PDO ENGINEERING STANDARDS AND PROCEDURES

PROJECT MANAGEMENT – CFDH: UEP - (Julian Masters) MECHANICAL STATIC EQUIPMENT ENGINEERING – CFDH: UEP1S - (Abdulnabi Balushi) ELECTRICAL ENGINEERING – CFDH: UIE (UEE2) - (Mohammed Aghbari)
Doc. ID Document Title Additional Notes Rev./DEM Date Doc. ID Document Title Additional Notes Rev./DEM Date Doc. ID Document Title Additional Notes Rev./DEM Date
Project Engineering – Electrical Equipment –
SP-1188 Chemical Injection Skids Rev. 5 May-10 SP-1099 Electrical Infrastructure - Specification for Electrical Installation Practice Ver. 5.0 Dec-06
SP-1200 Procurement Specifications for Pipeline Check Valves Ver. 2.0 Sep-11
SP-1100 Specification for Testing & Commissioning of Electrical Equipment Ver. 3.0 Jun 04
CP-117 Project Engineering Code of Practice Rev. 5.0 Jan-12 SP-1201 Procurement Specification for Pipeline Ball Valves Ver. 2.0 Sep-11
CP-122 Health, Safety and Environment Management System Manual Ver. 5.0 Jul-11 SP-1101 Electrical Infrastructure Specification for installation of Overhead Transmission Ver. 2.0 May-08
SP-2020 Flange Connections - Bolt Tourquing & Tensioning Ver. 0 Jan-06
CP-131 Risk and Opportunity Management Code of Practice Ver. 3.0 Dec-06 SP-2039 Mechanical Standard Drawings Ver. 1.0 Sep-05 Lines
CP-206 Management of Change Code of Practice Rev. 1.0 Nov-11 SP-2044 Specification for Screwed Fittings Rev. 1.0 Nov-05 SP-1102A Electrical Infrastructure Specification for Design of 33kV Overhead Power Ver. 6.0 Aug-08
SP-2051 Specification for Flushing, Pressure Testing, Pickling and Sensitive Leak Testing Ver. 2.0 May-10 Lines on Wooden Poles
PR-1150 Project Close Out Procedure – Engineering CAPEX & OPEX Projects Ver. 3.0 Apr-04 SP-1102B Electrical Infrastructure Specification for Design of 33kV Overhead Power Ver. 7.1 Dec-10
of Mechanical Equipment and Piping
PR-1153 Field Trouble Report Procedure Ver. 2.0 Feb 06
SP-2069 Mechanical Engineering - Specification for Pressure Vessels Ver. 0 Sep-08 Lines on Concrete Poles
PR-1247 Project Management of Change Procedure Ver. 4.1 May-12 SP-2070 Mechanical Engineering - Specification for Air Cooled Heat Exchangers Ver. 1 Jun-10 SP-1103 Electrical Engineering Guidelines Amend’t/Suppl’t to DEP 33.64.10.10-Gen (Feb-11) Ver. 5.0 Oct-11
PR-1358 Procedure for Concept Selection and Preparing a Basis for Design Ver. 2.0 Dec-04
SP-1105 Electrical Infrastructure - Electrical Standard Drawings List Ver. 4.0 May-06
PR-1979 Procedure for Project Delivery Assurance Boards (PDAB’s) Rev. 1 Mar-11 DEP 30.06.10.11 (Ι)
Equipment in LPG Installations DEM-1 Feb-11
DEP 30.06.10.12 (Ι)
Pressurised Bulk Storage Installations for LPG Amended by Circular 58/11 DEM-1 Feb-11 SP-1106 Electrical Infrastructure - Specification for Coding and Identification of Ver. 2.0 May-08
SP-1134 Specification for Detailed Design and Engineering of Oil & Gas Facilities Rev. 1.0 Aug-06 DEP 30.06.10.13 (Ι)
LPG Bulk Transfer & Transportation Amended by Circular 34/11 DEM-1 Feb-11 Overhead Line Systems
SP-2050 Specification for Construction Activities on Oil, Gas and Utility Facilities Projects Ver. 1.0 Jul-06 DEP 30.06.10.18 Pressurised Bulk Storage Installations for LPG – At Customer Premises
(Ι) Feb-12 SP-1107 Electrical Infrastructure - Specification for Electrical Protection System Ver. 3.0 Jul-08
SP-2100 Contract Cost Engineering Specification Ver. 1.0 Dec-09 DEP 30.48.60.13 Design and installation of chemical-resistant brick lining for Process Sep-12 SP-1109 Specification for Earthing and Bonding Ver. 4.0 Mar-04
equipment (based on EN 14879-Parts 1, 4 and 6) SP-1110 Electrical Infrastructure - Specification for Electrical Supplies for Mobile Camps Ver. 5.0 May-06
GU-484 Project Engineering – Scheduling & Reporting Guideline Ver.2.0 Feb-11 DEP 30.75.10.10 (Ι) Steam, Condensate and Boiler Feed Water Systems DEM-1 Feb-12 SP-1111 Electrical Infrastructure - Specification for Temporary Electrical Supplies Ver 4.0 Apr-06
GU-556 Guideline for Vendor Project Document Deliverables Rev.1.0 Feb-07 DEP 30.75.10.30 Water Tube Boilers Amended by Circular 48/12 Dec-08 for Construction & Maintenance Work
GU-569 Project Cost Engineering Rev.1.0 Jan-07 DEP 31.06.11.11 (Ι) Loading Facilities for Bulk Road Vehicles Amended by Circular 83/11 DEM-1 Feb-11 SP-1112 Electrical Infrastructure - Electrical Specification for Drilling Rigs Ver. 4.0 Apr-06
GU-663 Project Controls Plan Guideline Rev. 0 Jun-11 DEP 31.10.03.10 Symbols & Identification System – Mechanical Feb-12 SP-1113 Electrical Infrastructure - Specification for 132kV Substation Ver. 4.0 Apr-08
DEP 31.20.20.31 Internals for Columns Amended by Circular Sep-12 Feb-12 SP-1114A Electrical Infrastructure - Specification for Design of 132kV Overhead Power
DEP 00.00.07.10 Design Class Tables Complex and/or High Value projects only - Evaluate & justify on case by case basis Sept-11 DEP 31.21.01.11 (Ι) Printed Circuit Heat Exchangers – Selection & Application DEM-1 Feb-12 Lines on Wooden Poles Ver. 4.0 May-08
DEP 01.00.09.10 (Ι) Operational Tagging Requirements Feb-12 DEP 31.21.01.12 (Ι) Shell & Tube Heat Exchangers – Selection & Application DEM-1 Feb-12 SP-1114B Electrical Infrastructure Specification for Design of 132/220 kV Overhead Ver 2.0 May-08
DEP 30.10.01.10 Requisitions Index Feb-12 DEP 31.21.01.13 (Ι) Welded Plate-Bloc Heat Exchangers – Application, Design & Fabrication Feb-12 Power Lines on Steel Towers
DEP 70.10.90.11 (Ι) Spares Parts Feb-12 DEP 31.21.01.30 (Ι) Shell & Tube Heat Exchangers - Amendments/Supplements to ISO 16812 Amended by Circular 13/12 DEM-1 Feb-11 SP-1114C Electrical Infrastructure – Specification for Design of TWIN ELM 132kV Ver. 2 Dec-10
DEP 31.21.01.32 (Ι) Plate & Frame Heat Exchangers- Amendments/Supplements to ISO15547-1:2005 DEM-1 Feb-12 Overhead Power Lines on Concrete Poles
DEP 82.00.10.12 Life Cycle Costing (Endorsement of ISO 15663-1) Feb-11
DEP 31.21.01.33 (Ι) Printed Circuit Heat Exchangers – Design & Fabrication Amended by Circular 44/11 DEM-1 Feb-11 SP-1115 Specification for Digital Power Line Carrier Communication System Ver 2.0 Jun-04
