthrough Time 480 min When prolonged or frequently repeated contact may occur a glove with a protection class of 6 breakthrough time greater
than 480 minutes according to EN 374 is recommended When only brief contact is expected a glove with a protection class of 2 or higher breakthrough time greater than 30
minutes according to EN 374 is recommended NOTICE The selection of a specific glove for a particular application and duration of use in a workplace should also take into
account all relevant workplace factors such as but not limited to Other chemicals which may be handled physical requirements cut puncture protection dexterity thermal
protection potential body reactions to glove materials as well as the instructions specifications provided by the glove supplier The user must check that the final choice of type
of glove selected for handling this product is the most appropriate and takes into account the particular conditions of use as included in the user s risk assessment Usually no
respiratory protection required Respiratory protection in case of dust or spray mist formation particle filter EN143 type P2 Respiratory protection in case of vapour formation half
mask with combination filter A2-P2 till concentrations of 0 5 Vol Do not allow to enter drains or watercourses
First Aid :
Remove contact lenses irrigate copiously with clean fresh water holding the eyelids apart for at least 10 minutes and seek immediate medical advice Remove contaminated
clothing and shoes Wash skin thoroughly with soap and water or use recognised skin cleanser Do NOT use solvents or thinners Remove to fresh air Keep person warm and at
rest If not breathing if breathing is irregular or if respiratory arrest occurs provide artificial respiration or oxygen by trained personnel General In all cases of doubt or when
symptoms persist seek medical attention Never give anything by mouth to an unconscious person If unconscious place in recovery position and seek medical advice If
swallowed seek medical advice immediately and show the container or label Keep person warm and at rest Do NOT induce vomiting
Disposal :
The generation of waste should be avoided or minimised wherever possible Disposal of this product solutions and any by-products should at all times comply with the
requirements of environmental protection and waste disposal legislation and any regional local authority requirements Dispose of surplus and nonrecyclable products via a
licensed waste disposal contractor Waste should not be disposed of untreated to the sewer unless fully compliant with the requirements of all authorities with jurisdiction Do not
allow to enter drains or watercourses Dispose of according to all federal state and local applicable regulations If this product is mixed with other wastes the original waste
product code may no longer apply and the appropriate code should be assigned For further information contact your local waste authority The generation of waste should be
avoided or minimised wherever possible Waste packaging should be recycled Incineration or landfill should only be considered when recycling is not feasible This material and
its container must be disposed of in a safe way Empty containers or liners may retain some product residues Avoid dispersal of spilt material and runoff and contact with soil
waterways drains and sewers
Fire :
Recommended alcohol-resistant foam CO2 powders water spray Do not use water jet Fire will produce dense black smoke Exposure to decomposition products may cause a
health hazard Cool closed containers exposed to fire with water Do not release runoff from fire to drains or watercourses Appropriate breathing apparatus may be required
Decomposition products may include the following materials carbon monoxide carbon dioxide smoke oxides of nitrogen
Spillages :
Do not allow to enter drains or watercourses If the product contaminates lakes rivers or sewers inform the appropriate authorities in accordance with local regulations
Environmental precautions for containment and cleaning up For non-emergency personnel For emergency responders If specialised clothing is required to deal with the
spillage take note of any information in Secton suitable and unsuitable materials See also the information in For non-emergency personnel
Storage :
Avoid contact with skin and eyes Avoid inhalation of vapour spray or mist Eating drinking and smoking should be prohibited in areas where this material is handled stored and
processed Put on appropriate personal protective equipment Never use pressure to empty Container is not a pressure vessel Always keep in containers made from the same
material as the original one Comply with the health and safety at work laws Do not allow to enter drains or watercourses
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 300/471
COSHH ASSESSMENT
Trade Name : ALL PURPOSE WOOD FILLER Class : Filler for interior and exterior use.
Manufacture :ICI Paints AkzoNobel Phone : 44 (0) 333 222 70 7
Desc : Filler for interior and exterior use. Format : Liquid
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 301/471
COSHH ASSESSMENT
Trade Name : All types of Sand, Gravel, Granite, Gritstone, Crushed Class : All types of Sand, Gravel, Granite, Gritstone, Crushed Rock
Rock containing Quartz, Limestone. containing Quartz, Limestone.
Manufacture :Tarmac Trupak Phone : 01302 718400
Desc : All types of Sand, Gravel, Granite, Gritstone, Crushed Rock Format : Solid
containing Quartz, Limestone.
Constituents
Natural aggregates are produced from naturally occurring rock sand and gravel deposits and consists of combinations of various minerals including
silica This product contains free crystalline silica quartz in the range of 30 to 100
Effect :
Health effects On Eyes On Skin By Inhalation By Ingestion Chronic Exposure Others May cause transient irritation Unlikely to cause harm on brief or
occasional contact Inhalation of large quantities of respirable silica may lead to progressive lung damage This may cause permanent disability and in
extreme cases may be fatal Unlikely to cause harm High level exposure to silica may cause progressive silicosis None known
Action :
Not applicable
Protective Clothing :
Occupational Exposure Limits Free Crystalline silica Maximum Exposure Limit - 4mg cu Metre respirable dust 8 hour time weighted average
Recommended Short Term Exposure Limit 1 2mg cu Metre respirable dust 15mins reference period All types of dust have an Occupational Exposure
Standard of 10mg cu metre inhalable dust 8 hour time weighted average Recommended Short Term Exposure Limit 30mg cu metre 15 mins reference
period Engineering Control Measures Personal Protection Hand Protection Eye Protection See section 7 Handling Storage Respiratory protection to
HSE approved standard Abrasive resistant gloves To HSE Approved standard for dust goggles
First Aid :
Irrigate or flood the eye s with copious amounts of clean water Seek medical advice if the particles cannot be removed by this method Wash with water
Remove from exposure to fresh air
Disposal :
Is not classified as hazardous for disposal purposes Subject to local authority requirements
Fire :
None required aggregates are non-flammable
Spillages :
Personal Precautions Environmental measures Method of Cleaning In the event of a spillage or leakage wear eye protection Avoid breathing dust by
wearing respiratory protective equipment No hazard Aggregates should be disposed of in accordance with local authority requirements Use methods
which will minimise generation of dust Avoid dry sweeping If possible spray the material with mater to prevent airbourne dust If a vacuum system is
used to clear up dry material the vacuum should be fitted with a high efficiency filter suitable for harmful dusts
Storage :
The product should be handled and stored to minimise generation of dust Avoid dry sweeping If possible spray the material with water to prevent
airbourne dust If a vacuum system is used to clear up dry material the vacuum should be fitted with a high efficiency filter suitable for harmful dusts
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 302/471
COSHH ASSESSMENT
Trade Name : All types of Sand, Gravel, Granite, Gritstone, Class : All types of Sand, Gravel, Granite, Gritstone, Crushed Rock
containing Quartz, Limestone.
Crushed Rock containing Quartz, Limestone.
Manufacture :Tarmac Trupak Phone : 01302 718400
Desc : All types of Sand, Gravel, Granite, Gritstone, Format : Solid
Crushed Rock containing Quartz, Limestone.
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 303/471
COSHH ASSESSMENT
Constituents
Hydraulic Cement No given standard Silica Flour 0 1mg cu metre 8hr T W A
Effect :
Harmful by inhalation
Action :
Avoid inhalation of dust
Protective Clothing :
First Aid :
Eyes Irrigate eyes with copious amounts of clean fresh water for at least 10 mins Seek medical advice Skin Rinse
contaminated area of skin with plenty of water Ingestion If swallowed wash mouth with water give plenty of water
to drink seek medical advice asap Inhalation If inhaled remove to fresh air and rest
Disposal :
Dispose of in a safe manner
Fire :
Non flammable
Spillages :
Wash spillages with large amounts of water
Storage :
No special requirements
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 304/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 305/471
COSHH ASSESSMENT
Constituents
Aluminum Silicates Various 75-85 Quartz 14808-60-7 Varies Iron Compounds Various 0-5 Calcium Compounds Various 0-12 Manganese Compounds
Various 0-3 Magnesium Compounds Various 0-3 Zinc Compounds 1314-13-2 0-10 Iron Chromite 1308-31-2 0-3
Effect :
Eyes May cause irritation by abrasion with dust chips Skin Brick dust or chips may cause allergic reactions in hypersensitive individuals may cause cuts
and skin abrasions Inhalation Brick dust or chips may cause congestion and irritation in nasal and respiratory passages Ingestion No known acute
effects Excessive exposures to reparable particulates dust over an extended period of time may result in the development of pulmonary diseases such
as silicosis
Action :
Not Applicable
Protective Clothing :
Feet Use of steel toe shoes is recommended when handling brick Eyes and Face Face shields should be used when sawing brick Skin Use gloves and
or protective clothing if abrasions or allergic reactions are experienced OTHER Use of wet sawing methods is recommended anytime that bricks must
be cut
First Aid :
If exposed or concerned Get medical advice attention If skin rash occurs Get medical advice attention If in eyes Rinse cautiously with water for several
minutes Remove contact lenses if present and easy to do Continue rinsing If eye irritation persists Get medical advice attention If brick dust is inhaled
Remove person to fresh air and keep comfortable for breathing Call poison center doctor if you feel unwell Ingestion None no known acute effects
Inhalation Remove from exposure to airborne particulates Consult a physician if breathing does not return to normal Medical Conditions Excessive dust
exposure may aggravate any existing respiratory disorders or diseases Aggravated by Exposure Possible complications or allergies resulting in irritation
to skin eyes and respiratory tract may occur from excessive exposure to dusts
Disposal :
Dispose of waste in accordance with all applicable laws and regulations
Fire :
Extinguishing Media Not Applicable Advice for Fire-Fighters None
Spillages :
Not Applicable
Storage :
Minimize dust generation and accumulation Avoid breathing dust
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 306/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 307/471
COSHH ASSESSMENT
Constituents
Unknown Not applicable
Effect :
Mildly irritant in contact with eyes and skin
Action :
Avoid creation of dust Silica Avoid inhalation of dust Silica
Protective Clothing :
Wear appropriate protective clothing
First Aid :
Eyes Irrigate eyes with copious amounts of clean fresh water for at least 10 mins Seek medical advice Skin Wash
from skin with a recognised hand cleaner and then with soap and water
Disposal :
Dispose of to site accepting builders waste
Fire :
Non flammable
Spillages :
Not applicable
Storage :
Not applicable
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 308/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 309/471
COSHH ASSESSMENT
Constituents
Dry processed fibreboard having moisture content of less than 20 at the forming stage and having a density 450 kg m3 These boards are essentially produced under heat and
pressure with the addition of a synthetic adhesive
Effect :
Health The following health problems are among the effects that have been associated with exposure to wood dust - Skin disorders - Obstruction in the nose and rhinitis -
Asthma - a rare type of nasal cancer a Exposure Controls During processing adequate ventilation and or extraction should be provided to minimise airborne dust Whenever
possible fit dust extraction equipment even when using hand-held machines b Personal Protection Dust will be created during processing use appropriate respiratory protection
equipment Wear gloves and overalls as required to prevent skin contact Wear eye protection to prevent dust particles from entering eyes Wear the correct clothing and use
other safety equipment as necessary
Action :
a Materials to avoid Reducing and oxidising agents b Conditions to avoid Heating and ignition sources and damp atmospheres Thermal decomposition products may include
CO CO2 aldehydes including formaldehyde HCHO particulate matter and other organic compounds c Other Hazards Processing of MDF will generate wood dust Appropriate
protection from inhalation of the dust is recommended See section 8 also refer to Safe collection of wood waste Prevention of fire and explosion WIS32 HSE Books 1997 and
Safe handling of combustible dusts HSG103 HSE books1994
Protective Clothing :
In bulk wood is unlikely to give rise to toxicological effects the hazardous forms that may give rise to health risks are dust and sap latex or lichens associated with the wood a
Immediate Hazards Inhalation Skin Eyes Dust generated during processing may cause irritation of the nose and throat Dust generated during processing may cause irritation
Dust generated during processing may cause irritation MDF is largely composed of softwood bound together usually with a urea formaldehyde or melamine urea formaldehyde
resin When it is machined very fine dust is produced Just like natural wood dust this is a potentially hazardous substance and it must be controlled For example wood dust can
cause skin disorders and asthma Hardwood dust in particular can very rarely cause nasal cancer - and as such is classified as a carcinogen in Control Of Substances
Hazardous to Health COSHH Regulations The evidence that softwood dust can cause cancer is less conclusive It is not classified as a carcinogen in the UK However all wood
can cause irritation and we draw your attention to the guidance given in HSE woodworking sheet no 30 Toxic woods Under COSHH Regulations softwood dust has a maximum
exposure limit MEL of 5 mg m3 8 hr TWA - this is the relevant limit for controlling exposure to MDF dust Exposure must be reduced as far as is reasonably practicable below
this limit - usually with properly designed and maintained dust extraction equipment fitted to woodworking machines When using portable or hand-held tools extraction
