Professional Documents
Culture Documents
Method Statement For Static Equipment (T-4701, T-4302, D-4302, D-4304, D-4606) - 2 PDF
Method Statement For Static Equipment (T-4701, T-4302, D-4302, D-4304, D-4606) - 2 PDF
REV. No.: A
PTSC PTSC
DISCIPLINE PTSC APPROVAL YSE APPROVAL
PREPARED REVIEWED
A MECHANICAL
RECORD OF REVISION
TABLE OF CONTENTS
1. PURPOSE .............................................................................................................................................................. 3
2. SCOPE ................................................................................................................................................................... 3
3. REFERENCE ......................................................................................................................................................... 3
7. RECORDING ........................................................................................................................................................ 8
9. APPENDICIES ...................................................................................................................................................... 9
1. PURPOSE
3. REFERENCE
4. CONSTRUCTION MANPOWER
Position Man
Engineer/ Supervisor /HSE supervisor 03
Crane Operator 02
Signal man 01
Rigger 04
Fitter/ Aligement 02
Scaffolder 02
5.6. Scaffolding
Scaffolding shall be arranged with 2x6x4.5m at D-4302 Equipment final position.
5.7. Cleaning
- Clean the surfaces of the soleplate that will be in contact with the finished grout to
remove any oil, grease, dirt and rust. (Sandblast and prime if necessary) by others. The
bottom of the soleplate could be painted with Epoxy grout to provide a secure bond of
the sole plate to the finish grout.
- Anchor bolt holes and the bottom of equipment soleplate shall be cleaned and free of
laitance loose particles, oil or grease. Concrete surface shall be chipped.
- Anchor bolts shall also be cleaned and kept out of dirty and rust, etc…
- The internal surfaces of all equipment shall be surveyed for its cleaning condition.
Every precaution shall be taken to prevent foreign matters such as sand, soil, clay and
Document No.: PP4-CM-PP-4001 Rev. A Page No.: 5 of 16
HSVC1 PP4 PROJECT
METHOD STATEMENT FOR INSTALLATION/ASSEMBLY EQUIPMENT
1. Foundation checking.
2. Chipping and Padding foundation.
3. Final foundation checking.
4. Platform, Insulation Assembly (If have material)
5. Equipment Installation.
6. Orientation adjustment, Centering and Leveling.
7. Anchor Bolt Tightening (80%).
8. Preliminary Coupling alignment (for rotating Equipment).
9. 2nd Coupling Alignment (for rotating Equipment).
10. Grouting.
11. Final Anchor Bolt Tightening.
12. Piping Connection and Accessory Attachment.
13. Lange Alignment for Connected Piping.
HSVC1 PP4 PROJECT
METHOD STATEMENT FOR INSTALLATION/ASSEMBLY EQUIPMENT
7. RECORDING
Quality Control Plan for Mechanical Installation records shall be made and maintained in
QC Form.
8. SAFETY AND ENVIRONMENT PROTECTION
8.1. Safety
- Safety training will be performed for all construction staff before commencement the
work.
- Labor safety will be earnestly implemented following project HSE requirements.
- If working on high condition (2m high or higher) the safety belts must be applied and
properly used.
- All device operators shall have valid certificates and inspected by authorities parties.
The certifications will be submitted to approve before commencement work.
- All works related to unloading, handling and erection of equipment will be conducted
according to safe practices by the Company Safety Manual, and HSE plan.
- Maintenance and record keeping shall be carried out for all cranes.
- The loads imposed on slings, fittings, etc. shall not exceed the safe working load.
Open hooks shall not be used for hoisting.
- Chains, belts, ropes, etc. shall have valid certificates and inspected before use
8.2. Environment
- Particular care shall be taken to maintain a clean/safe working environment.
- Housekeeping shall be continuously conducted and all wooden timber scrap/packing
material removed from site.
- Equipment shall be regularly maintained and kept free of fluid/oil leakages corrected.
- All produced waste will be disposal of according to approved Waste Management
Plan.
- All paint materials shall be received in the manufacturer’s original containers and
legibly marked with the description of the content. Storage shall be done in dry, clean
and well ventilated areas.
- Paint type, brand name, date of manufacture, batch number and other information shall
be documented for traceability and shelf life.