DEP 31.21.01.36 (Ι) Heat Exchangers for Packaged Equipment – Design & Fabrication Feb-12 SP-1116 Electrical Infrastructure - Specification for SCADA of Electrical System Ver. 3.0 Jan-07
Design / Drafting – DEP 31.21.70.10 (Ι) Air-Cooled Heat Exchangers; Selection and Application Amended by Circular 98/11 DEM-1 Feb-11 SP-1117 Specification for Power Transformers Amend’t/Suppl’t to DEP-33.65.40.31-Gen (Oct-01) Ver. 4.0 Nov-03
DEP 31.21.70.31 (Ι) Air-cooled Heat Exchangers - Amendments/Supplements to ISO13706 Amended by Circular 08/12 DEM-1 Feb-11 SP-1118 Specification for Power Station Ver. 2.0 Oct-04
SP-1131 Specification for Hand Over and As Built Documentation Ver. 3.0 May-06 DEP 31.22.10.35 Manufacturing Report for Pressure Vessels Sep-12 SP-1119 Specifications for Electrical Machines Cage Induction Types Amend’t/Suppl’t to DEP 33.66.05.31-Gen (Jan-99) Ver. 4.0 Jun-06
SP-1132 Specification for Plant Design Reference Manual Ver. 3.0 Apr-06 DEP 31.22.20.31 (Ι) Pressure Vessels - Based on ASME Section VIII Amended by Circular Sep-12 DEM-1 Feb-12 SP-1120 Specifications for High Voltage Switchgear and Control Assemblies Amend’t/Suppl’t to DEP 33.67.51.31-Gen (Jul-98) Ver. 3.0 Jun-04
SP-2047 Specification for the Preparation and Content of Engineering Drawings Ver. 2.0 Feb-10 DEP 31.22.30.14 Glass-Fibre Reinforced Plastic Vessels Sep-12 SP-1121 Specifications for Low Voltage Switchgear and Control Assemblies Amend’t/Suppl’t to DEP 33.67.01.31-Gen (Jan-98) Ver 4.0 Jun-05
DEP 31.24.00.30 (Ι) Fired Heaters - Amendments/Supplements to ISO13705 Amended by Circular 97/11 DEM-1 Feb-11 SP-1144 Infrastructure Power Systems Department – Oil and Gas Directorate Service Ver. F May-05
PR-1666 Project Drawing Procedure Ver. 1.0 May-06 DEP 31.24.00.31 Calculation of Heater-Tube Thickness- Endorsement of ISO 13704 Dec-07 Level Agreement
DEP 00.00.06.06 Standard Drawings Index Sep-12 DEP 31.24.40.12 Fabric Expansion Joints- Endorsement of RAL-GZ719 Sep-12 SP-1242 HSE Specification for Activities in the Vicinity of Overhead Power Lines Ver 4.0 Oct-04
DEP 00.00.07.30 (Ι) Application of a functional specification Sep-12 DEP 31.27.21.10 (Ι) Filters for Removing Particles from Hydroprocessor Feeds Feb-12 SP-1267 Specification for Synchronous AC Machines Amend’t/Suppl’t to DEP-33.65.11.31-Gen (Jan 99) Ver.2.0 Jun-06
(endorsement of ISO 13879, ISO 13880 and ISO/TR 13881) - Type Selection and Design Rules
DEP 02.00.00.10 Preparation & Microfilming of Technical Drawings Amended by Circulars 15/99, 64/01 & 56/03 Oct-95 DEP 31.36.10.30 (Ι) Hydraulic Systems for the Operation of On/Off Valves in Protective Functions Amended by Circular 65/11 DEM-1 Feb-11 PR-1168 Power Systems – Emergency Response Procedure Ver 7.0 Mar-09
DEP 31.37.00.11 (Ι) Instrument Air Supply DEM-1 Feb-12 Volume VII: Power Systems Operstions Interior
DEP 31.38.01.10 (Ι) Piping Classes – Basis of Design DEM-1 Feb-12 PR-1259 Infrastructure Management Procedure Ver. 2.0 Sep-99
Standards Administration – DEP 31.38.01.11 (Ι) Piping - General Requirements Amended A01 – Sep-12 DEM-1 Feb-12 PR-1265 Procedures for Maintaining Power System Network Models Ver. 2.0 Nov-06
DEP 31.38.01.12 (Ι) Piping Classes - Refining And Chemicals DEM-1 Feb-12 PR-1353 Electrical System Faults & Analysis Procedure Ver. 4.0 Jun-05
PR-1561 WinPCS Procedure Rev. 0 Mar-04 DEP 31.38.01.13 Compilation of Bill of Material for Piping Isometrics Feb-12 PR-1421 Infrastructure Power Systems Department MHEW Interconnector Operation Ver 3.0 Dec-04
GU-453 Guidelines for WinPCS Users Rev. 02 Jul-06 DEP 31.38.01.15 (Ι) Piping Classes – Exploration and Production DEM-1 Feb-12 Maintenance Procedure
DEP 31.38.01.21 Compilation of a Specification For Piping Systems Sep-11 PR-1613 Procedure for Assessment of Protection Relay Testing Engineers Ver. 2.0 Jun-10
ORM Opportunity Realisation Manual Apr-10 DEP 31.38.01.29 Pipe Supports Feb-12
DEP 31.38.60.10 (Ι) Hot Tapping on Pipelines, Piping and Equipment Amended by Circular 76/11 DEM-1 Feb-11 GU-290 Infrastructure Power Systems Department – Power Systems Asset Management Ver. 2.0 Apr-06
DEP 00.00.00.30 (Ι) Procedure for Global Technical Standards Publications Sep-12 DEP 31.46.00.31 (I) Acoustic Insulation for Piping- Amendments/Supplements to ISO 15665 Feb-12 GU-323 Infrastructure Power Systems Department - Key Business Control Ver. 3.0 May-06
DEP 00.00.05.05 Global Technical Standards Index Sep-12 DEP 34.51.01.31 (I) Vertical Steel Storage Tanks – Selection & Design DEM-1 Feb-11 Documentation Guidelines
DEP 00.00.10.05 Standard Forms Index Sep-12 (Amendments/Supplements to EN14015:2004)
DEP 00.00.20.10 The Use of SI Quantities – Endorsement of ISO-31, ISO-1000 & ISO 80000 Feb-11 DEP 34.51.11.30 (Ι) Mounded Horizontal Cylindrical Vessels for Pressurised Storage of LPG at DEM-1 Feb-11 DEP 33.64.10.10 (Ι) Electrical Engineering Design Amended & Supplemented by SP-1103 DEM 1 Feb-11
Ambient Temperatures (Endorsement of EEMUA 190) DEP 33.64.10.12 (I) Electrical Supply and Generation-Design and Operation Sep-11
DEP 34.51.90.10 Demolition of Storage Tanks (Endorsement of EEMUA 154) Sep-12 DEP 33.64.10.32 (I) Electrical Network Monitoring and Control System for Industrial Sep-11
DEP 70.08.10.11 Mechanical Maintenance Equipment and Tools Sep-11 Networks - Specification
INFORMATION MANAGEMENT / ENGINEERING DESIGN SYSTEMS – UEPI (Philippa De Glanville) DEP 70.10.80.11 Cleaning of Equipment
DEP 74.00.10.10 (Ι) Shop & Field Pressure Testing of Piping Systems
WITHDRAWN
DEM-1
Jan-98
Feb-12
DEP 33.64.10.33
DEP 33.65.11.31 (I)
Electromagnetic Compatibility (EMC)
Synchronous AC Machines – Amendments/Supplements to IEC 60034-1 & Amended and Supplemented by SP-1267
Sep-12
Feb-12
DEP 80.36.00.30 (Ι) Relief Devices - Selection, Sizing and Specification Amended A01 – Sep-12 DEM-1 Feb-12 IEC 60034-14