equipment often is not practicable or available in which case a suitable dust mask should be worn If possible MDF should be machined in a well-ventilated workplace for
example outside
First Aid :
Inhalation Inhalation of MDF dust can only occur during processing If inhalation of dust causes adverse effects remove to fresh air If discomfort persists seek medical advice
Skin In case of irritation from dust generated from processing of MDF wash with water Eyes If particles enter the eyes during processing immediately flush eyes with plenty of
water Seek medical attention if irritation persists
Disposal :
Manufacturing waste must be disposed of as a controlled waste Special consideration should be given to containing dust to prevent spillage during transit
Fire :
Non-flammable at room temperature but will burn In case of fire soak flood with water For large fires fire fighters should wear full emergency protective equipment including self-
contained breathing apparatus Wood waste or dust may present a fire or explosion hazard- good housekeeping practises must be followed
Spillages :
MDF does not represent a hazard in sheet form However dust generated from processing MDF should be contained carefully collected and removed
Storage :
a Manual Handling In sheet form MDF can present a manual handling risk due to its physical dimensions and weight Good lifting practice should be followed Note A 2440 mm
by 1220 mm sheet of 18 mm standard MDF weighs approximately 40 Kg
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 310/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 311/471
COSHH ASSESSMENT
Constituents
Calcium Silicates 10 mg cu metre inhalable dust Gypsum 5 mg cu metre respirable dust 8 hr TWA Aluminates
10mg cu metre 8hr T W A Fero-Aluminates No given standard Sulfates No given standard Alkali No given
standard Chlorides No given standard Lime No given standard
Effect :
Irritant in contact with eyes Harmful if inhaled in dust form Irritant after prolonged contact with skin
Action :
Avoid contact with skin or eyes Remove contaminated clothing Avoid creation of dust Use only in well ventilated
area
Protective Clothing :
Wear suitable dust mask to BS EN 149 2001 A1 2009 spec if necessary Wear appropriate gloves and eye face
protection Wear protective clothing to cover all areas of skin which will come into contact with this product
First Aid :
Ingestion If swallowed DO NOT induce vomiting give plenty of water to drink and seek medical advice Seek
immediate medical attention Inhalation If inhaled take to fresh air transfer to hospital at any sign of dizziness or
breathing difficulties Eyes Irrigate eyes with copious amounts of clean fresh water for at least 10 mins Seek
medical advice Skin Wash from skin with a recognised hand cleaner and then with soap and water
Disposal :
Dispose of in accordance with Local Authority Regulations
Fire :
Non flammable
Spillages :
Sweep or pick up by vacuum cleaner Wear suitable respiratory equipment when clearing spillages
Storage :
Store in a cool dry area
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 312/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 313/471
COSHH ASSESSMENT
Constituents
Mercaptan Terminated Polymer No given standard 2 1 6-Tri Dimethylamino Methyl Phenol 5 p p m 8hr T W A
Effect :
Irritant in contact with eyes and skin Irritant to respiratory system Irritant by ingestion
Action :
Wash hands thoroughly after use Avoid contact with skin and eyes Avoid breathing fumes Do not eat drink or
smoke when using Ensure adequate ventilation
Protective Clothing :
Wear P V C neoprene or other solvent resisting gloves Wear goggles to BS 2092 2C or BS EN166 1FD
specification Wear coveralls Wear suitable respiratory equipment to BS EN 405 A1 P3 where ventilation is
insufficient
First Aid :
Skin Thoroughly wash from skin with soap and water Eyes Irrigate eyes with copious amounts of water for 5
minutes seek medical attention Inhalation If inhaled remove to fresh air and seek immediate medical attention
Ingestion If swallowed DO NOT induce vomiting - seek medical advice
Disposal :
Dispose of in accordance with Local Authority Regulations
Fire :
Gives off toxic gases if burnt wear self contained breathing equipment Cool containers exposed to heat with water
spray provided it is safe to do so Use foam dry powder or C02 extinguishers Water spray extinguishers may be
used
Spillages :
Place Contaminated material into suitable container for disposal Wear appropriate protective clothing Contain
spillages and soak up with sand or earth
Storage :
Do not store near epoxy resins Keep containers tightly sealed
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 314/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 315/471
COSHH ASSESSMENT
Constituents
Mono Ethylene Glycol 10 mg cu Metre 8hr T W A Particulate Pigments No given standard Carbon Black 3 5 mg
cu metre 8hr T W A Dust 10 mg cu Metre 8hr T W A Total Inhalable Dust Glycol Ether solvents 10 p p m 8hr T W
A Dust 5 mg cu metre respirable dust 8 hr TWA
Effect :
May cause sensitisation by skin contact May cause irritation to skin with prolonged contact If ingested may cause
slight irritation of mouth and upper digestive tract May cause irritation to the eyes
Action :
Avoid contact with skin or eyes Remove contaminated clothing Use only in a well ventilated area if necessary
local exhaust ventilation should be provided Ensure adequate personal hygiene Wash hands and exposed skin
before eating drinking or smoking and after work
Protective Clothing :
Wear chemically resistant gloves footwear and coveralls Wear safety glasses with eye shields or goggles
First Aid :
Ingestion If swallowed DO NOT induce vomiting Wash out mouth with water and seek medical attention Skin
Wash with soap and water Eyes In case of contact with eyes rinse immediately with water Inhalation If inhaled
remove to fresh air keep warm and at rest
Disposal :
Dispose of in accordance with Local and National regulations
Fire :
Use foam dry chemical carbon dioxide or water spray extinguishers Cool containers exposed to heat with water
spray provided it is safe to do so Wear self contained breathing equipment Combustion may release noxious
fumes
Spillages :
Wear eye protection chemically resistant gloves boots and coveralls Do not allow to enter drains or water courses
Contain and collect spillage Place in plastic container for disposal DO NOT MIX with other waste materials
Storage :
Avoid strong oxidising agents
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 316/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 317/471
COSHH ASSESSMENT
Trade Name : DECORATORS VARNISH GLOSS, SATIN, DEAD Class : DECORATORS VARNISH GLOSS, SATIN, DEAD FLAT.
FLAT.
Manufacture :Polyvine Limited Phone : 44 845 017 1671
Desc : DECORATORS VARNISH GLOSS, SATIN, DEAD FLAT. Format : Milky liquid
Constituents
Water based dispersion of methacrylic esters with no hazard classification Chemical characterisation Acrylic CAS N o Names Conc
Effect :
INHALATION - May be irritating to respiratory system INGESTION - May be harmful if swallowed SKIN CONTACT- may cause skin irritation LONG
TERM EXPOSURE - No information available
Action :
This product is stable under normal conditions of use
Protective Clothing :
Respiratory - Hand - Eye - Skin - O E L Masks when spraying Gloves if risk of skin contact Goggles if risk of splashing Standard industrial overalls if
splashing
First Aid :
GENERAL Immediately remove all contaminated clothing In all cases of doubt or when symptoms persist seek proper medical attention Never give
anything by mouth to an unconscious person INHALATION Remove to fresh air keep patient warm and at rest if breathing is irregular or stopped
administer artificial respiration Giving nothing by mouth If unconscious place in recovery position and seek medical advice EYE CONTACT Holding
eyelids apart flush copiously with clean fresh water for at least 10 minutes and seek medical advice SKIN CONTACT Remove contaminated clothing
Wash skin thoroughly with soap and water or use recognised skin cleaner DO NOT use solvents or thinners INGESTION If accidentally swallowed
obtain medical attention Keep at rest DO NOT induce vomiting
Disposal :
Product recommendation Do not allow into drains or watercourses Empty containers are to be disposed according to official rules Contaminated
packaging recommendation Contaminated packaging must be emptied of all residues and following appropriate cleaning may be sent to approved
recycling plant Uncleaned packaging must be disposed of in the same manner as the medium
Fire :
Aqueous dispersions will not burn Dried films are combustible and may emit noxious fumes Water foam carbon dioxide or dry powder extinguishers are
all suitable Wear breathing apparatus
Spillages :
Spillage should not be washed into any drain Spillage should be soaked up with an inert absorbent e g sand for disposal
Storage :
HANDLING This product should be handled in accordance with good safety and hygiene practices Small levels of volatile organic compounds may
accumulate in the headspace of containers which should be opened in ventilated surroundings STORAGE Sealed containers should be stored between
5 C and 40C Bulk tanks should be externally vented
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 318/471
COSHH ASSESSMENT
Trade Name : DECORATORS VARNISH GLOSS, SATIN, Class : DECORATORS VARNISH GLOSS, SATIN, DEAD FLAT.
DEAD FLAT.
Manufacture :Polyvine Limited Phone : 44 845 017 1671
Desc : DECORATORS VARNISH GLOSS, SATIN, DEAD Format : Milky liquid
FLAT.
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 319/471
COSHH ASSESSMENT
Constituents
Unknown Not applicable
Effect :
Irritant in contact with eyes and skin Harmful by inhalation and if swallowed Prolonged or repeated contact with
skin can cause irritation or dermatitis
Action :
Wash with recognised hand cleaner or soap and water DO NOT use solvents or thinners Use only in a well
ventilated area if necessary local exhaust ventilation should be provided Keep away from sources of heat and
ignition Avoid breathing fumes or spray mist
Protective Clothing :
Wear appropriate protective clothing Wear suitable respiratory equipment if spraying Eye protection is required
Barrier creams may protect exposed skin but are not suitable for full physical protection DO NOT apply once
exposure has occurred
First Aid :
Ingestion If swallowed DO NOT induce vomiting - seek medical advice Eyes Irrigate eyes with copious amounts of
clean fresh water for at least 15 mins Seek medical advice Inhalation If inhaled remove to fresh air and rest Skin
Wash from skin with a recognised hand cleaner and then with soap and water
Disposal :
Consign to licenced site or specialist contractor
Fire :
Non flammable
Spillages :
Ventilate area Eliminate all sources of ignition Contain spillages and soak up with sand or earth Do not allow to
enter drains or water courses
Storage :
Keep in a secure dry well ventilated area Keep away from foodstuffs Keep containers tightly sealed
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 320/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 321/471
COSHH ASSESSMENT
Trade Name : Dulux Vinyl Matt Emulsion Class : Waterborne coating for interior use
Manufacture :ICI Paints AkzoNobel Phone : 44 (0) 333 222 70 7
Desc : Waterborne coating for interior use Format : Liquid
Constituents
Effect :
Information on toxicological effects There are no data available on the mixture itself The mixture is not classified as dangerous according to Directive 1999 45 EC and its
amendments If splashed in the eyes the liquid may cause irritation and reversible damage This takes into account where known delayed and immediate effects and also
chronic effects of components from short-term and long-term exposure by oral inhalation and dermal routes of exposure and eye contact
Action :
Reactivity No specific test data related to reactivity available for this product or its ingredients Chemical stability Stable under recommended storage and handling conditions
Possibility of hazardous reactions Under normal conditions of storage and use hazardous reactions will not occur Conditions to avoid When exposed to high temperatures may
produce hazardous decomposition products Incompatible materials Keep away from the following materials to prevent strong exothermic reactions oxidising agents strong
alkalis strong acids Hazardous decomposition products Under normal conditions of storage and use hazardous decomposition products should not be produced
Protective Clothing :
Appropriate engineering controls Provide adequate ventilation Where reasonably practicable this should be achieved by the use of local exhaust ventilation and good general
extraction Hygiene measures Wash hands forearms and face thoroughly after handling chemical products before eating smoking and using the lavatory and at the end of the
working period Appropriate techniques should be used to remove potentially contaminated clothing Wash contaminated clothing before reusing Ensure that eyewash stations
and safety showers are close to the workstation location Eye face protection Use safety eyewear designed to protect against splash of liquids Hand protection There is no one
glove material or combination of materials that will give unlimited resistance to any individual or combination of chemicals The breakthrough time must be greater than the end
use time of the product The instructions and information provided by the glove manufacturer on use storage maintenance and replacement must be followed Gloves should be
replaced regularly and if there is any sign of damage to the glove material Always ensure that gloves are free from defects and that they are stored and used correctly The
performance or effectiveness of the glove may be reduced by physical chemical damage and poor maintenance Barrier creams may help to protect the exposed areas of the
skin but should not be applied once exposure has occurred Gloves For prolonged or repeated contact use protective gloves Barrier creams may help to protect the exposed
areas of skin they should however not be applied once exposure has occurred Skin should be washed after contact Use chemical resistant gloves classified under Standard
EN 374 Protective gloves against chemicals and micro-organisms Recommended gloves Viton or Nitrile Breakthrough Time 480 min When prolonged or frequently repeated
contact may occur a glove with a protection class of 6 breakthrough time greater than 480 minutes according to EN 374 is recommended When only brief contact is expected a
glove with a protection class of 2 or higher breakthrough time greater than 30 minutes according to EN 374 is recommended NOTICE The selection of a specific glove for a
particular application and duration of use in a workplace should also take into account all relevant workplace factors such as but not limited to Other chemicals which may be
handled physical requirements cut puncture protection dexterity thermal protection potential body reactions to glove materials as well as the instructions specifications provided
by the glove supplier The user must check that the final choice of type of glove selected for handling this product is the most appropriate and takes into account the particular
conditions of use as included in the user s risk assessment Other skin protection Appropriate footwear and any additional skin protection measures should be selected based
