Project Description : HIS Clean Up 7E-96

SR/WI No. : XXXXXX


SR Start: 1-Oct-18
SR Finish 31-Oct-18
Site 7E-96
CS PT. XXX

No WBS & Task Description Unit

1 Clearing & Grubbing


1.1 Land Clearing Sq. Meter
Soil/Dirt Hauling, distance 0-10 KM (without compaction) Cu. Meter

Earthworks Fill from Company Designated Location, Haul & Compacted


(with hauling distance from 0.5 KM to 15 KM)
Cu. Meter

Earthworks Fill from Company Designated Location, Haul & Compacted,


Additional Cost per KM Above 15 KM Hauling Distance Cu. Meter
Earthworks Compaction Sq. Meter
Monitoring Well diameter 4"
Supply and Pouring Concrete - K175
Supply and Install Traffic Sign, Single Post Pipe
Productivities
Volume (Resource/day) Resources Name Resources Load Duration

10000 5000 Excavator 2 1


2000 100 Dump Truck 4 5.0

Dump Truck,Excavator,Sheep
Foot Compactor,Smooth
6000 100 Drum Compactor,Dozer 4 15.0
Contingency Remarks