CP-139 Corporate Data Management Ver. 3.0 Feb-09 DEP 80.46.30.11 (Ι) Interlocking Systems for Safety/Relief Valves Amended by Circular 66/11 & 66/12 DEM-1 Feb-11 DEP 33.65.11.32 Packaged Unit AC Generator Sets Apr-03
DEP 33.65.40.31 (I) Power Transformers – Amendments/Supplements to IEC 60076-01 & Amended and Supplemented by SP-1117 Sep-11
SP-2065 Document Management for Projects Rev. 4.0 Aug-12 IEC 60076-11
SP-2067 PDMS Model Specification NEW REQUIREMENT Rev A02 Oct-12 DEP 33.65.50.31 (Ι) Static DC Uninterruptible Power Supply (DC UPS) Units DEM-1 Feb-11
SP-2099 2D Drafting Specification NEW REQUIREMENT Ver. 1.0 Jul-12
SP-2122 Project IM Specification Ver. 1.0 Oct-11 MECHANICAL ROTATING EQUIPMENT ENGINEERING – CFDH: UEP1R – (Saad Harrasy) DEP 33.65.50.32
DEP 33.65.60.30
(Ι)
(I)
Static AC Uninterruptible Power Supply Unit (Static A.C.UPS unit)
Solar Power Systems
DEM-1 Feb-11
Feb-12
SP-2133 Project ‘Engineering Design Systems’ (EDS) Specification Ver. 1.0 Feb-12 DEP 33.66.05.31 (I) Electrical Machines - Cage-Induction Types – Amendments/Supplements Amended and Supplemented by SP-1119 Feb-12
SP-2144 Project Engineering – Engineering Project IM ‘Scope of Work’ – Tender Contract Input NEW REQUIREMENT Rev. 1 Aug-12 to IEC 60034-1 & IEC 60034-14
Doc. ID Document Title Additional Notes Rev./DEM Date
DEP 33.66.05.33 (I) AC Electrical Variable Speed Drive Systems Feb-12
DEP 82.00.10.30 (Ι) Engineering Information Specification (EIS) Feb-12 DEP 33.67.01.31 (Ι) Low Voltage Switchgear & Control Gear Assemblies Amended and Supplemented by SP-1121 Feb-11
SP-1252 Specification for Instrument Air Compression Package Ver. 3 Sep-10
SP-2013 High Energy ( ≥500kW) Centrifugal Pumps Ver. 2.0 Oct-11 – Amendments/Supplements to IEC 60439-1
SP-2030 Low Energy (≤500kW) Centrifugal Pumps Amend’t/Suppl’t to DEP 31.29.02.30-Gen Ver. 0 Jun-05 DEP 33.67.51.31 (I) High-Voltage Switch Gear and Control Gear Assemblies for Rated Voltages Amended and Supplemented by SP-1120 Feb-12
SP-2033 Functional Specification for PDO Machinery Health Monitoring Systems - MHMS Rev. 02 Jun-05 between 1kV & 52kV – Amendments/Supplements to IEC 62271-200
DEP 33.68.30.32 Electrical Trace Heating Sep-10
QUALITY MANAGEMENT– CFDH: UEQ - (Gary Briston) SP-2045
SP-2054
Procurement Specification for Beam Pump Units
Specification for Centrifugal Compressor Packages
Rev. 5
Rev. 3
May-12
Aug-08 DEP 33.68.30.33 Electrical Process Heaters Nov-06
DEP 63.10.08.11 (I) Field Commissioning & Maintenance of Electrical Installations & Equipment Sep-11
PL-15 Quality Management Policy 2008 Edition
PR-1565 String/Performance Tests Procedure for Centrifugal Pumps Vers 1.0 Jun-04
CP-190 Project Engineering: Quality Management System for Project Delivery: Code of Practice Ver. 1 Oct-09 Electrical Safety Operational Procedures (ESOP’s)–
GU-396 Engineering of Process Pumps Guideline Ver. 1.0 May-05
PR-1858 Material Handling, Storage and Preservation Procedure Rev. 0 Oct-09 GU-397 Engineering of Process Gas Compression Guideline Ver. 1.0 May-05 SP-1145 Guide to Safety Operability (SAFOP) Studies on Electrical Systems Ver. 3.0 Oct-03
PR-1866 Quality Audit Procedure NEW REQUIREMENT Rev. A01 Mar-10
PR-1964 Equipment and/or Materials Receipt Inspection Procedure Rev. A1 Dec-10 DEP 31.25.00.10 Hoisting Facilities And Weather Protection For Rotating Equipment Nov-08 PR-1947 Electrical Safety Rules Ver. 8.0 Aug-10
PR-1984 Criticality Rating Procedure Ver. 1.0 Jun -11 DEP 31.29.00.10 Installation of Rotating Equipment - Amendments /Supplements to API RP 686 Sep-11 PR-1948 Electrical Safety Operating Procedures Ver. 9.0 May-10
DEP 31.29.00.30 Oil Mist Lubrication Systems Amended by Circular 98/08 Jul-08
SP-1122 Specification for Project Quality Plan Ver. 2.02 Feb-08
DEP 31.29.00.32 Special Purpose Gear Units for Petroleum, Chemical & Gas Industry Services Feb-12
SP-1171 Specification for Quality Management System Requirements for Ver. 3,0 Jun-12
- Amendments / Supplements to API 613
Product and Service
DEP 31.29.00.33 (Ι) Shaft Sealing Systems for Centrifugal and Rotary Pumps Amended by Circular 62/11 & A01 – Sep-12 DEM-1 Feb-11
SP-2061 Functional Technical Directorates - Technical Authority System Rev. 2.0 Jun-10
- Amendments/Supplements to ISO 21049:2004
DEP 31.29.00.36 Flexible Couplings for Mechanical Power Transmission – Special Purpose Applications Dec-07
GU-398 Guidelines on Scope and Areas Covered During Vendor/Contractor Evaluation NEW REQUIREMENT Rev. 2.0 Apr-09
- Amendments/Supplements to ISO 10441
& Assessment
DEP 31.29.00.39 Shaft Sealing Systems for Centrifugal and Rotary Pumps WITHDRAWN Feb-11 PIPELINE & FLOWLINE ENGINEERING – CFDH: UIPT(UEL) - (Said Asmi)
DEP 82.00.10.10 Project Quality Assurance Feb-12 - Selection, Testing & Installation
DEP 31.29.00.41 Gears – Selection, Testing & Installation Feb-12
Pumps – Selection, Testing & Installation Doc. ID Document Title Additional Notes Rev./DEM Date
Lifting & Hoisting – DEP 31.29.02.11 Sep-12
DEP 31.29.02.30 (Ι) Centrifugal Pumps - Amendments/Supplements to ISO-13709:2003 Amended by Circular 85/11 DEM-1 Feb-11
DEP 31.29.06.30 Centrifugal Submerged Motor Pumps (in Refrigerated Product or Pressurised Amended by Circular 52/11 Feb-11 SP-1032 Specification for the Design, Operation, Maintenance & Inspection Ver. 3.0 Sep-11
SP-1251 Training Requirements for Lifting Operations Personnel Ver. 4.0 Sep-11 of Pipeline Block Valve Stations
Storage Service)
DEP 31.29.12.30 Reciprocating Positive Displacement Pumps and Metering Pumps Amended by Circulars 01/02, 25/04, 50/04 & 84/08 Dec-99 SP-1199 Procurement Specification for Pipeline Split Tees Ver. 2.0 May-11
PR-1708 Lifting & Hoisting Procedure – Part 1: Framework Ver. 1 Sep-11 SP-1208 Pipeline Construction Specification Ver. 3.0 Mar-11
- Amendments/Supplements to API 674 and API 675
– Part 2: Inspection, Testing and Certification SP-1210 Pipeline Operations and Maintenance Ver. 2.0 Dec-03
DEP 31.29.22.11 (I) Positive Displacement Pumps – Rotary (Amendments/Supplements to API 676) Feb-12
PR-1709 Lifting & Hoisting – Lift Planning / Execution Procedure Ver. 1 Sep-11 SP-1211 Onshore Pipeline Engineering Ver. 3.0 Jan-11