on the task being performed and the risks involved and should be approved by a specialist before handling this product Respiratory protection Usually no respiratory protection
required Respiratory protection in case of dust or spray mist formation particle filter EN143 type P2 Respiratory protection in case of vapour formation half mask with
combination filter A2-P2 till concentrations of 0 5 Vol Environmental exposure Do not allow to enter drains or watercourses controls
First Aid :
General In all cases of doubt or when symptoms persist seek medical attention Never give anything by mouth to an unconscious person If unconscious place in recovery
position and seek medical advice Eye contact Check for and remove any contact lenses Immediately flush eyes with running water for at least 15 minutes keeping eyelids open
Seek immediate medical attention Inhalation Remove to fresh air Keep person warm and at rest If not breathing if breathing is irregular or if respiratory arrest occurs provide
artificial respiration or oxygen by trained personnel Skin contact Remove contaminated clothing and shoes Wash skin thoroughly with soap and water or use recognised skin
cleanser Do NOT use solvents or thinners Ingestion If swallowed seek medical advice immediately and show the container or label Keep person warm and at rest Do NOT
induce vomiting Protection of first-aiders No action shall be taken involving any personal risk or without suitable training
Disposal :
Product - Methods of disposal The generation of waste should be avoided or minimised wherever possible Disposal of this product solutions and any by-products should at all
times comply with the requirements of environmental protection and waste disposal legislation and any regional local authority requirements Dispose of surplus and
nonrecyclable products via a licensed waste disposal contractor Waste should not be disposed of untreated to the sewer unless fully compliant with the requirements of all
authorities with jurisdiction Hazardous waste Within the present knowledge of the supplier this product is not regarded as hazardous waste as defined by EU Directive 91 689
EEC Disposal considerations Do not allow to enter drains or watercourses Dispose of according to all federal state and local applicable regulations If this product is mixed with
other wastes the original waste product code may no longer apply and the appropriate code should be assigned For further information contact your local waste authority
Packaging - Methods of disposal The generation of waste should be avoided or minimised wherever possible Waste packaging should be recycled Incineration or landfill
should only be considered when recycling is not feasible Disposal considerations Using information provided in this safety data sheet advice should be obtained from the
relevant waste authority on the classification of empty containers Empty containers must be scrapped or reconditioned Dispose of containers contaminated by the product in
accordance with local or national legal provisions Special precautions This material and its container must be disposed of in a safe way Empty containers or liners may retain
some product residues Avoid dispersal of spilt material and runoff and contact with soil waterways drains and sewers
Fire :
Suitable extinguishing media Recommended alcohol-resistant foam CO2 powders water spray Unsuitable extinguishing media Do not use water jet Hazards from the
substance or mixture Fire will produce dense black smoke Exposure to decomposition products may cause a health hazard Hazardous thermal decomposition products
Decomposition products may include the following materials carbon monoxide carbon dioxide smoke oxides of nitrogen Special protective actions for fire-fighters Cool closed
containers exposed to fire with water Do not release runoff from fire to drains or watercourses Special protective equipment for fire-fighters Appropriate breathing apparatus
may be required
Spillages :
For non-emergency personnel Avoid breathing vapour or mist For emergency responders Take note if specialised clothing is required to deal with the spillage Environmental
precautions Do not allow to enter drains or watercourses If the product contaminates lakes rivers or sewers inform the appropriate authorities in accordance with local
regulations Methods and material for containment and cleaning up Contain and collect spillage with non-combustible absorbent material e g sand earth vermiculite or
diatomaceous earth and place in container for disposal according to local regulations Preferably clean with a detergent Avoid using solvents
Storage :
Precautions for safe handling Avoid contact with skin and eyes Avoid inhalation of vapour spray or mist Eating drinking and smoking should be prohibited in areas where this
material is handled stored and processed Put on appropriate personal protective equipment Never use pressure to empty Container is not a pressure vessel Always keep in
containers made from the same material as the original one Comply with the health and safety at work laws Do not allow to enter drains or watercourses When operators
whether spraying or not have to work inside the spray booth ventilation is unlikely to be sufficient to control particulates and solvent vapour in all cases In such circumstances
they should wear a compressed air-fed respirator during the spraying process and until such time as the particulates and solvent vapour concentration has fallen below the
exposure limits Conditions for safe storage including any incompatibilities Store in accordance with local regulations Notes on joint storage Keep away from oxidising agents
strong alkalis strong acids Additional information on storage conditions Store in a dry cool and well-ventilated area Keep container tightly closed No smoking Prevent
unauthorised access Containers that have been opened must be carefully resealed and kept upright to prevent leakage
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 322/471
COSHH ASSESSMENT
Trade Name : DuluxVinyl Matt Emulsion Class : Waterborne coating for interior use
Manufacture :ICI
Paints AkzoNobel Phone : 44 (0) 333 222 70 7
Desc : Waterborne coating for interior use Format : Liquid
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 323/471
COSHH ASSESSMENT
Constituents
White Spirit 575mg cu metre 8hr T W A
Effect :
Action :
Do not smoke Keep away from sources of ignition Avoid breathing fumes vapour
Protective Clothing :
First Aid :
Disposal :
Fire :
Spillages :
Storage :
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 324/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 325/471
COSHH ASSESSMENT
Constituents
Aliphatic Hydrocarbon 100 p p m 8hr T W A Toluene 50 p p m 8hr T W A Methyl Ethyl Ketone MEK 200 p p m 8hr
TWA
Effect :
Harmful by inhalation Irritant in contact with eyes and skin Irritant by ingestion
Action :
Avoid contact with skin and eyes Ensure adequate ventilation Do not smoke Keep away from sources of ignition
Avoid breathing fumes vapour
Protective Clothing :
Wear suitable respiratory equipment to BS EN 405 A1 P3 where ventilation is insufficient Wear goggles to BS
2092 2C or BS EN166 1FD specification Wear P V C neoprene or other solvent resisting gloves Wear coveralls
First Aid :
Ingestion If swallowed DO NOT induce vomiting - seek medical advice Inhalation If inhaled remove to fresh air
and seek immediate medical attention Eyes Irrigate eyes with copious amounts of water for 5 minutes seek
medical attention Skin Wipe from skin with paper towels Skin Wash from skin with resin removing cream and
water Use skin conditioning cream SOLVENTS SHOULD NOT BE USED
Disposal :
Dispose of in accordance with the Control of Pollution special waste Regulations 1980
Fire :
Use dry powder or foam extinguishers DO NOT USE WATER Gives off toxic gases if burnt wear self contained
breathing equipment
Spillages :
Contain spillages and soak up with sand or earth Place contaminated material in a metal container prior to
transfer to disposal site Eliminate all sources of ignition Ventilate area Do not allow to enter drains or water
courses
Storage :
Avoid strong oxidising agents Store in accordance with the The Dangerous Substances and Explosive
Atmospheres Regulations 2002 Store at temperatures between 5 30 degrees C Keep containers tightly sealed
Store in a cool well ventilated place Keep out of reach of children Keep away from heat and sources of ignition
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 326/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 327/471
COSHH ASSESSMENT
Constituents
Name BUTANONE CYCLOHEXANE ETHYL ACETATE FORMALDEHYDE HEPTANE AND ISOMERS HEXANE MIXTURE OF ISOMERS HEXANE-
norm METHYLCYCLOHEXANE N-HEXANE PENTANE PROPAN-2-OL ROSIN XYLENE EC No 201-159-0 203-806-2 205-500-4 200-001-8 203-777-6
203-624-3 203-777-6 203-692-4 200-661-7 232-475-7 215-535-7 CAS-No 78-93-3 110-82-7 141-78-6 50-00-0 110-54-3 108-87-2 110-54-3 109-66-0
67-63-0 8050-09-7 1330-20-7 Content 10-30 10-30 10-30 1 5-10 1-5 1 1-5 1 1 1 1 1 Classification F R11 Xi R36 R66 R67 F R11 Xn R65 Xi R38 R67 N
R50 53 F R11 Xi R36 R66 R67 Carc3 R40 T R23 24 25 C R34 R43 Xn R65 Xi R38 F R11 N R50 53 R67 Xn R65 Xi R38 F R11 N R51 53 R67 F R11
Repr3 R62 Xn R65 R48 20 Xi R38 R67 N R51 53 F R11 Xn R65 Xi R38 R67 N R51 53 F R11 Repr3 R62 Xn R65 R48 20 Xi R38 R67 N R51 53 F R12
Xn R65 R66 R67 N R51 53 F R11 Xi R36 R67 R43 R10 Xn R20 21 Xi R38
Effect :
INHALATION Drowsiness dizziness disorientation vertigo SKIN CONTACT Prolonged contact may cause dryness of the skin EYE CONTACT Irritating
to eyes
Action :
STABILITY Avoid Heat sparks flames
Protective Clothing :
ENGINEERING MEASURES Explosion-proof general and local exhaust ventilation RESPIRATORY EQUIPMENT Respiratory protection must be used
if air contamination exceeds acceptable level Wear mask supplied with Gas cartridge suitable for organic substances HAND PROTECTION Protective
gloves must be used if there is a risk of direct contact or splash Use protective gloves made of Nitrile EYE PROTECTION Wear splash-proof eye
goggles to prevent any possibility of eye contact OTHER PROTECTION Wear appropriate clothing to prevent repeated or prolonged skin contact
HYGIENE MEASURES Wash promptly if skin becomes contaminated Wash at the end of each work shift and before eating smoking and using the toilet
First Aid :
INHALATION Remove victim immediately from source of exposure Move the exposed person to fresh air at once Get medical attention INGESTION DO
NOT induce vomiting Get medical attention immediately Promptly wash contaminated skin with soap or mild detergent and water Promptly remove
clothing if soaked through and wash as above Get medical attention if irritation persists after washing EYE CONTACT Rinse the eye with water
immediately Continue to rinse for at least 15 minutes and get medical attention
Disposal :
GENERAL INFORMATION Waste is classified as hazardous waste DISPOSAL METHODS Dispose of waste and residues in accordance with local
authority requirements
Fire :
EXTINGUISHING MEDIA Fire can be extinguished using Foam carbon dioxide or dry powder SPECIAL FIRE FIGHTING PROCEDURES Fight
advanced or massive fires from safe distance or protected location Keep run-off water out of sewers and water sources Dike for water control Ventilate
closed spaces before entering them Keep up-wind to avoid fumes UNUSUAL FIRE EXPLOSION HAZARDS May travel considerable distance to source
of ignition and flash back Heat may cause the containers to explode Solvent vapours may form explosive mixtures with air Vapours are heavier than air
and may spread near ground to sources of ignition SPECIFIC HAZARDS Toxic gases vapours fumes of Carbon dioxide CO2 Carbon monoxide CO
PROTECTIVE MEASURES IN FIRE Wear self contained breathing apparatus
Spillages :
PERSONAL PRECAUTIONS In case of inadequate ventilation use respiratory protection Use protective gloves goggles and suitable protective clothing
Avoid inhalation of vapours and contact with skin and eyes Provide adequate ventilation ENVIRONMENTAL PRECAUTIONS Prevent entry into drains
SPILL CLEAN UP METHODS Absorb with sand or other inert absorbent Containers with collected spillage must be properly labelled with correct
contents and hazard symbol
Storage :
USAGE PRECAUTIONS Keep away from heat sparks and open flame Avoid spilling skin and eye contact Ventilate well avoid breathing vapours Use
approved respirator if air contamination is above accepted level STORAGE PRECAUTIONS Flammable combustible - Keep away from oxidisers heat
and flames Ground container and transfer equipment to eliminate static electric sparks Store at moderate temperatures in dry well ventilated area
STORAGE CLASS Flammable liquid storage
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 328/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 329/471
COSHH ASSESSMENT
Constituents
BUTANONE 201-159-0 78-93-3 10-30 F R11 Xi R36 R66 R67 MAN-MADE VITREOUS SILICATE FIBRES 1-5 Xi R38 NAPHTHA PETROLEUM
295-434-2 HYDRODESULFURIZED LIGHT DEAROMATIZED 0 1 BENZENE 92045-53-9 5-10 Xn R65 Xi R38 F R11 N R51 53 R67 NAPHTHA
PETROLEUM HYDROTREATED 265-151-9 LIGHT 0 1 BENZENE 64742-49-0 1-5 Xn R65 Xi R38 F R11 N R51 53 R67 XYLENE 215-535-7 1330-20-7
5-10 R10 Xn R20 21 Xi R38
Effect :
Highly flammable Vapours may cause drowsiness and dizziness Irritating to skin Harmful to aquatic organisms may cause long-term adverse effects in
the aquatic environment Vapours are heavier than air and can travel long distances to a source of ignition Pilot lights can ignite the vapour
CLASSIFICATION 1999 45 Xi R38 F R11 R52 53 R67
Action :
PERSONAL PRECAUTIONS Avoid skin and eye contact Ensure adequate ventilation Wear personal protective equipment Wear self contained
breathing apparatus Avoid breathing vapour ENVIRONMENTAL PRECAUTIONS Prevent entry into drains and water courses SPILL CLEAN UP
METHODS Wear necessary protective equipment Extinguish all ignition sources Avoid sparks flames heat and smoking Ventilate Absorb onto sand
earth or abosorbent granules Pick up with non-sparking tools and place into metal containers with sealable lids Mark containers with details of hazards
and store in designated area ready for disposal Runoff or release to sewer waterway or ground is forbidden
Protective Clothing :
ENGINEERING MEASURES Provide adequate general and local exhaust ventilation Explosion-proof general and local exhaust ventilation
RESPIRATORY EQUIPMENT Respiratory protection must be used if air contamination exceeds acceptable level Wear mask supplied with Gas
cartridge suitable for organic substances HAND PROTECTION Protective gloves must be used if there is a risk of direct contact or splash Use
protective gloves made of Nitrile EYE PROTECTION Wear splash-proof eye goggles to prevent any possibility of eye contact HYGIENE MEASURES
DO NOT SMOKE IN WORK AREA Wash at the end of each work shift and before eating smoking and using the toilet Promptly remove any clothing that
becomes contaminated Wash promptly with soap water if skin becomes contaminated When using do not eat drink or smoke
First Aid :
INHALATION Move the exposed person to fresh air at once Get medical attention if any discomfort continues INGESTION DO NOT induce vomiting Get
medical attention immediately SKIN CONTACT Promptly flush contaminated skin with water Promptly remove clothing if soaked through and flush the
