FABRICATED PIPING SYSTEMS.

SAFE WORK PROCEDURE / PLANNED JOB OBSERVATION

SAFE WORK PROCEDURES PLANNED JOB


OBSERVATIONS
Steps (In sequence) Critical Points Comments on No
(Items to be emphasised) Deviations from
Standards
Ensure all hand tools are placed on register and are
Obtain all necessary tools for task at hand.
inspected on a monthly basis.
Employee to make use of hand tool (punch) to line up holes.
Install control valve, magflow and manual valve. (Manual)
Employees are to make use of gloves.
Supervisor is to ensure that all hand tools are fitted with wrist
lanyard.
Area where Installation of valves are to be done is to be well
Install control valve, magflow and manual valve. (By compacted
crane) Sleepers are too placed under outriggers for stability

Crane operator is to be trained, certified and legally appointed


internally and by Mine.
See Risk Assessment FPS 010 – Use of mobile crane.
Lifting equipment, to be inspected, certified, colour coded and
Obtain lifting tackle from stores.
placed on register.
Safe access to be given by means of existing platform,
Scaffolding or by means of boatswains chair.
Employees to access area where valve/item is to be
installed.
Employees are to secure themselves to structure/lifeline at all
times whilst working on elevated areas.
Slings are now to be hooked/attached onto load, Supervisor and riggers are to ensure that pre lift inspection is
done for all lifts under 5 Ton and Rigging Study’s are to be
done for all difficult loads and loads over 5 Ton.

Rigger to be trained, certified and legally appointed.


34 Point pre-lift checklist together with lifting plan sketch to be
FABRICATED PIPING SYSTEMS.

completed.

No overhead work allowed, Area where lift is taking place is


to be barricaded and signs are to be displayed.
Rigger to make use of whistle to warn employees that there is
Valve/ Item is now to be picked up by means of crane.
a lift in progress

Rigger to make use of guide rope to control swinging load.


Employees must guide item to be installed by means of guide
Valve/Item to be slewed into position and then to be
rope and not by hand
secured by means of bolts.
Employees are to make use of PPE(Gloves)
On completion of installation of valves/Items all lifting
All equipment to be returned to stores at end of shift.
tackle and tools used are to be returned to stores.
FABRICATED PIPING SYSTEMS.

Method Statement
Company: F.P.S
Date: 26/03/2010
Task / Job: FPS 015 – Installation of valves
Supervisor: All supervisors

Method statement

1.
1 Obtain all necessary tools for task at hand.

2.
2 Install control valve, magflow and manual valve. (Manual)

3.
4 Install control valve, magflow and manual valve. (By crane)

4.
7 Obtain lifting tackle from stores.

5.
8 Employees to access area where valve/item is to be installed.

6.
9 Slings are now to be hooked/attached onto load,

7.
1 Valve/ Item is now to be picked up by means of crane.

8.
1 Valve/Item to be slewed into position and then to be secured by means of bolts.

9. On completion of installation of valves/Items all lifting tackle and tools used are to be
FABRICATED PIPING SYSTEMS.

1
returned to stores.