DEP 31.29.40.10 Compressors Selection, Testing & Installation Sep-11
PR-1710 Lifting Equipment Numbering NEW REQUIREMENT Ver. 0 Apr-12 SP-1212 DEP 31.40.40.38-PDO Hydrostatic Pressure Testing of New Pipelines Based on DEP 31.40.40.38-Gen (Jan-10) Rev. 2.0 Mar-11
DEP 31.29.40.30 (Ι) Axial, Centrifugal & Expander Compressors - Amendments/Supplements to API Std 617 Amended by Circular 86/11 DEM-1 Feb-11
DEP 31.29.40.31 (Ι) Reciprocating Compressors - Amendments/supplements to API 618 Amended by Circular 82/11 DEM-1 Feb-11 SP-1235 DEP 31.40.60.12-PDO Pipeline Repairs (Supplement to ASME B31.4 & B31.8) Based on DEP 31.40.60.12-Gen (Jan-10) Rev. 2.0 Mar-11
DEP 31.29.40.33 Packaged, Integrally Geared, Centrifugal Plant and Instrument Air Compressors Feb-12 SP-1236 DEP 31.40.21.31-PDO Pipeline Isolating Joints - Amendments/Supplements to MSS SP-75 Based on DEP 31.40.21.31-Gen (1999) Ver. 1.0 Dec 02
- Amendments/Supplements to API 672
PR-1067 Infrastructure - Emergency Response Document Part III Contingency Plans Ver. 8.0 Jul-09
SAFETY ENGINEERING – CFDH: MSE4 - (Anthony Sipkema) DEP 31.29.42.30
DEP 31.29.47.30
Liquid Ring Vacuum Pumps And Compressors - Amendment/Supplements to API Std 681
Centrifugal Fans - Amendments/Supplements to ISO 13705, Annex E
Feb-12
Sep-11 - Vol. 4: Main Oil Line
DEP.31.29.47.31 Centrifugal fans for petroleum, chemical, and gas industry services Feb-12 PR-1146 Engineering and Operations - Flowline Cold Cutting Procedure Ver. 3.0 Dec-06
(amendments/supplements to API 673) PR-1235 Main Oil Line System - Management Procedure Rev. 02 Jun-08
Doc. ID Document Title Additional Notes Rev./DEM Date PR-1236 South Oman Gas Line System - Management Procedure Rev. 02 Jun-08
DEP 31.29.47.32 Fans – Selection, Testing & Installation Feb-12
DEP 31.29.60.32 (Ι) Lubrication, Shaft-Sealing and Control Oil System and Auxiliaries Amended by Circular 80/11 DEM-1 Feb-11 PR-1416 Procedures for the Use of Pipe-RBA Methodology Rev. 1 Mar-03
Human Factors Engineering PR-1504 Facilities Change Proposal Procedure for Main Oil Line, South Oman Gas Line Rev. 0 Feb-02
DEP 30.00.60.10 (Ι) Human Factors Engineering in Projects Feb-11 - Amendments/Supplements to ISO 10438
DEP 31.29.60.33 (Ι) Lubrication, Shaft-Sealing and Oil-Control System – Selection, Testing & Installation Sep-11 and MAF Terminal
DEP 30.00.60.13 (Ι) Human Factors Engineering – Valve Analysis Sep-11
DEP 31.29.70.11 Combustion Gas Turbines - Selection, Testing & Installation Sep-11 PR-1506 Pipeline Hot Tap Management Procedure Rev. 01 Oct-02
DEP 30.00.60.14 (Ι) Human Factors Engineering – Application During Construction Sep-12
DEP 31.29.70.31 (Ι) Gas Turbines for the Petroleum, Chemical and Gas Industry Services Amended by Circular 64/11 DEM-1 Feb-11 PR-1522 Procedure for Analysis of Pipeline Road Crossing Rev. 1.0 May-12
DEP 30.00.60.15 (Ι) Human Factors Engineering – Control Room Design Feb-12
- Amendments/Supplements to API 616 PR-1629 Installation of Epoxy Grouted Sleeve & Clock Spring Repairs Ver. 2.0 Dec-09
DEP 30.00.60.16 Human Factors Engineering – Human / Machine Interface Design for Situation Awareness Owner: Control and Automation Aug-09
DEP 31.29.70.32 Gas Turbine Combustion Air Intake And Exhaust Systems Feb-11 PR-1642 Procedure for “COSASCO” Retrieving Equipment Operation, Corrosion Monitoring Ver. 2.0 Dec-09
DEP 30.00.60.18 Human Factors Engineering – Design and Procurement of Skid-Packaged Units Sep-12
DEP 31.29.80.30 Diesel Engines Dec-00 and Weight Loss Coupon Analysis
DEP 30.00.60.19 (Ι) Human Factors Engineering – Design for Process Safety Critical Tasks Feb-11
DEP 31.29.90.30 Spark Ignited Gas Fuelled Engines Mar-01 PR-1799 Procedure for Emergency Pipeline Repair Material Management Ver. 1.0 Sep-08
DEP 30.00.60.20 (Ι) Human Factors Engineering – Workspace Design Sep-11
DEP 30.00.60.21 (Ι) Human Factors Engineering – Labeling of Facilities, Equipment & Piping Feb-12
GU-379 Pipeline Emergency Repair Manual (Class 1 Pipelines) Rev. 5.0 May-12
Fire Engineering GU-501 Excavation and Working Around Live Pipelines Rev. 2.0 Sept-11
SP-1075 HSE Specification – Fire and Explosion Risk Management Rev. 2.0 Jul-02 MATERIALS SELECTION & CORROSION ENGINEERING – CFDH: UEOC - (Nasser Behlani)
GU-230 Fire & Explosion Risk Management Guidelines Rev. 2.0 Jul-02 DEP 31.38.60.10 (Ι) Hot Tapping on Pipelines, Piping and Equipment - Owner – Mechanical Static Amended by Circular 76/11 DEM-1 Feb-11
DEP 31.40.10.12 (Ι) Design Of Multiple-pipe Slug Catchers Amended by Circular 19/12 DEM-1 Feb-11
DEP 32.30.20.11 (Ι) Fire, Gas and Smoke Detection Systems - Owner: C&A Amended by Circular 72/12 DEM-1 Sep-11 Doc. ID Document Title Additional Notes Rev./DEM Date DEP 31.40.10.13 (Ι) Design of Pipeline Pig Trap Systems Amended by Circular 84/11 DEM-1 Feb-11
DEP 80.47.10.30 (Ι) Assessment of the Fire Safety of Onshore Installations Amended by Circular 38/11 DEM-1 Feb-11 General - DEP 31.40.10.16 Upheaval Buckling of Pipelines Apr-06
DEP 80.47.10.31 (Ι) Active Fire Protection Systems and Equipment for Onshore Facilities Amended by Circular 51/11 & 38/12 DEM-1 Feb-11 DEP 31.40.20.33 (Ι) Line Pipe Induction Bends - Amendments / Supplements to ISO 15590-1 Amended by Circular 102/11 & 56/12 DEM-1 Feb-11
DEP.80.47.10.32 (Ι) Fire Fighting Agents and Portable/Mobile Fire Fighting Equipment Sep-11 CP-208 Corrosion Management Code of Practice NEW REQUIREMENT Ver. 1.0 Jul-12 DEP 31.40.20.37 (Ι) Line Pipe for Critical Service - Amendments / Supplements to ISO 3183:2007 Amended by Circular 100/11 DEM-1 Feb-11
for Onshore Applications DEP 31.40.21.30 Pipeline Fittings- Amendments / Supplements to ISO-15590-2 Jun-07
DEP 80.47.10.33 (Ι) Fire Fighting Vehicles and Fire Stations Feb-12 SP-1128 Specification for Cathodic Protection Design Ver. 2.0 Dec 05 DEP 31.40.21.31 Pipeline Isolation Joints - Amendments / Supplements to ISO 15590-2 Sep-11