skin with water Get medical attention if irritation persists after washing EYE CONTACT Rinse the eye with water immediately Continue to rinse for at
least 15 minutes and get medical attention
Disposal :
GENERAL INFORMATION This material is classified as special waste as defined by Special Waste Regulations 1996 and must be disposed of by an
authorised contractor DISPOSAL METHODS Dispose of waste and residues in accordance with local authority requirements
Fire :
EXTINGUISHING MEDIA Foam Powder SPECIFIC HAZARDS Fire creates Toxic gases vapours fumes of Carbon dioxide CO2 Carbon monoxide CO
PROTECTIVE MEASURES IN FIRE Wear self contained breathing apparatus
Spillages :
PERSONAL PRECAUTIONS Avoid skin and eye contact Ensure adequate ventilation Wear personal protective equipment Wear self contained
breathing apparatus Avoid breathing vapour ENVIRONMENTAL PRECAUTIONS Prevent entry into drains and water courses SPILL CLEAN UP
METHODS Wear necessary protective equipment Extinguish all ignition sources Avoid sparks flames heat and smoking Ventilate Absorb onto sand
earth or abosorbent granules Pick up with non-sparking tools and place into metal containers with sealable lids Mark containers with details of hazards
and store in designated area ready for disposal Runoff or release to sewer waterway or ground is forbidden
Storage :
USAGE PRECAUTIONS Keep away from heat sparks and open flame Provide good ventilation Avoid spilling skin and eye contact Avoid acids moisture
and combustible materials STORAGE PRECAUTIONS Flammable combustible - Keep away from oxidisers heat and flames Isolate from other materials
Store in tightly closed original container in a dry cool and well-ventilated place Ground container and transfer equipment to eliminate static electric
sparks STORAGE CLASS Flammable liquid storage
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 330/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 331/471
COSHH ASSESSMENT
Constituents
AMINOSILANE 1-5 CAS-No EC No Classification 67 548 EEC Xi R36 38 Classification EC 1272 2008 Skin Irrit 2 - H315 Eye Irrit 2 - H319
TRIMETHOXYVINYLSILANE 1-5 CAS-No 2768-02-7 EC No 220-449-8 Registration Number 01-2119513215-52 Classification EC 1272 2008 Flam Liq
3 - H226 Acute Tox 4 - H332 Classification 67 548 EEC Xn R20 R10
Effect :
Ingestion Ingestion of this material may cause obstruction Skin Contact Prolonged or repeated contact may lead to irritation
Action :
Stable under normal temperature conditions Hazardous Polymerisation Unknown Avoid excessive heat for prolonged periods of time Materials To Avoid
No incompatible groups noted Fire creates Carbon monoxide CO Carbon dioxide CO2 During hardening a small amount of Methanol will be released
Protective Clothing :
Engineering Measures All handling to take place in well-ventilated area Hand Protection Use suitable protective gloves if risk of skin contact Use thin
cotton gloves inside the rubber gloves if allergy risk Eye Protection If risk of splashing wear safety goggles or face shield Other Protection Wear suitable
protective clothing as protection against splashing or contamination Hygiene Measures Wash promptly if skin becomes wet or contaminated Promptly
remove any clothing that becomes contaminated When using do not eat drink or smoke Wash at the end of each work shift and before eating smoking
and using the toilet Use appropriate skin cream to prevent drying of skin DO NOT SMOKE IN WORK AREA
First Aid :
General Information General first aid rest warmth and fresh air Inhalation Move the exposed person to fresh air at once Get medical attention if any
discomfort continues Ingestion DO NOT induce vomiting Get medical attention immediately Skin Contact Remove affected person from source of
contamination Rinse the skin immediately with lots of water Get medical attention if irritation persists after washing Eye Contact Rinse the eye with
water immediately Continue to rinse for at least 15 minutes and get medical attention
Disposal :
Dispose of waste and residues in accordance with local authority requirements Recover and reclaim or recycle if practical
Fire :
Extinguishing Media This product is not flammable Use fire-extinguishing media appropriate for surrounding materials Specific Hazards Fire or high
temperatures create Toxic gases vapours fumes of Carbon dioxide CO2 Carbon monoxide CO
Spillages :
Stop leak if possible without risk Do not contaminate water sources or sewer Pick up with vacuum or absorbent solid store in closed container for
disposal Avoid generation and spreading of dust Avoid contact with skin or inhalation of spillage dust or vapour Wear necessary protective equipment
Containers with collected spillage must be properly labelled with correct contents and hazard symbol
Storage :
Avoid spilling skin and eye contact Do not handle broken packages without protective equipment Store in tightly closed original container in a dry cool
and well-ventilated place Keep in original container
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 332/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 333/471
COSHH ASSESSMENT
Constituents
Diphenylmethane Disocyanate MDI 0 2 p p m 10min T W A Hydrocarbon No given standard Dimethyl Ether 400 p
p m 8hr T W A
Effect :
May cause sensitation by inhalation Irritating to eyes and skin R36 38 Harmful by inhalation Irritating to respiratory
system
Action :
Vapours are heavier than air may spread along floors Exclude sources of heat sparks and open flame Do not
inhale smoke if burnt Heating may cause pressure rise with risk of container bursting Keep away from sources of
heat and ignition Do not eat drink or smoke when using Wash hands and exposed skin before eating drinking or
smoking and after work Ensure adequate personal hygiene
Protective Clothing :
Wear impervious clothing gloves and eye protection Wear suitable respiratory equipment to BS EN 405 A1 P3
where ventilation is insufficient
First Aid :
Skin Wipe off with cloth or paper Wash with soap and water Eyes In case of contact with eyes rinse immediately
with plenty of water and seek medical advice Inhalation If inhaled remove to fresh air and rest Seek medical
advice if symptoms persist Ingestion If ingested seek medical advice Inhalation If smoke or fumes from burning
are inhaled immediately seek fresh air and medical assistance In case of accident or if unwell seek medical
advice immediately
Disposal :
Where possible allow to cure or set before disposal EMPTY CONTAINER COMPLETELY and dispose of safely
Do not puncture container even when empty Dispose of to site accepting builders waste DO NOT incinerate
Fire :
Use dry powder or foam extinguishers Water spray extinguishers may be used Do Not use carbon dioxide Gives
off toxic gases if burnt wear self contained breathing equipment
Spillages :
Remove by mechanical means Do not allow to enter drains or water courses
Storage :
Store containers in an upright position Keep out of reach of children Store in a well ventilated area out of direct
sunlight Do not expose to temperatures exceeding 50 degreees C
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 334/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 335/471
COSHH ASSESSMENT
Trade Name : FIRE FOAM B1 - HAND HELD AND GUN GRADE Class : Filling, fixing and insulating gaps and cavities.
Manufacture :Everbuild Building Products Lt Phone : 0113 240 3456
Desc : Filling, fixing and insulating gaps and cavities.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 336/471
COSHH ASSESSMENT
Trade Name : FIRE FOAM B1 - HAND HELD AND GUN Class : Filling, fixing and insulating gaps and cavities.
GRADE
Manufacture :Everbuild Building Products Lt Phone : 0113 240 3456
Desc : Filling, fixing and insulating gaps and cavities.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 337/471
COSHH ASSESSMENT
Constituents
Respirable dust during fabrication 5mg cu metre 8hr T W A Methyl Ethyl Ketone MEK 200 p p m 8hr T W A
Cyclohexanone 25 p p m 8hr T W A Tetrahydrofuran 200 p p m 8hr T W A
Effect :
Action :
Protective Clothing :
First Aid :
Disposal :
Fire :
Spillages :
Storage :
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 338/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 339/471
COSHH ASSESSMENT
Constituents
N A Refer to supplier s Safety Data Sheets for specific information on components
Effect :
N A Refer to supplier s Safety Data Sheets for specific information on components
Action :
Kits are stable if stored in the original package in cool and dry conditions Do not subject kits to high temperatures
or excessively humid conditions Refer to supplier s Safety Data Sheets for specific information on components
Protective Clothing :
Refer to supplier s Safety Data Sheets for specific information on components
First Aid :
Inhalation Provide patient with fresh air and seek medical advice Skin Contact Do not use solvents Wash with
soap and water Eye Contact Irrigate thoroughly with water and seek medical advice Ingestion Get medical aid
immediately
Disposal :
Refer to supplier s Safety Data Sheets for specific disposal information of components Other solid portions of the
kits may be disposed of as domestic waste in accordance with local laws and regulations
Fire :
Suitable Extinguishing Media Large volumes of water Sand Specific Hazards From Combustion Refer to supplier
s Safety Data Sheets for specific information on components Personal Protection Use air-ventilated full mask and
full protective clothing
Spillages :
Hazardous materials are contained in sealed units within packed kits Spills should pose no threat if sealed units
are not breached Refer to supplier s Safety Data Sheets for specific information on components
Storage :
These units should be stored in a cool dry area away from danger of sparks heat or flames Refer to supplier s
Safety Data Sheets for specific information on components
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 340/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 341/471
COSHH ASSESSMENT
Constituents
None Listed Not applicable
Effect :
Over exposures are irritating to eyes and respiratory system Harmful by inhalation and if swallowed Irritant after
prolonged contact with skin Irritant in contact with eyes
Action :
Do not breathe vapour and ensure adequate ventilation
Protective Clothing :
Wear suitable respiratory equipment to BS EN 405 A1 P3 where ventilation is insufficient Wear appropriate
protective clothing Eye and face protection is required
First Aid :
Inhalation If inhaled take to fresh air transfer to hospital at any sign of dizziness or breathing difficulties Skin Wash
from skin with a recognised hand cleaner and then with soap and water Ingestion If ingested do not induce
vomiting and give nothing by mouth
Disposal :
Dispose of in accordance with Local Authority Regulations
Fire :
Use foam dry powder or CO2
Spillages :
Wash spill area thoroughly
Storage :
Store in a cool dry area
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 342/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 343/471
COSHH ASSESSMENT
Trade Name : Gyproc Joint Filler Gyproc Easi-Fill Gyproc Cove Class : General purpose gypsum-based jointing materials for use with
Adhesive Gyproc Easi-Fill 45 British Gypsum dry lining systems.
Manufacture :British Gypsum Phone : 0115-9456123
Desc : General purpose gypsum-based jointing materials for use with Format : Dry powder
British Gypsum dry lining systems.
Constituents
General composition Calcium sulphate hemihydrate and limestone Natural constituents may include clay and minor amounts of quartz Additives may
include minor amounts polymer binders and aggregates Gyproc Easi-Fill and Easi-Fill 45 also contain perlite aggregate
Effect :
Inhalation Dust may irritate the respiratory system No known long term effects Skin contact Dry powder may cause skin irritation Eye contact Dry
powder can cause irritation Ingestion Small quantities of plaster should not cause any significant reaction or long term effect
Action :
This preparation is stable under the recommended handling and storage conditions None under normal conditions of use
Protective Clothing :
Eye face protection - Avoid contact with eyes Wear Eye protection to EN166 standard Category 5-K Hand protection - Wear suitable protective gloves to
prevent prolonged or repeated skin contact Recommended properties impervious gloves to EN374 standard P280 - Wear protective gloves Body
protection - Work clothing worn by personnel should be laundered regularly Respiratory protection - Avoid breathing dust P285 - In case of inadequate
ventilation wear respiratory protection EN149 2001 minimum recommended FFP2
First Aid :
Eye contact P305 P313 - If in eyes get medical advice P337 P351 - If eye irritation persists rinse cautiously with water for several minutes Skin contact
P264 - Wash hands thoroughly after handling Ingestion P301 P330 - If swallowed rinse mouth Inhalation P261 - avoid breathing dust P304 P340 - if
inhaled remove victim to fresh air and keep at rest in a position comfortable for breathing P312 - Call a doctor if you feel unwell General Get medical
attention if any symptoms persist
Disposal :
Do not pour into drains or waterways Wastes from gypsum products are normally classified as non-hazardous but should not be co-disposed with
municipal waste P501 - Dispose of contents of containers at an authorised landfill site in accordance with the Waste Management Licensing
Regulations
Fire :
The product does not pose a fire hazard However some packaging materials may burn Suitable extinguishing media water foam carbon dioxide or dry
powder
Spillages :
Avoid creating dust Avoid eye contact or prolonged repeated contact with skin Prevent plasters from contaminating drains
Storage :
Use Minimise dust generation when opening bags mixing or sanding products in poorly ventilated places Avoid eye contact or prolonged or repeated
contact with skin - see Section 8 for recommended personal protective equipment and Section 2 for hazards identification P264 - Wash hands
thoroughly after handling P270 - Do not eat drink or smoke when handling this product P271 - Use only outdoors or in a well ventilated area Manual
handling Supplied in up to 12 5kg bags use an appropriate lifting technique Mechanical handling To avoid potentially overloading a lift truck it is
important that any effect on load centres is considered The nominal weight of each palletised load is given within the weights table in this section of this
document
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 344/471
COSHH ASSESSMENT
Trade Name : Gyproc Joint Filler Gyproc Easi-Fill Gyproc Class : General purpose gypsum-based jointing materials for use with
British Gypsum dry lining systems.
Cove Adhesive Gyproc Easi-Fill 45
Manufacture :British Gypsum Phone : 0115-9456123
Desc : General purpose gypsum-based jointing materials Format : Dry powder
for use with British Gypsum dry lining systems.
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 345/471
COSHH ASSESSMENT
Trade Name : Gyproc Moisture Resistant Class : Gyproc plasterboards are used as internal linings in buildings.
Manufacture :British Gypsum Phone : 0115-9456123
Desc : Gyproc plasterboards are used as internal linings in buildings. Format : Flat sheet boards in different widths and thicknesses, with a
square or tapered edge.