- The paint shall be thoroughly stirred before, during and after mixing by appropriate
agitator. All paint mixing shall be done according to manufacturer’s recommendation
in clean containers and free from traces of grease or other contaminants.
- The paint maximum shelf life and pot life shall be as per the paint manufacturer’s
recommendation.
- No intermixing of different brand or type of paints will be permitted.
- Coating materials that has gelled or otherwise deteriorated during storage and with
expired shelf life shall not be used.
- No thinner shall be added unless necessary for proper application as recommended or
established by paint manufacturer.
- Blasting abrasives shall be placed on wooden block or other stocking method in a dry
and covered area.
- All blasting abrasives shall be dry and free from contaminants.
Document No.: PP4-CM-PP-4001 Rev. A Page No.: 8 of 16
HSVC1 PP4 PROJECT
METHOD STATEMENT FOR INSTALLATION/ASSEMBLY EQUIPMENT
9. APPENDICIES
Appendix 1: General Assembly Drawing
Appendix 2: Lifting Plan
Appendix 3: Pressure Ground
Appendix 4: Crane Chart
Appendix 5: Certificate of lifting gear
Appendix 6: Job Safety Analysis
Appendix 7: Other
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.20 m
Max distance to neutral axis, Ymax 5.17 m
Xcog 1.15 m
Ycog 0.00 m
Total weight applied on ground, P 731.71 T
Moment about x axis, Mx 0.00 T.m
Moment about y axis, My 844.46 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 9.12 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 2.69 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 9.12 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 2.69 T/m2
Swing Angle ∅= 25 Deg
Mass COG to COR
Components
(T) X(m) Y(m)
Supper Structure w/o Winches 55.00 -2.56 -1.19
H1 & H2 Winches + Conecting Frame 36.80 -0.39 -0.18
Main CounterWeight 180.00 -5.56 -2.59
Central Ballast 60.00 -3.48 -1.62
SL-Counterweight 150.00 -13.59 -6.34
Crawlers 45.00 0.00 0.00
SL-Mast 30m 22.80 -6.00 -2.80
Main Boom 112.25 19.58 9.13
Luffing Jib - - -
Upper Luffing Mast - - -
Lower Luffing Mast - - -
Hook Block 2x300T 4.80 38.06 17.75
Rigging Weight 0.60 38.06 17.75
Load Weight 28.46 38.06 17.75
Steel Mats Weight 36.00 0.00 0.00
Total weight 731.71 1.14 -0.03
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.25 m
Max distance to neutral axis, Ymax 4.95 m
Xcog 1.14 m
Ycog -0.03 m
Total weight applied on ground, P 731.71 T
Moment about x axis, Mx -25.44 T.m
Moment about y axis, My 833.90 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 9.07 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 2.64 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 9.17 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 2.74 T/m2
Swing Angle ∅= 98 Deg
Mass COG to COR
Components
(T) X(m) Y(m)
Supper Structure w/o Winches 55.00 0.39 -2.79
H1 & H2 Winches + Conecting Frame 36.80 0.06 -0.43
Main CounterWeight 180.00 0.85 -6.08
Central Ballast 60.00 0.53 -3.80
SL-Counterweight 150.00 2.09 -14.85
Crawlers 45.00 0.00 0.00
SL-Mast 30m 22.80 0.92 -6.56
Main Boom 112.25 -3.01 21.40
Luffing Jib - - -
Upper Luffing Mast - - -
Lower Luffing Mast - - -
Hook Block 2x300T 4.80 -5.85 41.59
Rigging Weight 0.60 -5.85 41.59
Load Weight 28.46 -5.85 41.59
Steel Mats Weight 36.00 0.00 0.00
Total weight 731.71 0.98 -0.08
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.25 m
Max distance to neutral axis, Ymax 4.95 m
Xcog 0.98 m
Ycog -0.08 m
Total weight applied on ground, P 731.71 T
Moment about x axis, Mx -59.61 T.m
Moment about y axis, My 716.01 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 8.55 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 3.03 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 8.78 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 3.26 T/m2