SP-1129 Specification for Construction, Installation and Commissioning of Cathodic Protection Systems Ver. 2.0 Sep-05 DEP 31.40.21.33 Pig Signallers : Intrusive Type Sep-11
Facility Layout SP-1130 Specification for Cathodic Protection Materials and Equipment Rev. 1.0 Sep-99 DEP 31.40.21.34 Carbon And Low Alloy Steel Pipeline Flanges For Use in Oil & Gas Operations Jun-07
SP-1127 Specification for Facility Siting, Layout & Spacing Ver. 3.0 Oct-10 SP-1136 Cathodic Protection Drawings Ver. 2.0 Dec 05 - Amendments/Supplements to ISO 15590-3
SP-1190 Design for Sour Service Specification Ver 3.0 Sep-11 SP-1189 Specification for Duplex Stainless Steel Line Pipe - Amendments/Supplements to API 5LC REPLACES DEP 31.40.20.34 Ver. 1.0 Dec-00 DEP 31.40.50.30 (I) Pre-commissioning of Pipelines Sep-11
SP-1195 Specification for the Wall Thickness Measurement of Pipelines by Automated Ver. 1.0 Jan-01 DEP 31.40.60.11 Pipeline Leak Detection Amended by Circular 41/08 Sep-02
DEP 34.17.10.35 (Ι) Siting of Onshore Occupied Portable Buildings Owner: Civil DEM-1 Feb-11 Ultrasonic Techniques
DEP 80.00.10.10 (Ι) Area Classification Amended by Circular 63/12 DEM-1 Feb-11 SP-1246 Specification for Painting and Coating of Oil and Gas Production Facilities Ver. 2.0 Apr-10
DEP 80.00.10.11 (Ι) Layout of Onshore Facilities Amended by Circular 68/11 & 43/12 DEM-1 Feb-11 (Parts 1 to 5)
and Amendment A03 Sep-12 SP-2034 Specification for Internal FBE Coating of Line Pipe Ver. 1.0 Sep 05
(Amendments/Supplements to API REP 5L7)
HEMP/HSE Cases SP-2041 Specification for Cracking Resistant Materials in H2S Containing Environment Ver. 2 Mar-11
SP-1258 Technical Safety Engineering - Quantitative Risk Assessment Specification Rev. 3.0 Jul-10 SP-2092-1 GRP Specification – Part 1 (Qualification & Manufacturing) Ver. 0 Jan-10
SP-2062 Specification for HSE Cases Ver. 1 Mar-11 SP-2094 Specification for Polyethylene Liners in Carbon Steel Flowlines & Pipelines Ver. 0 Aug-10
PR-1696 HAZOP Procedure Owner: Process Engineering Rev. 3 Jun-12
SP-2095 Internal Liquid Coating for Carbon Steel Piping and Line Pipes Ver. 1.0 Sept-09 CIVIL ENGINEERING – CFDH: UEP1C (UEB) - (Hilal Aghbari)
GU-648 Guide for Applying Process Safety in Projects Rev. 1 Dec-10 PR-1180 Performance Testing of Coating Systems for Pipeline Rehabilitation Ver. 2.0 Nov-05
PR-1234 Safe Working Procedures for Cathodic Protection Systems Ver. 2.0 Mar-01 Doc. ID Document Title Additional Notes Rev./DEM Date
EP95-0230 HSES Guideline – Design 1995 PR-1503 Procedure for Determining Pipeline’s Assessed Corrosion Rate (ACR) Ver. 2.0 Dec-09
EP2005-0300 Hazard and Effects Management Process (HEMP) – General Requirements Ver. 1 Aug-04 PR-2006 Replacement (Like/Like) of Carbon Steel / Other Spools Connected to GRP Lines Ver. 1.0 Nov-11
Civil / Structures -
EP2009-9009 Safety Critical Element Management Manual 2nd Edition Feb-09 SP-1143 Specifications for Earthmoving & Construction Equipment NEW REQUIREMENT Rev. 2 May-12
EP95-0312 HAZID Rev. 0 Sep-95 GU-368 Guidelines For The Protection Of Buried Sections of Surface Laid Pipelines/Flowlines Rev. 0 May-00 SP-1274 Specification for Civil & Buildings Construction - Materials Testing Ver. 2.0 Dec-09
EP95-0314 Physical Effects Modelling Rev. 0 Oct-98 GU-475 Corporate Flowline Materials Selection Guideline Ver. 1.0 Sep-04 SP-1275 Specification & Criteria for Design of Civil & Building Works Ver. 2.0 Dec-09
GU-486 Screening & Monitoring Bacteria Guidelines Ver. 1.0 Oct 05 SP-1277 Specification for Transportable Accommodation Units Ver. 2.0 Dec-09
Other Health & Safety GU-637 Sour Wells Completion, Material Selection Guidelines Ver. 1.0 May-10 SP-1279 Specification for Civil & Building Construction Ver. 2.0 Dec-09
SP-1232 Public Health NEW REQUIREMENT (Owner MCOH) Ver. 5.0 Jun 12
SP-1234 HSE Specification - Personal Protective Equipment (Owner MSE1) Rev. 3 Aug-12 DEP 30.10.02.11 Metallic Materials-Selected Standards Feb-12 SP-1281 Engineering Specification for Safe Road Works Ver. 2.0 Dec-09
DEP 30.10.02.13 (Ι) Non-Metallic Materials-Selection & Application Feb-12 SP-1282 Specification for Reinforced Concrete - Production & Construction Ver. 2.0 Dec-09
PR-1232 Process Safety Review (Formerly Design Integrity Review) Ver. 2.0 Feb-12 DEP 30.10.02.14 (Ι) Carbon Steel Corrosion Engineering Manual for Upstream Facilities DEM-1 Feb-11 SP-1284 Specification for Sign & Signboards - Standard Signs Catalogue Ver. 2.0 Dec-09
DEP 30.10.02.31 (Ι) Metallic Materials-Prevention of Brittle Fracture in New Assets Amended by Circular 59/11 DEM-1 Feb-11
DEP 31.10.00.31 (Ι) Noise Control (Amendments/Supplements to ISO 15664) Feb-12 DEP 30.46.00.31 (Ι) Thermal Insulation Amended by Circular 70/12 Sep-12 GU-628 Guide to Civil & Buildings Standard Drawings Ver 2.0 Dec-09
Revised by Amendment A02 – Sept-12 GU-629 Guideline for Application & Selection of Standard Pipe Supports Ver 1.0 Dec-09
ANSI/1SEA Z358.1-2009 American National Standard for Emergency Eyewash and Shower Equipment Sep-09
DEP 30.48.00.31 Protective Coatings for Onshore Facilities Amended & Supplemented by SP-1246 Jan-09 GU-630 Guideline to Design & Construction of Swimming Pools Ver 2.0 Dec-09
DEP 30.48.00.32 (Ι)
Coating of Fasteners Feb-12 GU-631 Guideline for Sunshade – Specification, Design Requirements & Standard Drawings Ver 1.0 Dec-09
DEP 30.48.30.31 (Ι)
Cement Lining of Pipes (Based on EN 10298) Sep-12
DEP 30.48.40.31 Thermal Spray Coatings of Aluminium Feb-12 DEP 34.00.01.30 (I) Structural Design & Engineering of Onshore Structures Sep-11
PROCESS ENGINEERING – CFDH: OSE/1 - (Said Alawi) DEP 30.48.41.31
DEP 30.48.60.10
Electroless Nickel Plating - Amendments/Supplements to ASTM B 733
Rubber-Lined Process Equipment
Jan-08
Sep-12
DEP 34.11.00.10 (I) Onshore & Nearshore Site Investigations Sep-11
DEP 34.11.00.11 (I) Site Preparations & Earthworks Including Tank Foundations and Tank Farms Sep-11
DEP 31.10.00.10 (Ι) Positive Material Identification (PMI) Program DEM-1 Sep-11 DEP 34.11.00.12 (Ι) Geotechnical & Foundation Engineering – Onshore Amended by Circular 99/11 & 68/12 Feb-11