Constituents
Calcium sulphate dihydrate encased in paper liners natural constituents may include minor amounts of quartz Small quantities of chopped glass fibre
microsilica and vermiculite may be added with starch foam and dispersants - Any board may contain small quantities of chopped manmade mineral fibre
and microsilica - Gyproc Moisture Resistant includes a silicone and or wax additive
Effect :
No known toxicological effects
Action :
No special physical conditions need to be avoided No specific restrictions regarding incompatible materials
Protective Clothing :
Respiratory P284 -Use only in well-ventilated areas Wear eye face protection Face masks to EN 149 FFP2 Skin P303 -Wear suitable protective clothing
Eye P305 - Wear eye face protection P313 Eye protection to BS EN 166
First Aid :
Eye contact Skin contact Ingestion Inhalation P305 - In case of contact with eyes rinse P313 P264 immediately with plenty of water and seek medical
advice - After contact with skin wash immediately with plenty of soap and water All weights are approximate P331 -If swallowed do not induce vomiting
seek medical advice immediately and show this document P301 - If swallowed rinse mouth with water P330 only if the person is conscious P304 - In
case of accident by inhalation P340 remove casualty to fresh air and keep at rest
Disposal :
Gypsum the main raw material for plasterboard is a sulphate but is classified as non-hazardous Waste from gypsum plasterboard products is fully
recyclable For more information contact the British Gypsum Plasterboard Recycling Service Team on 0800 633 5040 or visit the British Gypsum website
at british-gypsum com
Fire :
Suitable extinguishing media water foam carbon dioxide or dry powder
Spillages :
Not applicable
Storage :
Use Minimise dust generation when sawing or sanding in poorly ventilated places Avoid eye contact - Plasterboards will not support body weight
between rafters joints or frame members Manual handling Sheets of plasterboard can be unwieldy use an appropriate lifting technique Mechanical
handling The dimensions of the pallet vary depending on the product size To avoid potentially overloading a lift truck it is important that any effect on
load centres is considered The nominal weight of each palletised load is given within the weights table in this section of this document Storage Store on
pallets supplied in dry conditions To maintain stability place pallets on firm level ground and ensure that stacks are both level and vertical
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 346/471
COSHH ASSESSMENT
Trade Name : Gyproc Moisture Resistant Class : Gyproc plasterboards are used as internal linings in buildings.
Manufacture :British
Gypsum Phone : 0115-9456123
Desc : Gyproc plasterboards are used as internal linings in Format : Flat sheet boards in different widths and thicknesses, with a
square or tapered edge.
buildings.
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 347/471
COSHH ASSESSMENT
Trade Name : Gyproc plasterboards Class : Gyproc plasterboards are used as internal linings in buildings.
Manufacture :British Gypsum Phone : 0115-9456123
Desc : Gyproc plasterboards are used as internal linings in buildings. Format : Flat sheet boards in different widths and thicknesses, with a
square or tapered edge.
Constituents
General composition Calcium sulphate dihydrate encased in paper liners natural constituents may include minor
amounts of quartz Small quantities of chopped glass fibre microsilica and vermiculite may be added with starch
foam and dispersants Any board may contain small quantities of chopped man-made mineral fibre and microsilica
Effect :
No known toxicological effects
Action :
No special physical conditions need to be avoided No specific restrictions regarding incompatible materials
Protective Clothing :
Respiratory Use in a well ventilated area Where practicable use engineering methods to control dust levels If the
exposure standards could be exceeded use a disposable face mask complying with EN 149 FFP2 Skin Wear
appropriate clothing to protect against repeated or prolonged skin contact Eye If there is a risk of material entering
the eye wear eye protection to BS EN 166
First Aid :
Eye contact Skin contact Ingestion Wash eyes with clean water Wash thoroughly with soap and water DO NOT
INDUCE VOMITING Rinse out mouth thoroughly and give plenty of water Inhalation General If irritation occurs
remove person to fresh air Get medical attention if any symptoms persist
Disposal :
Waste from gypsum plasterboard products is normally classified as non-hazardous non-inert and is fully
recyclable Please refer to the British Gypsum Plasterboard Recycling Service literature or contact the
Plasterboard Recycling Customer Service Centre on 0800 6335040 for details Other methods of disposal are
available Always seek the advice of a trained and competent professional
Fire :
The products do not pose a fire hazard However some packaging materials or facings may burn Suitable
extinguishing media water foam carbon dioxide or dry powder
Spillages :
Not applicable
Storage :
Use Minimise dust generation when sawing or sanding in poorly ventilated places Avoid eye contact
Plasterboards will not support body weight between rafters joints or frame members Manual handling Sheets of
plasterboard can be unwieldy use an appropriate lifting technique The weight of each sheet can vary between
products
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 348/471
COSHH ASSESSMENT
Trade Name : Gyproc plasterboards Class : Gyproc plasterboards are used as internal linings in buildings.
Manufacture :British
Gypsum Phone : 0115-9456123
Desc : Gyproc plasterboards are used as internal linings in Format : Flat sheet boards in different widths and thicknesses, with a
square or tapered edge.
buildings.
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 349/471
COSHH ASSESSMENT
Trade Name : Gyproc SoundBloc Class : Gyproc plasterboards are used as internal linings in buildings.
Manufacture :British Gypsum Phone : 0115-9456123
Desc : Gyproc plasterboards are used as internal linings in buildings. Format : Flat sheet boards in different widths and thicknesses, with a
square or tapered edge.
Constituents
General composition Calcium sulphate dihydrate encased in paper liners natural constituents may include minor amounts of quartz Small quantities of
chopped glass fibre microsilica and vermiculite may be added with starch foam and dispersants Any board may contain small quantities of chopped
manmade mineral fibre and microsilica
Effect :
No known toxicological effects
Action :
No special physical conditions need to be avoided No specific restrictions regarding incompatible materials
Protective Clothing :
Respiratory P284 - Use only in well-ventilated areas Wear eye face protection Face masks to EN 149 FFP2 Skin P303 - Wear suitable protective
clothing Eye P305 - Wear eye face protection P313 Eye protection to BS EN 166
First Aid :
Eye contact P305 - In case of contact with eyes rinse P313 immediately with plenty of water and seek medical advice Skin contact P264 - After contact
with skin wash immediately with plenty of soap and water Ingestion P331 - If swallowed do not induce vomiting seek medical advice immediately and
show this document P301 - If swallowed rinse mouth with water P330 only if the person is conscious Inhalation P304 - In case of accident by inhalation
P340 remove casualty to fresh air and keep at rest General Get medical attention if any symptoms persist
Disposal :
Gypsum the main raw material for plasterboard is a sulphate but is classified as non-hazardous Waste from gypsum plasterboard products is fully
recyclable For more information contact the British Gypsum Plasterboard Recycling Service Team on 0800 633 5040 or visit the British Gypsum website
at british-gypsum com
Fire :
Suitable extinguishing media water foam carbon dioxide or dry powder The product does not pose a fire hazard However some packaging materials
may burn
Spillages :
Not applicable
Storage :
Use Minimise dust generation when sawing or sanding in poorly ventilated places Avoid eye contact - see Section 8 for recommended personal
protective equipment and Section 3 for hazards identification Plasterboards will not support body weight between rafters joints or frame members
Manual handling Sheets of plasterboard can be unwieldy use an appropriate lifting technique The weight of each sheet can vary between products For
manual handling purposes assume the following Board thickness mm Board width mm Board length mm Board weight kg Pallet weight tonnes 12 5
1200 2400 2700 3000 34 1 38 5 42 9 1 9 1 8 1 9 15 1200 2400 2700 3000 41 5 46 8 52 1 1 8 1 9 1 9 Mechanical handling The dimensions of the pallet
vary depending on the product size To avoid potentially overloading a lift truck it is important that any effect on load centres is considered The nominal
weight of each palletised load is given within the weights table in this section of this document
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 350/471
COSHH ASSESSMENT
Trade Name : Gyproc SoundBloc Class : Gyproc plasterboards are used as internal linings in buildings.
Manufacture :British
Gypsum Phone : 0115-9456123
Desc : Gyproc plasterboards are used as internal linings in Format : Flat sheet boards in different widths and thicknesses, with a
square or tapered edge.
buildings.
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 351/471
COSHH ASSESSMENT
Trade Name : Gyproc WallBoard Class : Gyproc plasterboards are used as internal linings in buildings.
Manufacture :British Gypsum Phone : 0115-9456123
Desc : Gyproc plasterboards are used as internal linings in buildings. Format : Flat sheet boards in different widths and thicknesses, with a
square or tapered edge.
Constituents
Calcium sulphate dihydrate encased in paper liners natural constituents may include minor amounts of quartz Small quantities of chopped glass fibre
microsilica and vermiculite may be added with starch foam and dispersants
Effect :
No known toxicological effects
Action :
No specific reactivity hazards associated with this product 10 2 Chemical Stability Stable under normal temperature conditions 10 3 Possibility of
hazardous reactions None in normal conditions of use 10 4 Conditions to avoid None 10 5 Imcompatible materials None 10 6 Hazardous decomposition
products None in normal conditions of use
Protective Clothing :
Respiratory P284 Skin P303 - Use only in well-ventilated areas Wear eye face protection Face masks to EN 149 FFP2 - Wear suitable protective
clothing Eye P305 - Wear eye face protection P313 Eye protection to BS EN 166
First Aid :
Eye contact Skin contact Ingestion Inhalation General P305 - In case of contact with eyes rinse P313 P264 immediately with plenty of water and seek
medical advice - After contact with skin wash immediately with plenty of soap and water P331 -If swallowed do not induce vomiting seek medical advice
immediately and show this document P301 - If swallowed rinse mouth with water P330 only if the person is conscious P304 - In case of accident by
inhalation P340 remove casualty to fresh air and keep at rest Get medical attention if any symptoms persist
Disposal :
Gypsum the main raw material for plasterboard is a sulphate but is classified as non-hazardous Waste from gypsum plasterboard products is fully
recyclable For more information contact the British Gypsum Plasterboard Recycling Service Team on 0800 6335040 or visit the British Gypsum website
at british-gypsum com
Fire :
Suitable extinguishing media - water foam carbon dioxide or dry powder 5 2 Special hazards arising from the substance or mixture The product does not
pose a fire hazard However some packaging materials may burn 5 3 Advice for fire fighters Use protective equipment appropriate for surrounding
materials
Spillages :
Wear protective clothing as described in section 8 of this safety data sheet
Storage :
Manual handling Sheets of plasterboard can be unwieldy use an appropriate lifting technique The weight of each sheet can vary between products
Mechanical handling The dimensions of the pallet vary depending on the product size To avoid potentially overloading a lift truck it is important that any
effect on load centres is considered The nominal weight of each palletised load is given within the weights table in this section of this document
Plasterboards will not support body weight in between rafters joints or frame members Storage Store on pallets supplied in dry conditions To maintain
stability place pallets on firm level ground and ensure that stacks are both level and vertical
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 352/471
COSHH ASSESSMENT
Trade Name : Gyproc WallBoard Class : Gyproc plasterboards are used as internal linings in buildings.
Manufacture :British
Gypsum Phone : 0115-9456123
Desc : Gyproc plasterboards are used as internal linings in Format : Flat sheet boards in different widths and thicknesses, with a
square or tapered edge.
buildings.
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 353/471
COSHH ASSESSMENT
Constituents
Effect :
Action :
Protective Clothing :
First Aid :
Disposal :
Fire :
Spillages :
Storage :
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 354/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 355/471
COSHH ASSESSMENT
Constituents
Phosphate No given standard White Spirit 575mg cu metre 8hr T W A TR15 2-Ethyl-Hexyl 1 p p m 8hr T W A
Effect :
Not a substance hazardous to health for the purposes of COSHH regulations
Action :
Do not eat drink or smoke when using
Protective Clothing :
No protective clothing required in normal use
First Aid :
SOLVENTS SHOULD NOT BE USED Seek medical attention if irritation persists Contact Lenses should be
removed Ingestion If swallowed DO NOT induce vomiting Wash out mouth and give patient plenty of water to
drink Skin After contact with skin wash immediately with plenty of clean water Skin Wipe off with cloth or paper
Wash with soap and water
Disposal :
Dispose of in accordance with Local and National regulations
Fire :
DO NOT use water jets Gives off toxic gases if burnt wear self contained breathing equipment Do not allow
extinguishing waters to run into streams rivers lakes or ground water Use foam dry chemical carbon dioxide or
water spray extinguishers
Spillages :
Collect up and place in a suitable labelled container pending disposal Wash Spill area preferably with a detergent
Do not allow to enter drains or water courses
Storage :
Store at temperatures between 5 30 degrees C No special requirements Keep out of reach of children
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 356/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 357/471
COSHH ASSESSMENT
Constituents
Polyurethane Foam No given standard Aluminium Metal 10 mg cu Metre 8hr T W A Total Inhalable Dust
Aluminium Metal 5 mg cu metre respirable dust 8 hr TWA Steel No given standard
Effect :
Irritant in contact with eyes Irritant to respiratory system If cut dust will be produced
Action :
Avoid contact with eyes Avoid breathing dust fibres Ensure adequate ventilation
Protective Clothing :
Wear dust mask if necessary Eye protection to BS2092 2C or BS EN 166 1F3 must be worn Wear gloves if
necessary
First Aid :
No Action specified
Disposal :
Dispose of in accordance with Local Authority Regulations
Fire :
Gives off toxic gases if burnt Wear self contained breathing equipment
Spillages :
Not applicable
Storage :
No specific instructions given by manufacturer
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 358/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 359/471
COSHH ASSESSMENT
Trade Name : Kingspan Therma: Thermapitch TP10 Thermaroof TR21 Class : insulation
Thermaroof TR22 Thermaroof TR26 LPC / FM Thermaroo
Manufacture :Kingspan Insulation Ltd Phone : 01544 388601
Desc : insulation Format : Yellow foam with composite foil or alternative facings of Glass
reinforced perforated cellulose; cork; Coated glass tissue; WBP exterior
grade plywood.
