Professional Documents
Culture Documents
On Shaft Studies: Update
On Shaft Studies: Update
-. , . .?.&L.,7
.;.
. c.?q
on DeepShaft Studies
Prepared by
Parsons Brinckerhoff Quack & Douglas, Inc
New York
September 1976
-,, *
.> -. 3
DISCLAIMER
This report was prepared as an account of work sponso'red by the United States
Government. Neither the United Srates nor the Energy Research and Dcvclopment
Administration, nor any of their employees, nor any of their contractors,
subcontractors, or their employees, makes any warranty, express or implied, or
assumes any legal liability or responsibility for the accuracy, completeness or
usefulness of any information, apparatus, product or process disclosed, or represents
that its use would not infringe privately owned rights.
September 1976 €@
DISTRIBUTION OF THIS DOCUPAENT IS UNLIMITE.~
TABLE OF CONTENTS
. ..
c ha'pter Page
Letter of Transmittal
Summary
1. Introduction
A. General
B. Scope of Investigation
2, Geology
3. Shaft Sinking
A. R e s e a r c h a n d Development
B. Safety
C . ventilation
D. Other S i z e C o n s i d e r a t i o n s
E. Costs
A. G e n e r a l Procedures
B. W a t e r Control Techniques ' '
C . Excavation ~ e c h n i q u e s
15. Linings
E. In-Service Leakage C o n t r o l
F. Representative Projects
A. General
B. R a i s e Boring
C . Blind Drilling
D . ' Down Hole Boring IvT a c h i n e s
E. Representative Projects
TABLE OF CONTENTS
(Cont'd)
Chapter
A. Materials
B. Out s i d e Migration
C . Observation C h a s e s
D. Differential Settlements
E. .Earthquakes
F. Alternative Layouts
References
SHAFT SINKING
STATE OF THE ART
S U M M A R Y
11. M a j o r r e c e n t d e v e l o p m e n t s a r e a l l c o n t i n u a t i o n s of t h e trend t o m e c h a n i -
zation'. The u s e nf r a i s e boring h a s i n c r e a s e d dramatically i n t h e
l a s t f i v e y e a r s . S u b s t a n t i a l a d v a n c e s i n l a r g e hole blind drilling
c a p a b i l i t y h a v e a l s o o c c u r r e d . Down h o l e boring m a c h i n e s a r e n e a r e r
t h e time of p r a c t i c a l a p p l i c a t i o n .
12. C o n v e n t i o n a l s h a f t sinking a d v a n c e r a t e s c a n b e i n c r e a s e d d r a m a t i c a l l y
by u s i n g a n a d v a n c e pilot h o l e a n d a n a d j a c e n t s m a l l d i a m e t e r shaft
- - both on t h e order of s i x t o eight. f e e t i n diameter -- for muck
h a n d l i n g . The muck is dropped down' t h e "glory-hole" p i l o t , t r a n s f e r r e d
through a c r o s s drift t o t h e o t h e r s h a f t a n d r a i s e d t o t h e s u r f a c e i n
t h a t s h a f t . This permits both a f u l l f a c e a d v a n c e a n d g r e a t e r round
l e n g t h s ( d e p t h s ) ; e a c h significantlly r e d u c e s s i n k i n g t i m e .
The f i r s t shaft of a development project m u s t be sunk e i t h e r c o n -
ventionally or by blind d r i l l i n g . The combination procedure..described
in t h e previous paragraph is. e x c e l l e n t for expediting a n d reducing
t h e c o s t of t h e principal s h a f t . It a l s o permits n e c e s s a r y pre-
production development work a t t h e mining l e v e l t o proceed c o n -
currently w i t h t h e principal s h a f t . e x c a v a t i o n , shortening t h e time t o
t h e beginning of mine production.
iii.
CHAPTER 1
A. General
1. Review of a n e a r l i e r report o n d e e p s h a f t s .
GEOLOGY
7. The fewer adverse rock strata above the mining l e v e l , the better
the geology.
The lower the long term modulus i s , the greater the a r e a l settlement
resulting from e x t e n s i v e mining operations. (Creep and long term modulus,
while r e l a t e d , are considered separate c h a r a c t e r i s t i c s here .) This areal
settlement in turn c a n c r e a t e differential settlement between the shaft and
the surrounding m a t e r i a l s , again leading t o d i s t r e s s in t h e shaft. However,
if too much material is removed from even a high modulus medium, i . e . , if
multiple tunnels a r e too c l o s e l y s p a c e d , a r e a l settlement and resulting
problems c a n occur.