Doc. ID Document Title Additional Notes Rev./DEM Date DEP31.24.40.31 (Ι) Materials for High Temperature Conversion Process Furnace Parts Feb-12 & Amendment A03-Sep-12
DEP 31.40.10.20 Spoolable Fibre-Reinforced Plastic Pipes Sep-12 DEP 34.13.20.31 (I) Road Paving , Surfacing, Slope Protection & Fencing Sep-11
CP-200 Water Management Code of Practice Ver. 1.0 Nov-11 DEP 31.40.20.32 (I) CRA Clad or Lined Steel Pipe - Amendments/Supplements to API Spec 5LD Sep-11 DEP 34.14.20.31 (Ι) Drainage systems and primary treatment facilities Amended by Circular 55/11 DEM-1 Feb-11
DEP 31.40.30.31 (Ι) External Polyethylene & Polypropylene Coating for Line Pipe Feb-11 DEP 34.17.00.32 (Ι) Design & Engineering of Buildings Amended/Supplemented by SP-1275 Sep-12
SP-1125 Isolation of Process Equipment Specification Rev. 4.0 Jun-12 - Amendments/Supplements to ISO/DIS 21809-1:2009 DEP 34.17.10.30 (Ι) Design of Blast Resistant Onshore Buildings, Control Rooms, & Field Auxiliary Rooms DEM-1 Feb-12
SP-1126 Drain Systems Specification Ver. 3.0 Jun-12 DEP 31.40.30.32 External Fusion-Bonded Epoxy Powder Coating for Line Pipe Feb-11 DEP 34.17.10.31 Laboratories Sep-12
SP-1166 Specification for Identification of On-Plot Pipework Ver. 2.0 Sep-04 - Amendments/Supp;ements to ISO 21809-2:2007 DEP 34.17.10.33 (Ι) Portable Blast-Resistant Modules Amended by Circular 71/11 & 42/12 DEM-1 Feb-11
SP-1190 Design for Sour Service Specification Owner: Safety Engineering Ver. 3.0 Sep-11 DEP 31.40.30.34 Thermoplastic Lined Pipelines Amended by Circulars 05/02 & 39/08 Dec-99 DEP 34.17.10.35 (Ι) Siting of Onshore Occupied Portable Buildings DEM-1 Feb-11
DEP 31.40.30.35 Internal Coating of Line Pipe for Non-Corrisive Gas Transmission Service Sep-12 DEP 34.19.20.11 (Ι) Fireproofing of Steel Structures Amended by Circular 03/12 DEM-1 Feb-11
PR-1696 HAZOP Procedure Contact OSE/1 & MSE4 Before Use Rev. 3 Jun-12 - Amendments/Supplements to ISO 15741 DEP 34.19.20.31 (I) Reinforced Concrete Structures Sep-11
GU-665 Water Treatment Strategy Ver. 0 Oct-11 DEP 31.40.30.37 External Field Joint and Rehabilitation Coating Systems for Line Pipe Jan-08 DEP 34.24.26.31 Chimneys selection, design and engineering (based on EN 1992-1-1, Sep-12
DEP 39.01.10.11 (Ι) Selection Of Material For Life Cycle Performance (Upstream Facilities) Amended by Circular 35/12 DEM-1 Feb-11 EN 1993-3-2, EN 1443, EN 13084 Parts 1, 2, 4, 5, 6, 7 and 8)
DEP 01.00.01.30 (Ι) Definition & Determination of Temperature, Pressure and Toxicity Levels DEM-1 Feb-12 - Materials Selection Process DEP 34.28.00.31 (I) Onshore Steel Structures Sep-11
DEP 01.00.02 11 (Ι) Preparation of Process Flow Schemes & Process Engineering Flow Schemes DEM-1 Feb-11 DEP 39.01.10.12 (Ι) Selection of Materials for Life Cycle Performance (Upstream Facilities) Amended by A01 Sep-12 DEM-1 Feb-12 DEP 34.28.00.33 (I) Onshore Ancillary Steel Structures Amended by Circular 52/12 Sep-11
DEP 01.00.02.12 (Ι) Preparation of Safeguarding Memoranda & Process Safeguarding Flow Schemes DEM-1 Feb-11 – Equipment
DEP 20.04.10.10 Glycol Type Gas Dehydration System Amended by Circulars 50/06, 74/08 & 05/10 Jan-05 DEP 39.01.10.32 (Ι) Specification of nickel base alloy 718 (UNS N07718) for oil and gas drilling and Amended by Circular 36/12 DEM-1 Feb-11
DEP 20.05.50.10 (Ι) Heat Transfer Fluid (HTF) Systems Amended by Circular 42/11 DEM-1 Feb-11 production equipment (amendments/supplements to API spec 6A718)
DEP 20.05.60.10 (Ι) Fuel Systems Amended by Circular 27/11 DEM-1 Feb-11 DEP 70.10.70.11 (Ι) Preservation of New and Old Equipment Standing Idle Feb-11 Building Services -
DEP 20.21.00.31 Fouling Resistance For Heat Transfer Equipment Feb-11
DEP 30.05.10.30 (Ι) Nitrogen / Oxygen Supply & Distribution System DEM-1 Feb-12 Welding - SP-1285 Specification for Civil & Building Services Ver. 2.0 Dec-09
DEP 30.10.05.11 Plant Model Construction & Review Feb-12
DEP 30.75.10.10 (Ι) Steam, Condensate and Boiler Feed Water Systems DEM-1 Feb-12 SP-1097 Specification for Welding of Duplex Stainless Steel Pipelines Ver. 2.0 May-05 DEP 31.76.10.10 Heating, Ventilation and Air Conditioning for Plant Building Amended by Circular 43/08 Jul-98
DEP 31.22.05.11 Gas/Liquid Separators - Type Selection and Design Rules Feb-12 - Amendments/Supplements to API Std 1104 DEP 31.76.10.11 Installation, Testing and Balancing, and Commissioning of HVAC Systems Apr-06
DEP 31.22.05.12 Liquid/Liquid and Gas/Liquid/Liquid Separators - Type Selection and Design Rules Feb-12 SP-1167 Specification for Welding on Pressurised Pipes Ver. 2.0 Oct-06 DEP 34.14.20.31 (Ι) Drainage systems and primary treatment facilities Amended by Circular 55/11 DEM-1 Feb-11
DEP 37.05.10.11 (Ι) Diesel Oil Systems DEM-1 Feb-12 SP-1173 Specification for Welding on On-Plot Pipe-Work REPLACES DEP 31.38.01.31-GEN Ver. 1.3 May-08
DEP 80.10.10.31 (Ι) Breathing Air & Supply Systems NEW REQUIREMENT – TBC Sep-12 - Amendments/Supplements to ASME B31.3 & Amend/Supl’t DEP 30.10.60.18-GEN
DEP 80.45.10.10 (Ι) Design of Pressure Relief, Flare and Vent Systems Amended A01 – Sep-12 DEM-1 Feb-12 SP-1174 Specification for Welding of Class 2 & Class 3 Pipelines Ver. 2.0 Dec-04
DEP 80.45.10.11 (Ι) Overpressure and Under-pressure – Prevention and Protection DEM-1 Feb-12 - Amendments/Supplements to API Std 1104
DEP 80.45.10.12 (Ι) Emergency Depressuring and Sectionalizing Amended by Circular 77/12 DEM-1 Feb-11 SP-1177 Specification for Welding of Class 1 Pipelines Ver. 2.0 Oct-05
Amended A03 – Sep-12 - Amendments/Supplements to API Std 1104
DEP 80.45.11.12 (Ι) Flare Details (Amendments/Supplements to ISO 25457) Amended by Circular 01/12 DEM-1 Feb-11 PR-1272 Standard Welding Procedure Qualification Records for On-Plot Piping Ver. 2.0 Jun-05
(No Doc No) De-oiling Manual Ver 2.0 Dec-10 PR-1274
PR-1276
Standard Welding Procedure Qualification Records For Class 2 Pipelines
Standard Procedure Qualification Records for Welding on to Pressurised Pipes
Ver. 2.0
Ver. 2.0
Jun-05
Jun-05