Constituents
Rigid thermoset urethane PIR as defined in EN13165 insulation Either Composite foil Glass reinforced perforated cellulose Glass tissue Cork Coated
glass tissue WBP exterior grade plywood
Effect :
No information available at this time
Action :
Stable and un-reactive during normal use
Protective Clothing :
Dust is non-hazardous Dust from timber facings may cause respiratory irritation As with all cutting procedures it is recommended that a disposable dust
mask be worn Where dust is generated through mechanical cutting in confined spaces it is recommended that extraction be used It is recommended
that gloves be worn when handling the product Eye protection recommended during mechanical cutting When installing a product with reflective foil
facings in very bright or sunny weather it is advisable to wear UV protective sunglasses or goggles Non-sensitising It is recommended to wear gloves
when handling the product When installing a product with reflective facings in bright sunlight it is advisable to consider skin protection from UV The
product is non-load bearing Access and work should not be carried out on un-supported boards TR31 is load bearing in spanning applications when
approved and fixed in accordance with manufacturers guidelines The smooth facing used on some Therma products can be slippery underfoot when
wet
First Aid :
Dust is non-hazardous Remove the person to fresh air Non-sensitising When glass facing is handled skin irritation may occur Wash carefully using soap
and water or a proprietary cleanser to remove Dust particles should be removed by flushing with clean water No information available Seek medical
attention if discomfort persists
Disposal :
Waste insulation is non-hazardous Product dust created in the installation process is regarded as nuisance dust only because of its inert nature
Observe usual safety precautions with polythene bags wrapping and packaging Waste product should be disposed of in accordance with local laws and
regulations Clean undamaged product may be re-used
Fire :
It is prudent to take precautions against ignition fire spread and smoke hazard Suitable media Waterspray fog Foam CO2 or Dry Chemical Un-suitable
media Not applicable Fire fighters should use self contained breathing apparatus and saturate burning foam with water from a spray nozzle Dust is
classified as weakly explosive St Class 1
Spillages :
Not applicable
Storage :
Store in original packing in a location free from any ignition hazard such as open flames cutting and welding torches high surface temperature electric
heaters and other forms of direct radiant heat ii Keep product protected from the elements Ensure stability of stack and provide adequate aisle space for
access between stacks
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 360/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 361/471
COSHH ASSESSMENT
Trade Name : Lead sheet Class : No specific uses advised against have been identified, other
than legal restrictions on lead
Manufacture :3M (UK) Ltd Phone : 01344 858000
Desc : No specific uses advised against have been identified, other Format : Grey-Blue Solid
than legal restrictions on the use of lead.
Constituents
Substance EC Number REACH registration number if applicable Concentration w w Hazard Classification Lead 231-100-4 99 None Copper 231-159-6 0 03-0 06 None Non-
hazardous impurities n a n a remainder None
Effect :
Lead in massive or sheet form is not a significant health hazard However the following information is relevant if your blood lead is elevated as a result of breathing in lead dust
fume or vapour or as a result of swallowing lead due to poor hygiene practices Toxicokinetic assessment Lead is slowly absorbed by ingestion and inhalation and poorly
absorbed through the skin If absorbed it will accumulate in the body with low rates of excretion leading to long-term build up Part of risk management is to take worker blood
samples for analysis to ensure that exposure levels are acceptable acute toxicity Lead massive metal is not considered to be acutely toxic It is not easily inhaled or ingested
and if it is accidentally ingested normally passes through the gastrointestinal system without significant absorption into the body Lead is not easily absorbed through the skin b
skin corrosion irritation Studies have shown that sparingly soluble inorganic lead compounds are not corrosive or irritating to skin and this lack of effect is expected also for
metallic lead This conclusion is supported by the lack of reports of irritant effects from occupational settings c serious eye damage irritation Studies have shown that sparingly
soluble inorganic lead compounds are not corrosive or irritating to eyes and this lack of effect is expected also for metallic lead This conclusion is supported by the lack of
reports of irritant effects from occupational settings d respiratory skin sensitisation There is no evidence that lead causes respiratory or skin sensitisation e germ cell
mutagenicity The evidence for genotoxic effects of highly soluble inorganic lead compounds is contradictory with numerous studies reporting both positive and negative effects
Responses appear to be induced by indirect mechanisms mostly at very high concentrations that lack physiological relevance f carcinogenicity There is some evidence that
inorganic lead compounds may have a carcinogenic effect and they have been classified by IARC as probably carcinogenic to humans Group 2A However it is considered that
this classification does not apply to lead in articles given the very low bioavailability of metallic lead Carcinogenicity studies of lead metal powder have been negative
Epidemiology studies of workers exposed to inorganic lead compounds have found a limited association with stomach cancer IARC has concluded that lead metal is possibly
carcinogenic to humans Group 2B g reproductive toxicity Exposure to high levels of inorganic lead compounds may cause adverse effects on male and female fertility including
adverse effects on sperm quality Prenatal exposure to inorganic lead compounds is also associated with adverse effects on the development of the unborn child There is
evidence that neurobehavioral development in children is affected by exposure to lead h STOT-single exposure Inorganic lead compounds have generally been found to be of
relatively low acute toxicity by ingestion in contact with skin and by inhalation with no evidence of any local or systemic toxicity from such exposures The bioavailability of lead
metal is low and acute lead exposure is not expected to result in acute toxicity effects i STOT-repeated exposure Lead is a cumulative poison and may be absorbed into the
body through ingestion or inhalation Although inhalation and ingestion of lead in massive form are unlikely poor hygiene practises may result in hand to mouth transfer which
maybe significant over a prolonged period of time Inorganic lead compounds have been documented in observational human studies to produce toxicity in multiple organ
systems and body function including the haemotopoetic blood system kidney function reproductive function and the central nervous system j aspiration hazard Lead metal is a
solid and aspiration hazards are not expected to occur
Action :
Lead is not a reactive substance and no reactive hazards are expected 10 2 Chemical stability Expected to be stable under normal conditions of use 10 3 Possibility of
hazardous reactions No hazardous reactions expected under normal conditions of use 10 4 Conditions to avoid Not applicable 10 5 Incompatible materials Strong oxidizing
agents 10 6 Hazardous decomposition products No decomposition if used as directed
Protective Clothing :
Respiratory protection Suitable respiratory protective device recommended if work activity is likely to result in formation of lead fumes vapours or dust In case of brief or low
level exposure use dust mask or half mask with particle filter P2 Assess the need to wear respiratory protective equipment in production areas Consider use of effective masks
accompanied by a compliance policy ensure proper shaving ensure workers do not remove RPE in production areas in order to communicate Where masks are used employ
formal mask cleaning and filter changing strategies Hand Protection Protective gloves Material of gloves Neoprene or Leather Eye protection Safety glasses Skin protection
Wear protective work clothing For workers in areas of significant exposure provide sufficient working clothes to enable daily change into clean clothes In such cases all work
clothing should be cleaned by the employer on a daily basis and is not permitted to leave the work site
First Aid :
Description of first aid measures EYE CONTACT Ensure that contact lenses are removed before rinsing eyes Separate eyelids wash the eyes thoroughly with water 15 min
Seek medical attention if irritation persists INHALATION Move person to fresh air Seek medical attention SKIN CONTACT Remove contaminated clothing Wash skin
immediately with soap and water Seek medical attention if irritation persists INGESTION Rinse out mouth and give plenty of water to drink Seek medical attention 4 2 Most
important symptoms and effects both acute and delayed Clinical manifestations of lead poisoning include weakness irritability asthenia nausea abdominal pain with
constipation and anaemia 4 3 Indication of any immediate medical attention and special treatments needed Symptoms of poisoning may occur after several hours seek medical
attention
Disposal :
Waste treatment methods Should be reclaimed and recycled If this is not possible dispose as hazardous waste Do not allow product to reach sewage system Different lead-
bearing wastes resulting from the manufacturing processes described above are generated in the form of dross flue dust and slag These waste products should either be
recycled in the production process or landfilled
Fire :
Water spray jet Dry sand Extinguishing media that must not be used for safety reasons Full water jet Foam 5 2 Special hazards arising from the substance or mixture In case of
fires hazardous combustion gases are formed Lead fumes Lead oxide 5 3 Advice for fire fighters Appropriate breathing apparatus may be required Wear protective clothing
Spillages :
Ensure adequate ventilation Avoid dust formation Avoid contact with skin eyes and clothing 6 2 Environmental precautions Do not discharge into the drains surface waters
groundwater In case of entry into waterways soil or drains inform the responsible authorities 6 3 Methods and materials for containment and clearing up Collect mechanically
preferably in dry condition Send in suitable containers for recovery or disposal When picked up treat material as prescribed under heading Disposal considerations
Storage :
Provide good ventilation of working area local exhaust ventilation if necessary The product is not combustible Lead is a heavy material and care must be taken during handling
or lifting 7 2 Conditions for safe storage including any incompatibili
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 362/471
COSHH ASSESSMENT
Trade Name : Lead sheet Class : No specific uses advised against have been identified, other
than legal restrictions on lead
Manufacture :3M (UK) Ltd Phone : 01344 858000
Desc : No specific uses advised against have been Format : Grey-Blue Solid
identified, other than legal restrictions on the use of lead.
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 363/471
COSHH ASSESSMENT
Trade Name : ROCKWOOL Insulation Class : Thermal insulation, acoustic insulation, fire protection
Manufacture :Rockwool Limited Phone : 01656 862621
Desc : Thermal insulation, acoustic insulation, fire protection Format : Solid, grey-green.
Constituents
Mineral wool - Man-made vitreous silicate fibres with random orientation with alkaline oxide and alkali earth oxide Na2O K20 CaO MgO BaO content greater than 18 by weight
01-2119472313-44 287922-11-6 95-99 Bakelite synthetic thermosetting resin binder - - Up to 5 Mineral oil for water repellency or - - Up to 0 3 Silicon oil or Silicon emulsion for
water repellency - - Up to 0 5
Effect :
11 1 Information on toxicological effects a acute toxicity None b irritation In the case of coarser fibres there can be physical effects on skin upper respiratory system mucous
membranes and eyes than can cause temporary self-fading effects e g itching No chemical effects ensue c corrosivity None d sensitisation None e repeated dose toxicity None
f carcinogenicity None Owing to their high bio-solubility the fibre types of ROCKWOOL stone wool insulation materials are assessed as free from suspicion of possible
carcinogenic effects in accordance with EU Directive 97 69 EC Note Q In October 2001 the International Agency for Research on Cancer IARC classified mineral wool
insulation as Group 3 not classifiable as to its carcinogenicity in humans i e not classified as possibly carcinogenic to humans g mutagenicity None h toxicity for reproduction
None
Action :
10 1 Reactivity Not reactive 10 2 Chemical stability Stable 10 3 Possibility of hazardous reactions Not reactive 10 4 Conditions to avoid None specified 10 5 Incompatible
materials None specified 10 6 Hazardous decomposition products When insulation wool is heated to approximately 200OC for the first time s release of binder components and
binder decomposition products occurs
Protective Clothing :
Workplace exposure limit WEL 5mg m3 gravimetric measure total inhalable dust and 2 fibres ml airborne fibre limit 8-hour time weighted averages HSE guidance assumes that
the gravimetric measure would be reached before the fibre measure 8 2 Exposure controls 8 2 1 Appropriate engineering controls None required 8 2 2 Individual protection
measures such as personal protective equipment a Eye protection With heavy dust development or when working with product above head height the use of safety goggles is
advised b Skin protection Hands It is recommended that gloves are worn for comfort Other No special requirements It is recommended for comfort that long-legged long-
sleeved work clothing is worn c Respiratory protection If the WEL is likely to be exceeded for example when using high speed cutting tools or when working in confined spaces
disposable face masks complying with BS EN149 FFP1 or FFP2 should be used and are suitable for most applications When insulation wool is heated to approximately 200OC
for the first time s release of binder components and binder decomposition products occurs The fumes can be detectd by their acrid odour and high concentrations of these
gases may irritate the eyes and respiratory system In general decomposition products from pyrolysis or burning of organic material can cause respiratory sensitisation There
are no recorded incidents of respiratory sensitisation from gases released from Rockwool Ltd products However general dilution ventilation and or local exhaust ventilation
should be provided as necessary to control exposure to fumes when high temperature appliances are first put into service
First Aid :
4 1 Description of first aid measures 4 1 1 Inhalation If irritation occurs clean throat by rinsing with cold potable water Leave dusty area for fresh air Consult a physician if
irritation persists 4 1 2 Skin If irritation occurs wash off under cold running water prior to washing with mild soap Do not rub or scratch Consult a physician if irritation persists 4
1 3 Eye If irritation occurs check for and remove any contact lenses flush eyes with potable cold water Do not rub eyes Seek medical attention 4 1 4 Ingestion If ingested may
cause transient irritation to the digestive tract Seek medical attention 4 2 Most important symptoms and effects both acute and delayed The mechanical effect of fibres in
contact with throat skin or eyes may cause temporary irritation 4 3 Indication of any immediate medical attention and special treatment needed None required
Disposal :
13 1 Waste treatment methods ROCKWOOL material is recyclable Please refer to our website www rockwool co uk for more information ROCKWOOL insulation is classified
as non-hazardous waste ROCKWOOL insulation waste is covered by the non-hazardous entry 17 06 04 insulation materials other than those mentioned in 17 06 01 and 17 06
03 in the European Waste Catalogue established by EC Decision 2000 532 EC hazardous waste Under landfill regulations ROCKWOOL insulation waste is categorised as
waste accepted at landfills for non-hazardous waste in accordance with EC Decision 2003 33 EC landfill acceptance criteria
Fire :
5 1 Extinguishing media 5 1 1 Suitable Extinguishing media Water foam carbon dioxide or dry powder 5 1 2 Unsuitable extinguishing media None 5 2 Special hazards arising
from the substance or mixture The products are non-combustible and do not pose a fire hazard Some facings and packaging materials may burn 5 3 Advice for firefighters
Observe normal firefighting procedures
Spillages :
6 1 Personal precautions protective equipment and emergency procedures No special requirements It is recommended for comfort that long-legged long-sleeved clothing and
gloves are worn Safety goggles may be worn if a lot of dust has been generated 6 2 Environmental precautions None required 6 3 Methods and materials for containment and
cleaning up Spray with water before sweeping or use vacuum equipment
Storage :
7 1 Precautions for safe handling Unpack materials at application site to avoid unnecessary handling of product Dispose of scrap material and debris in suitable containers
Keep work areas clean Do not eat drink or smoke in work areas Wash hands after use rinsing under cold water before using soap Change clothes and wash on completing
work 7 2 Conditions for safe storage including any incompatibilities Keep material in original packaging until it is to be used Store material to protect against damage including
the weather 7 3 Specific end use s None required
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 364/471
COSHH ASSESSMENT
Trade Name : ROCKWOOL Insulation Class : Thermal insulation, acoustic insulation, fire protection
Manufacture :Rockwool Limited Phone : 01656 862621
Desc : Thermal insulation, acoustic insulation, fire Format : Solid, grey-green.