SHAFT SIZING
A. Re s e a r c h a n d Development
B. Safety '
C. Ventilation
A, General Procedure
P
other illustrations in the c h a p t e r , i s taken from "Complex Equipment for
Sinking and Drilling of Vertical S h a f t s , " by I T . A. Malevich.
Even though the rock is of good quality, the shaft may be advanced in
s t e p s (half-faces) rather than full f a c e (full shaft c r o s s section). That i s ,
there may be a s t e p on the order of 4 f e e t high between the two b e n c h e s ,
( f a c e s ) , with work alternating between benches. This permits sumping if
w a t e r is present, i t a l s o permits "blowing down" with a i r t o c l e a n the f a c e
of rock before drilling begins. This is a n important safety feature that h e l p s
locate any h o l e s containing unexploded dynamite cartridges. (A 9-foot d e e p
round may be drilled, and 9 f e e t "pulled"; t h i s lowers t h e bench, originally
4 feet above the other shaft bench t o four f e e t below t h e other bench.)
Figure 4-2
Fig. 62. Dhgrammatic sketch of equipment b c a t i a in shajt while sinking
wiih complex KB -1.
-
1 bucket BPS-2;2 - p u m p PPN-50x12; 3 - pipeline fm lozucring
concrefe mix; 4 - winch LPPG for suspending pneulnatic loader
-
KS-3F;5 -pipeline for compressed a i r ; 6 safely ladder; 7 - p i p e -
-
line for venfilafion;8 - rope for srspending shuttering; 9 r o p e
-
fw srtspending platform; 10 -guide ropes; I 1 cables for signall-
~ connection; 12 - firw cuble.
ing, l i g l ~ t i n gand
Figure 4 - 4
Phase n Phase m Phase n
Figure 4-5
The shaft is partially equipped from t b t o p deck of the s t a g e a s i t
d e s c e n d s . The concrete forms are first removed for r e u s e , then the various
pipe l i n e s installed. A separate trip o f the s t a g e is n e c e s s a r y t o complete
the equipping of t h e shaft -- placing buntons, brattice w a l l s , e t c .
The rate of sinking varies greatly with s p e c i f i c s . At l e a s t three
months i s typically required t o collar the s h a f t , erect t h e headframe, and
equip for sinking. A r a t e of sinkin'g of 150 t o 200 f e e t per month is considered
a good advance in the United S t a t e s , but new techniques may i n c r e a s e t h i s
by 50 percent. (As a n item of i n t e r e s t , a Southern African shaft .--Western
Reefs No. 4 -- w a s sunk 1 , 1 1 8 f e e t in October, 1961, but t h e daily down
shaft crew totalled 450 men!)
B. W a t e r Control Techniques
i
If ground w a t e r is minimal, the shaft may be advanced through both
overburden and bedrock using only sumping in t h e bottom of the excavation.
If greater control i s required in t h e overburden a d the overburden is granular,
a few d e e p w e l l s w i l l control t h e w a t e r and permit excavation in t h e dry.
If the s o i l is fine grained, one or more s t a g e s of w e l l p o i n t s . c a n be u s e d o r ,
if s p a c e i s r e s t r i c t e d , eductors may be u s e d .
P of the grouts varies a s does the g e l time. The problem in grouting is t o inter-
s e c t a l l of the flow c h a n n e l s . A "shoot and grout" technique h a s been
developed recently where small explosive charges a r e s e t off for the Purpose
of creating more, but intersecting, f i s s u r e s ; the method appears t o improve
grouting efficiency.
C . Excavation Techniques
D. ' Linings
E . In-Service ~ e a k a q e ' c o n t r o l
F. - - R e p r e s e n t a t i v e Projects
-
Large d i a m e t e r , d e e p c i r c u l a r s h a f t s h a v e b e e n c o n s t r u c t e d i n a t . l e a s t
three widely s e p a r a t e d geographical a r e a s w h i c h a r e pertinent t o t h i s d i s -
c u s s i o n . T h e s e i n c l u d e t h e p o t a s h s h a f t s in S a s k a t c h e w a n , C a n a d a , s h a f t s
i n t h e s o u t h w e s t e r n United S t a t e s a n d c o a l mining s h a f t s in t h e Netherlands
a n d t h e German Ruhr. T h e s e a r e d e s c r i b e d in t h e following paragrslphs o r
i n t h e following c h a p t e r . Emphasis is g i v e n t o t h e difficult p r o j e c t s t o
i l l u s t r a t e t h e t r o u b l e s t h a t c a n be encountered i n s h a f t s i n k i n g .