FEED OFFICE ENGINEERING – Manager: UEP1 - (Paul Bennington) ** FOR USE IN FEED OFFICE ONLY**
EP 95-0312 HAZID Hazard Identification Technique Rev. 0 Sep-95
EP 95-0313 HAZOP Hazard & Operability Technique Rev. 0 Oct-95 PR-1659 Pipeline Emergency Repair PQR’S Welding / Pipeline Procedures Ver. 1.0 Oct 05
EP 98-5632 Best Practices Guide - Gas Sweetening Technology Dec-98 DEP 30.10.60.18 Welding of Metals Amended and Supplemented by SP-1173 Feb-12 Doc. ID Document Title Additional Notes Rev./DEM Date
EP 99-5266 Removal of Heavy Metals from Waste Water – Desk Study Feb-99 - Amendments/ Supplements to API RP 582 FEED Office Management
EP 99-5508 Key Multiphase and Hydrate Learning Points from the Main Gas Condensate Sep-99 DEP-30.10.60.30 (Ι) Welding on Pressurised Pipes Amended and Supplemented by SP-1167 DEM 1 Feb-11
Systems in the Shell Group - Amendments/Supplements to ANSI / API RP 1107 Amended by Circular 60/11 PR-1741 FEED Office - Quality Management System Manual Rev. A06 Apr-12
EP 99-5806 Best Practice in Produced Water Treatment Dec-99 DEP-30.10.60.31 Oxidation of Stainless Steel Weldments Dec-98 PR-1742 FEED Office - Risk & Opportunity Management Procedure Rev. A02 Apr-11
EP 2003-5184 Shell Expro Topsides Solids Management Guide Sep-03 DEP 61.40.20.30 (Ι) Welding of Pipelines and Related Facilities Amended by Circular 07/12 DEM 1 Feb-11 PR-1743 FEED Office - Project On-Boarding Procedure Rev. A03 May-11
EP 2007-5644 EP Guideline on Process Safeguarding Nov-07 (Amendments/Supplements to ISO 13847:2000) PR-1764 FEED Office - New entrant Induction Program Procedure Rev. A04 Apr-11
EPTL-GL-PRO-0001 Global Process Engineering Guideline – Facility Line Sizing Dec-08 PR-1765 FEED Office - Knowledge Management (Lessons Learned) Rev. A02 May-11
GS 06.53139 Guide for Fluid Characterization using C7PLUS Method in HYSYS Dec-06
Inspection- PR-2004 FEED Office – Monthly Project Review Procedure Rev. A01 Feb-12
GS 08.53105 Hydrate Guidelines Aug-08
PR-1013 Static Equipment Inspection and Maintenance Procedure Ver. 3.0 May-05 HSE/Technical Safety
GS 09.50282 Flow Assurance Guideline Jan-09
GS 09.51858 Guidelines for the Hydraulic Design and Operation of Multiphase Flow Pipeline Systems Previously GS.06.50701 May-09 GU-256 Static Equipment Inspection Guideline Ver. 2.0 May-05 PR-1744 FEED Office – Managing Safety During Visits to Vendor and Contractor Sites Rev. A02 May-11
GS 09.53369 Plant and Pipeline Depressuring Guideline Dec-09 GU-363 Guideline for the Use of Scaffolding Ver. 1.0 Aug-00 PR-1776 FEED Office - HSE Action Close-out Procedure Rev. A02 May-11
GS 10.50828 Heat Exchanger Selection Guideline Previously EP 2005-5186 Apr-10 GU-432B Guideline for Automated Ultrasonic Testing Scope Ver. 1.0 May-03
SR 11.11103 Guide for Fluid Characterization using C7PLUS Method in UNISIM Apr-11 Definition for Class 1 Piggable Pipelines
GU-450 Guideline for Inspection and Integrity Assessment of Ver. 1.0 Nov-03 Engineering
Carbon Steel Non-Piggable Pipelines
SP-2067 FEED Office - PDMS Model specification Rev. A01 Sept-08
DEP 30.55.03.30 Validation of NDE for Fabrication Inspection Feb-12
CONTROL & AUTOMATION ENGINEERING – CFDH: UEOA2 (UES) - (Salim Hinai) DEP 61.10.08.11 Field Inspection prior to Commissioning of Mechanical Equipment Feb-11 PR-1727
PR-1728
FEED Office - Preparation of "Basis for Design" Procedure
FEED Office - Preparation of Project Specification (FEED Output) Procedure
Rev. A02
Rev. A02
May-11
May-11
PR-1729 FEED Office - Technical Integrity During Design & Execution Phase Procedure Rev. A02 Oct-09
Doc. ID Document Title Additional Notes Rev./DEM Date PR-1730 FEED Office - Engineering & Projects Calculation Procedure Rev. A02 May-11
PR-1733 FEED Office – Technical Information Note Procedure Rev. A04 Oct-12
Instrument Equipment FEED Office – Process System Design Review Procedure
SECURITY– CFDH: UIC (Salim Ambusaidi) PR-1734
PR-1735 FEED Office - Codes and Standards Procedure
Rev. A02
Rev. A01
May-11
May-11
SP-1089 Instrument Impulse Lines WITHDRAWN – Replaced by DEP 32.37.10.11 Ver 1.0 Jan 01 PR-1736 FEED Office - Site Survey Procedure Rev. A03 Oct-12
SP-1090 Instrument Signal Lines Based on DEP 32.37.20.10 (May 2004) Ver. 2.0 Dec 05 Doc. ID Document Title Additional Notes Rev./DEM Date PR-1749 FEED Office - Register of Holds Procedure Rev. A02 Sep-11
SP-1206 C & A Standard Drawings Ver. 2.0 Dec-10 PR-1750 FEED Office - Contract and Third Party Services Management Procedure Rev. A04 Apr-11
SP-1243 Corporate Philosophy for Control and Automation Ver. 2.0 Jun-11 SP-1279 Specification for Civil & Building Construction – Owner: Civil Engineering Chapter P – Fences & Gates Ver. 2.0 Dec-09
SP-2084 Specification for IP Video Surveillance, Perimeter Security & Access Ver. 2 Jul-12 PR-1752 FEED Office – Project Execution Procedure (Define Phase) Rev. A02 Nov-09
SP-1245 Fieldbus Control System Specification Ver. 3.0 Dec-10 PR-1768 FEED Office - Project Deliverables - Checking and Approval Procedure Rev. A03 Jun-10
SP-2098 Smart Plant Instrumentation Specification NEW REQUIREMENT Ver. 2.0 May-12 Control Systems
PR-1773 FEED Office - Equipment Supplier Document Requirements Procedure Rev. A04 May-12
SP-2121 DACA PCD Systems Access & Control Management Ver. 1.0 Dec-11 PR-1778 FEED Office - Standard Calculation Spreadsheet QC Procedure Rev. A02 May-11
PR-1938 FEED Office – Change Control Procedure Rev. A01 Apr-10
PR-1094 Instrumented Protective Functions Test Procedure Rev. 1.0 Aug-04 PR-1939 FEED Office – Multi-Discipline Equipment Data Sheet Specification Procedure Rev. A01 Apr-10
PR-1293 Main Oil Line (MOL) Metering Systems Verification Procedure Rev. 1 May-09
PR-1304
PR-1315
Product Flow Measurement
Measurement Equipment Calibration/Recertification Procedure
Rev. 3.0
Rev. 2.0
Jul-11
Aug-11
TELECOMS - UIID (Said Shidhani) GU-603 FEED Office - Project Deliverables Guideline ORP Phase 3: Define Rev. A02 Apr-11

PR-1619 Mina Al Fahal Terminal Oil Material Balance Rev. 1.0 Mar-11 SP-1265 Specification for ADSS Fibre-Optic Cables and Key Accessories Ver. 2.0 Aug-08 Cost & Planning