protection
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 365/471
COSHH ASSESSMENT
Constituents
Unknown Not applicable
Effect :
Mildly irritant in contact with eyes and skin Irritant and caustic when mixed with cement and lime In wet state
Action :
Avoid inhalation of dust Use only in well ventilated area Obtain special instructions before use Remove
contaminated clothing immediately Wash hands before meals and after work with a recognised hand cleaner soap
water
Protective Clothing :
Wear appropriate gloves and eye face protection Wear suitable dust mask to BS EN 149 2001 A1 2009 spec if
necessary Use barrier cream for additional protection
First Aid :
Skin Wash from skin with a recognised hand cleaner and then with soap and water Eyes Irrigate eyes with
copious amounts of clean fresh water for at least 10 mins Seek medical advice Seek medical attention if irritation
persists
Disposal :
Dispose of to landfill site
Fire :
Non flammable
Spillages :
Storage :
Not applicable
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 366/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 367/471
COSHH ASSESSMENT
Constituents
Quartz SiO2 98 EINECS 238-878-4 CAS 14808-60-70
Effect :
The mixture has not been assessed for toxicological effects the mixture classification based on individual component contents
Action :
No specific information available Chemical Stability Stable under normal conditions Possibility of hazardous reactions No specific hazardous reactions
known Conditions to avoid No specific data Incompatible materials No specific materials to avoid Hazardous decomposition products Under normal
conditions of storage and use hazardous decomposition products should be produced
Protective Clothing :
Individual protection measures such as personal protective equipment a Wear safety glasses with side-shields in circumstances where there is a risk of
penetrative eye injuries Eye face protection b No specific requirement For hands see below Appropriate protection e g protective clothing barrier cream
is recommended for workers who suffer from dermatitis or sensitive skin Skin protection c Appropriate protection e g gloves barrier cream is
recommended for workers who suffer from dermatitis or sensitive skin Wash hands at the end of each work session Hand protection d Respiratory
protection In case of prolonged exposure to airborne dust concentrations wear a respiratory protective equipment that complies with the requirements of
European or national legislation
First Aid :
Movement of the exposed individual from the area to fresh air is recommended Skin Eye exposure Skin No special first aid measures necessary Eyes
Immediately rinse with clean water for 15 minutes Obtain medical attention if symptoms develop or persist
Disposal :
Disposal method in accordance with all applicable national environment laws and regulations
Fire :
No specific extinguishing media is needed Special Hazards arising from the substance or mixture Non combustible No hazardous thermal
decomposition Advice for fire-fighters No specific fire-fighting protection is required
Spillages :
Personal precautions protective equipment and emergency procedures Avoid airborne dust generation wear personal protective equipment in
compliance with national legislation Environmental Precautions No special requirements Methods and material for containment and cleaning up Avoid
dry sweeping and use water spraying or vacuum cleaning systems to prevent airborne dust generation Wear PPE in compliance with national regulation
Storage :
Avoid airborne dust generation Provide exhaust ventilation at places where airborne dust is generated In case of insufficient ventilation wear suitable
respiratory protective equipment Handle packaged products carefully to prevent accidental bursting If you require advice on safe handling please
contact your supplier Do not eat drink or smoke in work areas wash hands after use remove contaminated clothing and PPE before entering eating
areas Conditions for safe storage including any incompatibilities Store in a cool dry atmosphere in original labelled containers Refer to manufacturer for
maximum safe stacking height Specific end use s Horticultural uses - blending in compost mixes and dressing
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 368/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 369/471
COSHH ASSESSMENT
Constituents
Unknown Not applicable
Effect :
Mildly irritant in contact with eyes and skin
Action :
Avoid contact with skin and eyes
Protective Clothing :
Wear safety glasses with eye shields or goggles Wear protective gloves
First Aid :
Ingestion If swallowed DO NOT induce vomiting - seek medical advice Ingestion If ingested give milk and water to
drink and seek medical advice Eyes Irrigate eyes with copious amounts of clean fresh water for at least 10 mins
Seek medical advice Skin Thoroughly wash from skin with soap and water Remove contaminated clothing
Disposal :
Dispose of in accordance with the control of Pollution Act 1974 Dispose of to landfill site Dispose of in accordance
with Local Authority Regulations
Fire :
Use water CO2 or Dry Foam
Spillages :
Contain spillages and soak up with sand or earth Clean up contaminated area with detergents
Storage :
Store in a cool dry area Avoid strong oxidising agents Protect from frost Keep out of reach of children
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 370/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 371/471
COSHH ASSESSMENT
Trade Name : Softwood Plywood Class : This panel product contains a softwood veneer face and back
bonded to other wood veneer using phenol
Manufacture :Timber Products Company Phone : (541) 747-4577
Desc : This panel product contains a softwood veneer face and back Format : Solid
bonded to other wood veneer using phenol-formaldehyde resin.
Constituents
Ligno-cellulosic Materials 90-93 Polymerized Phenol-Formaldehyde Resin 6-9 9003-35-4 Formaldehyde CAS 50-00-0 0 5 ppm Action Level 0 75 ppm TWA 2 ppm STEL 15 mg
m3 TWA Total 5 mg m3 TWA RF 3 0 30 ppm Ceiling Wood Dust Ligno-cellulosic fibers all species except Western Red Cedar 1 2 1 0 mg m3 TWA IF 3
Effect :
Acute Health Hazards Signs and symptoms of exposure emergency and first aid procedures Ingestion Not applicable Inhalation Formaldehyde may cause temporary irritation
to the nose and throat Wood dust may cause unpleasant deposits and obstructions in nasal passages dryness of nose dry cough and headaches Eye Contact Formaldehyde
may cause temporary irritation or a temporary burning sensation Wood dust may cause mechanical irritation Treat dust in eye as a foreign object Flush with water to remove
dust particle Get medical attention if irritation persists Skin Contact Formaldehyde or wood dust may cause allergic contact dermatitis in sensitized individuals Wood dust may
also mechanically irritate the skin and cause erythema and hives Get medical attention if rash irritation or dermatitis persists Medical conditions Generally Aggravated by
Exposure Formaldehyde or wood dust may irritate preexisting respiratory conditions or allergies Chronic Health Hazards Formaldehyde has been shown to cause cancer in
certain laboratory animals after long terms exposure to high concentration Wood dust may cause dermatitis respiratory sensitization and or irritation after repeated contact and
has been asserted to cause paranasal sinus cancer from certain European oak and beech
Action :
Stability Stable under normal conditions Conditions to avoid Avoid contact with oxidizing agents Avoid open flame Product may ignite in excess of 400oF High relative humidity
and temperature may increase the rate of emission of formaldehyde Incompatibility materials to avoid Avoid open flame and oxidizing agents Hazardous Decomposition
Thermal and or thermal oxidative decomposition s can produce irritating and toxic fumes and gases including carbon monoxide hydrogen cyanide aldehydes organic acids and
polynuclear aromatic compounds Hazardous Polymerizations Not applicable
Protective Clothing :
First Aid :
Inhalation Wood dust may cause unpleasant obstruction in the nasal passages resulting in dryness of nose dry cough sneezing and headaches Remove to fresh air Get
medical attention if irritation persists severe coughing or breathing difficulty occurs Eye Contact Wood dust may cause mechanical irritation Treat dust in eye as foreign object
Flush eyes with large amounts of water Remove to fresh air If irritation persists get medical attention Skin Contact Wash affected areas with soap and water Get medical
attention if rash or irritation persists or dermatitis occurs Ingestion Not Applicable
Disposal :
Fire :
Flash Point Not applicable Autoignition Temperature Not available will depend upon duration of exposure to heat source and other variables Explosive Limits in Air See below
under Unusual fire and Explosive Hazards Extinguishing Media Water Carbon Dioxide and Sand Special Fire Fighting Procedures None Unusual Fire and Explosion Hazards
Sawing sanding or machining can produce wood dust as a by- product that may present an explosion hazard if a dust cloud contacts an ignition source Particle size will
determine LEL
Spillages :
Respiratory Protection Not applicable for this product in purchased form A NIOSH-MSHA approved respirator is recommended when the allowable exposure limits may be
exceeded Protective Goggles Not required Cloth canvas or leather glove are recommended Eye Protection Not applicable for product in purchased form Goggles or safety
glasses are recommended when product is machined Other protection clothing or equipment Outer garments may be desirable in extremely dusty areas Work Hygienic
Practices Follow good hygienic and housekeeping practices
Storage :
Steps to be taken if spilled or released Not applicable in purchased form Wood dust may be vacuumed or shoveled for recovery or disposal Avoid dusty conditions and provide
good ventilation Use NIOSH- MSHA approved respirator and goggles where ventilation is not possible Waste Disposal method Place recovered wood dust in container for
proper disposal landfill or incinerate in accordance with federal state and local regulations Precautions to be taken in handling and storage Keep in dry place away from open
flame This product will release small amounts of formaldehyde Store in a well-ventilated area
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 372/471
COSHH ASSESSMENT
Trade Name : Softwood Plywood Class : This panel product contains a softwood veneer face and back
bonded to other wood veneer using phenol
Manufacture :Timber Products Company Phone : (541) 747-4577
Desc : This panel product contains a softwood veneer face Format : Solid
and back bonded to other wood veneer using phenol-
formaldehyde resin.
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 373/471
COSHH ASSESSMENT
Constituents
Dust during fabrication 5 mg cu metre respirable dust 8 hr TWA Dust during Fabrication 10 mg cu metre inhalable
dust
Effect :
Irritant in contact with eyes and skin Irritant to respiratory system
Action :
Forced ventilation is required in confined spaces Wash hands before meals and after work with a recognised
hand cleaner soap water Avoid contact with skin and eyes Ensure fabrication is carried out in area with adequate
ventilation
Protective Clothing :
Dust mask and eye protection is required in areas of inadequate ventilation
First Aid :
Inhalation If Dust inhaled remove to fresh air and seek medical advice Eyes Wash from eyes immediately and
seek medical attention if irritation persists Skin Reduce irritation by rinsing skin with water before washing with
recognised hand cleaner soap water
Disposal :
Dispose of to site accepting builders waste
Fire :
If CO2 or Halon extinguishers are used in a confined space breathing apparatus is required Use foam dry powder
or CO2
Spillages :
Not applicable
Storage :
Keep away from heat and sources of ignition Keep away from foodstuffs Keep in a secure dry well ventilated area
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 374/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 375/471
COSHH ASSESSMENT
Trade Name : Thistle BondingCoat Class : Gypsum building plaster used to provide a smooth, flat surface
to internal walls and ceilings.
Manufacture :British Gypsum Phone : 0115-9456123
Desc : Gypsum building plaster used to provide a smooth, flat surface Format : Dry powder.
to internal walls and ceilings.
Constituents
Calcium sulphate hemihydrate Natural constituents may include clay limestone and minor amounts of quartz
Additives may include minor amounts less than 1 of hydrated lime
Effect :
Inhalation Skin contact Eye contact Ingestion Plaster dust may irritate the respiratory system No known long term
effects Wet plaster may form an alkaline solution and irritate the skin Dry powder can cause irritation Wet plaster
may form an alkaline solution and cause eye irritation Dry powder can cause irritation Small quantities of plaster
should not cause any significant reaction or long term effect
Action :
10 1 Reactivity No special physical conditions need to be avoided No specific restrictions regarding incompatible
materials 10 2 Chemical stability This preparation is stable under the recommended handling and storage
conditions 10 3 Possibility of hazardous reactions None under normal conditions of use 10 4 Conditions to avoid
Avoid dust formation 10 5 Incompatible materials No specific restrictions regarding incompatible materials 10 6
Hazardous decomposition products No data available
Protective Clothing :
P280 - Wear protective gloves to EN374 standard Wear Protective clothing Wear Eye protection to EN166
standard Category 5-K P285 - In case of inadequate ventilation wear respiratory protection EN149 2001 minimum
recommended FFP2
First Aid :
Eye contact Skin contact Ingestion P305 P313 - If in eyes get medical advice P337 P351 - If eye irritation persists
rinse cautiously with water for several minutes P264 - Wash hands thoroughly after handling P301 P330 - If
swallowed rinse mouth Inhalation P261 - avoid breathing dust P304 P340 - if inhaled remove victim to fresh air
and keep at rest in a position comfortable for breathing P312 - Call a doctor if you feel unwell General Get medical
attention if any symptoms persist
Disposal :
Wastes from gypsum products are normally classified as non-hazardous but should not be co-disposed with
municipal waste P501 - Dispose of contents of containers at an authorised landfill site in accordance with the
Waste Management Licensing Regulations
Fire :
The product does not pose a fire hazard However some packaging materials may burn Suitable extinguishing
media water foam carbon dioxide or dry powder
Spillages :
Avoid creating dust - Plaster can be mixed with water Avoid eye contact or prolonged repeated contact with skin -
Prevent plasters from contaminating drains
Storage :
Use Minimise dust generation when opening bags mixing or sanding plasters in poorly ventilated places Avoid
eye contact or prolonged or repeated contact with skin P264 - Wash hands thoroughly after handling P270 - Do
not eat drink or smoke when handling this product P271 - Use only outdoors or in a well ventilated area Manual
handling Supplied in approximately 25kg bags use an appropriate lifting technique
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 376/471
COSHH ASSESSMENT
Trade Name : Thistle BondingCoat Class : Gypsum building plaster used to provide a smooth, flat surface
to internal walls and ceilings.
