You are on page 1of 1

CADANGAN PEMBINAAN JAMBATAN BAGI MENGHALANG BERLAKUNYA BANJIR DI MASJID NEGERI DAERAH TIMUR LAUT, PULAU PINANG.

Detailed Engineering Design


Implementation Schedule

ACTIVITIES Weeks YEAR 2011 YEAR 2012


Jun July Aug Sept Oct Nov Dis Jan Feb Mac Apr Mei Jun July
1 Interim Report 4

2 Topographical Survey (Start 1/7/11) 4

3 Prepare Typical Cross Sections and Standard Detail Drawings 8

4 Preliminary Design (Start 15/7/11) 4


- Geometric
- Bridge G.A

5 Approval from JKR 2

7 Soil Investigation 4

10 Hydrological and Drainage Design 6

12 Geotechnical Design and Analysis 6

15 Pavement Design 4

16 Relocation of Services (PBA/TNB/Telekom/Gas) 16

17 Bridges Detail Design 8

20 Traffic management Plan 4

22 Approval from JPS/TNB/PBA/Telekom/PLUS 8

24 Final Engineering Drawings 4

25 Final Quantities and Cost Estimates 6

26 Tender Documents 4

27 Approval from JKR 2

28 Tender 4

29 Tender Evaluation 4
12 months
30 Construction 52

Constructions = 12 Months

You might also like