PR-1620 Mina Al Fahal Terminal Dip Procedure Rev. 2.0 Sep-10 SP-1266 Specification for Installation of ADSS Fibre Optic Cables Ver. 2.0 Aug-06
PR-1809 Production Measurement Management System Procedure Ver 1.0 Nov-08 SP-2004 Fibre Optic Cable Installation Specifications Ver. 5.0 Jul-12 PR-1737 FEED Office - Finance Flow Procedure Rev. A02 Apr-10
SP-2084 Specification for IP Video Surveillance, Perimeter Security NEW REQUIREMENT Ver. 2 Jul-12 PR-1738 FEED Office - Business Review Procedure Rev. A02 Feb-12
PR-1995 DACA PCDP & PCD Systems Access Request Procedures Ver. 1.0 Dec-11
& Access Control Systems PR-1746 FEED Office - Time writing Procedure Rev. A02 May-11
PR-1996 Venturi Based Wet Gas Meter (WGM) Sizing, Commissioning, Update & Review Rev. 1.0 Nov-11
DEP 32.71.00.10 (Ι) Plant Telecommunication NEW REQUIREMENT DEM-1 Feb-10 PR-1770 FEED Office - Planning & Progress Reporting Procedure Rev. A02 Apr-10
DEP.32.71.00.11 Telecommunications Standards NEW REQUIREMENT May-04 PR-1771 FEED Office - Cost Planning Work-flow Procedure Rev. A02 May-11
GU-437 SIL Assessment & Implementation Guidelines Ver. 2.0 May-09
DEP.32.71.00.14 Telecommunications Tower and Guyed Masts NEW REQUIREMENT Dec-08
GU-513 Guidelines for Alarm Management and Rationalisation Ver. 2.0 Dec-09 GU-616 FEED Office - Standard CTR Catalogue Rev. A03 Apr-10
GU-656 Guideline for the use of Level Measuring Instruments Rev. 1.0 Sep-11 GU-640 FEED Office – CTR Catalogue Template (Minor Projects) Rev. A01 Nov-10

DEP 30.00.60.15 (Ι) Human Factors Engineering – Control Room Design Feb-12 Quality Management
DEP 30.00.60.16 Human Factors Eng. – Human/Machine Interface Design for Situation Awareness REPLACES SP-1192 Aug-09
DEP 31.40.70.30 (Ι)
DEP 32.01.20.12
Quarter Turn Actuators for On/Off Valves
Process Control Domain -
- Enterprise industrial automation information technology and security
Amended by Circular 50/11 DEM-1 Feb-11
Feb-12 Notes: PR-1726
PR-1745
FEED Office - Control of QMS Documents Procedure
FEED Office - Customer Feedback Procedure
Rev. A04
Rev. A04
Apr-12
Apr-12
PR-1756 FEED Office - Control of Non-Conformance, Corrective and Preventative Actions Rev. A03 Apr-12
DEP 32.01.23.17 (Ι) Process Control Domain – Security Requirements for Suppliers DEM-1 Feb-11 1. This Document can be accessed from LiveLink: http://sww4.pdo.shell.om/CMFportal/Default.aspx PR-1772 FEED Office - Management Review Procedure Rev. A03 Apr-12
DEP 32.01.40.31 (Ι) Requirements for Real-Time Production Operations and Production-Critical
Real-Time Data
Feb-12
2. DEP’s (V35 – Sep-12) are Shell Documents and can be accessed from: http://swwep-deps.shell.com/
DEP 32.10.03.10 (Ι) Instrument Symbols and Identification on Process Engineering Flow Schemes DEM-1 Feb-11 a) Note: as of v32, new/revisions to DEP’s are split into ‘Specification’ and ‘Informative’ – See Tabs at top of DEP web-page Information Management
DEP 32.24.20.44 (Ι) Instrumentation Control & Protection for Fired Equipment DEM-1 Feb-12 (Ι) denotes the DEP’s where this Specification and Informative split has been implemented PR-1722 FEED Office - Information Management Services to FEED Office Procedure Rev. A02 Feb-11
DEP 32.29.20.10 (I) Safeguarding & Instrumented Protective Functions for Rotating Equipment Amended by Circular 74/11 DEM-1 Feb-11
DEP 32.30.20.11 (I) Fire, Gas and Smoke Detection Systems Amended by Circular 72/12 DEM-1 Sep-11 3. PDO Management System Documents are available on Livelink: http://sww4.pdo.shell.om/CMFportal/Default.aspx PR-1723
PR-1725
FEED Office - Information Documents and Records Procedure
FEED Office - Supplier document Procedure
Rev. A03
Rev. A02
Jun-10
Jun-11
DEP 32.30.20.14 (I) Instrument Asset Management Feb-12
DEP 32.30.20.15 (I) DCS Basic Application Standards Sep-11 PDO Hierarchy: PR-1761 FEED Office - Hand-over Documentation Procedure Rev. A02 May-11
DEP 32.30.20.16 Baselayer Control Applications Sep-11
DEP 32.30.20.17 Integration Of Motor Controls Into BPCS Feb-12
a) CMF Corporate Management Framework Mandatory GU-600 FEED Office - Live link &Assai Usage Rev. A02 Feb-11
DEP 32.30.20.18 Real Time Optimisation Project Standards NEW REQUIREMENT – TBC Sep-12 b) PL Policy Mandatory
DEP 32.31.00.32 (Ι) Instruments for Measurement and Control Amended by Circular 73/11 & 46/12 Feb-11
DEP 32.31.00.34 (I) Instrumentation Documents and Drawings Sep-11 c) CP Code of Practice Mandatory
DEP 32.31.09.31 (I) Instrumentation for Equipment Packages Amended by Circular 47/12 Sep-11 d) SP Specification Mandatory
DEP 32.31.50.10 On-line Process Analysers Sep-12
DEP 32.31.50.13 Analyser Housing Sep-12 e) PR Procedure Mandatory
DEP 32.32.00.11
DEP 32.32.00.12
Turbine Fiscal Metering Systems for Liquid Hydrocarbons
Fiscal Flow Measurement of Natural Gas
DEP 32.36.01.17 (Ι) Control Valves – Selection, Sizing & Specifications
Amended by Circular 11/10
Amended by Circular 06/12 & (A03 – Sep-12) DEM-1
Sep-12
Jun-07
Feb-11 4.
f) GU Guideline
The Hardcopy of this Document (Wall Chart) is issued every 6 Months in Arrears – The document may be
Non-Mandatory CAUTION
DEP 32.37.10.11 (Ι) Installation of On-Line Instruments NEW REQUIREMENT – Replaces SP-1089 Sep-12 MAKE SURE YOU HAVE LATEST REVISION (CHECK IN LIVELINK or SHELL DEP WEBSITE)
DEP 32.45.10.10 (Ι) Instrumentation of Depressuring Systems Amended by Circular 49/11 DEM-1 Feb-11 revised between hard-copy issues – please check Livelink for latest revision
DEP 32.80.10.10 (Ι) Instrumented Protective Functions (IPF) Amended by Circular 72/11 DEM-1 Feb-11
DEP 32.80.10.14 (I) Alarm Management Amended by Circular 43/11 DEM-1 Feb-11 5. All changes since last revision are shown in BOLD
Revision: 18a
GU-611
DEP 61.38.10.10 Shop and Field Fabrication of Orifice Meter Runs Feb-12
DEP 62.10.08.11 (Ι) Inspection & Functional Testing of Instruments Amended by Circular 11/12 DEM-1 Feb-11
6. Please notify UEPI of any revisions required to this wallchart
Document Owner: UEPI