Manufacture :British Gypsum Phone : 0115-9456123
Desc : Gypsum building plaster used to provide a smooth, Format : Dry powder.
flat surface to internal walls and ceilings.
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 377/471
COSHH ASSESSMENT
Constituents
Gypsum Plaster 5 mg cu metre respirable dust 8 hr TWA Cement 10 mg cu metre inhalable dust Cement 4mg cu
metre respirable dust Hydrated Lime 10 mg cu metre inhalable dust Hydrated Lime 4mg cu m 8hr TWA Quartz
silica 0 3mg cu metre respirable dust
Effect :
Mildly irritant in contact with eyes and skin Dust may cause irritation to upper respiratory tract nose throat
Action :
Supplied in 25kg bags Avoid contact with eyes and skin when mixing Ensure adequate ventilation The Manual
Handling Operations Regs may apply to handling containers of this product Refer to the guide weight indicated
when carrying out assessments Minimise and control dust when opening bags
Protective Clothing :
Wear impervious gloves Wear safety glasses suitable for dust protection Wear plastic apron Barrier creams can
be used
First Aid :
Skin Wash from skin with soap and water Seek medical advice Inhalation If inhaled remove to fresh air and rest
Eyes Irrigate eyes with copious amounts of clean fresh water for at least 10 mins Seek medical advice
Disposal :
Dispose of to site accepting builders waste
Fire :
Non flammable
Spillages :
Sweep or pick up by vacuum cleaner Do not allow to enter drains or water courses
Storage :
Keep in a secure dry well ventilated area
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 378/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 379/471
COSHH ASSESSMENT
Trade Name : Thistle Multi-Finish Class : Gypsum building plaster used to provide a smooth, flat surface
to internal walls and ceilings.
Manufacture :British Gypsum Phone : 0115-9456123
Desc : Gypsum building plaster used to provide a smooth, flat surface Format : Dry Powder
to internal walls and ceilings.
Constituents
General composition Calcium sulphate hemihydrate Natural constituents may include clay limestone and minor amounts of quartz Additives may include
minor amounts less than 4 of hydrated lime
Effect :
Inhalation Skin contact Eye contact Ingestion Plaster dust may irritate the respirable system No known long term effects Wet plaster may form an
alkaline solution and irritate the skin Dry powder can cause irritation Wet plaster may form an alkaline solution and irritate the eye Dry powder can cause
irritation Small quantities of plaster should not cause any significant reaction or long term effect
Action :
No special physical conditions need to be avoided No specific restrictions regarding incompatible materials
Protective Clothing :
Respiratory Use in a well ventilated area Where practicable use engineering methods to control dust levels If the exposure standards could be
exceeded use a disposable face mask complying with EN 149 FFP2 Skin Wear appropriate clothing to protect against repeated or prolonged skin
contact Eye If there is a risk of material entering the eye wear eye protection to BS EN 166
First Aid :
Eye contact Skin contact Ingestion Inhalation General Wash eyes with clean water Wash thoroughly with soap and water DO NOT INDUCE VOMITING
Rinse out mouth thoroughly and give plenty of water If irritation occurs remove person to fresh air Get medical attention if any symptoms persist
Disposal :
Wastes from gypsum products are normally classified as non-hazardous but should not be co-disposed with municipal waste Dispose at an authorised
landfill site in accordance with the Waste Management Licensing Regulations
Fire :
The product does not pose a fire hazard However packaging materials may burn Suitable Extinguishing Media water foam carbon dioxide or dry powder
Spillages :
Avoid creating dust - Exposure control personal protection for recommended personal protective equipment Plaster can be mixed with water avoid eye
contact or prolonged repeated contact with skin Hazards identification Prevent plasters from contaminating drains
Storage :
Use Minimise dust generation when opening bags mixing or sanding plasters in poorly ventilated places Avoid eye contact or prolonged or repeated
contact with skin Manual handling Supplied in approximately 25kg bags use an appropriate lifting technique Mechanical handling In order to maintain
the stability of the palletised load it is important that the lift truck fork length and centres are set to correctly support the load Storage Store in dry
conditions All powdered products can settle in transport To maintain stability place pallets on firm level ground Do not stack more than one lift high
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 380/471
COSHH ASSESSMENT
Trade Name : Thistle Multi-Finish Class : Gypsum building plaster used to provide a smooth, flat surface
to internal walls and ceilings.
Manufacture :British Gypsum Phone : 0115-9456123
Desc : Gypsum building plaster used to provide a smooth, Format : Dry Powder
flat surface to internal walls and ceilings.
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 381/471
COSHH ASSESSMENT
Constituents
Calcium Silicates 4mg cu metre respirable dust Aluminates 10mg cu metre 8hr T W A Aromatic Solvents 60 p p m
2hr T W A Calcium Silicates 10 mg cu metre inhalable dust
Effect :
Irritant to respiratory system Mildly irritant in contact with eyes and skin Prolonged or repeated contact with skin
can cause irritation or dermatitis
Action :
Ensure adequate ventilation Avoid inhalation of dust Avoid contact with skin and eyes
Protective Clothing :
Wear suitable respiratory equipment to BS EN 405 A1 P3 where ventilation is insufficient Wear protective clothing
to cover all areas of skin which will come into contact with this product Protective clothing to be sent to laundry or
disposed of safely when heavily soiled
First Aid :
Remove contaminated clothing Skin Wash thoroughly from skin with cold water Inhalation If inhaled remove to
fresh air and rest Ingestion If ingested give milk and water to drink and seek medical advice Eyes Irrigate eyes
with copious amounts of clean fresh water for at least 10 mins Seek medical advice
Disposal :
Dispose of in a safe manner
Fire :
Non flammable
Spillages :
Sweep up and clear contaminated area with plenty of water
Storage :
Keep in a secure dry well ventilated area Store under cover
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 382/471
COSHH ASSESSMENT
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 383/471
COSHH ASSESSMENT
Trade Name : Visqueen Vapour Checktrade name:Visqueen Vapour Class : Visqueen Vapour Checktrade name:Visqueen Vapour
BarrierVisqueen High Performance Vapour BarrierVisqu BarrierVisqueen High Performance Vapour BarrierVisqu
Manufacture :Visqueen Building Products Phone : 0333 202 6800
Desc : Visqueen Vapour Checktrade name:Visqueen Vapour Format : Sheet material in roll form
BarrierVisqueen High Performance Vapour BarrierVisqueen DPM to
PIFAVisqueen EcoMembraneVisqueen High Performance
DPMVisqueen Urban Drainage Geomembrane Visqueen
RadonMembraneVisqueen RadonBLOKVisqueen Low Permeability
Gas MembraneVisqueen Gas BarrierVisqueen GX Hydocarbon
GeomembraneVisqueen GX Flexi Hydrocarbon BarrierVisqueen Gas
Vent MatVisqueen Pre Applied MembraneVisqueen
Protect&DrainVisqueen Eco TPSVisqueen Pallet CoversVisqueen
Polythene product
Constituents
General information The products are manufactured from polyethylene co-polymers and containstandard additives including UV stabilizer organic and
inorganic pigment additives and fillers with or without aluminum foil
Effect :
No known hazard
Action :
Conditions to avoid Stable under normal handling and storage conditions Materials to avoid Strong oxidizingagents Solvents or solvented products
Hazardous decompositionproducts Smoke carbon monoxide carbon dioxide
Protective Clothing :
Exposure control Not applicable Personal protection equipment-Footprotection Wearsafety shoes when handling rolls Hand protection Wear heavy duty
gloves to protect against skin abrasion or cuts Hygiene measures Good hygiene measures should be followed at all times
First Aid :
General advice First aid procedures apply when the product is subjected to high temperature e g in a fire In all cases of doubtor when symptoms persist
obtain medical attention Skin eyecontact Not applicable under normal working conditions In the event of contact with molten product e g in a fire
immediately cool affected areas and irrigate thoroughly with clean cold water Do not remove molten product from the skin Seek medical attention
Ingestion Ingestion unlikely If significant irritation or discomfort occurs seek medical attention Inhalation Not applicable under normal working conditions
In the event of a fire remove to fresh air andseek medical attentionif necessary
Disposal :
General information The product is classified as equivalent to municipal waste It can be reused or recycled Dispose of waste material in accordance
with national and local regulations
Fire :
Suitable extinguishing media Use foam carbon dioxide dry powder sandor earth Unsuitable extinguishing media Do NOT use water Special hazards in
fire Fire will produce smoke Decomposition products may be a hazard to health Burning can be accompanied by the release of molten flaming
dropletsthat could ignite adjacent flammable material Required special protectiveIn confined spaces fire-fighters should wear self-contained
breathingequipment for fire-fighters apparatus and protective clothing
Spillages :
Not applicable
Storage :
Handling precautions Employ safe lifting procedures when handling rolls Storage precautions Store under cover away from sources of heat and ignition
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 384/471
COSHH ASSESSMENT
Trade Name : Visqueen Vapour Checktrade Class : Visqueen Vapour Checktrade name:Visqueen Vapour
BarrierVisqueen High Performance Vapour BarrierVisqu
name:Visqueen Vapour BarrierVisqueen High
Performance Vapour BarrierVisqu
Manufacture :Visqueen Building Products Phone : 0333 202 6800
Desc : Visqueen Vapour Checktrade name:Visqueen Format : Sheet material in roll form
Vapour BarrierVisqueen High Performance Vapour
BarrierVisqueen DPM to PIFAVisqueen
EcoMembraneVisqueen High Performance
DPMVisqueen Urban Drainage Geomembrane Visqueen
RadonMembraneVisqueen RadonBLOKVisqueen Low
Permeability Gas MembraneVisqueen Gas
BarrierVisqueen GX Hydocarbon
GeomembraneVisqueen GX Flexi Hydrocarbon
BarrierVisqueen Gas Vent MatVisqueen Pre Applied
MembraneVisqueen Protect&DrainVisqueen Eco
TPSVisqueen Pallet CoversVisqueen Polythene product
Does Use of this substance for this activity present a significant risk? No
If "YES", can a safer alternative product be used? No
Yes
Alternative Product Yes
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 385/471
(If "Yes". what type and how often?)
Additional Information:
The following have had the assessment explained to them and understand the controls to be followed.
Name Signature Name Signature
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 386/471
RISK ASSESSMENT FOR
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 387/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 388/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 389/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 390/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 391/471
RISK ASSESSMENT FOR
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 392/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 393/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 394/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 395/471
RISK ASSESSMENT FOR
Assessment
High
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 396/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 397/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 398/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 399/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 400/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 401/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 402/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 403/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 404/471
RISK ASSESSMENT FOR
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 405/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 406/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 407/471
RISK ASSESSMENT FOR
Assessment
High
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 408/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 409/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 410/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 411/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 412/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 413/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 414/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 415/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 416/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 417/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 418/471
RISK ASSESSMENT FOR
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 419/471
RISK ASSESSMENT FOR
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 420/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
High
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 421/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 422/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 423/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 424/471
RISK ASSESSMENT FOR
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 425/471
RISK ASSESSMENT FOR
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 426/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 427/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 428/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 429/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 430/471
RISK ASSESSMENT FOR
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 431/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 432/471
RISK ASSESSMENT FOR
Likelihood
High
Assessment
High
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 433/471
RISK ASSESSMENT FOR
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 434/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 435/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 436/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 437/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 438/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 439/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 440/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 441/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 442/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 443/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 444/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 445/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 446/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 447/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 448/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 449/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 450/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 451/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 452/471
RISK ASSESSMENT FOR
Assessment
Medium
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 453/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 454/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 455/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 456/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 457/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 458/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 459/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 460/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 461/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 462/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 463/471
RISK ASSESSMENT FOR
Assessment
High
Likelihood
Medium
Assessment
Medium
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 464/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 465/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 466/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
Medium
Likelihood
Medium
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 467/471
RISK ASSESSMENT FOR
Likelihood
Medium
Assessment
High
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 468/471
RISK ASSESSMENT FOR
Assessment
Medium
Likelihood
Low
Assessment
High
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 469/471
RISK ASSESSMENT FOR
Likelihood
Assessment
Likelihood
Assessment
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 470/471
Credibuild Ltd Operatives RAMS Register
I hereby understand the aforementioned Method Statement and risk Assessments and acknowledge my
responsibility to adhere to the methods / controls.
Compiled by Safety Services (UK) Ltd. The correct use of any material is the responsibility of the user.
© Safety Services (U.K.) Limited 1983 - 2018 :: Page 471/471
Powered by TCPDF (www.tcpdf.org)