GROUND PRESSURE UNDER THE CRAWLER OF CC2800-1 CRANE WHILE LIFTING PLAN OF T-4302 EQUIPMENT
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.20 m
Max distance to neutral axis, Ymax 5.17 m
Xcog 1.13 m
Ycog 0.00 m
Total weight applied on ground, P 573.82 T
Moment about x axis, Mx 0.00 T.m
Moment about y axis, My 650.31 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 7.11 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 2.15 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 7.11 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 2.15 T/m2
Swing Angle ∅= 25 Deg
Mass COG to COR
Components
(T) X(m) Y(m)
Supper Structure w/o Winches 55.00 -2.56 -1.19
H1 & H2 Winches + Conecting Frame 36.80 -0.39 -0.18
Main CounterWeight 180.00 -5.56 -2.59
Central Ballast 60.00 -3.48 -1.62
SL-Counterweight 0.00 -13.59 -6.34
Crawlers 45.00 0.00 0.00
SL-Mast 30m 22.80 -6.00 -2.80
Main Boom 112.25 16.63 7.75
Luffing Jib - - -
Upper Luffing Mast - - -
Lower Luffing Mast - - -
Hook Block 2x300T 4.80 23.56 10.99
Rigging Weight 5.00 23.56 10.99
Load Weight 16.17 23.56 10.99
Steel Mats Weight 36.00 0.00 0.00
Total weight 573.82 1.10 0.79
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.25 m
Max distance to neutral axis, Ymax 4.95 m
Xcog 1.10 m
Ycog 0.79 m
Total weight applied on ground, P 573.82 T
Moment about x axis, Mx 455.07 T.m
Moment about y axis, My 629.55 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 7.94 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 3.08 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 6.18 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 1.32 T/m2
Swing Angle ∅= 98 Deg
Mass COG to COR
Components
(T) X(m) Y(m)
Supper Structure w/o Winches 55.00 0.39 -2.79
H1 & H2 Winches + Conecting Frame 36.80 0.06 -0.43
Main CounterWeight 180.00 0.85 -6.08
Central Ballast 60.00 0.53 -3.80
SL-Counterweight 0.00 2.09 -14.85
Crawlers 45.00 0.00 0.00
SL-Mast 30m 22.80 0.92 -6.56
Main Boom 112.25 -2.55 18.17
Luffing Jib - - -
Upper Luffing Mast - - -
Lower Luffing Mast - - -
Hook Block 2x300T 4.80 -3.62 25.75
Rigging Weight 5.00 -3.62 25.75
Load Weight 16.17 -3.62 25.75
Steel Mats Weight 36.00 0.00 0.00
Total weight 573.82 0.99 1.86
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.25 m
Max distance to neutral axis, Ymax 4.95 m
Xcog 0.99 m
Ycog 1.86 m
Total weight applied on ground, P 573.82 T
Moment about x axis, Mx 1066.32 T.m
Moment about y axis, My 565.26 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 8.87 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 4.51 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 4.75 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 0.39 T/m2
GROUND PRESSURE UNDER THE CRAWLER OF CC2800-1 CRANE WHILE LIFTING PLAN OF D-4302 EQUIPMENT
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.20 m
Max distance to neutral axis, Ymax 5.17 m
Xcog 1.11 m
Ycog 0.00 m
Total weight applied on ground, P 758.08 T
Moment about x axis, Mx 0.00 T.m
Moment about y axis, My 842.44 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 9.33 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 2.91 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 9.33 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 2.91 T/m2
Swing Angle ∅= 25 Deg
Mass COG to COR
Components
(T) X(m) Y(m)
Supper Structure w/o Winches 55.00 -2.56 -1.19
H1 & H2 Winches + Conecting Frame 36.80 -0.39 -0.18
Main CounterWeight 180.00 -5.56 -2.59
Central Ballast 60.00 -3.48 -1.62
SL-Counterweight 150.00 -13.59 -6.34
Crawlers 45.00 0.00 0.00
SL-Mast 30m 22.80 -6.00 -2.80
Main Boom 112.25 15.60 7.28
Luffing Jib - - -
Upper Luffing Mast - - -
Lower Luffing Mast - - -
Hook Block 2x300T 4.50 30.81 14.37
Rigging Weight 0.60 30.81 14.37
Load Weight 55.13 30.81 14.37