Two shafts constructed in 1965 and 1968 near t h e above shaft shed
some interesting light on the .matter of shaft c o s t s . A shaft 18.5 f e e t in
lined diameter w a s constructed a t only four percent more c o s t than the
adjacent shaft with a lined diameter of 16 f e e t , despite t h e 15 percent
greater diameter and 33 percent greater c r o s s s e c t i o n a l a r e a . It should
be noted, however, t h a t t h e s e diameters are c l o s e . t o the optimum s i z e for
sha.ft sinking, a n d , therefore the variation i s l e s s than probably would
occur with substantially greater diameters.
Reasons given for the different procedures and linings were that the
rock shaft had t o be absolutely watertight and constructed within a rigid
schedule t o meet a production deadline w h i l e the man shaft did not have
t o meet t h e s e conditions; a l s o , the man shaft w a s estimated t o c o s t a
million dollars l e s s , a savings which w a s not r e a l i z e d due t o grouting
difficulties and the high c o s t of the s p e c i a l grout. The c o n s u l t a n t s (a
German firm) f e l t t h a t the freezing technique w a s the only one predictable
enough t o meet the deadline and the only way the shaft could be made dry
enough for welding. They considered that the tubbing could not be made
sufficiently watertight a t the high water pressures t o be encountered; i t
w a s a l s o f e l t that s e a s o n a l temperature variations would eventually produce
new l e a k s through the tubbing.
S i n c e t h e t h i c k l a y e r of bitumen prevented i n t e r m e d i a t e s u p p o r t ,
e h e e n t i r e l i n i n g s h a d t o b e supported o n a foundation c u t i n t o b e a r i n g
s t r a t a of a d e q u a t e s t r e n g t h . T h i s o c c u r r e d a t t h e 800-foot l e v e l of Hendrik a n d
t h e 750-foot l e v e l a t M a u r i t s w h e r e a stratum w i t h a c o m p r e s s i v e s t r e n g t h
of 1 , 4 0 0 p s i w a s a v a i l a b l e .
The u s e of c a s t iron l i n i n g s in t h e D u t c h m i n e s w a s d i s c o n t i n u e d
s u b s e q u e n t l y b e c a u s e of t h e i n a b i l i t y of s u c h liningssto t a k e u n e q u a l r a d i a l
l o a d s , t o work e f f e c t i v e l y c o m p o s i t e l y w i t h c o n c r e t e , or t o work w i t h t h i c k
bitumen l a y e r s ; b e c a u s e t h e joints m u s t b e r e c a u l k e d r e p e a t e d l y a s t h e
s h a f t is t h a w e d a n d b e c a u s e of c o s t .
O t h e r difficult s h a f t s u s i n g s p e c i a l t e c h n i q u e s a r e d e s c r i b e d a t t h e
e n d of t h e following c h a p t e r .
CHAPTER 5
A s u s e d in t h i s r e p o r t , c o n v e n t i o n a l s h a f t sinking r e f e r s s p e c i f i c a l l y
t o t h e . u s e of drill a n d b l a s t procedures a n d t h e r e s u l t i n g intermittent ' a d v a n c e
of t h e f a c e w h e r e a s m e c h a n i z e d s h a f t s i n k i n g i n v o l v e s t h e u s e of m a c h i n e s .
rather than e x p l o s i v e s t o break t h e r o c k a n d r e s u l t s in a nearly c o n t i n u o u s
a d v a n c e of t h e f a c e . The term "drilled s h a f t s 1 ' is frequently u s e d a s t h e
procedure is not u n l i k e t h e u s e of g i a n t d r i l l s .
Procedures u s e d i n m e c h a n i z e d s h a f t sinking c a n r e s u l t i n s i g n i f i c a n t
a d v a n c e s i n sinking r a t e s , a n d therefore i n reduction of c o s t s . C e r t a i n
of t h e s e t e c h n i q u e s c a n b e combined w i t h t h e c o n v e n t i o n a l procedures t o
provide similar i n c r e a s e s i n r a t e a n d d e c r e a s e s i n c o s t . For' e x a m p l e , a
l a r g e diameter s h a f t f i r s t may b e r a i s e bored t o a n intermediate diameter
a n d t h e s h a f t then i n c r e a s e d t o f i n a l diameter by " b r e a s t i n g u p " o r " s l a s h i n g
down" u s i n g c o n v e n t i o n a l , o r drill a n d b l a s t , p r o c e d u r e s .
