Professional Documents
Culture Documents
Plotting of grid lines for centre of column above the plinth/floor slab.
Locating and marking the centres of columns.
Binding & placing column reinforcement above the upper floor slab , as per the required height,
considering lap length of the bar.
Check for column reinforcement & their arrrangements as per the drawing .
Ring spacing and their arrangements as per the R.C.C drawing.
Proper binding of reinforcement with binding wire.
Fixing concrete or P.V.C cover blocks to reinforcement. (Refer Fig .No. 24.20)
CHECKING OF SHUTTERING
CHECKING OF REINFORCEMENT
FOR BEAMS
Bottom bars, top bars, bent-up bars, stirrups, distance of bent-up bars from face of supports,
extra bars over the supports, spacing of the stirrups as per the R.C.C. drawing , proper tying of
the stirrups. (Refer Fig. NO. 24.43)
Diameter of bars, binding of stirrups in plumb.
Length of bent-up bars continuing in adjacent beams.
‘L’ for bent-up bars at discontinuous ends.
Side covers and bottom covers for beams.
Check if a pin is provided at required places, i.e., more than 3 bars in one layer, for 15cm (6”)
wide beam. Also check the spacing and diameter of the pin provided.
Proper binding of laps in beams. if provided with the required length.
Extra stirrups at the junction of beam. (Refer Fig.No.24.44)
To check the concealed electric conduit work for slabs, as per the drawing and I.S.I. mark on the
P.V.C. pipes. Note down the length of all pipes for billing purpose.
Check the junctions and all electrical points as per the electric layout, position of fan
points, M.S. boxes, junction boxes.
Avoid breaking of pipes during concreting.
Check the slab & the certificate from the architect.
Check the slab & obtain certificate from the R.C.C. consultant.
Sieve analysis for sand to be carried out in advance, for the concrete mix design.
To measure silt content of sand.
MANAGEMENT
Check the stock of cement, sand and metal required for the casting of slab.
Check the arrangement of water and stand by arrangements, in case of electricity failure.
Check the labour strength required & available for slab casting.
Inform the contractor of the starting time of slab and maximum time to be allowed for slab
casting.
Decide the position of concrete joints, in case of a large slab, after consulting and obtaining the
approval from the R.C.C. consultant.
Cast the slab with the help of mixer, vibrator and the measuring boxes.
Check with the mechanic/operator that the mixer & vibrator are present on the site.
Proportion of aggregate should be decided.
Cast six cube moulds of various batches for testing.
Ensure proper leveling of the slab by masons.
Maintain the slab register.
Ensure that wooden pieces, paper etc. are cleared away from the slab or beam before casting.
Arrange the planks over the slab for labour movement, along with the M.S. walk ways, to
prevent any disturbance to top reinforcement.
Arrange for petrol and diesel for vibrator and mixer.
Check the working of the lift before commencing the work and ensure a rigid scaffolding for the
lift.
Ensure sufficient light arrangements, in case of late night concreting.
CHECKLIST AFTER CONCRETING
24.11 FORM-WORK
(1) DEFINITION
The temporary structure erected to support the concrete in it’s required shape, till it hardens and
becomes self supporting is known as the form-work or centering or shuttering.
The form-work must be water-proofed, so as to prevent the absorption of water from the
concrete.
The form-work must be strong enough to bear the load of concrete, workmen, the liquid
pressure of the fresh concrete and the impact effect of ramming or vibrating.
The form-work should be as light as possible and stiff enough to have the minimum deflection.
All joints in the form-work should be true and the surface should be plane to minimize the cost
of surface finishing.
The form-work should be easily removable, without damages.
(3) CHOICE OF FORM-WORK MATERIAL WOODEN PROPS, STEEL PLATES & PLYWOOD
In this type of form-work , the material could be steel plate, plywood wooden plank or wooden prop.
Steel Plate
Size of steel plates are different : i.e., 3’0” x 2’0” x 1” ( 90cm x 60 cm x 25 cm ) thick plate is generally
being used but plates in size 4’ 0”x 2’ 0” (120 cm x 60 cm), 1’ 6” x 3’ 0” (45 cm x 90 cm ) ,0’ 9” x 3’ 0” ( 23
cm x 90 cm ) etc. are also available.
Size of angles, generally used for plates, are 25 x 25 x 5 mm.
Plywood
1. LOCATION OF CONCRETING
2. DATE OF CASTING
3. PROPOSED DATE OF CASTING
4. REASONS FOR DELAY (IF ANY)
5. GRADE OF CONCRETE MIX
6. BRAND NAME OF CEMENT
7. WATER-CEMENT RATIO MAINTAINED
8. TIME OF COMMENCEMENT
9. TIME OF COMPLETION
10. QUANTITY OF CONCRETE
11. TOTAL BAGS CONSUMED & CEMENT RATIO
12. REINFORCEMTNT CHECKED BY / DATE
13. SHUTTERING CHECKED BY
14. NAME OF CONTRACTOR
15. TOTAL LABOUR FORCE
16. MACHINERY USE
17. FAILURE OF MACHINERY DURING CONCRETING ( IF ANY )
18. PERIOD OF INTERVAL
19. ANY ADMIXTURES ADDED
20. DETAILS OF CUBE TAKEN
(A) NOS. OF CBUES TAKEN (B) CODING ON CUBES
21. DUE DATES FOR CUBE TESTING (For 7 & 28 Days )
22. VISITORS WHILE CONCRETING
23. INSTRUCTIONS / ADVICE BY
24. LOCATION OF CONSTRUCTION JOINT
25. HEIGHT OF SLAB
26. ACCIDENTS ( IF ANY ) DURING CONCRETING
27. FAILURE OF ELECTRICITY
28. SHORTAGE OF MATERIAL ( IF ANY )
29. ANY SEVERE PROBLEM IN SHUTTERING
30. NAME OF ENGINEERS / SUPERVISORS PRESENT
(A) NEAR MIXER
(B) ON SLAB
(C) BELOW SLAB
31. GENERAL INFORMATION IF ANY
JR. ENGR. SR. ENGR. PROJECT . ENGR. QUALITY CONTROL ENGR. CHIEF.ENGR.