Steel Mats Weight 36.00 0.00 0.00
Total weight 758.08 1.10 0.04
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.25 m
Max distance to neutral axis, Ymax 4.95 m
Xcog 1.10 m
Ycog 0.04 m
Total weight applied on ground, P 758.08 T
Moment about x axis, Mx 30.62 T.m
Moment about y axis, My 834.53 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 9.39 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 2.96 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 9.27 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 2.84 T/m2
Swing Angle ∅= 98 Deg
Mass COG to COR
Components
(T) X(m) Y(m)
Supper Structure w/o Winches 55.00 0.39 -2.79
H1 & H2 Winches + Conecting Frame 36.80 0.06 -0.43
Main CounterWeight 180.00 0.85 -6.08
Central Ballast 60.00 0.53 -3.80
SL-Counterweight 150.00 2.09 -14.85
Crawlers 45.00 0.00 0.00
SL-Mast 30m 22.80 0.92 -6.56
Main Boom 112.25 -2.40 17.05
Luffing Jib - - -
Upper Luffing Mast - - -
Lower Luffing Mast - - -
Hook Block 2x300T 4.50 -4.73 33.67
Rigging Weight 0.60 -4.73 33.67
Load Weight 55.13 -4.73 33.67
Steel Mats Weight 36.00 0.00 0.00
Total weight 758.08 0.98 0.09
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.25 m
Max distance to neutral axis, Ymax 4.95 m
Xcog 0.98 m
Ycog 0.09 m
Total weight applied on ground, P 758.08 T
Moment about x axis, Mx 71.75 T.m
Moment about y axis, My 746.33 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 9.13 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 3.38 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 8.85 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 3.10 T/m2
GROUND PRESSURE UNDER THE CRAWLER OF CC2800-1 CRANE WHILE LIFTING PLAN OF D-4304 EQUIPMENT
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.20 m
Max distance to neutral axis, Ymax 5.17 m
Xcog 1.18 m
Ycog 0.00 m
Total weight applied on ground, P 556.09 T
Moment about x axis, Mx 0.00 T.m
Moment about y axis, My 658.23 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 6.99 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 1.98 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 6.99 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 1.98 T/m2
Swing Angle ∅= 25 Deg
Mass COG to COR
Components
(T) X(m) Y(m)
Supper Structure w/o Winches 55.00 -2.56 -1.19
H1 & H2 Winches + Conecting Frame 36.80 -0.39 -0.18
Main CounterWeight 180.00 -5.56 -2.59
Central Ballast 60.00 -3.48 -1.62
SL-Counterweight 0.00 -13.59 -6.34
Crawlers 45.00 0.00 0.00
SL-Mast 30m 22.80 -6.00 -2.80
Main Boom 112.25 18.13 8.45
Luffing Jib - - -
Upper Luffing Mast - - -
Lower Luffing Mast - - -
Hook Block 2x300T 4.80 30.81 14.37
Rigging Weight 0.60 30.81 14.37
Load Weight 2.84 30.81 14.37
Steel Mats Weight 36.00 0.00 0.00
Total weight 556.09 1.14 0.66
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.25 m
Max distance to neutral axis, Ymax 4.95 m
Xcog 1.14 m
Ycog 0.66 m
Total weight applied on ground, P 556.09 T
Moment about x axis, Mx 366.62 T.m
Moment about y axis, My 635.07 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 7.64 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 2.75 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 6.23 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 1.33 T/m2
Swing Angle ∅= 98 Deg
Mass COG to COR
Components
(T) X(m) Y(m)
Supper Structure w/o Winches 55.00 0.39 -2.79
H1 & H2 Winches + Conecting Frame 36.80 0.06 -0.43
Main CounterWeight 180.00 0.85 -6.08
Central Ballast 60.00 0.53 -3.80
SL-Counterweight 0.00 2.09 -14.85
Crawlers 45.00 0.00 0.00
SL-Mast 30m 22.80 0.92 -6.56
Main Boom 112.25 -2.78 19.81
Luffing Jib - - -
Upper Luffing Mast - - -
Lower Luffing Mast - - -
Hook Block 2x300T 4.80 -4.73 33.67
Rigging Weight 0.60 -4.73 33.67
Load Weight 2.84 -4.73 33.67
Steel Mats Weight 36.00 0.00 0.00