A. General
M e c h a n i z e d s h a f t sinking w i l l b e c o n s i d e r e d h e r e a s d i v i d e d i n t o
t h r e e g e n e r a l a r e a s - - r a i s e boring, blind d r i l l i n g , a n d down h o l e boring
m a c h i n e s . A fourth procedure, reaming u p o r down is r e a l l y a modification
of r a i s e boring a n d is so c o n s i d e r e d h e r e . The g r e a t e s t a d v a n c e s i n r e c e n t
y e a r s i n s h a f t sinking technology h a v e b e e n i n t h e f i e l d of r a i s e boring;
h o w e v e r , t h i s t e c h n i q u e r e q u i r e s a n e x i s t i n g m i n e , o r a t l e a s t s o m e prior
development a t t h e proposed mining l e v e l . It is a highly d e v e l o p e d t e c h n i q u e
a n d future a d v a n c e s w i l l be i n s o p h i s t i c a t i o n of equipment.
. . Blind drilling a d v a n c e s have not been a s dramatic. It i s f e l t t h e
g r e a t e s t potential for t h i s method l i e s in 'handling c e r t a i n very difficult
ground conditions .
Down hole boring m a c h i n e s a p p e a r t o hold the g r e a t e s t poteGtial.
A Bureau of M i n e s funded demonstration project sche.duled for the summer
of 1977 may a c h i e v e t h e breakthrough, long d i s c u s s e d , t h a t w i l l make t h i s
procedure a n effective', practical s h a f t s i n k e r ' s tool.
B. R a i s e Boring
.
C a v i n g ground (e g . s h a l e ) a l s o p o s e s problems for r a i s e borers. W h i l e
a light lining c a n b e s u s p e n d e d from t h e s h a f t of the boring m a c h i n e , a n d
brought u p the hole w i t h the h e a d , i t is difficult t o control t h e ground ,in t h i s
f a s h i o n . In conventional p r o c e d u r e s , t h e lining c a n b e brought down t o
w i t h i n a few f e e t of t h e f a c e , a n d s p e c i a l procedures, b a c k p a c k i n g , a n d
grouting accomplished a s required for control.
C. Rlind Drilling
E. , R e p r e s e n t a t i v e projects
B. OutsideMigration
C. Observation C h a s e s
D . Differential Settlements
C o n s i d e r a b l e a t t e n t i o n h a s been paid in t h i s a n d o t h e r c h a p t e r s t o t h e
problems of w a t e r in s h a f t s i n k i n g . This is b e c a u s e i t is a common problem.
In s a l t , however, t h e most s i g n i f i c a n t long term problems may b e long term
c r e e p (settlement) under t h e s h a f t a n d differential s e t t l e m e n t s between
s h a f t a n d surrounding formations d u e t o a r e a l s e t t l e m e n t s . This concern
h a s prompted t h e c o n s i d e r a b l e a t t e n t i o n given e l s e w h e r e t o bitumen protective
l i n i n g s . If a thick layer of properly d e s i g n e d bitumen surrounds t h e struc-
tural lining, it w i l l a b s o r b t h e s e movements without undue d i s t r e s s in t h e
lining.
E. Earthquakes
D e s p i t e i t s a p p a r e n t m a s s , t h e s h a f t is a n extremely f l e x i b l e s t r u c t u r e
i n s o f a r a s seismic r e s p o n s e is c o n c e r n e d . The deflection of t h e t o p of t h e
s h a f t w i t h r e s p e c t t o i t s b a s e is a function of t h e fourth power of t h e r a t i o of
i t s length t o diameter. Since t h i s length-diameter r a t i o is unlikely t o be l e s s
t h a n 6 0 , t h e extreme flexibility of t h e s h a f t is a p p a r e n t . The s h a f t , t h e r e f o r e ,
w i l l b e c o n s t r a i n e d t o t h e limits of motion i n t h e surrounding medium. T h e s e
a r e unlikely t o e x c e e d 1/200th of t h e s h a f t d e p t h . Therefore, t h e f a c t t h a t a
major earthquake w i l l produce s t r e s s e s of l e s s t h a n o n e p s i i n t h e s h a f t
lining is readily u n d e r s t a n d a b l e .
F. Alternative Layouts