The document summarizes a project to conduct emergency maintenance on a road in Rainas 4, Nepal. It includes a bill of quantities (BoQ) listing the quantity, units, unit rate, and total estimated cost for gravel works, which is the only item. The total estimated cost for 452.25 cubic meters of gravel works is NPR 1,45,624.50. Measurement sheets provide additional details on the quantity of gravel works needed.
The document summarizes a project to conduct emergency maintenance on a road in Rainas 4, Nepal. It includes a bill of quantities (BoQ) listing the quantity, units, unit rate, and total estimated cost for gravel works, which is the only item. The total estimated cost for 452.25 cubic meters of gravel works is NPR 1,45,624.50. Measurement sheets provide additional details on the quantity of gravel works needed.
The document summarizes a project to conduct emergency maintenance on a road in Rainas 4, Nepal. It includes a bill of quantities (BoQ) listing the quantity, units, unit rate, and total estimated cost for gravel works, which is the only item. The total estimated cost for 452.25 cubic meters of gravel works is NPR 1,45,624.50. Measurement sheets provide additional details on the quantity of gravel works needed.
Tinpiple, Lamjung, Gandaki Province,Nepal 2017 Name of Project :- Emergency Maintenance of road Location:- Rainas 4 BoQ S.N. Particulars Quantity Units Unit Rate Amount 1 Gravel Works 452.25 m3 322.00 145624.50 Total estimated Cost 145624.50
Lakshman Khanal Er.Bhim Prasad Dahal Ramchandra Adhikari Rainas Municipality Office of the Municipal Executive Tinpiple, Lamjung, Gandaki Province,Nepal 2017 Name of Project :- Emergency Maintenance of road Location:- Rainas 4 Measurenment Book S.N. Nos. Length Breadth Height Quantity Units Remarks
1 Gravel Works 452.25 m3
Main Road 1 402.00 4.50 0.25 452.25 m3
Prepared By: Checked By: Approved By:
Lakshman Khanal Er.Bhim Prasad Dahal Ramchandra Adhikari Norms no 26, 3-1 Norms Unit 1.00 m3 collection for natural Gravel & Transportation by Items DescriptioTruck or Tractor (10.00 km per hour ) 5.0 km lead Annex 1 and 55.3 ( G-13.2) stone aggregate having siz
Quantity Unit Rate Amount
Labour for 1.00 md 0.00 0.00 Labour Labour for 0.28 md 0.00 0.00 Tranpotation 0.00 Truck/Tract 0.543 hr 300.00 162.90 Ideal hour 0.234 hr 150.00 35.10 Equipment & fuel Diesel 1.240 ltr 100.00 124.00 Total 322.00 Rate per un 322.00