Total weight 556.09 0.98 1.54
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.25 m
Max distance to neutral axis, Ymax 4.95 m
Xcog 0.98 m
Ycog 1.54 m
Total weight applied on ground, P 556.09 T
Moment about x axis, Mx 859.05 T.m
Moment about y axis, My 543.96 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 8.25 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 4.05 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 4.92 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 0.73 T/m2
GROUND PRESSURE UNDER THE CRAWLER OF CC2800-1 CRANE WHILE LIFTING PLAN OF D-4606 EQUIPMENT
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.20 m
Max distance to neutral axis, Ymax 5.17 m
Xcog 1.16 m
Ycog 0.00 m
Total weight applied on ground, P 559.03 T
Moment about x axis, Mx 0.00 T.m
Moment about y axis, My 646.39 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 6.97 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 2.05 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 6.97 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 2.05 T/m2
Swing Angle ∅= 25 Deg
Mass COG to COR
Components
(T) X(m) Y(m)
Supper Structure w/o Winches 55.00 -2.56 -1.19
H1 & H2 Winches + Conecting Frame 36.80 -0.39 -0.18
Main CounterWeight 180.00 -5.56 -2.59
Central Ballast 60.00 -3.48 -1.62
SL-Counterweight 0.00 -13.59 -6.34
Crawlers 45.00 0.00 0.00
SL-Mast 30m 22.80 -6.00 -2.80
Main Boom 112.25 15.60 7.28
Luffing Jib - - -
Upper Luffing Mast - - -
Lower Luffing Mast - - -
Hook Block 2x300T 4.80 27.19 12.68
Rigging Weight 0.60 27.19 12.68
Load Weight 5.78 27.19 12.68
Steel Mats Weight 36.00 0.00 0.00
Total weight 559.03 1.12 0.46
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.25 m
Max distance to neutral axis, Ymax 4.95 m
Xcog 1.12 m
Ycog 0.46 m
Total weight applied on ground, P 559.03 T
Moment about x axis, Mx 257.82 T.m
Moment about y axis, My 624.61 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 7.42 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 2.60 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 6.42 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 1.60 T/m2
Swing Angle ∅= 98 Deg
Mass COG to COR
Components
(T) X(m) Y(m)
Supper Structure w/o Winches 55.00 0.39 -2.79
H1 & H2 Winches + Conecting Frame 36.80 0.06 -0.43
Main CounterWeight 180.00 0.85 -6.08
Central Ballast 60.00 0.53 -3.80
SL-Counterweight 0.00 2.09 -14.85
Crawlers 45.00 0.00 0.00
SL-Mast 30m 22.80 0.92 -6.56
Main Boom 112.25 -2.40 17.05
Luffing Jib - - -
Upper Luffing Mast - - -
Lower Luffing Mast - - -
Hook Block 2x300T 4.80 -4.18 29.71
Rigging Weight 0.60 -4.18 29.71
Load Weight 5.78 -4.18 29.71
Steel Mats Weight 36.00 0.00 0.00
Total weight 559.03 0.98 1.08
Ground Pressure
Crane Mats Height 0.30 m
Crawler width(On Crane Mats) 6.00 m
Crawler Length(On Crane Mats) 10.33 m
Track width 8.40 m
Total contact area of crawlers to ground, A 123.96 m2
Crawler Inertia moment, Jx 2558.53 m4
Crawler Inertia moment, Jy 1102.30 m4
Max distance to neutral axis, Xmax 4.25 m
Max distance to neutral axis, Ymax 4.95 m
Xcog 0.98 m
Ycog 1.08 m
Total weight applied on ground, P 559.03 T
Moment about x axis, Mx 604.12 T.m
Moment about y axis, My 548.95 T.m
Pressure on ground, A = (P/A+My/Jy*Xmax+Mx/Jx*Ymax) 7.80 T/m2
Pressure on ground, B = (P/A-My/Jy*Xmax+Mx/Jx*Ymax) 3.56 T/m2
Pressure on ground,C = (P/A+My/Jy*Xmax-Mx/Jx*Ymax) 5.46 T/m2
Pressure on ground, D = (P/A-My/Jy*Xmax-Mx/Jx*Ymax) 1.22 T/m2
HSVC1 PP4 PROJECT
METHOD STATEMENT FOR INSTALLATION/ASSEMBLY EQUIPMENT
Confirmation of Sub-contractor
Analyzed by In-Charge of Construction Supervisor In-charge of HSE SM or CM
Comments of Contractor
Section Manager
HSE Supervisor
HSE Manager KyungChun Park
HSVC1 PP4 PROJECT
METHOD STATEMENT FOR INSTALLATION/ASSEMBLY EQUIPMENT
Appendix 7: Other