Site Measurment

Drain Complete = 333.83 Rft


Only Wall (2 Side) = 17.00 rft
Only slab = 46.00 Rft
Culvert complete = 13.00 Rft
Extra work
Boundary Wall = 24'-0" x 7'- 10"
single column = 6'-0" x 0'-6" x 0'-6"
Details Measurment Of Drain & Extra Boundary Wall
1 Earth Work
= 333.83 Rft
= 13.00 Rft
= 346.83 Rft

2 Brick Flat Soling


= 1 * 48.33 * 6.33 = 305.93 Sft
= 1 * 285.50 * 5 = 1427.50 Sft
= 1 * 13.00 * 5 = 65.00 Sft
= 1798.43 Sft

3 RCC: (Bottom Slab)


= 1 * 48.33 * 6.33 * 0.67 = 204.97 Cft
= 1 * 285.50 * 5 * 0.67 = 956.43 Cft
= 1 * 13.00 * 5 * 0.83 = 53.95 Cft
= 1215.35 Cft
RCC: (Wall)
= 1 * 48.33 * 3 * 1 = 144.99 Cft
= 1 * 48.33 * 3 * 0.67 = 97.14 Cft
= 1 * 56.00 * 5.33 * 0.67 = 199.98 Cft
= 2 * 200.00 * 3 * 0.67 = 804.00 Cft
= 2 * 45.00 * 3.5 * 0.67 = 211.05 Cft
= 2 * 40.50 * 4 * 0.67 = 217.08 Cft
= 2 * 17.00 * 4.00 * 0.67 = 91.12 Cft
= 2 * 13.00 * 3.50 * 0.83 = 75.53 Cft
= 1840.89 Cft
RCC : (Top Slab)
= 1 * 48.33 * 5.33 * 0.5 = 128.80 Cft
= 1 * 254.50 * 5 * 0.5 = 636.25 Cft
= 1 * 31.00 * 5 * 0.67 = 103.85 Cft
= 1 * 46.00 * 5 * 0.5 = 115.00 Cft
= 1 * 13.00 * 5 * 0.83 = 53.95 Cft
= 1037.85 Cft
Total RCC = 4094.09 Cft
Summary Of Drain/Culvert
Earth Work = 346.83 Rft x 500 Tk. = 173415.00 Tk.
Brick Flat Soling = 1798.43 Sft x 5 Tk. = 8992.14 Tk.
RCC Work = 4094.09 Cft x 58 Tk. = 237457.32 Tk.
Total = 419864.46 Tk.
Extra Work Boundary wall

1 Brick Work
= 24 x 7.83 = 187.92 Sft
(Deduction -) = -4 x 7.83 x 0.67 = -20.9844 Sft
= -1 x 24 x 0.42 = -10.08 Sft
= 156.86 Sft
2 RCC Work
Column 1 Pich
= 6 x 0.5 x 0.5 = 1.5 Cft

3 Plaster
One Side Wall = 1 x 24 x 7.83 = 187.92 Sft
Column = 1 x 6 x 1.5 = 9.00 Sft
= 196.92 Sft