Generally, plywood is used for form-work of columns and beams . When good surface quality of
concrete is required , plywood is used for slab centering but it is costlier than steel plates. Size of
plywood 4’ 0” x 8’ 0” (1.20m x 2.40m) or 3’ 0” x 8’ 0” (0.9m x 2.40m), thickness of plywood should be
10 to 12 mm for the above work upto a depth of 2’0” (60 cm) concrete.
Quality of wood to be used of the silver oak type and should be free from knots, twists, shakes/ decay
and imperfections which could otherwise affect the strength of forms and finished surface of the
concrete.
Cheek the clear width of the planks used. Usually when we place an order for 6” (15 cm) width plan,
after cutting & finishing we receive 5” (14.5cm) width planks, due to which the total measurements of
beams & bays will be affected.
Prop
Diameter of props should be less than 3” (7.5cm) and it should be straight, as far as possible.
Steel form-work is the more expensive type of form-work, as it is made completely of steel. This
shuttering is easy to erect and to de-shutter. The man power required is very less. True horizontal and
vertical planes of concrete surface can be got, with the help of steel form-work which ultimately reduces
the thickness of the plaster and cost of construction. Nuts and bolts are used to clamp the sides of
beams, to prevent bulging of the sides.
ADJUSTABLE PROP
The props used for steel form-work are specially made to adjust the height of the prop as per the
requirement. These props can be used to accommodate the variations in the height of beam, slab and all
R. C. C. members. It is especially useful for heavy load bearing capacity, is very simple in operation time
and labour saving.
Propex is basically used where the height is greater than practical. More height for props in two or three
tiers requires vertical adjustment to the exact height and can be obtained by inserting a “PROPEX” at the
top of each scaffold.
ADJUSTABLE SPAN
The spans are used to support the centering plates for shuttering of slab. No prop is required in
between, so plenty of space is available below the slab shuttering. This can be adjusted for any length
between 2.0m to 4.0m. This span allows maximum safety, accommodates roof handling, reduces
maintenance cost, requires less space for storage and prevents any wastage as compared to wooden
form-work.
Centering plates are available in sheet metal bending type and angular frame welded and riveted as per
requirement.
The diameter of column can decided as per the requirements of the client.
These are totally bolted type for easy asscmbly and removal after casting.
Rolled sheets offer an excellent finish of columns after casting.
STEP CENTERING
Adjustable in length
Flexible utility for almost all widths of staircase
Sizes available 900 to 1400 mm
1000 to 1500 mm
All sizes mentioned in steel form may change as per manufacturers standards.
After completing the excavation for the column and footing, check the size of the pit before
P.C.C.
Allow P.C.C. work.
Check the level of P.C.C. Then mark the centre of the footing in cement mortar on P.C.C., with
the help of side rail or centre line pillar.
Place the footing form-work box, check the size and diagonals of the form-work box.
Check for gaps if any between form-work and P.C.C. top level. (Refer Fig. No.24.46)
Before concreting, clean the inner space of the box and P.C.C. with help of a water jet.
Give proper supports to footing box, so that it’s position should not change.
Mark centres of the footing with the help of a nail, on footing box or planks.
Centre marked on the footing box should match the centre marked on side rail or centre line
pillar.
Check the reinforcement of footing, column and concreting depth of footing and allow for
concreting (Refer Fig. No.24.26)
QUAILITY OF MATERIAL
(d) SLAB
Chajja is a part projecting outside the building , for protecting the window from rains. It is
generally designed as the cantilever. The following precautions should be taken while doing the
shuttering of the chajjas.
Lintel bottom is fixed using planks on the masonty walls.
After checking line and level of the lintel bottom, proper supports are given to it.
As per the width of the chajja M.S. plates are fixed in the level of lintel bottom with slating
supports as shown in the figure.
Cross-bracing is given to these slanting supports and the base of such supports are prevented
from sliding with the help of wooden wedges fixed on the window sill mansory as shown in the
figure.
Reinforcement is tied as per the drawing.
Sides of chajjas are fixed along with sides of the lintel.
Inner side of the lintel is kept hanging for homogeneous concreting of lintel and chajja. ( this is
called ‘Tang side’)
Proper tying for firmness is done with binding wire.
Width of lintel is maintained with wooden pieces of the required length trapped between the
sides of lintel.
Concreting is done in the slope as per the drawings.